SlideShare a Scribd company logo
1 of 1
Download to read offline
Benefits of Using High-Frequency Forced
Pulsed Waterjet for Refurbishing Delaminated
             Concrete Structures
          Figure 1 shows the photographs of the work done on
refurbishing the delaminated (deteriorated) concrete ceiling,
using VLN’s patented high-frequency forced pulsed waterjet
(FPW J) machine. The location was underground parking
garage, Lester B Pearson Building, Ottawa. The success of
the job is quite evident from the photographs.

         Prior to awarding this contract to VLN, Public
W orks Canada (PW C) was getting the job done by employing
a chipper (hammer & chisel), sandblaster, at a cost of
$40/sq.ft. W ith the employment of VLN’s machine,
sandblasting was eliminated, and as removing the deteriorated
concrete was so fast (see Fig. 2), the cost was reduced to
about $10/sq.ft! Furthermore, there was no need to shut the
entire parking garage because, as shown in Fig. 1 (C), it was    Fig. 1. Refurbishing of delaminated (deteriorated) concrete from the
only necessary to isolate working areas one at a time.           ceilings of underground multi-story buildings.
                                                                 (A) Usual appearance of the ceiling with loose concrete and rusted
         Before taking the R&D contract work for the PW C,       steel bars.
laboratory tests were conducted on several types of concrete.    (B) V LN’s forced pulsed waterjet (FPW J) at the underground
Sample results on cutting with FPW J and the corresponding       parking garage of External Affairs Building (Lester B Pearson) for
continuous waterjet (CW J) are illustrated in Fig. 2. W hile     refurbishing delaminated concrete.
FPW J removed 0.283-m 3/hr of hard concrete (not                 (C) FPW J in the process of removing and cleaning the steel bars.
deteriorated), CW J removed only 0.037-m 3/hr after four         (D) Appearance of the refurbished delaminated area, showing the
adjacent passes, both operating at identical conditions          clean steel bars.
(20,000-psi and power). In other words, to remove 1-m 3 of
concrete, FPW J took only 3.5-hrs, compared to 27-hrs by the
CW J. At a nominal wage of $25/hr, the contractor employing
the ubiquitous CW J pays $675, and a visionary contractor,
who would use FPW J, pays only $87.5 for the job of
removing 1-m 3 of concrete. The savings does not end here!

Savings in cost of Energy Consumption:

Total energy consumed by FPW J: 387-kW.hr

Total energy consumed by CW J:       2,490-kw.hr!

        At the rate of $3.25/kW .hr (based on the rate charged
to VLN by Ottawa Hydro, which includes delivery charge,          Fig. 2. These results clearly show the benefit of using FPW J
GST, etc), the contractor would save a staggering $6,800 to      compared to continuous waterjet (CW J), both operating at identical
remove 1-m 3 of concrete! AND,                                   operating conditions (pressure, power, etc).

Abatement of Pollution (Based on the Data Provided by
CANM ET)

         According to CANMET (a Department of Government of Canada), based on diesel fuel, CO 2 loading of the environment is: 71-
kg/GJ of energy comsumption. Therefore:

CO 2 emission by the use of FPW J: 99,000-kg

CO 2 emission by the use of FPW J: 636,400-kg (staggering!)

         This reduction, resulting by using FPW J, must make any environmentalist happy (how about the proponents of Kyoto?)

Note: These results apply to all applications VLN has investigated, ranging from cutting rocks to rem oving hard coatings of paints.

Prepared by:      M ohan Vijay, Ph.D., P.Eng., President, VLN Advanced Technologies, Ottawa, Canada (www.VLN-Tech.com).

More Related Content

What's hot

Session 76 Petri Varin
Session 76 Petri VarinSession 76 Petri Varin
Session 76 Petri Varinpetrivarin
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsInfocengrs63
 
BCPC LOADING JETTY AND STOCK PILE Presentation
BCPC  LOADING JETTY AND STOCK PILE  PresentationBCPC  LOADING JETTY AND STOCK PILE  Presentation
BCPC LOADING JETTY AND STOCK PILE PresentationAdi Sumanto
 
Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Chris Bridges
 
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...LOESCHE
 
Alaska LNG Summit
Alaska LNG SummitAlaska LNG Summit
Alaska LNG Summitalaskalng
 
Presentation fot Coal Loading Operation
Presentation fot Coal Loading OperationPresentation fot Coal Loading Operation
Presentation fot Coal Loading OperationAdi Sumanto
 
Lec 8 pile load test
Lec 8 pile load testLec 8 pile load test
Lec 8 pile load testGhulam Yasin
 

