EFFECTIVENESS OF IMPLEMENTING 5D
FUNCTIONS OF BUILDING INFORMATION
MODELING ON PROFESSIONS OF QUANTITY
SURVEYING
International Journal of Civil Engineering and Technology (IJCIET) Scopus Indexed
Achmad Yustofi
INTRODUCTION
• Though the quantity surveyors have improved their computing skills by utilizing
information technology still they lack achieving accuracy from estimating quantities
and cost using excel spreadsheets.
• One of these innovative technologies is Building Information Modeling (BIM) which
started to have strong effects on the construction industry over the last 10 years.
• Although automation of quantities using BIM tools provide wide opportunities of
BOQ improvement, quantity surveying profession need to adapt accordingly to
provide more efficient cost management services incorporated with time and cost
modelling and to streamline sharing of cost information with the project team as part
of the BIM integrated project delivery approach
BIM
• (Gardiner, 2013) Explained BIM as technological method applied by the
designer and contractor to create an actual 3 D building model covering all
detailed standard component of the building in which can be shared and
communicated with all project participant at the right time and to the right
person.
• Maturity levels of BIM consisting of 3 D model together with 4 D of project
timeline and 5 D of cost information.
Difference between BIM
and Conventional 3D CAD
• (Azhar et al 2008) explained the
difference between BIM and
conventional 3 D CAD is that the
building drawing by utilizing 3 D CAD
will be described independently in
three basic views of plan, elevation and
section which can be described by lines,
arcs and circles and any modifications
required for one view, all other views
should be updated which definitely
leads to errors and inaccuracy.
Benefits to adoption BIM
in Quantity Surveying
• (Muhammad 2015). Analysed and
discussed the benifits of adopting new
technology on the construction projects
by quantity surveyors in UAE as
displayed in Table 1. From the data
collection and analysis, it is
recommended to implement BIM
technology in quantity surveying
practices in UAE due its beneficial
prospects to persist in more effective
and competitive growths in the
construction industry.
BARRIERES TO BIM ADOPTION
• (Anthony 2014), highlighted the top difficulties encountered by the
organization to successfully implement BIM according to NBS National BIM
Report 2014. These obstacles are identified as fewer demands by the clients
and/or small organization which consists of five staff or less as cited by 73% of
those organizations. The other important obstacle as indicated by 71% of the
same organizations refer to the irrelevance of BIM to the type of their projects
in addition to the cost of infrastructure including software installation,
extensive training courses and the considerable time required to complete the
mentioned tasks. Contractors from their points of perspective with reluctance
to make any changes indicated that BIM would support the project only at the
early stage of execution.
CONCLUDING REMARKS
• 5D BIM, being a new technology, is employed for effective information on
total cost of design, construction and operation of the project using digital
information. Despite many benefits that have been identified in the
extensive literature review, there are limitations that need to be urgently
overcome. The contribution of BIM in the development of construction
industry is apparently very slow. There is a significant lack of cultural
awareness and management support in the implementation of the BIM
technology.
Analisa Kritis untuk Further Research
• Makalah ini membahas tentang teknologi BIM yang memiliki keunikan
tersendiri dan meninjau efektifitas penggunaan BIM oleh industri
konstruksi. Perlu untuk menguraikan manfaat penerapan teknologi
BIM di berbagai tingkatan proyek, dari yang skala kecil atau besar dan
kemampuan aplikasi 5D BIM dalam praktik quantity survey. Tantangan
utama dari pemanfaatan teknologi BIM adalah membawa revolusi di
bidang quantity suerey dan estimasi yang harus tepat dan cukup
dapat diterima oleh industri.
thankyou

More Related Content

Similar to EFFECTIVENESS OF IMPLEMENTING 5D BIM.pptx

IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...IRJET Journal
 
An Execution of Building Information Modelling for Factories and Warehouse Pr...
An Execution of Building Information Modelling for Factories and Warehouse Pr...An Execution of Building Information Modelling for Factories and Warehouse Pr...
An Execution of Building Information Modelling for Factories and Warehouse Pr...IRJET Journal
 
Review on Benefits, Features, Applications and Implementation of Building Inf...
Review on Benefits, Features, Applications and Implementation of Building Inf...Review on Benefits, Features, Applications and Implementation of Building Inf...
Review on Benefits, Features, Applications and Implementation of Building Inf...IRJET Journal
 
