SlideShare a Scribd company logo
1 of 17
Selection of Roof Casting Formwork
Systems for the Bird
Island Project: Case Study
Presentors:
Muhammad Umar nazir (cn-015)
Imran naeem (cn-012)
Selection of Roof Casting Formwork Systems for the
Bird
Island Project: Case Study
• Authors:
Tariq Abdelhamid, Ph.D
Mohamed El-Gafy, Ph.D, P.E
Panagiotis Mitropoulos, Ph.D
• JOURNAL:
PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND
CONSTRUCTION © ASCE / NOVEMBER 2009
Contents
• Abstract
• Scope
• Summary
• Objective
• Methodology
• Literature Review
• Data Analysis
• Conclusions
ABSTRACT
• Formwork is a major contributor to profitability—or the lack of it—on most large
and complex concrete jobs.
• Formwork has major consequences for the project schedule, as well as all related
trades, such as ironworkers and cement finishers.
• Consequently, selecting a formwork system and planning its field operations must
consider the effects of the system on the overall project.
• This may result in significant difficulties in meeting the project requirements.
• The paper illustrates the complexities involved in the selection and deployment of a
formwork
SCOPE
• This paper reports on an in-depth study of the formwork system selection
problem on the Bird Island Flats Tunnel project.
• The project is a part of the Central Artery/Tunnel project in Boston,
Massachusetts.
SUMMARY
• The challenge on this $290 million project was the budget and schedule requirements for the
tunnel roofs.
• The width and thickness of the roofs were on average 18.29 m 60 ft and 2.44 m 8 ft,
respectively.
• The conventional shoring methods were not able to keep the project on time for critical
interim milestones as well as on budget.
• The alternative forming systems available did not provide a solution because of the time
and effort required for setup and takedown operations.
• The management team solicited proposals from formwork manufacturers, and chose the
system from CONESCO Industries.
OBJECTIVE
• This study has two objectives:
• First to identify the issues involved in the selection and
sequencing of a custom-made formwork system
• Second to formulate a detailed analysis method to
improve decision-making.
METHODOLOGY
• The paper consists of two parts.
• The first part describes the project and presents the issues involved in the selection
of the formwork system. It identifies the complexities of the decisions that faced
the construction team, and describes how the selection was made and how the final
decision came about.
• The second part presents analytical methods and techniques to support the
decision-making process. A detailed analysis and comparison of formwork systems
is performed that accounts for all the key formwork parameters. Such analysis is
necessary in order to select the best system for the project.
LITERATURE REVIEW
• Conventional System
The conventional system available consisted of a number of aluminum joists
that are supported by standard I beams. The concrete is poured against 2.3 cm
3/4 in. plywood that is placed on the aluminum joist. The concrete, plywood,
aluminum joists, and standard I beams are supported on steel shoring legs. The
system is very similar to scaffolds used for work done at high elevations. The
systems available were categorized by the capacity of the shoring legs. 10, 25,
and 100 kip/leg shoring systems were available. The cross section and layout of
such a system is shown in Fig.
CONVENTIONAL FORMWORK
LITERATURE REVIEW
• CONESCO Roof Casting Machines
• The winning proposal for a formwork system called the “Roof Casting Machines”
was submitted by the CONESCO Corporation. Each Roof Casting Machine
consisted of two major components, a self-propelled traveler and the form set. The
traveler is a three-dimensional rectangular frame equipped with a gasoline engine
which makes it able to transport the custom form set to its desired location.
Hydraulic cylinders on the traveler are used for initial horizontal and vertical
adjustments of the form sets. The form set is also equipped with hydraulic cylinders
for further adjustment. A detailed illustration of the traveler and form set is shown
in Fig.
CONESCO ROOF CASTING MACHINE
Machine Types with Height and Width Changes
MACHINE
TYPE
HEIGHT
(meters)
WIDTH
(meters)
TRAVELLER
MIN MAX MIN MAX
I A 7.43 9.54 11.43 15.70 I A
I B 5.53 7.56 11.43 15.70 I B or II B
II A 7.41 7.60 12.95 22.71 II A or II B
II B 5.18 9.34 12.80 22.56 II B
III 6.28 9.05 17.53 28.50 III
CONESCO ROOF CASTING MACHINE
ANALYSIS
• M/O started the system evaluation process by comparing the available
conventional shoring systems and the CONESCO casting machines.
• This comparison was based on operating cost, acquisition cost, technical
performance of the systems, and ability to adjust formwork to tunnel
dimensions.
• The records we have state $4,772,300 in net savings, and 36 weeks saved in
schedule time, when comparing the conventional system to the CONESCO
casting machines
ANALYSIS
CONVENTIONAL CONESCO DIFFERENCE
COST ($) 1,500,000 3,500,000 -2,000,000
PRODUCTION
(m2/MH)
.42 1.62 1.2
MAN HOURS (MH)
REQUIRED
164,900 28,473 136427
TIME (WEEKS) 86 50 36 (8 months)
MH COST (50$/MH) 8,245,000 1,423,650 6,821,350
TOTAL COST ($) 9,745,000 4,923,650 4,821,350
CONCLUSIONS
• The case study has focused on time and cost related to the use of three different
formwork systems.
• A time-cost trade–off analysis was also followed when investigating alternative
sequencing schemes for the one system that was selected using computer
simulation.
• Contractors in projects involving nonconventional formwork must carefully
consider the implications of formwork systems selection and sequencing of
concrete casting operations.
• The use of simulation in this study reveals its utility to a long-term and
comprehensive approach to planning and management.

