SlideShare a Scribd company logo
1 of 50
Albany Turnpike over CSXT Railroad
Superstructure Replacement Project
East Chatham, New York
Intersection
Adjacent property
Intersection
Utilities
Existing Conditions
 Existing Bridge: Albany Turnpike over CSXT
 Constructed in 1906
 Town of East Chatham, New York
 Berlin Construction Co., Berlin, CT
 Double Warren Through Truss
 Approx. 115’ Span x 18 ‘ Roadway Width x 17’ Deep
 Single Lane Roadway
 Vertical Clearance = 21’- 7”
 Timber Deck / Asphalt Wearing Surface
ASCE/APWA Summer Meeting 2014
Given Information
 CSXT Owner (Major Maintenance)
 Low Volume, Minor Collector (Rural)
 Original Design Load H10 (10T = 20,000 lbs. GVW)
 NYSDOT Inspection (Critical Event)
 Rated for 20T prior to inspection
 Load Posted to 4T in 2012
 Structurally Deficient, Sufficiency Rating 43.3
 Numerous Deterioration “Red Flags”
 Emergency Contract:
 Bergmann Associates, Albany Office
First thoughts on the Project
Repair
Rehabilitate
Replace
• Original 20 Ton
rating not
possible in only
repairing minor
item(s).
• Repair current inspection
“red flags” and also ones
predicted for next inspection
cycle (“yellow flags”).
• Restore Previous Load
Posting (20 Ton) or Greater
• Most expensive
option and one that
the Owner had not
budgeted.
Rehabilitation Scope
 Remove Asphalt Overlay, Timber Curb, and Timber
Deck
 Complete Steel Repairs to Trusses, Floorbeams,
and Bottom Lateral Bracing
 Remove and Replace Timber Stringers (as needed)
 Install New Timber Deck & Curb, Pave Asphalt Wear
Crs.
 Re-open to Traffic
 Restrictions: No Construction Loads except Personnel; No
Temporary Reduction in Vertical Clearance; Temporary Shoring of
Diagonals and Floorbeams required during Gusset Plate
Repair/Replacement ; One Gusset Plate Repair at a Time
“Sleeved” Bridge Support & Platform
WAY-CR47 (Indian Mill Bridge) Rehabilitation
over the Sandusky River
Wyandot County, Ohio
Construction: U.S. Bridge/
Moving Toward Bid
 A couple problems came to light about this plan …
… IT WASN’T A LONG TERM SOLUTION SO
NO ONE WAS REALLY HAPPY WITH THE
SITUATION.
… IT WAS COSTING MORE THAN
EXPECTED.
Novel Idea
Repair
Rehabilitate
Replace
Superstructure
Replacement
Bid Item
Bid Results
 Bidding (Rehabilitation Plans)
 4 Contractors Invited to Submit Bid
 Mandatory Pre-Bid Site Visit
 Base Bid: Bridge Rehabilitation
 Alternate Bid: Superstructure Replacement (late addition)
 Bid Results
 Two Bids: $300k; $677k
 Only the Low Bidder Submitted an Alternate Bid: $550k
One last ‘i’ and one last ‘t’
 What was it going to cost to recondition the
existing abutments?
 If a ‘GO’, would the Town of East Chatham
be willing to own the bridge?
 So Bergmann prepared schematic TS&L
type plans (30%).
 They were.
Loads Reactions % of CDS
Concrete Deck Slab & SIP = 120 psf
Concrete Deck Slab (Strip or Foam) = 106
psf
Asphalt Filled Steel Floor = 89 psf
Exodermic Deck = 75 psf
Timber Panels = 62 psf
DL= 216 k
DL= 191 k
DL= 142 k
DL= 135 k
DL= 112 k
100%
93%
80%
78%
72%
Floor Framing Self Wt. = 22 psf
Truss Self Wt. = 306 plf
FWS = 25 psf
DL= 40 k
DL= 70 k
DL= 45 k
Final Total (Exodermic) DL= 72.6k
Loads Reactions % of CDS&SIP
Concrete Deck Slab & SIP = 120 psf
Concrete Deck Slab (Strip or Foam) = 106
psf
Asphalt Filled Steel Floor = 89 psf
Exodermic Deck = 75 psf
Timber Panels = 62 psf
DL= 54.1 k
DL= 47.8 k
DL= 35.6 k
DL= 33.8 k
DL= 27.9 k
100%
93%
80%
78%
72%
Floor Framing Self Weight = 22 psf
Truss Self Weight = 306 plf
FWS = 25 psf
DL= 9.9 k
DL= 17.6 k
DL= 11.3 k
Final Total (Exodermic) DL= 72.6 k
Dead Load Study
Acceptable - So we have a green light
to go forward …
New Scope of Work