A Review on Challenges Involved in Implementing Building Information Modeling...
A Review on Challenges Involved in Implementing Building Information Modeling...A Review on Challenges Involved in Implementing Building Information Modeling...
A Review on Challenges Involved in Implementing Building Information Modeling...IRJET Journal
 
IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET- Building Information Modeling in AEC Industry with its Implementation ...IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET- Building Information Modeling in AEC Industry with its Implementation ...IRJET Journal
 
A Research Study Done On The Adaptation Of Building Information Modelling In ...
A Research Study Done On The Adaptation Of Building Information Modelling In ...A Research Study Done On The Adaptation Of Building Information Modelling In ...
A Research Study Done On The Adaptation Of Building Information Modelling In ...Jessica Henderson
 
Software Application in Quantity Surveying - Report
Software Application in Quantity Surveying - ReportSoftware Application in Quantity Surveying - Report
Software Application in Quantity Surveying - ReportPang Khai Shuen
 
Exploring the adoption of building information
Exploring the adoption of building informationExploring the adoption of building information
Exploring the adoption of building informationeSAT Publishing House
 
Building Information Modeling (BIM) Research Paper
Building Information Modeling (BIM) Research PaperBuilding Information Modeling (BIM) Research Paper
Building Information Modeling (BIM) Research Paperabhishek chougule
 
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed
 
BIM Presentation
BIM PresentationBIM Presentation
BIM PresentationOmer Syed
 
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdfWaliEdwardian1
 
Role of building information modelling bim in quantity surveying practice
Role of building information modelling bim in quantity surveying practiceRole of building information modelling bim in quantity surveying practice
Role of building information modelling bim in quantity surveying practiceIAEME Publication
 
Exploring the adoption of building information modelling (bim) in the malaysi...
Exploring the adoption of building information modelling (bim) in the malaysi...Exploring the adoption of building information modelling (bim) in the malaysi...
Exploring the adoption of building information modelling (bim) in the malaysi...eSAT Journals
 
Sc bim
Sc bimSc bim
Sc bimLam Yu
 
Bim in Construction Management
Bim in Construction ManagementBim in Construction Management
Bim in Construction ManagementMd Manzoor Akhtar
 
5 reasons why bim adoption is important for architects
5 reasons why bim adoption is important for architects5 reasons why bim adoption is important for architects
5 reasons why bim adoption is important for architectsArpitGautam20
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...IRJET Journal
 

Similar to EFFECTIVENESS OF IMPLEMENTING 5D BIM.pptx (20)

IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
 
An Execution of Building Information Modelling for Factories and Warehouse Pr...
An Execution of Building Information Modelling for Factories and Warehouse Pr...An Execution of Building Information Modelling for Factories and Warehouse Pr...
An Execution of Building Information Modelling for Factories and Warehouse Pr...
 
Review on Benefits, Features, Applications and Implementation of Building Inf...
Review on Benefits, Features, Applications and Implementation of Building Inf...Review on Benefits, Features, Applications and Implementation of Building Inf...
Review on Benefits, Features, Applications and Implementation of Building Inf...
 
A Review on Challenges Involved in Implementing Building Information Modeling...
A Review on Challenges Involved in Implementing Building Information Modeling...A Review on Challenges Involved in Implementing Building Information Modeling...
A Review on Challenges Involved in Implementing Building Information Modeling...
 
IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET- Building Information Modeling in AEC Industry with its Implementation ...IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET- Building Information Modeling in AEC Industry with its Implementation ...
 
A Research Study Done On The Adaptation Of Building Information Modelling In ...
A Research Study Done On The Adaptation Of Building Information Modelling In ...A Research Study Done On The Adaptation Of Building Information Modelling In ...
A Research Study Done On The Adaptation Of Building Information Modelling In ...
 
Software Application in Quantity Surveying - Report
Software Application in Quantity Surveying - ReportSoftware Application in Quantity Surveying - Report
Software Application in Quantity Surveying - Report
 
Exploring the adoption of building information
Exploring the adoption of building informationExploring the adoption of building information
Exploring the adoption of building information
 
Building Information Modeling (BIM) Research Paper
Building Information Modeling (BIM) Research PaperBuilding Information Modeling (BIM) Research Paper
Building Information Modeling (BIM) Research Paper
 
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...
 
