Session 3:
Building Management and Operations for Performance and Efficiency
Track 3: Energy Technologies
Shanti Pless, Senior Energy Efficiency Research Engineer
National Renewable Energy Laboratory
August 11, 2015
Lets Review
• I have a new net zero energy building that
meets the Executive Orders – now what?
– Year 3 in our own net zero operations efforts in
the Research Support Facility at NREL
– Real Performance for Real Buildings
Our Net Zero Effort
NREL/DOE Research Support Facility
Location: Golden, CO
Primary Use: Office
Size: 360,000 ft2
Occupants: Approximately 1,325
LEED Rating: Platinum
Construction Cost: $254/ft2
Energy Budget: 35 kBtu/ft2/yr
Site Net Zero Energy Goal:
Offices, datacenter, and parking with
on-site PV and campus wood chip
boiler
End use metering as required in RFP
Zero Energy Building Operations Realities (data)
First year at Net Zero!
http://www.nrel.gov/news/features/feature_detail.cfm/feature_id=11369
Zero Energy Building Operations Realities (data)
Zero Energy Building Operations Realities (data)
Energy Exchange: Federal Sustainability for the Next Decade
Occupant Impact
Images: Dennis Schroeder, NREL
Occupants influence about 30%
of total energy consumption
Energy Exchange: Federal Sustainability for the Next Decade
RSF Performance Targets
Pie Chart: Chad Lobato, NREL; Graphic: Marjorie Schott, NREL, and
Stockphoto
Energy Exchange: Federal Sustainability for the Next Decade
Energy Exchange: Federal Sustainability for the Next Decade
Building Agent
Graphics: Nicholas Long, NREL
6 watt task light
50 fc
Ambient daylight
Ambient lighting with
daylight sensors for 25 fc
MANAGER TRAINING NEWSLETTER
MOVE MEETINGS
STAFF OPEN HOUSE
RSF EMAIL BOX
WEB PAGE
You have switches – use them
If you open a window – close it
If you are stuffy – open your window
If you have a glare issue – pull your shade
Turn on your power strip in the morning
Energy Exchange: Federal Sustainability for the Next Decade
Effective Visualization?
What does
this tell us?
Energy Exchange: Federal Sustainability for the Next Decade
Building Agent Dashboard
Graphic Design: Marjorie Schott, NREL
What about
this?
Energy Exchange: Federal Sustainability for the Next Decade
On Track Today – mostly..
(08:15 am MST 8/11/15)
Energy Exchange: Federal Sustainability for the Next Decade
Creating Expectations
26
Upper Expectation
Measured
Performance
Lower Expectation
Expectations combine
statistical and physical
energy models
Energy Exchange: Federal Sustainability for the Next Decade
Modeling Consumption
Vertical Irradiance (W/m2)
LPD(W/m2)
Statistical Models
Lighting
Physical Models
PV Generation
Combined Models
Plug Loads
Henze, G.P.; Pless, S.; Petersen, A.; Long, N.; Scambos, T. (2015).
“Control limits for building energy end use based on frequency analysis
and quantile regression." Energy Efficiency, published online. DOI:
10.1007/s12053-015-9342-6
Energy Exchange: Federal Sustainability for the Next Decade
Fault Detection Example:
Daylighting
Lighting higher
than expected
Lighting out of range
despite full daylighting
potential
Root Cause: Daylighting controls overridden
during repair of ballast and fixtures; controls
weren’t reset
6-Nov-20136-Nov-2013
Energy Exchange: Federal Sustainability for the Next Decade