What's hot (16)

Session 76 Petri Varin
Session 76 Petri VarinSession 76 Petri Varin
Session 76 Petri Varin
 
AML-8
AML-8AML-8
AML-8
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
 
Vedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas ShipsVedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas Ships
 
Vedam Design:- BWTS - Retrofits Services
Vedam Design:-  BWTS - Retrofits Services Vedam Design:-  BWTS - Retrofits Services
Vedam Design:- BWTS - Retrofits Services
 
BCPC LOADING JETTY AND STOCK PILE Presentation
BCPC  LOADING JETTY AND STOCK PILE  PresentationBCPC  LOADING JETTY AND STOCK PILE  Presentation
BCPC LOADING JETTY AND STOCK PILE Presentation
 
Barzan PJ Assignment
Barzan PJ AssignmentBarzan PJ Assignment
Barzan PJ Assignment
 
Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5
 
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
 
Lloyd ppt
Lloyd pptLloyd ppt
Lloyd ppt
 
Montrose BLP
Montrose BLPMontrose BLP
Montrose BLP
 
Alaska LNG Summit
Alaska LNG SummitAlaska LNG Summit
Alaska LNG Summit
 
Patras
PatrasPatras
Patras
 
Presentation fot Coal Loading Operation
Presentation fot Coal Loading OperationPresentation fot Coal Loading Operation
Presentation fot Coal Loading Operation
 
Experiencia en Viaductos
Experiencia en ViaductosExperiencia en Viaductos
Experiencia en Viaductos
 
Lec 8 pile load test
Lec 8 pile load testLec 8 pile load test
Lec 8 pile load test
 

Viewers also liked

Afiche 25 04-15
Afiche 25 04-15Afiche 25 04-15
Afiche 25 04-15doctorando
 
Software usado en Tecnología en la E.S.O.
Software usado en Tecnología en la E.S.O.Software usado en Tecnología en la E.S.O.
Software usado en Tecnología en la E.S.O.angel micelti
 
Tipos de procesos
Tipos de procesosTipos de procesos
Tipos de procesospolinho11
 
ورقة عمل الانعكاس
ورقة عمل الانعكاسورقة عمل الانعكاس
ورقة عمل الانعكاسnajah111
 
Bba403 international marketing
Bba403   international marketingBba403   international marketing
Bba403 international marketingsmumbahelp
 
Algoritmos
AlgoritmosAlgoritmos
AlgoritmosRamon
 
Room and chores spanish
Room and chores spanishRoom and chores spanish
Room and chores spanishke433987mhs88
 
Auditoriademercadeo 120303082751-phpapp01
Auditoriademercadeo 120303082751-phpapp01Auditoriademercadeo 120303082751-phpapp01
Auditoriademercadeo 120303082751-phpapp01Julio Carreto
 
Plantilla presentaciones cetach
Plantilla   presentaciones cetachPlantilla   presentaciones cetach
Plantilla presentaciones cetachadaarriola
 
M I S I O N V I S I O N D O F A
M I S I O N  V I S I O N  D O F AM I S I O N  V I S I O N  D O F A
M I S I O N V I S I O N D O F Aesneiderpiedrahita
 
Spanish transpaerency
Spanish transpaerencySpanish transpaerency
Spanish transpaerencyke433987mhs88
 

Viewers also liked (20)

Afiche 25 04-15
Afiche 25 04-15Afiche 25 04-15
Afiche 25 04-15
 
Software usado en Tecnología en la E.S.O.
Software usado en Tecnología en la E.S.O.Software usado en Tecnología en la E.S.O.
Software usado en Tecnología en la E.S.O.
 
La planificación
La planificaciónLa planificación
La planificación
 
Hizb 24
Hizb 24Hizb 24
Hizb 24
 
Tipos de procesos
Tipos de procesosTipos de procesos
Tipos de procesos
 
Gat 14+1 (with key)
Gat 14+1 (with key)Gat 14+1 (with key)
Gat 14+1 (with key)
 
ورقة عمل الانعكاس
ورقة عمل الانعكاسورقة عمل الانعكاس
ورقة عمل الانعكاس
 
Bba403 international marketing
Bba403   international marketingBba403   international marketing
Bba403 international marketing
 
Algoritmos
AlgoritmosAlgoritmos
Algoritmos
 
Room and chores spanish
Room and chores spanishRoom and chores spanish
Room and chores spanish
 
Descripciones Del Puesto
Descripciones Del PuestoDescripciones Del Puesto
Descripciones Del Puesto
 
