SlideShare a Scribd company logo
1 of 18
Download to read offline
Interconnection Issues at
Higher Penetrations
Sky C. Stanfield

1
Installed Grid-Connected Solar Capacity (MW)
3,500	
  
3,000	
  

3340	
  MW	
  

Capacity	
  (MW-­‐dc)	
  

2,500	
  
2,000	
  
1,500	
  

1800	
  MW	
  

U)lity	
  
Non-­‐Residen)al	
  
Residen)al	
  

1,000	
  
500	
  
0	
  
2
Number of Annual Grid-Connected Installations
100,000
90,000

95,000	
  

80,000
70,000
60,000
50,000
40,000

65,000	
  
U)lity	
  
Non-­‐Residen)al	
  
Residen)al	
  

30,000
20,000
10,000
0
3
Most Interconnection Procedures
Were Designed for a Different Era
•  FERC adopted SGIP in 2005, subsequently
many states adopted procedures modeled on
SGIP or the original California Rule 21
–  In 2005 the US installed 79 MW of grid connected
PV
–  In 2012 the US installed 3,300 MW of grid
connected PV

•  Until last year, few states had updated their
procedures to reflect this changing reality
4
Key Reasons for Updating
Interconnection Procedures
• 
• 
• 
• 
• 

High volume of interconnection applications
Increased penetration on distribution circuits
Backlogged study queues
Unclear review requirements
Lack of transparency regarding system
conditions
•  Better procedures = lower costs for solar
customers and utilities/rate payers
5
Interconnection Rules
Are Changing
•  Both state and federally regulated
procedures in California have been
updated
•  Hawaii, Massachusetts, Ohio and others
have recently adopted or are considering
changes
•  FERC is currently considering significant
updates to SGIP
6
A Few Principles for Efficient
Interconnection
•  Filter projects before applications are filed
•  Enable developers to select low-cost sites
•  Apply the appropriate amount of study to
each project
•  Ensure timelines are clear and complied
with
•  Allow opportunities for cost sharing
7
New and Noteworthy
Approaches to Interconnection
• 
• 
• 
• 
• 
• 

Pre-Application Reports and other tools
Fast Track size limits
Improved Supplemental Review
Differentiated Study Processes
Group/Cluster Studies
Up Next: Integrated Distribution Planning?
8
Pre-Application Report
•  Report on system conditions at a particular
point of interconnection
•  Reduces number of speculative projects
•  Help developers strategically locate projects
•  Maximizes utilization of existing infrastructure
•  Can help manage expectations
•  Minimizes study queues, conserves utility
staff time
9
Fast Track Size Limits
•  Most common Fast Track limit is 2 MW
•  May result in studies being required where
not needed to protect safety and reliability
•  Goal should be to filter projects that are
unlikely to pass the Fast Track screens
•  Size is a key factor, but location on the circuit
is also a key determining factor
•  Couple of options on the table at FERC
10
Fast Track Eligibility Proposals
Line Capacity

Fast Track Eligibilityregardless of location

Fast Track Eligibility- on >
600 amp line and < 2.5
miles from substation

< 4kV
5kV – 14 kV
15 kV – 30 kV
31 kV – 60 kV

< 1MW
< 2MW
< 3MW
< 4MW

< 2 MW
< 3 MW
< 4 MW
< 5 MW

Line Voltage

Fast Track Eligibility
Regardless of Location

Fast Track Eligibility on a
Mainline* and <2.5 Miles**
from Substation

< 5 kilovolt (kV)
≥ 5 kV and < 15 kV
≥ 15 kV and < 30 kV
≥ 30 kV and 69 kV

< 500 kW
< 2 MW
< 3 MW
< 4 MW

< 500 kW
< 3 MW
< 4 MW
< 5 MW

* For purposes of this table, a mainline will typically constitute lines with wire sizes of 4/0 AWG, 336.5 kcmil, 397.5 kcmil, 477
kcmil and 795 kcmil
** Electrical Line Miles
*** An Interconnection Customer can determine this information in advanced by requesting a pre-application report pursuant to
section 1.2.