Fault Detection Example:
Lighting Controls
Lighting load is too high
in evening hours (6–10
PM)
Response: Reduce auto-off delays; staff
outreach; lessons learned for future lighting
system design
Multiple Causes: Cleaning staff, individuals
working late
1-Jan-2014 5-Apr-2014
Is it OFF?
Credit: Jennifer Scheib/NREL
Energy Exchange: Federal Sustainability for the Next Decade
Fault Detection Example: Air
Handler
Solution: Installation of new
evaporative cooling unit to meet
local demand, enabling the AHU to
turn off at night
Problem: Large AHU on all night:
manually overridden to provide air
and cooling to a few night shift
security employees
16-Aug-2013
7-Oct-2013
Energy Exchange: Federal Sustainability for the Next Decade
Fault Detection Example: PV
Inverter Offline
PV output too low.
Why?
Time series suggests inverter
outage; offline inverter confirmed
via vendor web portal and repair
dispatched
20-Mar-2015 20-Mar-2015
Energy Exchange: Federal Sustainability for the Next Decade33
Production Tracking
Energy Exchange: Federal Sustainability for the Next Decade
• Have run 1.15 - 1.35 PUE
• Fully containing hot aisle difficult
• Custom aisle floor and door seals
• Ensure equipment designed for hot
aisle containment
• 100 kW datacenter load in 2010
• 141 kW January 2015
• Decommissioned older servers
• Ensured highest efficiency possible
power supplies
• Continued consolidation
• 123 kW June 2015
Can a Datacenter Use Less Energy Over Time?
NREL/PIX17897
Credit:MarjorieSchott/NREL
Energy Exchange: Federal Sustainability for the Next Decade
• Fix PV faults as soon as they are found
– 12% improvements possible
• Continued datacenter metric tracking
– 1.15 PUE and total 120 kW goals
• Lighting controls commissioning
– Occupancy sensors, daylighting set points
• Wood chip boiler controls improvements
– Over 50% natural gas savings planned
• Additional PV planned
• More thin clients
All while trying to fit in another 100 occupants…
35
Plan to return to net positive
High Performance Building Operators
Owners/Operators
Jim Dewey, City of Santa Barbara
John Elliott, UC Merced
Matt Ellis, Army
Jake Gedvilas, NREL
Rodney Martin, NASA
Scott Poll, NASA
Len Pettis, California State University
Kevin Rodgers, University of Chicago
Jason Sielcken, GSA
Darrell Smith, Microsoft
Scott Williams, Target
Designers and Energy Consultants
Porus Antia, Stantec
Matt Ganser, Carbon Lighthouse
Rob Peña, University of Washington and the
Integrated Design Laboratory
Zack Rogers, Daylighting Innovations
Phil Saieg, McKinstry
Resources
• General HPB operations process
linked by project phase
• Present a storyline for all HPB
operations key actions (above and
beyond current practice)
• Unique sections for topics that
create a base recipe that can be
used by all HPB owners and building
types
• Examples of unique lessons given to
generate motivation and confidence
to take action
• Setting and requiring energy targets
• Procuring an EIS
• Procuring MELs
• Datacenters
• Occupancy and occupant feedback
• Closing the loop with action plans
https://buildingdata.energy.gov/cbrd/resource/1913
Preparing for HPB Operations
Thanks and Questions
• Shanti Pless
• Shanti.pless@nrel.gov
• www.nrel.gov/rsf
39

