Cost Analysis for
Fabrication and Erection of Steel Arch Bridges on
East West Highway (H01)
Item of Work:
Steel Arch (Providing, Fabricating, assembling and erecting structural
steel components/elements including nut, bolt, gusset plate ,including
heavy zinc coat galvanization, facilities for inspection & test in gradual
assembling as per approved design, shop drawings, technical
specification and to the satisfaction of Engineer all complete)
Total Quantity:
12,555,255.00 KG (Two Packages)
Plan and Elevation of Bridge
Total Weight of Bridges
S.No Bridge Name Span No of Span Width
max Height of
bridge
Steel Weight
KG
Nut Bolts
Weight KG
mtr mtr mtr
Pack-x
1 b 79.5 2 13.95 13.5 1,506,740.00 41,362.40
2 k 87.6 4 13.95 14.9 3,353,504.00 90,809.36
3 n 79.5 2 13.95 13.5 1,506,740.00 41,362.40
6,366,984.00 173,534.16
Pack-y
4 B 79.5 2 13.95 14.6 1,506,740.00 41,362.40
5 L 85.25 2 18.65 14.6 1,820,800.00 54,588.37
6 R 87.6 3 18.65 14.9 2,860,731.00 82,093.13
6,188,271.00 178,043.90
Total Weight 12,555,255.00 351,578.06
Maximum Sizes and Weights
S.No Bridge Name
Max Lifting
Weight
Max Length of single
piece
MT m
Pack-x
1 b 14.6 11.6
2 k 15.5 12.4
3 n 14.6 11.6
Pack-y
4 B 14.6 11.6
5 L 15.3 11.8
6 R 15.6 12.4
Quantity of Plates in Different Thickness (E410)
Bridge Name
Plate Thickness
Total Qquantity
12mm 16mm 20mm 26mm 30mm 40mm
B 166718 183102 304235 162301 687233 3149 1506738
K 366740 417795 696074
326,304
1539602 6990 3353505
N 166718 183102 304235 162301 687233 3149 1506738
B 166718 183102 304235 162301 687233 3149 1506738
L 232660 263298 351008 179947 790392 3495 1820800
R 359357 399288 539806 0 1557036 5243 2860730
Total MT 1458.911 1629.687 2499.593 993.154 5948.729 25.175 12555.249
Percentage by
thickness 11.6% 13.0% 19.9% 7.9% 47.4% 0.2% 100%
* Length Prefered 12.5m (minimum 12m) *Width prefered 2.0m to 3m
Summary of Rate Analysis for 1MT of finished goods
(for 1000 kg weight/5% waste considered)
S. No Item Qty Unit
Unit
Rate
Amount
Assuming 6000
MT work)
Amount Assuming
12000 MT work)
1
Steel landed cost
1050 Kg 137.00 143,850.00 143,850.00
(78 IC CIF*1.6+7.5%+2.5 transport
Nepal)
2
Fabrication Consumables and
Electricity 7,500.00 7,500.00
3 Fabrication Labour 9,000.00 9,000.00
4 Erection labour 9,000.00 9,000.00
5 Erection Consumable and tools 5,000.00 5,000.00
6 Galvanization 17,970.00 17,970.00
7 Transportation to site 3,500.00 3,500.00
8
Depreciation of Equipments/Capital
Investment 29,683.33 18,266.67
225,503.33 214,086.67
OH Profit 7.50% 16,912.75 16,056.50
Rate/MT 242,416.08 230,143.17
Rate/Kg 242.42 230.14
Capital Investment Cost per KG
SN Items of Capital Investment
Cost/Kg for 6000
MT in total
Cost/Kg for 12000
MT in total
1 Fabrication Equipment 4.50 3.16
2 Erection Equipment 8.94 6.28
3 GI Structure and plant 7.42 4.41
4 Initial Zinc investment 8.82 4.41
Total 29.68 18.27
A Fabrication Equipment Qty Unit Unit Rate Amount
Cost/Kg for
6000 MT in
total
Cost/Kg for
12000 MT in
total
CNC cutting 2 Set 5,000,000.00 10,000,000.00
SAW 2 Set 2,000,000.00 4,000,000.00
Mig 10 Set 500,000.00 5,000,000.00
Crane 35 Mt 1 nos 17,500,000.00 17,500,000.00
Total 36,500,000.00
12% interest*2 years 24% 8,760,000.00
Recovery loses at the end of project 6000 MT Proj 50% 18,250,000.00
Recovery loses at the end of project 12000 MT Proj 80% 29,200,000.00
Total Effective Investment for 6000 MT Proj (intrest+rec. Loss) 27,010,000.00 4.50
Total Effective Investment for 12000 MT Proj (intrest+rec. Loss) 37,960,000.00 3.16
Sample Costing of Capital Investment (Fabrication Equipment)
General Approaches
to Carry Out the Project
Cutting
Method Tools/machine Explanation
Plasma Cutting
CNC Plasma Machine with 3.0m
x13.0m table up to 30mm Plate
cutting Capacity
Used for any shape of cutting,( linear and
curvilinear closed/open shape), specially for
curbed/cambered web plates, polygonal
gusset plates etc.
Oxyfuel Cutting
Pug Cutter with aluminium
Track,cutting Capacity up to 50 mm
thick plate
Generally used for Linear straight cutting
Hand cutting Tourch Used for rolled section cutting,
Shearing