11
Defined Supplemental Review
•  Retains the 10 existing initial review screens
– if any are failed options are:
1.  Approve anyway with “minor modifications”
2.  Offer to perform supplemental review, or
3.  Get agreement to study

•  Three supplemental review screens:
1.  100% of minimum load, daytime for PV;
2.  Power quality and voltage, and
3.  Safety and reliability
12
Differentiated Study Processes
• 
• 
• 
• 
• 
• 

Pre-Application (± 10 days)
Fast Track (± 30 days)
Supplemental Review (± 60 days)
Independent Study (± 6 months)
Distribution Group Study (± one year)
Transmission Cluster Study (± two years)
13
Group/Cluster Studies
•  Can be necessary to avoid serial-study queue
clogging
•  Have advantages in cost sharing for study
fees as well as upgrades
•  Longer study time per-project, but overall
shorter wait time to be studied
•  Still in the experiment stage in California
14
Integrated Distribution Planning
• 
• 
• 
• 

Proactive instead of Reactive
Advanced determination of hosting capacity
Can shorten project specific study time
Could even result in upgrades not done on a
project-by-project basis
•  For more see 3iForum talks on IDP

15
Questions?
Sky Stanfield
Keyes, Fox & Wiedman LLP
(510) 314-8204
sstanfield@kfwlaw.com

16
What is FERC Doing with SGIP?
•  Issued a NOPR in January 2013 post SEIA
petition
•  Workshops were held, Comments filed in June
•  Considering a rule similar to Rule 21
•  Why does it matter?
–  Model for state procedures
–  Could help facilitate greater penetration of DG at lower
cost to developers

•  Watch for decision later this year or early next
17
THANKS to our generous sponsors for the
2013 3iForum and 3iAwards

More Related Content

What's hot

A New QoS Renegotiation Mechanism for Multimedia Applications
A New QoS Renegotiation Mechanism for Multimedia ApplicationsA New QoS Renegotiation Mechanism for Multimedia Applications
A New QoS Renegotiation Mechanism for Multimedia Applications
ABDELAAL
 

What's hot (10)

406MHz - 430MHz Sharing and Trials
406MHz - 430MHz Sharing and Trials 406MHz - 430MHz Sharing and Trials
406MHz - 430MHz Sharing and Trials
 
2.4_Overview of Microgrid Research, Development, and Resiliency Analysis_Hovs...
2.4_Overview of Microgrid Research, Development, and Resiliency Analysis_Hovs...2.4_Overview of Microgrid Research, Development, and Resiliency Analysis_Hovs...
2.4_Overview of Microgrid Research, Development, and Resiliency Analysis_Hovs...
 
Sharing Defence Managed Spectrum - MOD
Sharing Defence Managed Spectrum - MODSharing Defence Managed Spectrum - MOD
Sharing Defence Managed Spectrum - MOD
 
3.3_Cyber Security R&D for Microgrids_Stamp_EPRI/SNL Microgrid
3.3_Cyber Security R&D for Microgrids_Stamp_EPRI/SNL Microgrid3.3_Cyber Security R&D for Microgrids_Stamp_EPRI/SNL Microgrid
3.3_Cyber Security R&D for Microgrids_Stamp_EPRI/SNL Microgrid
 
9.1_Thoughts on Testing, Demonstrations, and Pilots_Ellis_EPRI/SNL Microgrid ...
9.1_Thoughts on Testing, Demonstrations, and Pilots_Ellis_EPRI/SNL Microgrid ...9.1_Thoughts on Testing, Demonstrations, and Pilots_Ellis_EPRI/SNL Microgrid ...
9.1_Thoughts on Testing, Demonstrations, and Pilots_Ellis_EPRI/SNL Microgrid ...
 