 HL93 Live Load & NYSDOT Permit Vehicle
 Railing Service Level TL-2
 One Lane, 14’-0” Clear
 Match or Improve Existing Sight Distance
 Outboard Sidewalk for Pedestrians
 Improve Existing Vertical Clearance
 Design Reconstructed Abutment Caps
 Concrete Approach Slabs
Proposed Section
 Single Lane
 Outboard Sidewalk
 Curbed Roadway
 Vandal Protective
Fencing
Proposed Site Plan
 Guardrail upgrades or extensions (red)
 Gabion retaining walls (maroon)
 Pavement transitions (green)
Proposed Profile
 Maintain SSD
 Improve rail vertical
clearance to 21’-9”
 Recondition existing
abutments
Schedule
PO
issued
USB
8/6/13
Initial
Submittal
9/2513
Release
for Fab
10/3/13
Shipped
to Site
11/12/13
Begin
Shipments
to Site
11/18/1
3
Steel
Erected
11/26/1
3
Concrete
Slab Pour
01/14/1
4
Opened to
Traffic
01/31/1
4
50 days 8 days 46 days
8 days 49 days 17 days
Total = 178 days
Steel Bridge Design
 Early Coordination of Final Loads & Reactions
 Different skews caused different truss spans
 Left =112’-5 ¾”; Right Truss = 114’-11 ¾”
 AASHTO DL & LL Loads, Wind Loads
 Strength, Service, Fatigue & Extreme Event Load Comb.
 Top Chord/U-Frame Stability Check
 Gusset Plate Check (per 2009 FHWA Guidance Report)
Steel Bridge Design
 Extreme Profile Change/Unusual Framing
 Exodermic Deck Layout, Slab Reinforcing &
Coordination
 Bearing Pad Design: Fixed & Sliding CDB (Cotton
Duck)
 Armored Expansion Joint: Wabo WA300
Compression Seal
 Vandal Protection Fencing Coordination
 NYSDOT Level 1 Load Rating (LRFR)
Exodermic® Deck Details
Courtesy of the Bridge Grid Flooring Manufacturers Association (BGFMA) www.bgfma.org
For this project:
• WT4x5 Bearing Bars at 12” o.c.
• 1 ½” x 1/4” Distribution Bars at 6” o.c.
• 20 Ga. Haunch & Flat Pans
• Longitudinal: #3 bars at 6” o.c.
• Transverse: #5 bars at 8” o.c.
Steel Bridge Design
Looking South at the Forward Abutment
Steel Bridge Design
Looking South at the Forward Abutment
Steel Statistics
 Truss Girder Weight = 34,810 lbs.
 Heaviest Segment = 12,070 lbs.
 Floor Framing Weight = 40,443 lbs.
 Unique Floor Beams = 7; Unique Stringers = 18
 Heaviest Section (Truss): W14x82
 Heaviest Section (Framing): W18x50
 Total Weight Steel & Hardware = 136,754 lbs.
 Total Fasteners: 5,462 Bolts
 Most Common Size: 7/8” dia. x 2 ½” (2,012 Bolts)
 Shipped in 4 Truck Loads
Superstructure Replacement Cost
 Mobilization $50.0k
 WZTC $5.0k
 Remove Existing Bridge $80.0k
 Furnish New Truss $450.0k
 Install New Truss $130.0k
 Earthwork $100.0k
 Concrete Work $210.0k
 Approach Work $175.0k
 Total $1,200.0k ($1.2M)
Project Participants
 Owner: CSXT Railroad, Jacksonville, FL
 Ross White, Territory Manager
 Contractor: CP Ward, Inc. of Scottsville, NY
 Steve Phillips, Vice President
 Design Consultant: Bergmann Associates, Albany,
NY
 Michael Cooper, P.E., Project Manager
 Superstructure Design: Contech & U.S. Bridge
 Dave Morgan, P.E., Project Engineer
 Exodermic Deck Design: LB Foster, Pittsburgh, PA
 Ed Coholich, Project Manager
 Town of Chatham
 Mr. Jesse DeGroodt, Town Supervisor
construction
construction
construction
construction
construction
construction
construction
construction
construction
construction
construction
Model to Reality
Looking West at the Left Truss Girder
construction
construction
construction
construction
construction
construction
construction
What made this project work?
 Collaborative Partnership
 Innovative Thinking
 Non-binding alternate bid proposal
 Exodermic Deck
 Steel framing (both at the south abutment and sidewalk).
 Deck installation and pour sequence
- Leaving us with a unique project that was
successful for the Town and the Owner -
Questions?
Thank you