Hydraulic Shearing machine up to
25mm and 2.5 m wide cutting
Used for rectangular shaped plates cutting,
e.g for splice plates, stiffner etc.
Band saw machine
Up to 300mm x300mm profile
cutting Used for rolled section cutting,
Drill Marking and Drilling
Method Tools/machine Explanation
CNC Marking
The same machine used for
cutting is used for centre mark of
hole position
Any pattern of hole positions
can be marked on plates
Core Drill
Magnet Drill machine with core
cutter bit , capacity from 14mm
dia. Hole to 42mm dia. hole and
up to 50 mm thick plate
Used for plate and other section
drilling at shop and site
Edge Preparation
Method Tools/machine Explanation
Machined edge
preparation
Edge preparation Machine
with beveling/camphering
tools
Used to prepare plate
edge for welding where
required as per
specification
Oxyfuel cutting for edge
preparation
Pug cutter with tilted cutting
head adjustment facility. The
same machine for plate cutting
can be is used.
Jiggs Assembly
Method Tools/machine Explanation
Different Components are
arranged on jig and fixture to
make single assembled unit at
shop by welding.
Jigs and fixture are
product dependent and
fabricated at shop
according to size and
shape of components to
be assembled
Jigs and fixtures are most
essential to place each
component at correct
location/position and to
control distortion due to
welding
Welding and Testing
Method Tools/machine Explanation
Arc Welding
Autometic Submerge arc welding
(track travelling type)
For Heavy and continuous welding
Manual Arc Welding
For tack welding, small piece
welding and for position where
ASW can not be used
MIG welding
Track travelling type MIG welding
machine For Heavy and contineous welding
Manual MIG welding Machine
For tack welding, small piece
welding and for position where
ASW can not be used
Welding Tests: NDT
X-ray, Altrasound welding testing
machine, Chemical Penetration
test
Depends on size and shape, lot
size, and specified on technical
specification
The defected welding is removed
by grinding and re-welded and
checked again .
SAW Pictures
Factory Assembly and Checking
Method Tools/machine Explanation
Partly or whole
bridge is assembled at shop
to ensure the correctness of
fabrication .
Lifting crane/Hydra
Temporary assembling bolts
are used for bolted joints
Corrosion Protection (Hot Dip Galvanizing)
Method Tools/machine Explanation
Pickling and rinsing Galvanizing plant with
12.5m long 1.5m wide
and 2.5m deep zinc bath
and other processing
tanks shall be at least
same capacity of zinc
bath
Pickling is to remove rust and other foreign material
sticked on steel surface with the help of acid bath
Fluxing is to make thin protection layer to prevent
rusting before hot dipping process.
Fluxing Hot dipping is to dip the well dried flux coated steel
parts on zinc bath for zinc coating on surface.
Hot dipping Quenching is to quench the hot steel immediate after
hot dipping process
Quenching
Coating Testing Coating Meter
The Thickness of zinc coat on steel surface is
measured with the help of electronic coating meter to
ensure the required thickness of coating. If the
required thickness is less than specified the work
piece is subjected to re galvanizing
Erection Works at Site
Method Tools/machine Explanation
False Works:
Metal False work is installed on
filled and compacted ground
below the true position of bridge
at site
Fabricated post ties and
bracing, lifting crane up to
50 MT capacity
The false work member shall be
designed to withstand the load of
steel bridge at construction
phase, these supports are
removed after fully tightening the
bolts and placing bridge at
bearing position
Erection of Main Structure:
Bottom member and floor beams
are first placed at position
maintaining required in place
camber. Then Top Chord
,suspender and top lateral ties are
installed
Lifting Cranes 50 Tonne,
Electrical Winches,
Bolt tightening Wrench,
Torque Wrench to ensure
the tightening torque.
The Bolt tightening torque value
and tightening method shall be
followed
Erection Photos
THANK YOU !!!

