1. # OF STEPS STEPS DESCRIPTION
TIME
(SEC)
DISTANCE(
FT)
IMPORTANCE
1 Material Moved from rack to the cutting machine 300 2 Non- Value
2 Stacked near to the Cutting Machine 600 0 Non- Value
3 Placing to the materila to the machine 600 3 Non- Value
4 Starting , operating and changing the materials 300 0 Non- Value
5 Cutting Operation 120 0 Value
6 Moved to welding section 300 3 Non- Value
7 Placed near to the welding section 600 0 Non- Value
8 Placing the material on to the welding table 600 0 Value
9 Arranging the Material with the help of jigs and fixture 300 0 Value
10 Welding Operation 120 0 Value
11 Checking the corner of the frame 120 0 Non- Value
12 Moved to the df Buffing and polishing seciton 300 3 Non- Value
13 Placing the material on welding section 300 0 Non- Value
14 Placed on to the jigs and fixture 300 0 Value
15 Buffing Operation 120 0 Value
16 Moved to Poishing area 120 5 Non- Value
17 Staced the material for Polishig Operation 600 0 Non- Value
18 Moved to Polishing area 300 3 Non- Value
19 Polising Operation 120 0 Value
20 Moved to Assembly section 300 3 Non- Value
Total Activities 7 6 1 4 4 1.8 22 22
PROCESS CHART-xxxxModel-xxxxx
Prepared by Vivek Jacob John
4. Takt time
# of working days
# of working hrs/day 26 # of working days 26
total working hrs /month 7.5 # of working hrs/day 7.5
total working min 195 total working hrs /month 195
total working sec 11700 total working min 11700
total no of units 702000 total working sec 702000
20000000 total no of units 20000000
28.49002849 28.49002849
Cycle time
Prepared by Vivek Jacob John