SlideShare a Scribd company logo
1 of 15
Installation of Triethylene Glycol Contactor
Overhead Knock Out Drum in the Propylene
Carbonate system at Process Plant Specialists
(P.P.S), Savonetta
General
Manager

Ornella Ramsarran

Process
Consultant

Steffon Mohammed

Chief
Engineers

Dylan
Dhanpaul

Crystalgail
Ali Khan

Monique
LaFoucade

19-Nov-13

2






To define the activities and equipment required for
the installation and commission of a Triethylene
Glycol (TEG) Knock Out (K.O) Drum.
TEG K.O Drum serves to monitor and control the
level of glycol.
Plant Operation Department projected precise and
minimal cost of the project.

19-Nov-13

3
Outline of presentation:
 The Problem: Carryover of TEG into the PC
system.
 Implemented Solution: TEG Knockout Drum
 Details of Solution:
I. Procedure
II. Cost
III. Benefits

19-Nov-13

4










To determine the problem experienced at the Savonetta
plant, several studies and tests were conducted.
It was concluded that TEG was being carried over to the
Propylene Carbonate (PC) system.
The operating temperatures of the TEG contactors were
causing an increased viscosity of the TEG.
The increased viscosity prevented the elimination of TEG prior
to the PC system entrance. The TEG was then able to escape
into the PC system.

It was found that continuous degradation of the TEG was
occurring. This gave rise to large amounts of suspended
solids in the glycol.
19-Nov-13

5




This resulted in a deficiency in the CO2 removal process in the
PC system increasing the overall temperatures within the
methanator system.
Through this contamination an increased consumption of TEG
was being experienced. Also PC losses and general excess
expenditure was being suffered.



Due to the deficiency in the PC system an average production
loss of 15 tons of ammonia was being experienced daily.



Historical data of TEG, PC and H2O were observed.



It was confirmed that a loss of 90 drums of TEG averaging a
value of US$36,000.00 was being suffered yearly.
Remediation costs of the PC in the region of US$20,0000.00
yearly was also being suffered.

19-Nov-13

6








After in- depth study and analysis the origin of the problems
were found to be within the Glycol Stripping Air system of the
PC system.
It was concluded that a TEG Knockout Drum system would be
a successful implementation to the PC system.
To implement the new system properly, specifics of
pipes, nozzles and valves with high pressure. Conditions have
been calculated and sized to be installed prior to initializing
the TEG Knockout drum.
All calculations were done at an earlier time before the arrival
of the drum, so the incorporation of the new upgrade into the
existing system was an uninterrupted process.

19-Nov-13

7










Performed inspection checks on the existing system.
Inlet and outlet valves were installed before the plant was
brought back up.
Support landing was constructed at the work shop to secure
and mount the K.O. Drum for smooth operation and
maintenance.
Installation was readily done downstream to the existing
glycol contactor without upsetting the already existing
system production.
The TEG K.O. Drum level control system was equipped with
high and low alarm switches.
19-Nov-13

8
DETAILS OF SOLUTION

FIGURE 1: Shows design view of TEG Contactor K.O Drum
19-Nov-13

9
DETAILS OF SOLUTION
Pressure Saftey
Valve / Manway

Inlet
A

Outlet
Dry air leaves and goes to
CO2 Stripper

Dry air and TEG enters
¼” Weep Hole
below inside Nozzle

Nameplate

Removable Vane Type

LC/LG Bridle
Removable
Dacron Mesh
Drain

LC/LG Bridle

HORIZONTAL CONTACTOR KNOCKOUT DRUM
42” OD X 10 ‘ × 150 PSIG

Cleanout
w/PLG

EST WT: 4,400 LBS

FIGURE 2: SHOWS TEG K.O DRUM
19-Nov-13

10
TABLE: Shows Project Upgrade Economics
Production

Cost

MT / day increase in
production
TOTAL increase in
production for year
Contribution 1
SAVING /Year

75
$

2,738.00

$

Production

Cost/Value

Drums PC saving
/year

27.00

Per Drum

$

88.50

675.00

$ 18,225.00

$ 242,268.75
IRR –
5 Year Forecast

Drums of Glycol saving
/year
Per Drum

20.00
$

95%

NPV After 5 Years

$ 514,737.72

PAYBACK PERIOD

13 MONTHS

525.00

Savings /year

$ 10,500.00

Total Savings Per Year

$ 270,993.75
19-Nov-13

11
Main Benefits Gained by Usage of the TEG K.O Drum:


Reduced the amount of process gas vented.