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
 
A New QoS Renegotiation Mechanism for Multimedia Applications
A New QoS Renegotiation Mechanism for Multimedia ApplicationsA New QoS Renegotiation Mechanism for Multimedia Applications
A New QoS Renegotiation Mechanism for Multimedia Applications
 
9.3_Site-specific Controller Evaluation using HIL_Pratt_EPRI/SNL Microgrid Sy...
9.3_Site-specific Controller Evaluation using HIL_Pratt_EPRI/SNL Microgrid Sy...9.3_Site-specific Controller Evaluation using HIL_Pratt_EPRI/SNL Microgrid Sy...
9.3_Site-specific Controller Evaluation using HIL_Pratt_EPRI/SNL Microgrid Sy...
 
Issues in Interconnections
Issues in InterconnectionsIssues in Interconnections
Issues in Interconnections
 
Fv3610681072
Fv3610681072Fv3610681072
Fv3610681072
 

Similar to Interconnection Issues at Higher Penetrations

Show and Tell - Flexibility & Hydrogen Integration.pdf
Show and Tell - Flexibility & Hydrogen Integration.pdfShow and Tell - Flexibility & Hydrogen Integration.pdf
Show and Tell - Flexibility & Hydrogen Integration.pdf
SIFOfgem
 
KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016
sfact
 
Frequency Regulation of Grid Connected Solar PV System Using Battery Storage ...
Frequency Regulation of Grid Connected Solar PV System Using Battery Storage ...Frequency Regulation of Grid Connected Solar PV System Using Battery Storage ...
Frequency Regulation of Grid Connected Solar PV System Using Battery Storage ...
Wajdi Bellil
 
RT15 Berkeley | Grid Intergration Group - Lawrence Berkeley National Lab
RT15 Berkeley | Grid Intergration Group - Lawrence Berkeley National Lab RT15 Berkeley | Grid Intergration Group - Lawrence Berkeley National Lab
RT15 Berkeley | Grid Intergration Group - Lawrence Berkeley National Lab
OPAL-RT TECHNOLOGIES
 

Similar to Interconnection Issues at Higher Penetrations (20)

Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
 
14 berdner hawaiian adv inverters
14 berdner   hawaiian adv inverters14 berdner   hawaiian adv inverters
14 berdner hawaiian adv inverters
 
12 dessai epri sandia - pge vvo pilot
12 dessai epri sandia - pge vvo pilot12 dessai epri sandia - pge vvo pilot
12 dessai epri sandia - pge vvo pilot
 
Show and Tell - Flexibility & Hydrogen Integration.pdf
Show and Tell - Flexibility & Hydrogen Integration.pdfShow and Tell - Flexibility & Hydrogen Integration.pdf
Show and Tell - Flexibility & Hydrogen Integration.pdf
 
03 broderick qsts_sand2016-4697 c
03 broderick qsts_sand2016-4697 c03 broderick qsts_sand2016-4697 c
03 broderick qsts_sand2016-4697 c
 
KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016
 
Chap013.pptx
Chap013.pptxChap013.pptx
Chap013.pptx
 
2014 PV Distribution System Modeling Workshop: Hosting Capacity Analysis and ...
2014 PV Distribution System Modeling Workshop: Hosting Capacity Analysis and ...2014 PV Distribution System Modeling Workshop: Hosting Capacity Analysis and ...
2014 PV Distribution System Modeling Workshop: Hosting Capacity Analysis and ...
 
Staggering in Power System
Staggering in Power System Staggering in Power System
Staggering in Power System
 
CaLEAP Energy Strategies Workshop June 25, 2013
CaLEAP Energy Strategies Workshop June 25, 2013CaLEAP Energy Strategies Workshop June 25, 2013
CaLEAP Energy Strategies Workshop June 25, 2013
 
Frequency Regulation of Grid Connected Solar PV System Using Battery Storage ...
Frequency Regulation of Grid Connected Solar PV System Using Battery Storage ...Frequency Regulation of Grid Connected Solar PV System Using Battery Storage ...
Frequency Regulation of Grid Connected Solar PV System Using Battery Storage ...
 
