3. Existing Conditions
Existing Bridge: Albany Turnpike over CSXT
Constructed in 1906
Town of East Chatham, New York
Berlin Construction Co., Berlin, CT
Double Warren Through Truss
Approx. 115’ Span x 18 ‘ Roadway Width x 17’ Deep
Single Lane Roadway
Vertical Clearance = 21’- 7”
Timber Deck / Asphalt Wearing Surface
5. Given Information
CSXT Owner (Major Maintenance)
Low Volume, Minor Collector (Rural)
Original Design Load H10 (10T = 20,000 lbs. GVW)
NYSDOT Inspection (Critical Event)
Rated for 20T prior to inspection
Load Posted to 4T in 2012
Structurally Deficient, Sufficiency Rating 43.3
Numerous Deterioration “Red Flags”
Emergency Contract:
Bergmann Associates, Albany Office
6.
7. First thoughts on the Project
Repair
Rehabilitate
Replace
• Original 20 Ton
rating not
possible in only
repairing minor
item(s).
• Repair current inspection
“red flags” and also ones
predicted for next inspection
cycle (“yellow flags”).
• Restore Previous Load
Posting (20 Ton) or Greater
• Most expensive
option and one that
the Owner had not
budgeted.
8. Rehabilitation Scope
Remove Asphalt Overlay, Timber Curb, and Timber
Deck
Complete Steel Repairs to Trusses, Floorbeams,
and Bottom Lateral Bracing
Remove and Replace Timber Stringers (as needed)
Install New Timber Deck & Curb, Pave Asphalt Wear
Crs.
Re-open to Traffic
Restrictions: No Construction Loads except Personnel; No
Temporary Reduction in Vertical Clearance; Temporary Shoring of
Diagonals and Floorbeams required during Gusset Plate
Repair/Replacement ; One Gusset Plate Repair at a Time
9. “Sleeved” Bridge Support & Platform
WAY-CR47 (Indian Mill Bridge) Rehabilitation
over the Sandusky River
Wyandot County, Ohio
Construction: U.S. Bridge/
10. Moving Toward Bid
A couple problems came to light about this plan …
… IT WASN’T A LONG TERM SOLUTION SO
NO ONE WAS REALLY HAPPY WITH THE
SITUATION.
… IT WAS COSTING MORE THAN
EXPECTED.
12. Bid Results
Bidding (Rehabilitation Plans)
4 Contractors Invited to Submit Bid
Mandatory Pre-Bid Site Visit
Base Bid: Bridge Rehabilitation
Alternate Bid: Superstructure Replacement (late addition)
Bid Results
Two Bids: $300k; $677k
Only the Low Bidder Submitted an Alternate Bid: $550k
13. One last ‘i’ and one last ‘t’
What was it going to cost to recondition the
existing abutments?
If a ‘GO’, would the Town of East Chatham
be willing to own the bridge?
So Bergmann prepared schematic TS&L
type plans (30%).
They were.
14. Loads Reactions % of CDS
Concrete Deck Slab & SIP = 120 psf
Concrete Deck Slab (Strip or Foam) = 106
psf
Asphalt Filled Steel Floor = 89 psf
Exodermic Deck = 75 psf
Timber Panels = 62 psf
DL= 216 k
DL= 191 k
DL= 142 k
DL= 135 k
DL= 112 k
100%
93%
80%
78%
72%
Floor Framing Self Wt. = 22 psf
Truss Self Wt. = 306 plf
FWS = 25 psf
DL= 40 k
DL= 70 k
DL= 45 k
Final Total (Exodermic) DL= 72.6k
Loads Reactions % of CDS&SIP
Concrete Deck Slab & SIP = 120 psf
Concrete Deck Slab (Strip or Foam) = 106
psf
Asphalt Filled Steel Floor = 89 psf
Exodermic Deck = 75 psf
Timber Panels = 62 psf
DL= 54.1 k
DL= 47.8 k
DL= 35.6 k
DL= 33.8 k
DL= 27.9 k
100%
93%
80%
78%
72%
Floor Framing Self Weight = 22 psf
Truss Self Weight = 306 plf
FWS = 25 psf
DL= 9.9 k
DL= 17.6 k
DL= 11.3 k
Final Total (Exodermic) DL= 72.6 k
Dead Load Study
Acceptable - So we have a green light
to go forward …
15. New Scope of Work
HL93 Live Load & NYSDOT Permit Vehicle
Railing Service Level TL-2
One Lane, 14’-0” Clear
Match or Improve Existing Sight Distance
Outboard Sidewalk for Pedestrians
Improve Existing Vertical Clearance
Design Reconstructed Abutment Caps
Concrete Approach Slabs
22. Exodermic® Deck Details
Courtesy of the Bridge Grid Flooring Manufacturers Association (BGFMA) www.bgfma.org
For this project:
• WT4x5 Bearing Bars at 12” o.c.
• 1 ½” x 1/4” Distribution Bars at 6” o.c.
• 20 Ga. Haunch & Flat Pans
• Longitudinal: #3 bars at 6” o.c.
• Transverse: #5 bars at 8” o.c.
26. Superstructure Replacement Cost
Mobilization $50.0k
WZTC $5.0k
Remove Existing Bridge $80.0k
Furnish New Truss $450.0k
Install New Truss $130.0k
Earthwork $100.0k
Concrete Work $210.0k
Approach Work $175.0k
Total $1,200.0k ($1.2M)
27. Project Participants
Owner: CSXT Railroad, Jacksonville, FL
Ross White, Territory Manager
Contractor: CP Ward, Inc. of Scottsville, NY
Steve Phillips, Vice President
Design Consultant: Bergmann Associates, Albany,
NY
Michael Cooper, P.E., Project Manager
Superstructure Design: Contech & U.S. Bridge
Dave Morgan, P.E., Project Engineer
Exodermic Deck Design: LB Foster, Pittsburgh, PA
Ed Coholich, Project Manager
Town of Chatham
Mr. Jesse DeGroodt, Town Supervisor
49. What made this project work?
Collaborative Partnership
Innovative Thinking
Non-binding alternate bid proposal
Exodermic Deck
Steel framing (both at the south abutment and sidewalk).
Deck installation and pour sequence
- Leaving us with a unique project that was
successful for the Town and the Owner -
Questions?
Deck is removed, preliminary steel removals complete
Demo day, 9/24/13
Contractor was given a 4 hour window of track time to remove remaining floorbeams, bracing, and both trusses.
Tuesday from 5 (after last commuter train) to 9 pm.
Floorbeams cut at each end, lowered with forklift.
SLOW…consider pre-cutting, rivet pre-replacement with bolts, additional crew/equipment, etc
Picking the first truss
Second truss braced by cable to deadman anchors and struts to existing abutment; forklift at midspan for lateral brace
Second truss picked clean
Finished demo just in time for passage of two waiting freight trains.
New gabion retaining wall be concrete backwall and existing gabion wall.
New south approach paved with only days to spare before asphalt plants shut down.
Setting the first truss
Fit like a glove
Second truss
Note cable guys to deadman for first truss
Install floorbeams from one end; “zipper the trusses”. Three floorbeams required to keep span stable
Floorbeams are in
Exodermic deck pans are installed
Minimum vertical clearance, so couldn’t hang underdeck shielding beneath bridge. Shrink wrapped bridge to keep heat for concrete deck. VERY COLD WINTER!
Cast curbs first, used them as supports for air screed fininsher
Finished deck…
Underside of exodermic deck, sidewalk cantilever, utility brackets (conduit for future traffic signal by Town, or other use as needed)