BIM Presentation
BIM PresentationBIM Presentation
BIM Presentation
 
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
4058f1cb-2aef-4437-bf32-968325c024e7-160414132040.pdf
 
Role of building information modelling bim in quantity surveying practice
Role of building information modelling bim in quantity surveying practiceRole of building information modelling bim in quantity surveying practice
Role of building information modelling bim in quantity surveying practice
 
Exploring the adoption of building information modelling (bim) in the malaysi...
Exploring the adoption of building information modelling (bim) in the malaysi...Exploring the adoption of building information modelling (bim) in the malaysi...
Exploring the adoption of building information modelling (bim) in the malaysi...
 
Sc bim
Sc bimSc bim
Sc bim
 
Bim in Construction Management
Bim in Construction ManagementBim in Construction Management
Bim in Construction Management
 
5 reasons why bim adoption is important for architects
5 reasons why bim adoption is important for architects5 reasons why bim adoption is important for architects
5 reasons why bim adoption is important for architects
 
Building Information Model
Building Information ModelBuilding Information Model
Building Information Model
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
 
F1302033340
F1302033340F1302033340
F1302033340
 

Recently uploaded

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

EFFECTIVENESS OF IMPLEMENTING 5D BIM.pptx

  • 1. EFFECTIVENESS OF IMPLEMENTING 5D FUNCTIONS OF BUILDING INFORMATION MODELING ON PROFESSIONS OF QUANTITY SURVEYING International Journal of Civil Engineering and Technology (IJCIET) Scopus Indexed Achmad Yustofi
  • 2. INTRODUCTION • Though the quantity surveyors have improved their computing skills by utilizing information technology still they lack achieving accuracy from estimating quantities and cost using excel spreadsheets. • One of these innovative technologies is Building Information Modeling (BIM) which started to have strong effects on the construction industry over the last 10 years. • Although automation of quantities using BIM tools provide wide opportunities of BOQ improvement, quantity surveying profession need to adapt accordingly to provide more efficient cost management services incorporated with time and cost modelling and to streamline sharing of cost information with the project team as part of the BIM integrated project delivery approach
  • 3. BIM • (Gardiner, 2013) Explained BIM as technological method applied by the designer and contractor to create an actual 3 D building model covering all detailed standard component of the building in which can be shared and communicated with all project participant at the right time and to the right person. • Maturity levels of BIM consisting of 3 D model together with 4 D of project timeline and 5 D of cost information.
  • 4. Difference between BIM and Conventional 3D CAD • (Azhar et al 2008) explained the difference between BIM and conventional 3 D CAD is that the building drawing by utilizing 3 D CAD will be described independently in three basic views of plan, elevation and section which can be described by lines, arcs and circles and any modifications required for one view, all other views should be updated which definitely leads to errors and inaccuracy.
  • 5. Benefits to adoption BIM in Quantity Surveying • (Muhammad 2015). Analysed and discussed the benifits of adopting new technology on the construction projects by quantity surveyors in UAE as displayed in Table 1. From the data collection and analysis, it is recommended to implement BIM technology in quantity surveying practices in UAE due its beneficial prospects to persist in more effective and competitive growths in the construction industry.
  • 6. BARRIERES TO BIM ADOPTION • (Anthony 2014), highlighted the top difficulties encountered by the organization to successfully implement BIM according to NBS National BIM Report 2014. These obstacles are identified as fewer demands by the clients and/or small organization which consists of five staff or less as cited by 73% of those organizations. The other important obstacle as indicated by 71% of the same organizations refer to the irrelevance of BIM to the type of their projects in addition to the cost of infrastructure including software installation, extensive training courses and the considerable time required to complete the mentioned tasks. Contractors from their points of perspective with reluctance to make any changes indicated that BIM would support the project only at the early stage of execution.
  • 7. CONCLUDING REMARKS • 5D BIM, being a new technology, is employed for effective information on total cost of design, construction and operation of the project using digital information. Despite many benefits that have been identified in the extensive literature review, there are limitations that need to be urgently overcome. The contribution of BIM in the development of construction industry is apparently very slow. There is a significant lack of cultural awareness and management support in the implementation of the BIM technology.
  • 8. Analisa Kritis untuk Further Research • Makalah ini membahas tentang teknologi BIM yang memiliki keunikan tersendiri dan meninjau efektifitas penggunaan BIM oleh industri konstruksi. Perlu untuk menguraikan manfaat penerapan teknologi BIM di berbagai tingkatan proyek, dari yang skala kecil atau besar dan kemampuan aplikasi 5D BIM dalam praktik quantity survey. Tantangan utama dari pemanfaatan teknologi BIM adalah membawa revolusi di bidang quantity suerey dan estimasi yang harus tepat dan cukup dapat diterima oleh industri.