Auditoriademercadeo 120303082751-phpapp01
Auditoriademercadeo 120303082751-phpapp01Auditoriademercadeo 120303082751-phpapp01
Auditoriademercadeo 120303082751-phpapp01
 
Plantilla presentaciones cetach
Plantilla   presentaciones cetachPlantilla   presentaciones cetach
Plantilla presentaciones cetach
 
User2
User2User2
User2
 
M I S I O N V I S I O N D O F A
M I S I O N  V I S I O N  D O F AM I S I O N  V I S I O N  D O F A
M I S I O N V I S I O N D O F A
 
Metodo cientifico
Metodo cientificoMetodo cientifico
Metodo cientifico
 
Tema proyecto
Tema proyectoTema proyecto
Tema proyecto
 
Bosquejo
BosquejoBosquejo
Bosquejo
 
Spanish transpaerency
Spanish transpaerencySpanish transpaerency
Spanish transpaerency
 
Learn english why learn english
Learn english   why learn englishLearn english   why learn english
Learn english why learn english
 

Similar to Benefit Concrete

IRJET- Seismic Retrofitting
IRJET- Seismic RetrofittingIRJET- Seismic Retrofitting
IRJET- Seismic RetrofittingIRJET Journal
 
Sc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-aSc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-ajulio-civil
 
IRJET- Behavior of Compound Concrete Filled Reinforced PVC Tubes Under Compre...
IRJET- Behavior of Compound Concrete Filled Reinforced PVC Tubes Under Compre...IRJET- Behavior of Compound Concrete Filled Reinforced PVC Tubes Under Compre...
IRJET- Behavior of Compound Concrete Filled Reinforced PVC Tubes Under Compre...IRJET Journal
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
Prestressed concrete circular storage tanks
Prestressed concrete circular storage tanksPrestressed concrete circular storage tanks
Prestressed concrete circular storage tanksAman Bagrecha
 
Optimization of Precast Post-tensioned Concrete I-Girder Bridge
Optimization of Precast Post-tensioned Concrete I-Girder BridgeOptimization of Precast Post-tensioned Concrete I-Girder Bridge
Optimization of Precast Post-tensioned Concrete I-Girder BridgeIRJET Journal
 
Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Jeffrey Pickett
 
Design Parameters and Fluid Interaction of Amphibious Structures
Design Parameters and Fluid Interaction of Amphibious StructuresDesign Parameters and Fluid Interaction of Amphibious Structures
Design Parameters and Fluid Interaction of Amphibious StructuresIRJET Journal
 
Water NZ Article October 2013_WASTEWATER PUMP STATION 15 – A CASE STUDY IN AS...
Water NZ Article October 2013_WASTEWATER PUMP STATION 15 – A CASE STUDY IN AS...Water NZ Article October 2013_WASTEWATER PUMP STATION 15 – A CASE STUDY IN AS...
Water NZ Article October 2013_WASTEWATER PUMP STATION 15 – A CASE STUDY IN AS...Will Jacobson
 
IRJET- Analysis of Overhead Water Tank with Different Staging Height and Base...
IRJET- Analysis of Overhead Water Tank with Different Staging Height and Base...IRJET- Analysis of Overhead Water Tank with Different Staging Height and Base...
IRJET- Analysis of Overhead Water Tank with Different Staging Height and Base...IRJET Journal
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportJoshua Yu
 
Paper Bhr England 2008
Paper Bhr England 2008Paper Bhr England 2008
Paper Bhr England 2008williebloom
 
Concrete shear wall design
Concrete shear wall designConcrete shear wall design
Concrete shear wall designaj aj
 
Chapter 2 free vibration of single degree of freedom
Chapter 2 free vibration of single degree of freedomChapter 2 free vibration of single degree of freedom
Chapter 2 free vibration of single degree of freedomRafi sulaiman
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problemdhineshkumar002
 
Elevated water tank
Elevated water tankElevated water tank
Elevated water tankAamir Patni
 
Published-Badovli Mixture proportioning
Published-Badovli Mixture proportioningPublished-Badovli Mixture proportioning
Published-Badovli Mixture proportioningHamidreza Araghian
 
STRIPPING OF FORMWORK
STRIPPING OF FORMWORKSTRIPPING OF FORMWORK
STRIPPING OF FORMWORKK.K. PATHAK
 

Similar to Benefit Concrete (20)

IRJET- Seismic Retrofitting
IRJET- Seismic RetrofittingIRJET- Seismic Retrofitting
IRJET- Seismic Retrofitting
 
Sc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-aSc 0009-rwpc-pip-civ-cal-0511 0-a
Sc 0009-rwpc-pip-civ-cal-0511 0-a
 