More Related Content

What's hot

Design of waste heat driven vapour adsorption cooling system for vehicle air ...
Design of waste heat driven vapour adsorption cooling system for vehicle air ...Design of waste heat driven vapour adsorption cooling system for vehicle air ...
Design of waste heat driven vapour adsorption cooling system for vehicle air ...
eSAT Journals
 
M3C3098_LYRAS_POSTER
M3C3098_LYRAS_POSTERM3C3098_LYRAS_POSTER
M3C3098_LYRAS_POSTER
Vasilis Lyras
 
Six week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc LudhianaSix week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc Ludhiana
Gurjant Singh
 
Structural Component Design Optimization for Additive Manufacture
Structural Component Design Optimization for Additive ManufactureStructural Component Design Optimization for Additive Manufacture
Structural Component Design Optimization for Additive Manufacture
Altair
 

What's hot (20)

IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
 
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981) OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
 
Design of waste heat driven vapour adsorption cooling system for vehicle air ...
Design of waste heat driven vapour adsorption cooling system for vehicle air ...Design of waste heat driven vapour adsorption cooling system for vehicle air ...
Design of waste heat driven vapour adsorption cooling system for vehicle air ...
 
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
 
Design steps of structure.
Design steps of structure.Design steps of structure.
Design steps of structure.
 
Chapter02.structural design using staad pro
Chapter02.structural design using staad proChapter02.structural design using staad pro
Chapter02.structural design using staad pro
 
Company profile
Company profileCompany profile
Company profile
 
Seismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codesSeismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codes
 
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
Dbr kashmiri gate
Dbr kashmiri gateDbr kashmiri gate
Dbr kashmiri gate
 
Analysis and design of pre engineered building using is 800:2007 and Internat...
Analysis and design of pre engineered building using is 800:2007 and Internat...Analysis and design of pre engineered building using is 800:2007 and Internat...
Analysis and design of pre engineered building using is 800:2007 and Internat...
 
Analysis of warehouse in staad pro.
Analysis of warehouse in staad pro. Analysis of warehouse in staad pro.
Analysis of warehouse in staad pro.
 
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
 
construction management
construction managementconstruction management
construction management
 
M3C3098_LYRAS_POSTER
M3C3098_LYRAS_POSTERM3C3098_LYRAS_POSTER
M3C3098_LYRAS_POSTER
 
Introduction to prefabricated structures
Introduction to prefabricated structuresIntroduction to prefabricated structures
Introduction to prefabricated structures
 
Six week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc LudhianaSix week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc Ludhiana
 
Structural Component Design Optimization for Additive Manufacture
Structural Component Design Optimization for Additive ManufactureStructural Component Design Optimization for Additive Manufacture
Structural Component Design Optimization for Additive Manufacture
 
IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...
IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...
IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...
 