With the vessel in series the glycol and moisture carryover
was minimal.



With the contactor bypassed, on–line cleaning of its internals
can be performed without affecting the plant operation.



The piping has been configured for the vessel to operate in
series as well as bypass for the existing contactor.



Production increased by 15 tons per day.



Payback Time of 13 months .



Production increased by 75 metric tons per day with
$270,000.00 saving per year.
19-Nov-13

12








Plant Operation Department guarantees that the project has
been completed in accordance with the requirements of the
Contract.
We guarantee the project to be free of defects in
workmanship, equipment and materials.

Our department agrees to repair or replace any and all
components of the project, that may have been damaged or
displaced within a two (2) year period.
No expense whatsoever will be charged to Process Plant
Specialists under the warranty.

19-Nov-13

13






Problem: TEG was being carried over to the PC system.

Solution: Relevant tests and calculations were meticulously
carried out in order to begin implementation of the TEG K.O
Drum system.
Benefit: The Savonetta plant was able to cut financial losses
and excess expenditure, thanks to the initial capital invested
in the TEG K.O Drum.

19-Nov-13

14
19-Nov-13

15

More Related Content

What's hot

Fjell Technology Oil & Gas - A passion for innovation!
Fjell Technology Oil & Gas - A passion for innovation!Fjell Technology Oil & Gas - A passion for innovation!
Fjell Technology Oil & Gas - A passion for innovation!Njaal R. Soleng
 
CV timothy o'donoghue 2016
CV timothy o'donoghue 2016CV timothy o'donoghue 2016
CV timothy o'donoghue 2016timmy o'donoghue
 
Coal gen 2011 wet fgd performance upgrade at b.l. england unit 2
Coal gen 2011   wet fgd performance upgrade at b.l. england unit 2Coal gen 2011   wet fgd performance upgrade at b.l. england unit 2
Coal gen 2011 wet fgd performance upgrade at b.l. england unit 2NAES Corporation
 
Arun Goyle resume
Arun Goyle resumeArun Goyle resume
Arun Goyle resumeArun Goyle
 
curriculum vitae
curriculum vitaecurriculum vitae
curriculum vitaeMark Wagner
 
West.Robert.resume.2016-02
West.Robert.resume.2016-02West.Robert.resume.2016-02
West.Robert.resume.2016-02Robert West
 
Case Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent SolventsCase Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent SolventsKoch Modular Process Systems, LLC.
 
2016 Sales Brochure
2016 Sales Brochure2016 Sales Brochure
2016 Sales BrochureRocky Buras
 
Critical Variables in Catalytic Reforming and Unit Monitoring Best Practices
Critical Variables in Catalytic Reforming and Unit Monitoring Best PracticesCritical Variables in Catalytic Reforming and Unit Monitoring Best Practices
Critical Variables in Catalytic Reforming and Unit Monitoring Best PracticesGerard B. Hawkins
 
John Benson CV 2016 1
John Benson CV 2016 1John Benson CV 2016 1
John Benson CV 2016 1John Benson
 

What's hot (17)

Fjell Technology Oil & Gas - A passion for innovation!
Fjell Technology Oil & Gas - A passion for innovation!Fjell Technology Oil & Gas - A passion for innovation!
Fjell Technology Oil & Gas - A passion for innovation!
 
CV timothy o'donoghue 2016
CV timothy o'donoghue 2016CV timothy o'donoghue 2016
CV timothy o'donoghue 2016
 
SHREYAS__SABNIS CV
SHREYAS__SABNIS CVSHREYAS__SABNIS CV
SHREYAS__SABNIS CV
 
OHA LATEST CURRICULLUM
OHA LATEST CURRICULLUMOHA LATEST CURRICULLUM
OHA LATEST CURRICULLUM
 
Coal gen 2011 wet fgd performance upgrade at b.l. england unit 2
Coal gen 2011   wet fgd performance upgrade at b.l. england unit 2Coal gen 2011   wet fgd performance upgrade at b.l. england unit 2
Coal gen 2011 wet fgd performance upgrade at b.l. england unit 2
 