More Related Content

What's hot

Achieving net zero energy at scale gb12 111512
Achieving net zero energy at scale gb12 111512Achieving net zero energy at scale gb12 111512
Achieving net zero energy at scale gb12 111512Tom Hootman
 
Energy Modeling 2009 Presentation
Energy Modeling 2009 PresentationEnergy Modeling 2009 Presentation
Energy Modeling 2009 PresentationMatt Macko
 
Net Zero Energy Buildings
Net Zero Energy BuildingsNet Zero Energy Buildings
Net Zero Energy BuildingsIllinois ASHRAE
 
NREL case study 010512
NREL case study 010512NREL case study 010512
NREL case study 010512Tom Hootman
 
Building the Future: Net Zero and Net Zero Ready
Building the Future: Net Zero and Net Zero ReadyBuilding the Future: Net Zero and Net Zero Ready
Building the Future: Net Zero and Net Zero ReadyRDH Building Science
 
NZEB Office Building by David Walshe
NZEB Office Building by  David WalsheNZEB Office Building by  David Walshe
NZEB Office Building by David WalsheSustainableEnergyAut
 
Zero Energy Buildings
Zero Energy BuildingsZero Energy Buildings
Zero Energy BuildingsJeffrey Funk
 
The role of delivered performance june2009
The role of delivered performance june2009The role of delivered performance june2009
The role of delivered performance june2009Toronto 2030 District
 
Energy Efficiency in Permanent Modular Construction NREL Research Project Poster
Energy Efficiency in Permanent Modular Construction NREL Research Project PosterEnergy Efficiency in Permanent Modular Construction NREL Research Project Poster
Energy Efficiency in Permanent Modular Construction NREL Research Project PosterShanti Pless
 
Huge ‘Untapped’ Financial Benefits Exclusively For NYC Building Owners
Huge ‘Untapped’ Financial Benefits Exclusively For NYC Building Owners Huge ‘Untapped’ Financial Benefits Exclusively For NYC Building Owners
Huge ‘Untapped’ Financial Benefits Exclusively For NYC Building Owners EEReports.com
 
Building A Zero Carbon Internet
Building A Zero Carbon InternetBuilding A Zero Carbon Internet
Building A Zero Carbon InternetBill St. Arnaud
 
Energy modeling project
Energy modeling projectEnergy modeling project
Energy modeling projectHUI-LING CHANG
 
Sustainability and Energy Efficiency by Ciaran O'Connor
Sustainability and Energy Efficiency by Ciaran O'ConnorSustainability and Energy Efficiency by Ciaran O'Connor
Sustainability and Energy Efficiency by Ciaran O'ConnorSustainableEnergyAut
 
Carbon Neutral Apartment Retrofits
Carbon Neutral Apartment RetrofitsCarbon Neutral Apartment Retrofits
Carbon Neutral Apartment RetrofitsRDH Building Science
 
NZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean ArmstrongNZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean ArmstrongSustainableEnergyAut
 

What's hot (20)

Achieving net zero energy at scale gb12 111512
Achieving net zero energy at scale gb12 111512Achieving net zero energy at scale gb12 111512
Achieving net zero energy at scale gb12 111512
 
Energy Modeling 2009 Presentation
Energy Modeling 2009 PresentationEnergy Modeling 2009 Presentation
Energy Modeling 2009 Presentation
 
Net Zero Energy Buildings
Net Zero Energy BuildingsNet Zero Energy Buildings
Net Zero Energy Buildings
 
NREL case study 010512
NREL case study 010512NREL case study 010512
NREL case study 010512
 
Building the Future: Net Zero and Net Zero Ready
Building the Future: Net Zero and Net Zero ReadyBuilding the Future: Net Zero and Net Zero Ready
Building the Future: Net Zero and Net Zero Ready
 
NZEB Office Building by David Walshe
NZEB Office Building by  David WalsheNZEB Office Building by  David Walshe
NZEB Office Building by David Walshe
 
Nzeb case study esb
Nzeb case study   esbNzeb case study   esb
Nzeb case study esb
 
Zero Energy Buildings
Zero Energy BuildingsZero Energy Buildings
Zero Energy Buildings
 
The role of delivered performance june2009
The role of delivered performance june2009The role of delivered performance june2009
The role of delivered performance june2009
 
Energy Efficiency in Permanent Modular Construction NREL Research Project Poster
Energy Efficiency in Permanent Modular Construction NREL Research Project PosterEnergy Efficiency in Permanent Modular Construction NREL Research Project Poster
Energy Efficiency in Permanent Modular Construction NREL Research Project Poster
 
Huge ‘Untapped’ Financial Benefits Exclusively For NYC Building Owners
Huge ‘Untapped’ Financial Benefits Exclusively For NYC Building Owners Huge ‘Untapped’ Financial Benefits Exclusively For NYC Building Owners
Huge ‘Untapped’ Financial Benefits Exclusively For NYC Building Owners
 