Integrating Multiple Microgrids into an Active Network Management System
Integrating Multiple Microgrids into an Active Network Management SystemIntegrating Multiple Microgrids into an Active Network Management System
Integrating Multiple Microgrids into an Active Network Management System
 
DIGITALISATION OF POWER DISTRIBUTION SUSBSTATION
DIGITALISATION OF POWER DISTRIBUTION SUSBSTATIONDIGITALISATION OF POWER DISTRIBUTION SUSBSTATION
DIGITALISATION OF POWER DISTRIBUTION SUSBSTATION
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
 
RT15 Berkeley | Grid Intergration Group - Lawrence Berkeley National Lab
RT15 Berkeley | Grid Intergration Group - Lawrence Berkeley National Lab RT15 Berkeley | Grid Intergration Group - Lawrence Berkeley National Lab
RT15 Berkeley | Grid Intergration Group - Lawrence Berkeley National Lab
 
Oliver Spink
Oliver SpinkOliver Spink
Oliver Spink
 
Mingrid consultation paper3
Mingrid consultation paper3Mingrid consultation paper3
Mingrid consultation paper3
 
PP_lect1.pptx
PP_lect1.pptxPP_lect1.pptx
PP_lect1.pptx
 
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia LaboratoryRT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
 
Investigation of Solid State Hydrides For Autonomous Fuel Cell Vehicles
Investigation of Solid State Hydrides For Autonomous Fuel Cell VehiclesInvestigation of Solid State Hydrides For Autonomous Fuel Cell Vehicles
Investigation of Solid State Hydrides For Autonomous Fuel Cell Vehicles
 

More from Interstate Renewable Energy Council

More from Interstate Renewable Energy Council (20)

Virtual Net Metering & Shared Solar: National Perspective
Virtual Net Metering & Shared Solar: National PerspectiveVirtual Net Metering & Shared Solar: National Perspective
Virtual Net Metering & Shared Solar: National Perspective
 
Shared Solar: National Overview
Shared Solar: National OverviewShared Solar: National Overview
Shared Solar: National Overview
 
State Approaches to DERs: Skilled Ringmaster Required
State Approaches to DERs: Skilled Ringmaster RequiredState Approaches to DERs: Skilled Ringmaster Required
State Approaches to DERs: Skilled Ringmaster Required
 
Shared Solar: What's Working & What's Next
Shared Solar: What's Working & What's NextShared Solar: What's Working & What's Next
Shared Solar: What's Working & What's Next
 
15 Minutes You Can't Afford to Miss!
15 Minutes You Can't Afford to Miss!15 Minutes You Can't Afford to Miss!
15 Minutes You Can't Afford to Miss!
 
Shared Solar: What's Working & What's Next (IREC & SEPA)
Shared Solar: What's Working & What's Next (IREC & SEPA)Shared Solar: What's Working & What's Next (IREC & SEPA)
Shared Solar: What's Working & What's Next (IREC & SEPA)
 
IREC's Annual Solar Market Trends Report
IREC's Annual Solar Market Trends ReportIREC's Annual Solar Market Trends Report
IREC's Annual Solar Market Trends Report
 
Fair Compensation for Distributed Solar Generation
Fair Compensation for Distributed Solar GenerationFair Compensation for Distributed Solar Generation
Fair Compensation for Distributed Solar Generation
 
6 Trends to Watch for in 2015
6 Trends to Watch for in 20156 Trends to Watch for in 2015
6 Trends to Watch for in 2015
 
What's Next in Interconnection?
What's Next in Interconnection?What's Next in Interconnection?
What's Next in Interconnection?
 
What it all means: solar regulatory world 101
What it all means: solar regulatory world 101What it all means: solar regulatory world 101
What it all means: solar regulatory world 101
 
Credible Credentials: Coming of Age
Credible Credentials: Coming of AgeCredible Credentials: Coming of Age
Credible Credentials: Coming of Age
 
IREC's Annual Solar Market Trends Report
IREC's Annual Solar Market Trends ReportIREC's Annual Solar Market Trends Report
IREC's Annual Solar Market Trends Report
 
Why Market-Valued Credentials Matter
Why Market-Valued Credentials MatterWhy Market-Valued Credentials Matter
Why Market-Valued Credentials Matter
 
The Future of Net Metering
The Future of Net MeteringThe Future of Net Metering
The Future of Net Metering
 