Arun Goyle resume
Arun Goyle resumeArun Goyle resume
Arun Goyle resume
 
Experience
ExperienceExperience
Experience
 
M.reda cv
M.reda cvM.reda cv
M.reda cv
 
curriculum vitae
curriculum vitaecurriculum vitae
curriculum vitae
 
West.Robert.resume.2016-02
West.Robert.resume.2016-02West.Robert.resume.2016-02
West.Robert.resume.2016-02
 
vijay cv
vijay cvvijay cv
vijay cv
 
Case Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent SolventsCase Study: Modular Distillation System to Recover Spent Solvents
Case Study: Modular Distillation System to Recover Spent Solvents
 
khaled-2
khaled-2khaled-2
khaled-2
 
2016 Sales Brochure
2016 Sales Brochure2016 Sales Brochure
2016 Sales Brochure
 
Critical Variables in Catalytic Reforming and Unit Monitoring Best Practices
Critical Variables in Catalytic Reforming and Unit Monitoring Best PracticesCritical Variables in Catalytic Reforming and Unit Monitoring Best Practices
Critical Variables in Catalytic Reforming and Unit Monitoring Best Practices
 
John Benson CV 2016 1
John Benson CV 2016 1John Benson CV 2016 1
John Benson CV 2016 1
 
BDSResume1
BDSResume1BDSResume1
BDSResume1
 

Viewers also liked

Natural gas dehydration processes
Natural gas dehydration processesNatural gas dehydration processes
Natural gas dehydration processesdeltapuri
 
Sucker rod pumping short course!!! ~downhole diagnostic
Sucker rod pumping short course!!!   ~downhole diagnosticSucker rod pumping short course!!!   ~downhole diagnostic
Sucker rod pumping short course!!! ~downhole diagnosticenLightNme888
 
Dehydration and Sweetening of Natural Gas
Dehydration and Sweetening of Natural GasDehydration and Sweetening of Natural Gas
Dehydration and Sweetening of Natural GasMuhammad Hanif
 
NATURAL GAS DEHYDRATION
NATURAL GAS DEHYDRATION NATURAL GAS DEHYDRATION
NATURAL GAS DEHYDRATION Ahmed Shoman
 
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide Gerard B. Hawkins
 

Viewers also liked (7)

Esperpento
EsperpentoEsperpento
Esperpento
 
Natural gas dehydration processes
Natural gas dehydration processesNatural gas dehydration processes
Natural gas dehydration processes
 
Sucker rod pumping short course!!! ~downhole diagnostic
Sucker rod pumping short course!!!   ~downhole diagnosticSucker rod pumping short course!!!   ~downhole diagnostic
Sucker rod pumping short course!!! ~downhole diagnostic
 
Dehydration and Sweetening of Natural Gas
Dehydration and Sweetening of Natural GasDehydration and Sweetening of Natural Gas
Dehydration and Sweetening of Natural Gas
 
NATURAL GAS DEHYDRATION
NATURAL GAS DEHYDRATION NATURAL GAS DEHYDRATION
NATURAL GAS DEHYDRATION
 
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
 
Liquid recovery
Liquid recoveryLiquid recovery
Liquid recovery
 

Similar to P.P.S technical presentation

Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008 Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008 tasander
 
Somasundarreddy2020
Somasundarreddy2020Somasundarreddy2020
Somasundarreddy2020parry2125
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaUdhayakumar Venkataraman
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationAmeya Margaj
 
En Pres Cryogenic 0710 V2
En Pres Cryogenic 0710 V2En Pres Cryogenic 0710 V2
En Pres Cryogenic 0710 V2eurolinx
 
2016 SENTRO-Tech Online Chemical Cleaning_5-2016
2016 SENTRO-Tech Online Chemical Cleaning_5-20162016 SENTRO-Tech Online Chemical Cleaning_5-2016
2016 SENTRO-Tech Online Chemical Cleaning_5-2016SENTRO TECHNOLOGIES
 
TA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation OverhaulTA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation OverhaulMuhammad Asad Ullah
 
96924703 performance-monitoring-for-gas-turbine
96924703 performance-monitoring-for-gas-turbine96924703 performance-monitoring-for-gas-turbine
96924703 performance-monitoring-for-gas-turbinemanojg1990
 
A report on Economic Feasibility for a chemical Process.(For details on Appen...
A report on Economic Feasibility for a chemical Process.(For details on Appen...A report on Economic Feasibility for a chemical Process.(For details on Appen...
A report on Economic Feasibility for a chemical Process.(For details on Appen...Parag Patil
 
Dalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfDalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfBlentBulut5
 