IRJET- Behavior of Compound Concrete Filled Reinforced PVC Tubes Under Compre...
IRJET- Behavior of Compound Concrete Filled Reinforced PVC Tubes Under Compre...IRJET- Behavior of Compound Concrete Filled Reinforced PVC Tubes Under Compre...
IRJET- Behavior of Compound Concrete Filled Reinforced PVC Tubes Under Compre...
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Prestressed concrete circular storage tanks
Prestressed concrete circular storage tanksPrestressed concrete circular storage tanks
Prestressed concrete circular storage tanks
 
Optimization of Precast Post-tensioned Concrete I-Girder Bridge
Optimization of Precast Post-tensioned Concrete I-Girder BridgeOptimization of Precast Post-tensioned Concrete I-Girder Bridge
Optimization of Precast Post-tensioned Concrete I-Girder Bridge
 
Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.
 
Design Parameters and Fluid Interaction of Amphibious Structures
Design Parameters and Fluid Interaction of Amphibious StructuresDesign Parameters and Fluid Interaction of Amphibious Structures
Design Parameters and Fluid Interaction of Amphibious Structures
 
Water NZ Article October 2013_WASTEWATER PUMP STATION 15 – A CASE STUDY IN AS...
Water NZ Article October 2013_WASTEWATER PUMP STATION 15 – A CASE STUDY IN AS...Water NZ Article October 2013_WASTEWATER PUMP STATION 15 – A CASE STUDY IN AS...
Water NZ Article October 2013_WASTEWATER PUMP STATION 15 – A CASE STUDY IN AS...
 
IRJET- Analysis of Overhead Water Tank with Different Staging Height and Base...
IRJET- Analysis of Overhead Water Tank with Different Staging Height and Base...IRJET- Analysis of Overhead Water Tank with Different Staging Height and Base...
IRJET- Analysis of Overhead Water Tank with Different Staging Height and Base...
 
Retaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering ReportRetaining Structure Design, Professional Engineering Report
Retaining Structure Design, Professional Engineering Report
 
Paper Bhr England 2008
Paper Bhr England 2008Paper Bhr England 2008
Paper Bhr England 2008
 
Concrete shear wall design
Concrete shear wall designConcrete shear wall design
Concrete shear wall design
 
Chapter 2 free vibration of single degree of freedom
Chapter 2 free vibration of single degree of freedomChapter 2 free vibration of single degree of freedom
Chapter 2 free vibration of single degree of freedom
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
Fluids Mechanics.pdf
Fluids Mechanics.pdfFluids Mechanics.pdf
Fluids Mechanics.pdf
 
Elevated water tank
Elevated water tankElevated water tank
Elevated water tank
 
Published-Badovli Mixture proportioning
Published-Badovli Mixture proportioningPublished-Badovli Mixture proportioning
Published-Badovli Mixture proportioning
 
STRIPPING OF FORMWORK
STRIPPING OF FORMWORKSTRIPPING OF FORMWORK
STRIPPING OF FORMWORK
 
205
205205
205
 

More from williebloom

Navy Sample Tests
Navy Sample TestsNavy Sample Tests
Navy Sample Testswilliebloom
 
Landmines Norma Report
Landmines   Norma ReportLandmines   Norma Report
Landmines Norma Reportwilliebloom
 
How Pulse Jet Works(3)
How Pulse Jet Works(3)How Pulse Jet Works(3)
How Pulse Jet Works(3)williebloom
 
Vijay Hard Road Circ
Vijay Hard Road CircVijay Hard Road Circ
Vijay Hard Road Circwilliebloom
 
Asets Defense Presentation Fpwj 07 Feb2011
Asets Defense Presentation Fpwj 07 Feb2011Asets Defense Presentation Fpwj 07 Feb2011
Asets Defense Presentation Fpwj 07 Feb2011williebloom
 
Do D Policy Memo 8 April 2009
Do D Policy Memo 8 April 2009Do D Policy Memo 8 April 2009
Do D Policy Memo 8 April 2009williebloom
 
Bonnell Apwss Bhr 2010
Bonnell Apwss Bhr 2010Bonnell Apwss Bhr 2010
Bonnell Apwss Bhr 2010williebloom
 
Navy Sample Tests
Navy Sample TestsNavy Sample Tests
Navy Sample Testswilliebloom
 

More from williebloom (11)

Edc Nov.7.12
Edc Nov.7.12Edc Nov.7.12
Edc Nov.7.12
 
Wjta Paper 2011
Wjta Paper 2011Wjta Paper 2011
Wjta Paper 2011
 
Navy Sample Tests
Navy Sample TestsNavy Sample Tests
Navy Sample Tests
 
Landmines Norma Report
Landmines   Norma ReportLandmines   Norma Report
Landmines Norma Report
 