More Related Content

Similar to Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, NY (08-24-14)

Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)dgonano
 
KYC Harbour Redevelopment - AGM 2013 - Status Update
KYC Harbour Redevelopment  - AGM 2013 - Status UpdateKYC Harbour Redevelopment  - AGM 2013 - Status Update
KYC Harbour Redevelopment - AGM 2013 - Status Updatekingstonyc
 
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2dgonano
 
Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...mecocca5
 
Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design ProjectEd Guerra, P.E.
 
Prolonging the service life of existing reinforced concrete slab bridges
Prolonging the service life of existing reinforced concrete slab bridgesProlonging the service life of existing reinforced concrete slab bridges
Prolonging the service life of existing reinforced concrete slab bridgesEva Lantsoght
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)dgonano
 
Hotel Design
Hotel DesignHotel Design
Hotel Designkylejanco
 
Culvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsCulvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsPath Marketing Inc.
 
CE 316 design of RC cantilever bridge
CE 316 design of RC cantilever bridgeCE 316 design of RC cantilever bridge
CE 316 design of RC cantilever bridgenazifa tabassum
 
Thesis Poster Presentation
Thesis Poster PresentationThesis Poster Presentation
Thesis Poster PresentationPaul Trofimov
 
Bridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
Bridge Deck-Guardrail Anchorage Detailing For Sustainable ConstructionBridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
Bridge Deck-Guardrail Anchorage Detailing For Sustainable ConstructionMahmoud Sayed Ahmed
 
Bridge & Road Construction .pptx
Bridge & Road Construction .pptxBridge & Road Construction .pptx
Bridge & Road Construction .pptxMosaddekHaqueReyad
 
Lebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting PresentationLebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting PresentationCity of Lebanon
 
Senior Design Capstone Presentation
Senior Design Capstone PresentationSenior Design Capstone Presentation
Senior Design Capstone Presentationfinkjosh
 

Similar to Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, NY (08-24-14) (20)

Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
Bridge Alternate Type Study - Railroad Grade Separation (04-17-14)
 
KYC Harbour Redevelopment - AGM 2013 - Status Update
KYC Harbour Redevelopment  - AGM 2013 - Status UpdateKYC Harbour Redevelopment  - AGM 2013 - Status Update
KYC Harbour Redevelopment - AGM 2013 - Status Update
 
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
Bridge Alternate Type Study - Stream Crossing (09-04-12)v2
 
Nace barker presentation
Nace barker presentationNace barker presentation
Nace barker presentation
 
Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...
 
Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design Project
 
Prolonging the service life of existing reinforced concrete slab bridges
Prolonging the service life of existing reinforced concrete slab bridgesProlonging the service life of existing reinforced concrete slab bridges
Prolonging the service life of existing reinforced concrete slab bridges
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)
 
Floating Bridge
Floating BridgeFloating Bridge
Floating Bridge
 
Hotel Design
Hotel DesignHotel Design
Hotel Design
 
PRESENTATION (1)
PRESENTATION (1)PRESENTATION (1)
PRESENTATION (1)
 
Culvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsCulvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & Applications
 
CE 316 design of RC cantilever bridge
CE 316 design of RC cantilever bridgeCE 316 design of RC cantilever bridge
CE 316 design of RC cantilever bridge
 
Thesis Poster Presentation
Thesis Poster PresentationThesis Poster Presentation
Thesis Poster Presentation
 
Bridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
Bridge Deck-Guardrail Anchorage Detailing For Sustainable ConstructionBridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
Bridge Deck-Guardrail Anchorage Detailing For Sustainable Construction
 
ASCE San Ramon Canyon Storm Drain 6 4-15
ASCE San Ramon Canyon Storm Drain 6 4-15 ASCE San Ramon Canyon Storm Drain 6 4-15
ASCE San Ramon Canyon Storm Drain 6 4-15
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
Bridge & Road Construction .pptx
Bridge & Road Construction .pptxBridge & Road Construction .pptx
Bridge & Road Construction .pptx
 
Lebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting PresentationLebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting Presentation
 
Senior Design Capstone Presentation
Senior Design Capstone PresentationSenior Design Capstone Presentation
Senior Design Capstone Presentation
 

Albany Turnpike over CSXT Railroad Superstucture Replacement, East Chatham, NY (08-24-14)