Building A Zero Carbon Internet
Building A Zero Carbon InternetBuilding A Zero Carbon Internet
Building A Zero Carbon Internet
 
Energy modeling project
Energy modeling projectEnergy modeling project
Energy modeling project
 
Building the Case for Net Zero
Building the Case for Net ZeroBuilding the Case for Net Zero
Building the Case for Net Zero
 
Energy in Schools by John Dolan
Energy in Schools by John DolanEnergy in Schools by John Dolan
Energy in Schools by John Dolan
 
2014 energy modeling
2014 energy modeling2014 energy modeling
2014 energy modeling
 
Sustainability and Energy Efficiency by Ciaran O'Connor
Sustainability and Energy Efficiency by Ciaran O'ConnorSustainability and Energy Efficiency by Ciaran O'Connor
Sustainability and Energy Efficiency by Ciaran O'Connor
 
Carbon Neutral Apartment Retrofits
Carbon Neutral Apartment RetrofitsCarbon Neutral Apartment Retrofits
Carbon Neutral Apartment Retrofits
 
NZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean ArmstrongNZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean Armstrong
 
Energy Modeling
Energy ModelingEnergy Modeling
Energy Modeling
 

Similar to Energy Exchange 2015 Track 3 session 3: High Performance Buildings Operations

RSF Net zero operations 2020
RSF Net zero operations 2020RSF Net zero operations 2020
RSF Net zero operations 2020Shanti Pless
 
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...vvfvilar
 
Benchmarking/Performance Measuring
Benchmarking/Performance MeasuringBenchmarking/Performance Measuring
Benchmarking/Performance MeasuringASHRAE Region VI
 
Bringing Enterprise IT into the 21st Century: A Management and Sustainabilit...
Bringing Enterprise IT into the 21st Century:  A Management and Sustainabilit...Bringing Enterprise IT into the 21st Century:  A Management and Sustainabilit...
Bringing Enterprise IT into the 21st Century: A Management and Sustainabilit...Jonathan Koomey
 
Value of CSP with TES november 2014
Value of CSP with TES november 2014Value of CSP with TES november 2014
Value of CSP with TES november 2014Daniel Schwab
 
Unlock Your Buildings Hidden Energy Data - Corenet Seattle
Unlock Your Buildings Hidden Energy Data - Corenet SeattleUnlock Your Buildings Hidden Energy Data - Corenet Seattle
Unlock Your Buildings Hidden Energy Data - Corenet SeattleJason Burt
 
Jenna Ide GCC 2015
Jenna Ide GCC 2015Jenna Ide GCC 2015
Jenna Ide GCC 2015GWT
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyTransGrid AU
 
The Wilton E. Scott Institute for Energy Innovation at Carnegie Mellon Univer...
The Wilton E. Scott Institute for Energy Innovation at Carnegie Mellon Univer...The Wilton E. Scott Institute for Energy Innovation at Carnegie Mellon Univer...
The Wilton E. Scott Institute for Energy Innovation at Carnegie Mellon Univer...Amanda Finkenbinder, MPM
 
Foothill College Energy Program
Foothill College Energy ProgramFoothill College Energy Program
Foothill College Energy ProgramRobert Cormia
 
Building a Sustainable Data Center
Building a Sustainable Data CenterBuilding a Sustainable Data Center
Building a Sustainable Data CenterAngela Miller
 
2011 expo-smart grn-energy
2011 expo-smart grn-energy2011 expo-smart grn-energy
2011 expo-smart grn-energyEllieNowels
 
The New Role of Data in the Changing Energy & Utilities Landscape
The New Role of Data in the Changing Energy & Utilities LandscapeThe New Role of Data in the Changing Energy & Utilities Landscape
The New Role of Data in the Changing Energy & Utilities LandscapeDenodo
 
Zero Energy Commercial Buildings: Research For the Next Generation
Zero Energy Commercial Buildings: Research For the Next GenerationZero Energy Commercial Buildings: Research For the Next Generation
Zero Energy Commercial Buildings: Research For the Next GenerationShanti Pless
 