How Pulse Jet Works(3)
How Pulse Jet Works(3)How Pulse Jet Works(3)
How Pulse Jet Works(3)
 
Vijay Hard Road Circ
Vijay Hard Road CircVijay Hard Road Circ
Vijay Hard Road Circ
 
Asets Defense Presentation Fpwj 07 Feb2011
Asets Defense Presentation Fpwj 07 Feb2011Asets Defense Presentation Fpwj 07 Feb2011
Asets Defense Presentation Fpwj 07 Feb2011
 
Do D Policy Memo 8 April 2009
Do D Policy Memo 8 April 2009Do D Policy Memo 8 April 2009
Do D Policy Memo 8 April 2009
 
Bonnell Apwss Bhr 2010
Bonnell Apwss Bhr 2010Bonnell Apwss Bhr 2010
Bonnell Apwss Bhr 2010
 
Navy Sample Tests
Navy Sample TestsNavy Sample Tests
Navy Sample Tests
 
Aiac
AiacAiac
Aiac
 

Benefit Concrete

  • 1. Benefits of Using High-Frequency Forced Pulsed Waterjet for Refurbishing Delaminated Concrete Structures Figure 1 shows the photographs of the work done on refurbishing the delaminated (deteriorated) concrete ceiling, using VLN’s patented high-frequency forced pulsed waterjet (FPW J) machine. The location was underground parking garage, Lester B Pearson Building, Ottawa. The success of the job is quite evident from the photographs. Prior to awarding this contract to VLN, Public W orks Canada (PW C) was getting the job done by employing a chipper (hammer & chisel), sandblaster, at a cost of $40/sq.ft. W ith the employment of VLN’s machine, sandblasting was eliminated, and as removing the deteriorated concrete was so fast (see Fig. 2), the cost was reduced to about $10/sq.ft! Furthermore, there was no need to shut the entire parking garage because, as shown in Fig. 1 (C), it was Fig. 1. Refurbishing of delaminated (deteriorated) concrete from the only necessary to isolate working areas one at a time. ceilings of underground multi-story buildings. (A) Usual appearance of the ceiling with loose concrete and rusted Before taking the R&D contract work for the PW C, steel bars. laboratory tests were conducted on several types of concrete. (B) V LN’s forced pulsed waterjet (FPW J) at the underground Sample results on cutting with FPW J and the corresponding parking garage of External Affairs Building (Lester B Pearson) for continuous waterjet (CW J) are illustrated in Fig. 2. W hile refurbishing delaminated concrete. FPW J removed 0.283-m 3/hr of hard concrete (not (C) FPW J in the process of removing and cleaning the steel bars. deteriorated), CW J removed only 0.037-m 3/hr after four (D) Appearance of the refurbished delaminated area, showing the adjacent passes, both operating at identical conditions clean steel bars. (20,000-psi and power). In other words, to remove 1-m 3 of concrete, FPW J took only 3.5-hrs, compared to 27-hrs by the CW J. At a nominal wage of $25/hr, the contractor employing the ubiquitous CW J pays $675, and a visionary contractor, who would use FPW J, pays only $87.5 for the job of removing 1-m 3 of concrete. The savings does not end here! Savings in cost of Energy Consumption: Total energy consumed by FPW J: 387-kW.hr Total energy consumed by CW J: 2,490-kw.hr! At the rate of $3.25/kW .hr (based on the rate charged to VLN by Ottawa Hydro, which includes delivery charge, Fig. 2. These results clearly show the benefit of using FPW J GST, etc), the contractor would save a staggering $6,800 to compared to continuous waterjet (CW J), both operating at identical remove 1-m 3 of concrete! AND, operating conditions (pressure, power, etc). Abatement of Pollution (Based on the Data Provided by CANM ET) According to CANMET (a Department of Government of Canada), based on diesel fuel, CO 2 loading of the environment is: 71- kg/GJ of energy comsumption. Therefore: CO 2 emission by the use of FPW J: 99,000-kg CO 2 emission by the use of FPW J: 636,400-kg (staggering!) This reduction, resulting by using FPW J, must make any environmentalist happy (how about the proponents of Kyoto?) Note: These results apply to all applications VLN has investigated, ranging from cutting rocks to rem oving hard coatings of paints. Prepared by: M ohan Vijay, Ph.D., P.Eng., President, VLN Advanced Technologies, Ottawa, Canada (www.VLN-Tech.com).