CPM – Critical Path Method
CPM – Critical Path Method
Software Project Management 2 Maria Petridou
• It is determined by adding the times for the activities in each
sequence.
• CPM determines the total calendar time required for the project.
• If activities outside the critical path speed up or slow down (within
limits), the total project time does not change.
• The amount of time that a non-critical activity can be delayed
without delaying the project is called slack-time.
CPM – Critical Path Method
Software Project Management 3 Maria Petridou
 ET – Earliest node time for given activity duration and precedence
relationships
 LT – Latest node time assuming no delays
 ES – Activity earliest start time
 LS – Activity latest start time
 EF – Activity earliest finishing time
 LF – Activity latest finishing time
 Slack Time – Maximum activity delay time
Dummy Activities
Software Project Management 4 Maria Petridou
• Sometimes it is necessary to insert dummy activities (duration
zero) in order to maintain the clarity of the diagram and the
precedence relationships between activities.
• In activity-on-arrow PERT diagrams, each activity must be uniquely
identifiable by its start and end nodes.
• However, sometimes multiple tasks have the same predecessors
and successors.
Dummy Activities
Software Project Management 5 Maria Petridou
Case One
• A task should be uniquely identifiable from its start node and finish
node
 This means that two or more tasks cannot share the same start
and finish nodes
1 2 3 4A D
C
Tasks B and C
have the same
start and finish
nodes
Task D has
immediate
predecessors of
B and C
B
Network Planning Techniques
• Program Evaluation & Review Technique (PERT):
– Developed to manage the Polaris missile project
– Many tasks pushed the boundaries of science &
engineering (tasks’ duration = probabilistic)
• Critical Path Method (CPM):
– Developed to coordinate maintenance projects in the
chemical industry
– A complex undertaking, but individual tasks are routine
(tasks’ duration = deterministic)
PERT and CPM
• Graphically display the precedence
relationships & sequence of activities
• Estimate the project’s duration
• Identify critical activities that cannot be
delayed without delaying the project
• Estimate the amount of slack associated with
non-critical activities
8
Project Activities
in Constructing a House
9
PERT Network for
Constructing a House
Critical Path Method (CPM) Explained

More Related Content

What's hot

Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSHafiz JUNAID
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMMubashir Ali
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method Mkaur01
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsNishant Munjal
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Schedulingsaurabmi2
 
Project Manangement Introduction
Project Manangement IntroductionProject Manangement Introduction
Project Manangement Introductionasim78
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 

What's hot (20)

Pert
PertPert
Pert
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
An introduction to Critical Chain Project Management (CCPM)
An introduction to Critical Chain Project Management (CCPM)An introduction to Critical Chain Project Management (CCPM)
An introduction to Critical Chain Project Management (CCPM)
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Project Manangement Introduction
Project Manangement IntroductionProject Manangement Introduction
Project Manangement Introduction
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
project management
project managementproject management
project management
 

Viewers also liked

Critical path method
Critical path methodCritical path method
Critical path methodShubhi Verma
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)hoang tung
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysistutor2u
 
Critical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueCritical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueJomari Gingo Selibio
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)El Moro
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path PptJeff Hilton
 
Critical path method example by myassignmenthelp
Critical path method example by myassignmenthelpCritical path method example by myassignmenthelp
Critical path method example by myassignmenthelpwww.myassignmenthelp.net
 
Session 4 critical path method upload
Session 4   critical path method uploadSession 4   critical path method upload
Session 4 critical path method uploadArun
 
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisLesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisHoly Angel University
 
Critical Path Analysis Notes
Critical Path Analysis NotesCritical Path Analysis Notes
Critical Path Analysis Notesmattbentley34
 
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pertdjoufack
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path MethodSimplilearn
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)Nikhil Raj
 

Viewers also liked (20)

Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Critical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueCritical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review Technique
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
 
Critical path method example by myassignmenthelp
Critical path method example by myassignmenthelpCritical path method example by myassignmenthelp
Critical path method example by myassignmenthelp
 
Session 4 critical path method upload
Session 4   critical path method uploadSession 4   critical path method upload
Session 4 critical path method upload
 
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisLesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
 
Critical Path Analysis Notes
Critical Path Analysis NotesCritical Path Analysis Notes
Critical Path Analysis Notes
 
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pert
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)
 
Critical path method
Critical path methodCritical path method
Critical path method
 

Similar to Critical Path Method (CPM) Explained

06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxMdSabujHossen2
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking TechniquesAaliButt1
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdfJerryHung19
 
Software Project Mangmement (Lecture 5)
Software Project Mangmement (Lecture 5)Software Project Mangmement (Lecture 5)
Software Project Mangmement (Lecture 5)Syed Muhammad Hammad
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 

Similar to Critical Path Method (CPM) Explained (20)

Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
06 project time management
06  project time management06  project time management
06 project time management
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
lec11.ppt
lec11.pptlec11.ppt
lec11.ppt
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
project network
project networkproject network
project network
 
Bpp 3213 lecture 2
Bpp 3213 lecture 2Bpp 3213 lecture 2
Bpp 3213 lecture 2
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 
Software Project Mangmement (Lecture 5)
Software Project Mangmement (Lecture 5)Software Project Mangmement (Lecture 5)
Software Project Mangmement (Lecture 5)
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 

Recently uploaded

0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 

Recently uploaded (20)

0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 

Critical Path Method (CPM) Explained

  • 1. CPM – Critical Path Method
  • 2. CPM – Critical Path Method Software Project Management 2 Maria Petridou • It is determined by adding the times for the activities in each sequence. • CPM determines the total calendar time required for the project. • If activities outside the critical path speed up or slow down (within limits), the total project time does not change. • The amount of time that a non-critical activity can be delayed without delaying the project is called slack-time.
  • 3. CPM – Critical Path Method Software Project Management 3 Maria Petridou  ET – Earliest node time for given activity duration and precedence relationships  LT – Latest node time assuming no delays  ES – Activity earliest start time  LS – Activity latest start time  EF – Activity earliest finishing time  LF – Activity latest finishing time  Slack Time – Maximum activity delay time
  • 4. Dummy Activities Software Project Management 4 Maria Petridou • Sometimes it is necessary to insert dummy activities (duration zero) in order to maintain the clarity of the diagram and the precedence relationships between activities. • In activity-on-arrow PERT diagrams, each activity must be uniquely identifiable by its start and end nodes. • However, sometimes multiple tasks have the same predecessors and successors.
  • 5. Dummy Activities Software Project Management 5 Maria Petridou Case One • A task should be uniquely identifiable from its start node and finish node  This means that two or more tasks cannot share the same start and finish nodes 1 2 3 4A D C Tasks B and C have the same start and finish nodes Task D has immediate predecessors of B and C B
  • 6. Network Planning Techniques • Program Evaluation & Review Technique (PERT): – Developed to manage the Polaris missile project – Many tasks pushed the boundaries of science & engineering (tasks’ duration = probabilistic) • Critical Path Method (CPM): – Developed to coordinate maintenance projects in the chemical industry – A complex undertaking, but individual tasks are routine (tasks’ duration = deterministic)
  • 7. PERT and CPM • Graphically display the precedence relationships & sequence of activities • Estimate the project’s duration • Identify critical activities that cannot be delayed without delaying the project • Estimate the amount of slack associated with non-critical activities