Introduction to School Energy Management
Introduction to School Energy ManagementIntroduction to School Energy Management
Introduction to School Energy ManagementMeg Thompson
 
Energy Management Turned - Energy Productivity
Energy Management Turned - Energy ProductivityEnergy Management Turned - Energy Productivity
Energy Management Turned - Energy ProductivityEzra Nielsen
 

Similar to Energy Exchange 2015 Track 3 session 3: High Performance Buildings Operations (20)

RSF Net zero operations 2020
RSF Net zero operations 2020RSF Net zero operations 2020
RSF Net zero operations 2020
 
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
 
Can the Cloud Be Green?
Can the Cloud Be Green?Can the Cloud Be Green?
Can the Cloud Be Green?
 
Benchmarking/Performance Measuring
Benchmarking/Performance MeasuringBenchmarking/Performance Measuring
Benchmarking/Performance Measuring
 
IGBC2014 - Stephen Selkowitz, Lawrence Berkeley National Laboratory
IGBC2014 - Stephen Selkowitz, Lawrence Berkeley National LaboratoryIGBC2014 - Stephen Selkowitz, Lawrence Berkeley National Laboratory
IGBC2014 - Stephen Selkowitz, Lawrence Berkeley National Laboratory
 
Bringing Enterprise IT into the 21st Century: A Management and Sustainabilit...
Bringing Enterprise IT into the 21st Century:  A Management and Sustainabilit...Bringing Enterprise IT into the 21st Century:  A Management and Sustainabilit...
Bringing Enterprise IT into the 21st Century: A Management and Sustainabilit...
 
Value of CSP with TES november 2014
Value of CSP with TES november 2014Value of CSP with TES november 2014
Value of CSP with TES november 2014
 
Unlock Your Buildings Hidden Energy Data - Corenet Seattle
Unlock Your Buildings Hidden Energy Data - Corenet SeattleUnlock Your Buildings Hidden Energy Data - Corenet Seattle
Unlock Your Buildings Hidden Energy Data - Corenet Seattle
 
Jenna Ide GCC 2015
Jenna Ide GCC 2015Jenna Ide GCC 2015
Jenna Ide GCC 2015
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering Sydney
 
The Wilton E. Scott Institute for Energy Innovation at Carnegie Mellon Univer...
The Wilton E. Scott Institute for Energy Innovation at Carnegie Mellon Univer...The Wilton E. Scott Institute for Energy Innovation at Carnegie Mellon Univer...
The Wilton E. Scott Institute for Energy Innovation at Carnegie Mellon Univer...
 
Foothill College Energy Program
Foothill College Energy ProgramFoothill College Energy Program
Foothill College Energy Program
 
Building a Sustainable Data Center
Building a Sustainable Data CenterBuilding a Sustainable Data Center
Building a Sustainable Data Center
 
2011 expo-smart grn-energy
2011 expo-smart grn-energy2011 expo-smart grn-energy
2011 expo-smart grn-energy
 
The New Role of Data in the Changing Energy & Utilities Landscape
The New Role of Data in the Changing Energy & Utilities LandscapeThe New Role of Data in the Changing Energy & Utilities Landscape
The New Role of Data in the Changing Energy & Utilities Landscape
 
T5S4_Zhivov.pptx
T5S4_Zhivov.pptxT5S4_Zhivov.pptx
T5S4_Zhivov.pptx
 
Zero Energy Commercial Buildings: Research For the Next Generation
Zero Energy Commercial Buildings: Research For the Next GenerationZero Energy Commercial Buildings: Research For the Next Generation
Zero Energy Commercial Buildings: Research For the Next Generation
 
Energy Efficiency in Data Centers
Energy Efficiency in Data CentersEnergy Efficiency in Data Centers
Energy Efficiency in Data Centers
 
Introduction to School Energy Management
Introduction to School Energy ManagementIntroduction to School Energy Management
Introduction to School Energy Management
 