  • 1. Albany Turnpike over CSXT Railroad Superstructure Replacement Project East Chatham, New York
  • 3. Existing Conditions  Existing Bridge: Albany Turnpike over CSXT  Constructed in 1906  Town of East Chatham, New York  Berlin Construction Co., Berlin, CT  Double Warren Through Truss  Approx. 115’ Span x 18 ‘ Roadway Width x 17’ Deep  Single Lane Roadway  Vertical Clearance = 21’- 7”  Timber Deck / Asphalt Wearing Surface
  • 5. Given Information  CSXT Owner (Major Maintenance)  Low Volume, Minor Collector (Rural)  Original Design Load H10 (10T = 20,000 lbs. GVW)  NYSDOT Inspection (Critical Event)  Rated for 20T prior to inspection  Load Posted to 4T in 2012  Structurally Deficient, Sufficiency Rating 43.3  Numerous Deterioration “Red Flags”  Emergency Contract:  Bergmann Associates, Albany Office
  • 6.
  • 7. First thoughts on the Project Repair Rehabilitate Replace • Original 20 Ton rating not possible in only repairing minor item(s). • Repair current inspection “red flags” and also ones predicted for next inspection cycle (“yellow flags”). • Restore Previous Load Posting (20 Ton) or Greater • Most expensive option and one that the Owner had not budgeted.
  • 8. Rehabilitation Scope  Remove Asphalt Overlay, Timber Curb, and Timber Deck  Complete Steel Repairs to Trusses, Floorbeams, and Bottom Lateral Bracing  Remove and Replace Timber Stringers (as needed)  Install New Timber Deck & Curb, Pave Asphalt Wear Crs.  Re-open to Traffic  Restrictions: No Construction Loads except Personnel; No Temporary Reduction in Vertical Clearance; Temporary Shoring of Diagonals and Floorbeams required during Gusset Plate Repair/Replacement ; One Gusset Plate Repair at a Time
  • 9. “Sleeved” Bridge Support & Platform WAY-CR47 (Indian Mill Bridge) Rehabilitation over the Sandusky River Wyandot County, Ohio Construction: U.S. Bridge/
  • 10. Moving Toward Bid  A couple problems came to light about this plan … … IT WASN’T A LONG TERM SOLUTION SO NO ONE WAS REALLY HAPPY WITH THE SITUATION. … IT WAS COSTING MORE THAN EXPECTED.
  • 12. Bid Results  Bidding (Rehabilitation Plans)  4 Contractors Invited to Submit Bid  Mandatory Pre-Bid Site Visit  Base Bid: Bridge Rehabilitation  Alternate Bid: Superstructure Replacement (late addition)  Bid Results  Two Bids: $300k; $677k  Only the Low Bidder Submitted an Alternate Bid: $550k
  • 13. One last ‘i’ and one last ‘t’  What was it going to cost to recondition the existing abutments?  If a ‘GO’, would the Town of East Chatham be willing to own the bridge?  So Bergmann prepared schematic TS&L type plans (30%).  They were.
  • 14. Loads Reactions % of CDS Concrete Deck Slab & SIP = 120 psf Concrete Deck Slab (Strip or Foam) = 106 psf Asphalt Filled Steel Floor = 89 psf Exodermic Deck = 75 psf Timber Panels = 62 psf DL= 216 k DL= 191 k DL= 142 k DL= 135 k DL= 112 k 100% 93% 80% 78% 72% Floor Framing Self Wt. = 22 psf Truss Self Wt. = 306 plf FWS = 25 psf DL= 40 k DL= 70 k DL= 45 k Final Total (Exodermic) DL= 72.6k Loads Reactions % of CDS&SIP Concrete Deck Slab & SIP = 120 psf Concrete Deck Slab (Strip or Foam) = 106 psf Asphalt Filled Steel Floor = 89 psf Exodermic Deck = 75 psf Timber Panels = 62 psf DL= 54.1 k DL= 47.8 k DL= 35.6 k DL= 33.8 k DL= 27.9 k 100% 93% 80% 78% 72% Floor Framing Self Weight = 22 psf Truss Self Weight = 306 plf FWS = 25 psf DL= 9.9 k DL= 17.6 k DL= 11.3 k Final Total (Exodermic) DL= 72.6 k Dead Load Study Acceptable - So we have a green light to go forward …
  • 15. New Scope of Work  HL93 Live Load & NYSDOT Permit Vehicle  Railing Service Level TL-2  One Lane, 14’-0” Clear  Match or Improve Existing Sight Distance  Outboard Sidewalk for Pedestrians  Improve Existing Vertical Clearance  Design Reconstructed Abutment Caps  Concrete Approach Slabs
  • 16. Proposed Section  Single Lane  Outboard Sidewalk  Curbed Roadway  Vandal Protective Fencing
  • 17. Proposed Site Plan  Guardrail upgrades or extensions (red)  Gabion retaining walls (maroon)  Pavement transitions (green)
  • 18. Proposed Profile  Maintain SSD  Improve rail vertical clearance to 21’-9”  Recondition existing abutments
  • 19. Schedule PO issued USB 8/6/13 Initial Submittal 9/2513 Release for Fab 10/3/13 Shipped to Site 11/12/13 Begin Shipments to Site 11/18/1 3 Steel Erected 11/26/1 3 Concrete Slab Pour 01/14/1 4 Opened to Traffic 01/31/1 4 50 days 8 days 46 days 8 days 49 days 17 days Total = 178 days
  • 20. Steel Bridge Design  Early Coordination of Final Loads & Reactions  Different skews caused different truss spans  Left =112’-5 ¾”; Right Truss = 114’-11 ¾”  AASHTO DL & LL Loads, Wind Loads  Strength, Service, Fatigue & Extreme Event Load Comb.  Top Chord/U-Frame Stability Check  Gusset Plate Check (per 2009 FHWA Guidance Report)
  • 21. Steel Bridge Design  Extreme Profile Change/Unusual Framing  Exodermic Deck Layout, Slab Reinforcing & Coordination  Bearing Pad Design: Fixed & Sliding CDB (Cotton Duck)  Armored Expansion Joint: Wabo WA300 Compression Seal  Vandal Protection Fencing Coordination  NYSDOT Level 1 Load Rating (LRFR)
  • 22. Exodermic® Deck Details Courtesy of the Bridge Grid Flooring Manufacturers Association (BGFMA) www.bgfma.org For this project: • WT4x5 Bearing Bars at 12” o.c. • 1 ½” x 1/4” Distribution Bars at 6” o.c. • 20 Ga. Haunch & Flat Pans • Longitudinal: #3 bars at 6” o.c. • Transverse: #5 bars at 8” o.c.
  • 23. Steel Bridge Design Looking South at the Forward Abutment
  • 24. Steel Bridge Design Looking South at the Forward Abutment
  • 25. Steel Statistics  Truss Girder Weight = 34,810 lbs.  Heaviest Segment = 12,070 lbs.  Floor Framing Weight = 40,443 lbs.  Unique Floor Beams = 7; Unique Stringers = 18  Heaviest Section (Truss): W14x82  Heaviest Section (Framing): W18x50  Total Weight Steel & Hardware = 136,754 lbs.  Total Fasteners: 5,462 Bolts  Most Common Size: 7/8” dia. x 2 ½” (2,012 Bolts)  Shipped in 4 Truck Loads
  • 26. Superstructure Replacement Cost  Mobilization $50.0k  WZTC $5.0k  Remove Existing Bridge $80.0k  Furnish New Truss $450.0k  Install New Truss $130.0k  Earthwork $100.0k  Concrete Work $210.0k  Approach Work $175.0k  Total $1,200.0k ($1.2M)
  • 27. Project Participants  Owner: CSXT Railroad, Jacksonville, FL  Ross White, Territory Manager  Contractor: CP Ward, Inc. of Scottsville, NY  Steve Phillips, Vice President  Design Consultant: Bergmann Associates, Albany, NY  Michael Cooper, P.E., Project Manager  Superstructure Design: Contech & U.S. Bridge  Dave Morgan, P.E., Project Engineer  Exodermic Deck Design: LB Foster, Pittsburgh, PA  Ed Coholich, Project Manager  Town of Chatham  Mr. Jesse DeGroodt, Town Supervisor
  • 28.
  • 40. Model to Reality Looking West at the Left Truss Girder
  • 48.
  • 49. What made this project work?  Collaborative Partnership  Innovative Thinking  Non-binding alternate bid proposal  Exodermic Deck  Steel framing (both at the south abutment and sidewalk).  Deck installation and pour sequence - Leaving us with a unique project that was successful for the Town and the Owner - Questions?