Similar to Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study

CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 
July2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKJuly2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORK
Sameer Malvankar
 
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
ijtsrd
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017
Czero
 

Similar to Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study (20)

Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
 
Final project report
Final project reportFinal project report
Final project report
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
July2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKJuly2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORK
 
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
 
Resume 5 13 16 months
Resume 5 13 16 monthsResume 5 13 16 months
Resume 5 13 16 months
 
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdf
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdf
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
 
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss BuildingComparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
 
ADCS Full ppt-Lec 1-5 - Copy.pptx
ADCS Full ppt-Lec 1-5 - Copy.pptxADCS Full ppt-Lec 1-5 - Copy.pptx
ADCS Full ppt-Lec 1-5 - Copy.pptx
 
IRJET- Temperature Effect on Concrete Bridge
IRJET-  	  Temperature Effect on Concrete BridgeIRJET-  	  Temperature Effect on Concrete Bridge
IRJET- Temperature Effect on Concrete Bridge
 
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017
 
IRJET- Study & Improvement of Design and Construction Methodology of Precast ...
IRJET- Study & Improvement of Design and Construction Methodology of Precast ...IRJET- Study & Improvement of Design and Construction Methodology of Precast ...
IRJET- Study & Improvement of Design and Construction Methodology of Precast ...
 
An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...
An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...
An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...
 

Recently uploaded

Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
instagramfab782445
 
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
nirzagarg
 
Peaches App development presentation deck
Peaches App development presentation deckPeaches App development presentation deck
Peaches App development presentation deck
tbatkhuu1
 
B. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdfB. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdf
University of Wisconsin-Milwaukee
 
call girls in Dakshinpuri (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
call girls in Dakshinpuri  (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️call girls in Dakshinpuri  (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
call girls in Dakshinpuri (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Editorial design Magazine design project.pdf
Editorial design Magazine design project.pdfEditorial design Magazine design project.pdf
Editorial design Magazine design project.pdf
tbatkhuu1
 
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
amitlee9823
 
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
amitlee9823
 

Recently uploaded (20)

Case Study of Hotel Taj Vivanta, Pune
Case Study of Hotel Taj Vivanta, PuneCase Study of Hotel Taj Vivanta, Pune
Case Study of Hotel Taj Vivanta, Pune
 
Q4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentationQ4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentation
 
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
 
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
 
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
 
Peaches App development presentation deck
Peaches App development presentation deckPeaches App development presentation deck
Peaches App development presentation deck
 
Sector 105, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 105, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 105, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 105, Noida Call girls :8448380779 Model Escorts | 100% verified
 
Booking open Available Pune Call Girls Kirkatwadi 6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Kirkatwadi  6297143586 Call Hot Indian...Booking open Available Pune Call Girls Kirkatwadi  6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Kirkatwadi 6297143586 Call Hot Indian...
 
B. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdfB. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdf
 
call girls in Dakshinpuri (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
call girls in Dakshinpuri  (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️call girls in Dakshinpuri  (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
call girls in Dakshinpuri (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
 
Editorial design Magazine design project.pdf
Editorial design Magazine design project.pdfEditorial design Magazine design project.pdf
Editorial design Magazine design project.pdf
 
8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available
8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available
8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available
 
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
Hire 💕 8617697112 Meerut Call Girls Service Call Girls Agency
Hire 💕 8617697112 Meerut Call Girls Service Call Girls AgencyHire 💕 8617697112 Meerut Call Girls Service Call Girls Agency
Hire 💕 8617697112 Meerut Call Girls Service Call Girls Agency
 
Top Rated Pune Call Girls Saswad ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Saswad ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Saswad ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Saswad ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
 
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
 
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Basapura ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
 
VIP Model Call Girls Kalyani Nagar ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Kalyani Nagar ( Pune ) Call ON 8005736733 Starting From ...VIP Model Call Girls Kalyani Nagar ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Kalyani Nagar ( Pune ) Call ON 8005736733 Starting From ...
 
Sweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptxSweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptx
 

Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study

  • 1. Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study Presentors: Muhammad Umar nazir (cn-015) Imran naeem (cn-012)
  • 2. Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study • Authors: Tariq Abdelhamid, Ph.D Mohamed El-Gafy, Ph.D, P.E Panagiotis Mitropoulos, Ph.D • JOURNAL: PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION © ASCE / NOVEMBER 2009
  • 3. Contents • Abstract • Scope • Summary • Objective • Methodology • Literature Review • Data Analysis • Conclusions
  • 4. ABSTRACT • Formwork is a major contributor to profitability—or the lack of it—on most large and complex concrete jobs. • Formwork has major consequences for the project schedule, as well as all related trades, such as ironworkers and cement finishers. • Consequently, selecting a formwork system and planning its field operations must consider the effects of the system on the overall project. • This may result in significant difficulties in meeting the project requirements. • The paper illustrates the complexities involved in the selection and deployment of a formwork
  • 5. SCOPE • This paper reports on an in-depth study of the formwork system selection problem on the Bird Island Flats Tunnel project. • The project is a part of the Central Artery/Tunnel project in Boston, Massachusetts.
  • 6. SUMMARY • The challenge on this $290 million project was the budget and schedule requirements for the tunnel roofs. • The width and thickness of the roofs were on average 18.29 m 60 ft and 2.44 m 8 ft, respectively. • The conventional shoring methods were not able to keep the project on time for critical interim milestones as well as on budget. • The alternative forming systems available did not provide a solution because of the time and effort required for setup and takedown operations. • The management team solicited proposals from formwork manufacturers, and chose the system from CONESCO Industries.
  • 7. OBJECTIVE • This study has two objectives: • First to identify the issues involved in the selection and sequencing of a custom-made formwork system • Second to formulate a detailed analysis method to improve decision-making.
  • 8. METHODOLOGY • The paper consists of two parts. • The first part describes the project and presents the issues involved in the selection of the formwork system. It identifies the complexities of the decisions that faced the construction team, and describes how the selection was made and how the final decision came about. • The second part presents analytical methods and techniques to support the decision-making process. A detailed analysis and comparison of formwork systems is performed that accounts for all the key formwork parameters. Such analysis is necessary in order to select the best system for the project.
  • 9. LITERATURE REVIEW • Conventional System The conventional system available consisted of a number of aluminum joists that are supported by standard I beams. The concrete is poured against 2.3 cm 3/4 in. plywood that is placed on the aluminum joist. The concrete, plywood, aluminum joists, and standard I beams are supported on steel shoring legs. The system is very similar to scaffolds used for work done at high elevations. The systems available were categorized by the capacity of the shoring legs. 10, 25, and 100 kip/leg shoring systems were available. The cross section and layout of such a system is shown in Fig.
  • 11. LITERATURE REVIEW • CONESCO Roof Casting Machines • The winning proposal for a formwork system called the “Roof Casting Machines” was submitted by the CONESCO Corporation. Each Roof Casting Machine consisted of two major components, a self-propelled traveler and the form set. The traveler is a three-dimensional rectangular frame equipped with a gasoline engine which makes it able to transport the custom form set to its desired location. Hydraulic cylinders on the traveler are used for initial horizontal and vertical adjustments of the form sets. The form set is also equipped with hydraulic cylinders for further adjustment. A detailed illustration of the traveler and form set is shown in Fig.
  • 13. Machine Types with Height and Width Changes MACHINE TYPE HEIGHT (meters) WIDTH (meters) TRAVELLER MIN MAX MIN MAX I A 7.43 9.54 11.43 15.70 I A I B 5.53 7.56 11.43 15.70 I B or II B II A 7.41 7.60 12.95 22.71 II A or II B II B 5.18 9.34 12.80 22.56 II B III 6.28 9.05 17.53 28.50 III
  • 15. ANALYSIS • M/O started the system evaluation process by comparing the available conventional shoring systems and the CONESCO casting machines. • This comparison was based on operating cost, acquisition cost, technical performance of the systems, and ability to adjust formwork to tunnel dimensions. • The records we have state $4,772,300 in net savings, and 36 weeks saved in schedule time, when comparing the conventional system to the CONESCO casting machines
  • 16. ANALYSIS CONVENTIONAL CONESCO DIFFERENCE COST ($) 1,500,000 3,500,000 -2,000,000 PRODUCTION (m2/MH) .42 1.62 1.2 MAN HOURS (MH) REQUIRED 164,900 28,473 136427 TIME (WEEKS) 86 50 36 (8 months) MH COST (50$/MH) 8,245,000 1,423,650 6,821,350 TOTAL COST ($) 9,745,000 4,923,650 4,821,350
  • 17. CONCLUSIONS • The case study has focused on time and cost related to the use of three different formwork systems. • A time-cost trade–off analysis was also followed when investigating alternative sequencing schemes for the one system that was selected using computer simulation. • Contractors in projects involving nonconventional formwork must carefully consider the implications of formwork systems selection and sequencing of concrete casting operations. • The use of simulation in this study reveals its utility to a long-term and comprehensive approach to planning and management.