Energy Management Turned - Energy Productivity
Energy Management Turned - Energy ProductivityEnergy Management Turned - Energy Productivity
Energy Management Turned - Energy Productivity
 

More from Shanti Pless

ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...Shanti Pless
 
Innovative Capabilities to Integrate Energy Efficiency Strategies through Ad...
Innovative Capabilities to Integrate Energy Efficiency Strategies through  Ad...Innovative Capabilities to Integrate Energy Efficiency Strategies through  Ad...
Innovative Capabilities to Integrate Energy Efficiency Strategies through Ad...Shanti Pless
 
Getting to Zero Forum 2019 - Buildings and the Grid
Getting to Zero Forum 2019 - Buildings and the GridGetting to Zero Forum 2019 - Buildings and the Grid
Getting to Zero Forum 2019 - Buildings and the GridShanti Pless
 
Integrating Energy Efficiency into Advanced Manufacturing of Buildings
Integrating Energy Efficiency into Advanced Manufacturing of BuildingsIntegrating Energy Efficiency into Advanced Manufacturing of Buildings
Integrating Energy Efficiency into Advanced Manufacturing of BuildingsShanti Pless
 
Next Generation Net Zero Vision
Next Generation Net Zero VisionNext Generation Net Zero Vision
Next Generation Net Zero VisionShanti Pless
 
Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Buil...
Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Buil...Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Buil...
Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Buil...Shanti Pless
 
Human Side Of Net Zero - Rocky Mountain Green
Human Side Of Net Zero - Rocky Mountain GreenHuman Side Of Net Zero - Rocky Mountain Green
Human Side Of Net Zero - Rocky Mountain GreenShanti Pless
 
Occupant Engaged - A ZEB control concept for engaging occupants
Occupant Engaged -  A ZEB control concept for engaging occupantsOccupant Engaged -  A ZEB control concept for engaging occupants
Occupant Engaged - A ZEB control concept for engaging occupantsShanti Pless
 
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 201250% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012Shanti Pless
 
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...Shanti Pless
 
Rebuilding Greensburg to be a Zero Energy City
Rebuilding Greensburg to be a Zero Energy CityRebuilding Greensburg to be a Zero Energy City
Rebuilding Greensburg to be a Zero Energy CityShanti Pless
 
NASA Net Zero Roadmap: Federal Utilities Partnership Working Group, November ...
NASA Net Zero Roadmap: Federal Utilities Partnership Working Group, November ...NASA Net Zero Roadmap: Federal Utilities Partnership Working Group, November ...
NASA Net Zero Roadmap: Federal Utilities Partnership Working Group, November ...Shanti Pless
 
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...Shanti Pless
 

More from Shanti Pless (13)

ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
 
Innovative Capabilities to Integrate Energy Efficiency Strategies through Ad...
Innovative Capabilities to Integrate Energy Efficiency Strategies through  Ad...Innovative Capabilities to Integrate Energy Efficiency Strategies through  Ad...
Innovative Capabilities to Integrate Energy Efficiency Strategies through Ad...
 
Getting to Zero Forum 2019 - Buildings and the Grid
Getting to Zero Forum 2019 - Buildings and the GridGetting to Zero Forum 2019 - Buildings and the Grid
Getting to Zero Forum 2019 - Buildings and the Grid
 
Integrating Energy Efficiency into Advanced Manufacturing of Buildings
Integrating Energy Efficiency into Advanced Manufacturing of BuildingsIntegrating Energy Efficiency into Advanced Manufacturing of Buildings
Integrating Energy Efficiency into Advanced Manufacturing of Buildings
 
Next Generation Net Zero Vision
Next Generation Net Zero VisionNext Generation Net Zero Vision
Next Generation Net Zero Vision
 
Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Buil...
Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Buil...Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Buil...
Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Buil...
 