Editor's Notes

  1. Deck demolition
  2. Deck demolition
  3. Deck is removed, preliminary steel removals complete
  4. Demo day, 9/24/13 Contractor was given a 4 hour window of track time to remove remaining floorbeams, bracing, and both trusses. Tuesday from 5 (after last commuter train) to 9 pm.
  5. Floorbeams cut at each end, lowered with forklift. SLOW…consider pre-cutting, rivet pre-replacement with bolts, additional crew/equipment, etc
  6. Picking the first truss Second truss braced by cable to deadman anchors and struts to existing abutment; forklift at midspan for lateral brace Second truss picked clean Finished demo just in time for passage of two waiting freight trains.
  7. New gabion retaining wall be concrete backwall and existing gabion wall.
  8. New south approach paved with only days to spare before asphalt plants shut down.
  9. Setting the first truss
  10. Fit like a glove
  11. Second truss Note cable guys to deadman for first truss
  12. Install floorbeams from one end; “zipper the trusses”. Three floorbeams required to keep span stable
  13. Floorbeams are in
  14. Exodermic deck pans are installed
  15. Minimum vertical clearance, so couldn’t hang underdeck shielding beneath bridge. Shrink wrapped bridge to keep heat for concrete deck. VERY COLD WINTER!
  16. Cast curbs first, used them as supports for air screed fininsher
  17. Finished deck…
  18. Underside of exodermic deck, sidewalk cantilever, utility brackets (conduit for future traffic signal by Town, or other use as needed)
  19. Open to traffic, south approach