Improving Interconnection: Integrated Distribution Planning
Improving Interconnection: Integrated Distribution PlanningImproving Interconnection: Integrated Distribution Planning
Improving Interconnection: Integrated Distribution Planning
 
Shared Solar Programs: Growing the Market
Shared Solar Programs: Growing the MarketShared Solar Programs: Growing the Market
Shared Solar Programs: Growing the Market
 
Better Trained Workers Affect Your Bottom Line: The Solar Instructor Training...
Better Trained Workers Affect Your Bottom Line: The Solar Instructor Training...Better Trained Workers Affect Your Bottom Line: The Solar Instructor Training...
Better Trained Workers Affect Your Bottom Line: The Solar Instructor Training...
 
Building the Market: IREC Tackling Issues You Need for Success
Building the Market: IREC Tackling Issues You Need for Success Building the Market: IREC Tackling Issues You Need for Success
Building the Market: IREC Tackling Issues You Need for Success
 
The IREC Credentialing Process
The IREC Credentialing Process The IREC Credentialing Process
The IREC Credentialing Process
 

Recently uploaded

Brand experience Peoria City Soccer Presentation.pdf
Brand experience Peoria City Soccer Presentation.pdfBrand experience Peoria City Soccer Presentation.pdf
Brand experience Peoria City Soccer Presentation.pdf
tbatkhuu1
 
FULL ENJOY Call Girls In Majnu.Ka.Tilla Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu.Ka.Tilla Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu.Ka.Tilla Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu.Ka.Tilla Delhi Contact Us 8377877756
dollysharma2066
 

Recently uploaded (20)

Micro-Choices, Max Impact Personalizing Your Journey, One Moment at a Time.pdf
Micro-Choices, Max Impact Personalizing Your Journey, One Moment at a Time.pdfMicro-Choices, Max Impact Personalizing Your Journey, One Moment at a Time.pdf
Micro-Choices, Max Impact Personalizing Your Journey, One Moment at a Time.pdf
 
2024 Social Trends Report V4 from Later.com
2024 Social Trends Report V4 from Later.com2024 Social Trends Report V4 from Later.com
2024 Social Trends Report V4 from Later.com
 
Press Release Distribution Evolving with Digital Trends.pdf
Press Release Distribution Evolving with Digital Trends.pdfPress Release Distribution Evolving with Digital Trends.pdf
Press Release Distribution Evolving with Digital Trends.pdf
 
Best 5 Graphics Designing Course In Chandigarh
Best 5 Graphics Designing Course In ChandigarhBest 5 Graphics Designing Course In Chandigarh
Best 5 Graphics Designing Course In Chandigarh
 
Distribution Ad Platform_ The Role of Distribution Ad Network.pdf
Distribution Ad Platform_ The Role of  Distribution Ad Network.pdfDistribution Ad Platform_ The Role of  Distribution Ad Network.pdf
Distribution Ad Platform_ The Role of Distribution Ad Network.pdf
 
Brand experience Peoria City Soccer Presentation.pdf
Brand experience Peoria City Soccer Presentation.pdfBrand experience Peoria City Soccer Presentation.pdf
Brand experience Peoria City Soccer Presentation.pdf
 
Elevating Your Digital Presence by Evitha.pdf
Elevating Your Digital Presence by Evitha.pdfElevating Your Digital Presence by Evitha.pdf
Elevating Your Digital Presence by Evitha.pdf
 
Google 3rd-Party Cookie Deprecation [Update] + 5 Best Strategies
Google 3rd-Party Cookie Deprecation [Update] + 5 Best StrategiesGoogle 3rd-Party Cookie Deprecation [Update] + 5 Best Strategies
Google 3rd-Party Cookie Deprecation [Update] + 5 Best Strategies
 
[Expert Panel] New Google Shopping Ads Strategies Uncovered
[Expert Panel] New Google Shopping Ads Strategies Uncovered[Expert Panel] New Google Shopping Ads Strategies Uncovered
[Expert Panel] New Google Shopping Ads Strategies Uncovered
 
