Stabilizing slides and Road embankments
The spider excavator is an exceptional tool that can walk up steep slopes not accessible by normal tracked excavators.
they can safely work on 45 slopes and with cable stays can work on steeper slopes(using built-in winch)
Removal of continually failing headscarps is a concern for continued ravelling of a slope, and the raveled materials contributing to environmental degredation by entering water streams and also by plugging roadside ditches and diverting water flows across a road.
Contour drainage is used to "dry up" a moving slope and eliminate further mass slope movement(creep).
2. 2
Part 1 - Spider Excavator, (the tool)
Part 2 – Stabilizing Landslide Headscarps
Part 3 - Multiflow Drainpipe
Part 4 - Contour Drainage
Eric
Eric
Rob
Rob
Stabilizing Slides
3. 3.. .
Part 1 - Spider Excavator Description
Kaiser X5 M
4. 4
Work on steep slopes
100% (One to One slope)
Walks on 4 legs
Extending stick
Twist wrist bucket
Hydraulic thumb
Hydraulic winch 12,000lbs
Pushes and pulls itself around
Optional Hydrostatic drive (6kmph) Kaiser X5 M
Rolls on two back wheels
13. 13
Retrogressive Failures – Issues:
• Maintenance costs/problems – Loss of road use, temporary/permanent
• Impediment to re-establishment of vegetation
• Destruction of remedial works
• Loss of productive land inventory
19. 19
Multiflow pipe
Available in 15,30 & 46 cm widths
Made up of multiple
miniature “Big O” pipes
laid flat, joined together
and covered in a filter
fabric
A viable alternative for
Drain rock
21. 21
This site is located in the
Cariboo Mountains where a
“hanging glacial” valley
slopes into a typical “U
shaped glacial valley”.
Glacial fluvial out-wash
deposits are buried below
glacial till, resulting in
seepage related slope
instability problems.
22. 22
Road cut-slope. Tension crack showing evidence of slope
ilure, along with visible evidence of retrogression of the headscarp.
This site has been a an ongoing maintenance problem, with some
restriction of road use.
Tension crack – indicator
of slope failure
23. 23
The Spider Excavator digs a
trench above the crest of the
headscarp and behind the
tension crack.
The trench is 3m in depth with
the objective to interrupt the
sub-surface water flows.
he base of the trench should
lope at least 2% towards an
utlet end of the drainage.
24. 24
he multiflow drainage composite was put
to the bottom of the trench, against the uphill
ope, and a 6 mil polyethylene sheet placed
ainst the down slope side for an impervious
arrier.
l placement was done from the surface. Workers
re not permitted to enter the trench.
e Multiflow pipe was attached to the poly and
wered into the trench from the surface.
25. 25
The multiflow drainage
composite was put
into the bottom of the
trench, against the
uphill slope, and a 6
mil polyethylene sheet
against the down
slope side.
Excavator starts
backfilling the
trench. Woody
debris is then
scattered over top
Alternatively a
composite
“Blanket Drain”
material such as
Nudrain DM50 could
be employed
28. 28
inished swale above head scarp with debris scattered
over top.
wale directs surface water away from problem area.
(Picture has been stretched to emphasize the swale)
30. 30
table cut slope with reduced seepage after finishing the contour drainage wor
No longer a continuous road maintenance issue not is there the problem of loss of road use.
32. 32
References
Kaiser X5 M - JOHOE Inc
Joe Gisler 250 398-3507
Schaeff HS 40 D - Nu Creek Developments
Len Masson 250 833-0173
Schaeff HS 41 M - J W Berry Trucking
Brad Berry 250 724-4912
Rob Wilson - Weldwood - 250 392-7731
Eric L Kay - Kay & Associates - 250 337-5096