Human Side Of Net Zero - Rocky Mountain Green
Human Side Of Net Zero - Rocky Mountain GreenHuman Side Of Net Zero - Rocky Mountain Green
Human Side Of Net Zero - Rocky Mountain Green
 
Occupant Engaged - A ZEB control concept for engaging occupants
Occupant Engaged -  A ZEB control concept for engaging occupantsOccupant Engaged -  A ZEB control concept for engaging occupants
Occupant Engaged - A ZEB control concept for engaging occupants
 
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 201250% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
 
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
 
Rebuilding Greensburg to be a Zero Energy City
Rebuilding Greensburg to be a Zero Energy CityRebuilding Greensburg to be a Zero Energy City
Rebuilding Greensburg to be a Zero Energy City
 
NASA Net Zero Roadmap: Federal Utilities Partnership Working Group, November ...
NASA Net Zero Roadmap: Federal Utilities Partnership Working Group, November ...NASA Net Zero Roadmap: Federal Utilities Partnership Working Group, November ...
NASA Net Zero Roadmap: Federal Utilities Partnership Working Group, November ...
 
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
 

Recently uploaded

PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 

Recently uploaded (20)

PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 

Energy Exchange 2015 Track 3 session 3: High Performance Buildings Operations

  • 1. Phoenix Convention Center • Phoenix, Arizona Session 3: Building Management and Operations for Performance and Efficiency Track 3: Energy Technologies Shanti Pless, Senior Energy Efficiency Research Engineer National Renewable Energy Laboratory August 11, 2015
  • 2. Lets Review • I have a new net zero energy building that meets the Executive Orders – now what? – Year 3 in our own net zero operations efforts in the Research Support Facility at NREL – Real Performance for Real Buildings
  • 3. Our Net Zero Effort
  • 4. NREL/DOE Research Support Facility Location: Golden, CO Primary Use: Office Size: 360,000 ft2 Occupants: Approximately 1,325 LEED Rating: Platinum Construction Cost: $254/ft2 Energy Budget: 35 kBtu/ft2/yr Site Net Zero Energy Goal: Offices, datacenter, and parking with on-site PV and campus wood chip boiler End use metering as required in RFP
  • 5. Zero Energy Building Operations Realities (data)
  • 6. First year at Net Zero!
  • 8. Zero Energy Building Operations Realities (data)
  • 9. Zero Energy Building Operations Realities (data)
  • 10. Energy Exchange: Federal Sustainability for the Next Decade Occupant Impact Images: Dennis Schroeder, NREL Occupants influence about 30% of total energy consumption
  • 11. Energy Exchange: Federal Sustainability for the Next Decade RSF Performance Targets Pie Chart: Chad Lobato, NREL; Graphic: Marjorie Schott, NREL, and Stockphoto
  • 12.
  • 13.
  • 14. Energy Exchange: Federal Sustainability for the Next Decade
  • 15. Energy Exchange: Federal Sustainability for the Next Decade Building Agent Graphics: Nicholas Long, NREL
  • 16. 6 watt task light 50 fc Ambient daylight Ambient lighting with daylight sensors for 25 fc
  • 17.
  • 18.
  • 19. MANAGER TRAINING NEWSLETTER MOVE MEETINGS STAFF OPEN HOUSE RSF EMAIL BOX WEB PAGE
  • 20.
  • 21.
  • 22. You have switches – use them If you open a window – close it If you are stuffy – open your window If you have a glare issue – pull your shade Turn on your power strip in the morning
  • 23. Energy Exchange: Federal Sustainability for the Next Decade Effective Visualization? What does this tell us?
  • 24. Energy Exchange: Federal Sustainability for the Next Decade Building Agent Dashboard Graphic Design: Marjorie Schott, NREL What about this?
  • 25. Energy Exchange: Federal Sustainability for the Next Decade On Track Today – mostly.. (08:15 am MST 8/11/15)
  • 26. Energy Exchange: Federal Sustainability for the Next Decade Creating Expectations 26 Upper Expectation Measured Performance Lower Expectation Expectations combine statistical and physical energy models