ACARP project to industrialise wall-flow DPF technology for diesel engines us...
ACARP project to industrialise wall-flow DPF technology for diesel engines us...ACARP project to industrialise wall-flow DPF technology for diesel engines us...
ACARP project to industrialise wall-flow DPF technology for diesel engines us...NSW Environment and Planning
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic processsimachem
 
Steam turbine performance & condition assessment (Case Study)
Steam turbine performance & condition assessment (Case Study)Steam turbine performance & condition assessment (Case Study)
Steam turbine performance & condition assessment (Case Study)Pichai Chaibamrung
 
EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011abughaws
 
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
Boiler Modification for SHR & Reliability Improvement  SSL (IPP)Boiler Modification for SHR & Reliability Improvement  SSL (IPP)
Boiler Modification for SHR & Reliability Improvement SSL (IPP)Ashok Yadav
 

Similar to P.P.S technical presentation (20)

11-IAGT-202_paper
11-IAGT-202_paper11-IAGT-202_paper
11-IAGT-202_paper
 
Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008 Toronto solvent reduction esr presentation 7 15-2008
Toronto solvent reduction esr presentation 7 15-2008
 
Somasundarreddy2020
Somasundarreddy2020Somasundarreddy2020
Somasundarreddy2020
 
Nikkiso-PDF
Nikkiso-PDFNikkiso-PDF
Nikkiso-PDF
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performa
 
CNJ Career Path
CNJ Career PathCNJ Career Path
CNJ Career Path
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentation
 
En Pres Cryogenic 0710 V2
En Pres Cryogenic 0710 V2En Pres Cryogenic 0710 V2
En Pres Cryogenic 0710 V2
 
2016 SENTRO-Tech Online Chemical Cleaning_5-2016
2016 SENTRO-Tech Online Chemical Cleaning_5-20162016 SENTRO-Tech Online Chemical Cleaning_5-2016
2016 SENTRO-Tech Online Chemical Cleaning_5-2016
 
LinkedIn
LinkedInLinkedIn
LinkedIn
 
TA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation OverhaulTA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation Overhaul
 
96924703 performance-monitoring-for-gas-turbine
96924703 performance-monitoring-for-gas-turbine96924703 performance-monitoring-for-gas-turbine
96924703 performance-monitoring-for-gas-turbine
 
A report on Economic Feasibility for a chemical Process.(For details on Appen...
A report on Economic Feasibility for a chemical Process.(For details on Appen...A report on Economic Feasibility for a chemical Process.(For details on Appen...
A report on Economic Feasibility for a chemical Process.(For details on Appen...
 
Dalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfDalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdf
 
ACARP project to industrialise wall-flow DPF technology for diesel engines us...
ACARP project to industrialise wall-flow DPF technology for diesel engines us...ACARP project to industrialise wall-flow DPF technology for diesel engines us...
ACARP project to industrialise wall-flow DPF technology for diesel engines us...
 
Fugitive Emissions
Fugitive EmissionsFugitive Emissions
Fugitive Emissions
 
Compare cryogenic process
Compare cryogenic processCompare cryogenic process
Compare cryogenic process
 
Steam turbine performance & condition assessment (Case Study)
Steam turbine performance & condition assessment (Case Study)Steam turbine performance & condition assessment (Case Study)
Steam turbine performance & condition assessment (Case Study)
 
EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011
 
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
Boiler Modification for SHR & Reliability Improvement  SSL (IPP)Boiler Modification for SHR & Reliability Improvement  SSL (IPP)
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
 

Recently uploaded

Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 

Recently uploaded (20)

Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 

P.P.S technical presentation

  • 1. Installation of Triethylene Glycol Contactor Overhead Knock Out Drum in the Propylene Carbonate system at Process Plant Specialists (P.P.S), Savonetta
  • 3.    To define the activities and equipment required for the installation and commission of a Triethylene Glycol (TEG) Knock Out (K.O) Drum. TEG K.O Drum serves to monitor and control the level of glycol. Plant Operation Department projected precise and minimal cost of the project. 19-Nov-13 3
  • 4. Outline of presentation:  The Problem: Carryover of TEG into the PC system.  Implemented Solution: TEG Knockout Drum  Details of Solution: I. Procedure II. Cost III. Benefits 19-Nov-13 4
  • 5.      To determine the problem experienced at the Savonetta plant, several studies and tests were conducted. It was concluded that TEG was being carried over to the Propylene Carbonate (PC) system. The operating temperatures of the TEG contactors were causing an increased viscosity of the TEG. The increased viscosity prevented the elimination of TEG prior to the PC system entrance. The TEG was then able to escape into the PC system. It was found that continuous degradation of the TEG was occurring. This gave rise to large amounts of suspended solids in the glycol. 19-Nov-13 5
  • 6.   This resulted in a deficiency in the CO2 removal process in the PC system increasing the overall temperatures within the methanator system. Through this contamination an increased consumption of TEG was being experienced. Also PC losses and general excess expenditure was being suffered.  Due to the deficiency in the PC system an average production loss of 15 tons of ammonia was being experienced daily.  Historical data of TEG, PC and H2O were observed.  It was confirmed that a loss of 90 drums of TEG averaging a value of US$36,000.00 was being suffered yearly. Remediation costs of the PC in the region of US$20,0000.00 yearly was also being suffered. 19-Nov-13 6
  • 7.     After in- depth study and analysis the origin of the problems were found to be within the Glycol Stripping Air system of the PC system. It was concluded that a TEG Knockout Drum system would be a successful implementation to the PC system. To implement the new system properly, specifics of pipes, nozzles and valves with high pressure. Conditions have been calculated and sized to be installed prior to initializing the TEG Knockout drum. All calculations were done at an earlier time before the arrival of the drum, so the incorporation of the new upgrade into the existing system was an uninterrupted process. 19-Nov-13 7
  • 8.      Performed inspection checks on the existing system. Inlet and outlet valves were installed before the plant was brought back up. Support landing was constructed at the work shop to secure and mount the K.O. Drum for smooth operation and maintenance. Installation was readily done downstream to the existing glycol contactor without upsetting the already existing system production. The TEG K.O. Drum level control system was equipped with high and low alarm switches. 19-Nov-13 8
  • 9. DETAILS OF SOLUTION FIGURE 1: Shows design view of TEG Contactor K.O Drum 19-Nov-13 9
  • 10. DETAILS OF SOLUTION Pressure Saftey Valve / Manway Inlet A Outlet Dry air leaves and goes to CO2 Stripper Dry air and TEG enters ¼” Weep Hole below inside Nozzle Nameplate Removable Vane Type LC/LG Bridle Removable Dacron Mesh Drain LC/LG Bridle HORIZONTAL CONTACTOR KNOCKOUT DRUM 42” OD X 10 ‘ × 150 PSIG Cleanout w/PLG EST WT: 4,400 LBS FIGURE 2: SHOWS TEG K.O DRUM 19-Nov-13 10
  • 11. TABLE: Shows Project Upgrade Economics Production Cost MT / day increase in production TOTAL increase in production for year Contribution 1 SAVING /Year 75 $ 2,738.00 $ Production Cost/Value Drums PC saving /year 27.00 Per Drum $ 88.50 675.00 $ 18,225.00 $ 242,268.75 IRR – 5 Year Forecast Drums of Glycol saving /year Per Drum 20.00 $ 95% NPV After 5 Years $ 514,737.72 PAYBACK PERIOD 13 MONTHS 525.00 Savings /year $ 10,500.00 Total Savings Per Year $ 270,993.75 19-Nov-13 11
  • 12. Main Benefits Gained by Usage of the TEG K.O Drum:  Reduced the amount of process gas vented.  With the vessel in series the glycol and moisture carryover was minimal.  With the contactor bypassed, on–line cleaning of its internals can be performed without affecting the plant operation.  The piping has been configured for the vessel to operate in series as well as bypass for the existing contactor.  Production increased by 15 tons per day.  Payback Time of 13 months .  Production increased by 75 metric tons per day with $270,000.00 saving per year. 19-Nov-13 12
  • 13.     Plant Operation Department guarantees that the project has been completed in accordance with the requirements of the Contract. We guarantee the project to be free of defects in workmanship, equipment and materials. Our department agrees to repair or replace any and all components of the project, that may have been damaged or displaced within a two (2) year period. No expense whatsoever will be charged to Process Plant Specialists under the warranty. 19-Nov-13 13
  • 14.    Problem: TEG was being carried over to the PC system. Solution: Relevant tests and calculations were meticulously carried out in order to begin implementation of the TEG K.O Drum system. Benefit: The Savonetta plant was able to cut financial losses and excess expenditure, thanks to the initial capital invested in the TEG K.O Drum. 19-Nov-13 14