FULL ENJOY Call Girls In Majnu.Ka.Tilla Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu.Ka.Tilla Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu.Ka.Tilla Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu.Ka.Tilla Delhi Contact Us 8377877756
 
Alpha Media March 2024 Buyers Guide.pptx
Alpha Media March 2024 Buyers Guide.pptxAlpha Media March 2024 Buyers Guide.pptx
Alpha Media March 2024 Buyers Guide.pptx
 
W.H.Bender Quote 61 -Influential restaurant and food service industry network...
W.H.Bender Quote 61 -Influential restaurant and food service industry network...W.H.Bender Quote 61 -Influential restaurant and food service industry network...
W.H.Bender Quote 61 -Influential restaurant and food service industry network...
 
personal branding kit for music business
personal branding kit for music businesspersonal branding kit for music business
personal branding kit for music business
 
Unlocking the Mystery of the Voynich Manuscript
Unlocking the Mystery of the Voynich ManuscriptUnlocking the Mystery of the Voynich Manuscript
Unlocking the Mystery of the Voynich Manuscript
 
Instant Digital Issuance: An Overview With Critical First Touch Best Practices
Instant Digital Issuance: An Overview With Critical First Touch Best PracticesInstant Digital Issuance: An Overview With Critical First Touch Best Practices
Instant Digital Issuance: An Overview With Critical First Touch Best Practices
 
BDSM⚡Call Girls in Vaishali Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Vaishali Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Vaishali Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Vaishali Escorts >༒8448380779 Escort Service
 
BDSM⚡Call Girls in Sector 19 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 19 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 19 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 19 Noida Escorts >༒8448380779 Escort Service
 
Elevate Your Advertising Game: Introducing Billion Broadcaster Lift Advertising
Elevate Your Advertising Game: Introducing Billion Broadcaster Lift AdvertisingElevate Your Advertising Game: Introducing Billion Broadcaster Lift Advertising
Elevate Your Advertising Game: Introducing Billion Broadcaster Lift Advertising
 
VIP Call Girls Dongri WhatsApp +91-9833363713, Full Night Service
VIP Call Girls Dongri WhatsApp +91-9833363713, Full Night ServiceVIP Call Girls Dongri WhatsApp +91-9833363713, Full Night Service
VIP Call Girls Dongri WhatsApp +91-9833363713, Full Night Service
 
Unveiling the Legacy of the Rosetta stone A Key to Ancient Knowledge.pptx
Unveiling the Legacy of the Rosetta stone A Key to Ancient Knowledge.pptxUnveiling the Legacy of the Rosetta stone A Key to Ancient Knowledge.pptx
Unveiling the Legacy of the Rosetta stone A Key to Ancient Knowledge.pptx
 

