The document summarizes Engineers Without Borders' (EWB) current project to supplement the potable and non-potable water systems at a local school in Ilha Das Peças, Brazil. The project aims to increase the water supply through rainwater collection and purification of potable water, while also reducing potable water demand by providing a separate non-potable water source for uses like toilet flushing and irrigation. The upgrades will physically separate the potable and non-potable systems and include installing additional water storage tanks, drilling a new well, and improving water disinfection and filtration processes. Upon completion, the improved water systems aim to provide a more reliable water supply to support the 120 students and teachers at the school
15. Pump in kitchen transfer water from large tank to small tank in attic
16. Water gravity fed to existing toilets, sink, water fountain and kitchenFront view Large Tank Back view Kitchen 5
17. Existing Infrastructure Existing Kitchen Sink Existing Attic Tank Existing Piping in School Existing Bathrooms Existing Sink and Fountain Municipal water supplies kitchen, bathrooms, and fountain with potable water 6
31. Potable Water – Disinfection EPA Purification Requirements for Surface Water 12
32. Potable Water - Disinfection Pre-Storage Filtration Point of Use Sterilization Pentek 5 Micron Sediment Filter Pentek 0.5 Micron Carbon Block Filter Filtros & Filtros UV Purifier Main Storage Tank Sinks and Drinking Fountain Potable Water Attic Tank 13
33. Proposed System Potable Water Roof 500 L Attic tank 500 L Attic tank Gutters Overflow Overflow Physical Separation Between Water Systems New Pump Large Tank Well Head Constructed Wetlands Municipal Water Source Non Potable Water 14
34. Non-Potable Water Overflow New 500 L Attic tank New Attic Tank Valve Coupling Pump Controller New Pump Constructed Wetlands Well Head 15