Proposed and designed a preliminary highway route. Illustrated all the topographical features of the site. Designed horizontal and vertical curves. Analyzed to check if the design satisfied all the AASHTO Greenbook criteria.
4.
8 1 9
9 0 0
1000
950
900
850
8 5 2
E
A
B
1
1 0 1 1
9 4 0
850
E n d p o in t
E
B E G IN N I N G P O IN T
810
810
B
19 9 5
1 0 0 0
850
840
9 7 0
830
840ABONDONEDROAD
800
800
790
790
780
780
Specified end points of proposed highway
Beginning point – B
End point ‐ 1
DRAWING NO: Figure
Title: LOCATION OF PROPOSED HIGHWAY
SCALE (S) : As shown
5.
BACKGROUND AND SPECIFICATIONS
This section provides the basic information which the designer relies upon to
select the routes and undertake the design. The information should be clearly
stated also because it informs others about the base guidelines and assumptions
that have affected the outcome. These guidelines and assumptions may be the
subject of future policy changes resulting from the review of the preliminary
design but typically do not change during the preliminary design process.
In this project the background and specifications are presented in the
following pages:
Introduction and Background:
The preliminary route selection and design of the proposed highway is intended to exist in
exploring the cost and land use implications of connecting North road with Southwest Road at
points B and 1 respectively, shown on the location map. Tentative analysis of future traffic
levels has been made, including consideration of potential use of the state reservation as an
environmental research area, with possible public access.
Objectives:
In accordance with above background, it is required to conduct a preliminary route selection
and design for a 2 lane highway in accordance with AASHTO “Rural collector” highway design
standards. Two alternative routes initially investigated. However, only one Route is to be
selected for the design process, immediately following a brief screening of both routes.
Design policy:
In addition to Using the AASHTO policy on geometric design for “rural collector” highway as
basic design guidelines, several more specific guidelines has been defined within the IDOT and
general policy, resulting from examination or the environs of highway and its likely uses. The
traffic control devices should be provided in accordance with the latest version of MUTCD and
local regulations.
6.
Design designation:
Classification =Rural Collector
Design speed =40mph
ADT (current year) =0
ADT (future year) =4000
K =10%
D =60%
T =2%
Design Controls:
Design speed, V =40mph
Super elevation rate, e(max) =6%
Minimum Radius for above V and E =485 ft
(Also satisfies stopping sight dist. Requirements for horizontal curves)
Maximum grade, except at intersections =6%
Minimum grade (All locations) =0.5%
Maximum Vertical curve K value, drainage criteria =167
Design vehicle =WB‐50
Intersection Geometrics:
Horizontal intersection of proposed route with existing highway should be a minimum
of 100ft tangent segment as close to 90°as possible to the existing highway, but within
the range of 75° to 105°.
Maximum grade (+ or ‐) within 100ft of intersection
Lane Requirements:
Two lanes are minimum number of lanes for an adequate design. Therefore, the
highway will comprise 2‐12ft lanes with 8ft shoulders.
12.
SCREENING OF ALTERNATIVES
Examination of the profiles of Routes A and B, shown in figure , indicates that
both Routes A and B could provide a vertical profile which would conform with
the gradient and depth of cut and fill but that Route A requires excessive uphill
haul. For this and other reasons indicated in the summary screening process
shown in the figure, Route B is the one selected for technical feasibility.
SCREEN EVALUATION
S No. CRITERIA
ROUTE A ROUTE B
1
Length of Route 5322.29 ft 4919 FT
2
Conformance with
design controls
Full conformance
3
Cut and fill balance There is an even balance
Excessive cutting is
required
4
Need for bridges or
special structures
None None
5 Environmental impacts No obvious Environmental impacts
Excessive cut & fill
will lead to
environmental
impacts.
6
Potential high cost
items
None
Excessive hauling
& digging costs
involved
7
Haul direction Satisfactory
Excessive uphill
hauling.
CONCLUSIONS: Route‐A is longer than Route‐B, but Route B requires excessive
uphill haul and need to dispose of considerable earthwork off the site.
PROCEEDING WITH THE ROUTE‐A FOR ANALYSIS PURPOSES.
13.
HORIZONTAL ALIGNMENT
The horizontal alignment can be developed for alternative B and the relevant
dimensions and angles computed and checked. The development of tangent and
curve distances may then be converted to stations and an estimate of the
traverse closure made to ensure that no gross errors have been made in the
scaling of distances and angles. As well as the dimensions of each of the tangent
and curve segments of the proposed highway, the stations are computed for
points along the centerline of the route.
Care must be taken to define clearly the location of the beginning and end
points of the proposed route, in this case assumed to be the centerlines of the
existing highways. Each curve radius is checked for compliance with the minimum
allowable radius of 485ft (According to BDE manual).
During this preliminary design stage for this class of highway, no attempt has
been made to illustrate the use of transition curves, however, the superelevation
curve has been designed and calculated and shown on drawings.