Interconnection Issues at Higher Penetrations

  • 1. Interconnection Issues at Higher Penetrations Sky C. Stanfield 1
  • 2. Installed Grid-Connected Solar Capacity (MW) 3,500   3,000   3340  MW   Capacity  (MW-­‐dc)   2,500   2,000   1,500   1800  MW   U)lity   Non-­‐Residen)al   Residen)al   1,000   500   0   2
  • 3. Number of Annual Grid-Connected Installations 100,000 90,000 95,000   80,000 70,000 60,000 50,000 40,000 65,000   U)lity   Non-­‐Residen)al   Residen)al   30,000 20,000 10,000 0 3
  • 4. Most Interconnection Procedures Were Designed for a Different Era •  FERC adopted SGIP in 2005, subsequently many states adopted procedures modeled on SGIP or the original California Rule 21 –  In 2005 the US installed 79 MW of grid connected PV –  In 2012 the US installed 3,300 MW of grid connected PV •  Until last year, few states had updated their procedures to reflect this changing reality 4
  • 5. Key Reasons for Updating Interconnection Procedures •  •  •  •  •  High volume of interconnection applications Increased penetration on distribution circuits Backlogged study queues Unclear review requirements Lack of transparency regarding system conditions •  Better procedures = lower costs for solar customers and utilities/rate payers 5
  • 6. Interconnection Rules Are Changing •  Both state and federally regulated procedures in California have been updated •  Hawaii, Massachusetts, Ohio and others have recently adopted or are considering changes •  FERC is currently considering significant updates to SGIP 6
  • 7. A Few Principles for Efficient Interconnection •  Filter projects before applications are filed •  Enable developers to select low-cost sites •  Apply the appropriate amount of study to each project •  Ensure timelines are clear and complied with •  Allow opportunities for cost sharing 7
  • 8. New and Noteworthy Approaches to Interconnection •  •  •  •  •  •  Pre-Application Reports and other tools Fast Track size limits Improved Supplemental Review Differentiated Study Processes Group/Cluster Studies Up Next: Integrated Distribution Planning? 8
  • 9. Pre-Application Report •  Report on system conditions at a particular point of interconnection •  Reduces number of speculative projects •  Help developers strategically locate projects •  Maximizes utilization of existing infrastructure •  Can help manage expectations •  Minimizes study queues, conserves utility staff time 9
  • 10. Fast Track Size Limits •  Most common Fast Track limit is 2 MW •  May result in studies being required where not needed to protect safety and reliability •  Goal should be to filter projects that are unlikely to pass the Fast Track screens •  Size is a key factor, but location on the circuit is also a key determining factor •  Couple of options on the table at FERC 10
  • 11. Fast Track Eligibility Proposals Line Capacity Fast Track Eligibilityregardless of location Fast Track Eligibility- on > 600 amp line and < 2.5 miles from substation < 4kV 5kV – 14 kV 15 kV – 30 kV 31 kV – 60 kV < 1MW < 2MW < 3MW < 4MW < 2 MW < 3 MW < 4 MW < 5 MW Line Voltage Fast Track Eligibility Regardless of Location Fast Track Eligibility on a Mainline* and <2.5 Miles** from Substation < 5 kilovolt (kV) ≥ 5 kV and < 15 kV ≥ 15 kV and < 30 kV ≥ 30 kV and 69 kV < 500 kW < 2 MW < 3 MW < 4 MW < 500 kW < 3 MW < 4 MW < 5 MW * For purposes of this table, a mainline will typically constitute lines with wire sizes of 4/0 AWG, 336.5 kcmil, 397.5 kcmil, 477 kcmil and 795 kcmil ** Electrical Line Miles *** An Interconnection Customer can determine this information in advanced by requesting a pre-application report pursuant to section 1.2. 11
  • 12. Defined Supplemental Review •  Retains the 10 existing initial review screens – if any are failed options are: 1.  Approve anyway with “minor modifications” 2.  Offer to perform supplemental review, or 3.  Get agreement to study •  Three supplemental review screens: 1.  100% of minimum load, daytime for PV; 2.  Power quality and voltage, and 3.  Safety and reliability 12
  • 13. Differentiated Study Processes •  •  •  •  •  •  Pre-Application (± 10 days) Fast Track (± 30 days) Supplemental Review (± 60 days) Independent Study (± 6 months) Distribution Group Study (± one year) Transmission Cluster Study (± two years) 13
  • 14. Group/Cluster Studies •  Can be necessary to avoid serial-study queue clogging •  Have advantages in cost sharing for study fees as well as upgrades •  Longer study time per-project, but overall shorter wait time to be studied •  Still in the experiment stage in California 14
  • 15. Integrated Distribution Planning •  •  •  •  Proactive instead of Reactive Advanced determination of hosting capacity Can shorten project specific study time Could even result in upgrades not done on a project-by-project basis •  For more see 3iForum talks on IDP 15
  • 16. Questions? Sky Stanfield Keyes, Fox & Wiedman LLP (510) 314-8204 sstanfield@kfwlaw.com 16
  • 17. What is FERC Doing with SGIP? •  Issued a NOPR in January 2013 post SEIA petition •  Workshops were held, Comments filed in June •  Considering a rule similar to Rule 21 •  Why does it matter? –  Model for state procedures –  Could help facilitate greater penetration of DG at lower cost to developers •  Watch for decision later this year or early next 17
  • 18. THANKS to our generous sponsors for the 2013 3iForum and 3iAwards