  • 27. Energy Exchange: Federal Sustainability for the Next Decade Modeling Consumption Vertical Irradiance (W/m2) LPD(W/m2) Statistical Models Lighting Physical Models PV Generation Combined Models Plug Loads Henze, G.P.; Pless, S.; Petersen, A.; Long, N.; Scambos, T. (2015). “Control limits for building energy end use based on frequency analysis and quantile regression." Energy Efficiency, published online. DOI: 10.1007/s12053-015-9342-6
  • 28. Energy Exchange: Federal Sustainability for the Next Decade Fault Detection Example: Daylighting Lighting higher than expected Lighting out of range despite full daylighting potential Root Cause: Daylighting controls overridden during repair of ballast and fixtures; controls weren’t reset 6-Nov-20136-Nov-2013
  • 29. Energy Exchange: Federal Sustainability for the Next Decade Fault Detection Example: Lighting Controls Lighting load is too high in evening hours (6–10 PM) Response: Reduce auto-off delays; staff outreach; lessons learned for future lighting system design Multiple Causes: Cleaning staff, individuals working late 1-Jan-2014 5-Apr-2014
  • 30. Is it OFF? Credit: Jennifer Scheib/NREL
  • 31. Energy Exchange: Federal Sustainability for the Next Decade Fault Detection Example: Air Handler Solution: Installation of new evaporative cooling unit to meet local demand, enabling the AHU to turn off at night Problem: Large AHU on all night: manually overridden to provide air and cooling to a few night shift security employees 16-Aug-2013 7-Oct-2013
  • 32. Energy Exchange: Federal Sustainability for the Next Decade Fault Detection Example: PV Inverter Offline PV output too low. Why? Time series suggests inverter outage; offline inverter confirmed via vendor web portal and repair dispatched 20-Mar-2015 20-Mar-2015
  • 33. Energy Exchange: Federal Sustainability for the Next Decade33 Production Tracking
  • 34. Energy Exchange: Federal Sustainability for the Next Decade • Have run 1.15 - 1.35 PUE • Fully containing hot aisle difficult • Custom aisle floor and door seals • Ensure equipment designed for hot aisle containment • 100 kW datacenter load in 2010 • 141 kW January 2015 • Decommissioned older servers • Ensured highest efficiency possible power supplies • Continued consolidation • 123 kW June 2015 Can a Datacenter Use Less Energy Over Time? NREL/PIX17897 Credit:MarjorieSchott/NREL
  • 35. Energy Exchange: Federal Sustainability for the Next Decade • Fix PV faults as soon as they are found – 12% improvements possible • Continued datacenter metric tracking – 1.15 PUE and total 120 kW goals • Lighting controls commissioning – Occupancy sensors, daylighting set points • Wood chip boiler controls improvements – Over 50% natural gas savings planned • Additional PV planned • More thin clients All while trying to fit in another 100 occupants… 35 Plan to return to net positive
  • 36. High Performance Building Operators Owners/Operators Jim Dewey, City of Santa Barbara John Elliott, UC Merced Matt Ellis, Army Jake Gedvilas, NREL Rodney Martin, NASA Scott Poll, NASA Len Pettis, California State University Kevin Rodgers, University of Chicago Jason Sielcken, GSA Darrell Smith, Microsoft Scott Williams, Target Designers and Energy Consultants Porus Antia, Stantec Matt Ganser, Carbon Lighthouse Rob Peña, University of Washington and the Integrated Design Laboratory Zack Rogers, Daylighting Innovations Phil Saieg, McKinstry
  • 37. Resources • General HPB operations process linked by project phase • Present a storyline for all HPB operations key actions (above and beyond current practice) • Unique sections for topics that create a base recipe that can be used by all HPB owners and building types • Examples of unique lessons given to generate motivation and confidence to take action • Setting and requiring energy targets • Procuring an EIS • Procuring MELs • Datacenters • Occupancy and occupant feedback • Closing the loop with action plans https://buildingdata.energy.gov/cbrd/resource/1913
  • 38. Preparing for HPB Operations
  • 39. Thanks and Questions • Shanti Pless • Shanti.pless@nrel.gov • www.nrel.gov/rsf 39