More Related Content

Similar to Steel Bridge for a construction of highway bridge in Nepal

Aluminium + Ticp Matrix Composite Parting-Off Wheel-Production
Aluminium + Ticp Matrix Composite Parting-Off Wheel-ProductionAluminium + Ticp Matrix Composite Parting-Off Wheel-Production
Aluminium + Ticp Matrix Composite Parting-Off Wheel-ProductionIOSR Journals
 
Industrial training presentation (mechanical engineering)
Industrial training presentation (mechanical engineering)Industrial training presentation (mechanical engineering)
Industrial training presentation (mechanical engineering)Rahul Banerjee
 
Report on Industrial visit at Aditya Auto products, Doddballapura, Bangalore.
Report on Industrial visit at Aditya Auto products, Doddballapura, Bangalore.Report on Industrial visit at Aditya Auto products, Doddballapura, Bangalore.
Report on Industrial visit at Aditya Auto products, Doddballapura, Bangalore.abhishekPatne2
 
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...IRJET Journal
 
Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga BridgeAshish Kumar Yadav
 
Machinability Study on Al-7si Alloy Subjected To Grain Refinement
Machinability Study on Al-7si Alloy Subjected To Grain RefinementMachinability Study on Al-7si Alloy Subjected To Grain Refinement
Machinability Study on Al-7si Alloy Subjected To Grain RefinementIJERA Editor
 
DESIGN AND FABRICATION OF FATIGUE TESTING MACHINE
DESIGN AND FABRICATION OF FATIGUE TESTING MACHINEDESIGN AND FABRICATION OF FATIGUE TESTING MACHINE
DESIGN AND FABRICATION OF FATIGUE TESTING MACHINERakesh J M
 
Numerical simulation of friction stir butt welding processes for az91 magnesi...
Numerical simulation of friction stir butt welding processes for az91 magnesi...Numerical simulation of friction stir butt welding processes for az91 magnesi...
Numerical simulation of friction stir butt welding processes for az91 magnesi...eSAT Journals
 
Numerical simulation of friction stir butt welding processes for az91 magnesi...
Numerical simulation of friction stir butt welding processes for az91 magnesi...Numerical simulation of friction stir butt welding processes for az91 magnesi...
Numerical simulation of friction stir butt welding processes for az91 magnesi...eSAT Publishing House
 
MULTI-MATERIAL DED FOR HIGH-PERFORMANCE LOW-COST ADDITIVE MANUFACTURING
MULTI-MATERIAL DED FOR HIGH-PERFORMANCE LOW-COST ADDITIVE MANUFACTURINGMULTI-MATERIAL DED FOR HIGH-PERFORMANCE LOW-COST ADDITIVE MANUFACTURING
MULTI-MATERIAL DED FOR HIGH-PERFORMANCE LOW-COST ADDITIVE MANUFACTURINGDesignTeam8
 
200 tph crushing plant
200 tph crushing plant200 tph crushing plant
200 tph crushing plantEvita Lee
 
Pipelines welding handbook_welding_techn
Pipelines welding handbook_welding_technPipelines welding handbook_welding_techn
Pipelines welding handbook_welding_technAshraf Shaikh
 

Similar to Steel Bridge for a construction of highway bridge in Nepal (20)

Ppc 2
Ppc 2Ppc 2
Ppc 2
 
Aluminium + Ticp Matrix Composite Parting-Off Wheel-Production
Aluminium + Ticp Matrix Composite Parting-Off Wheel-ProductionAluminium + Ticp Matrix Composite Parting-Off Wheel-Production
Aluminium + Ticp Matrix Composite Parting-Off Wheel-Production
 
Industrial training presentation (mechanical engineering)
Industrial training presentation (mechanical engineering)Industrial training presentation (mechanical engineering)
Industrial training presentation (mechanical engineering)
 
Manufacturing processes
Manufacturing processesManufacturing processes
Manufacturing processes
 
toolwear.pptx
toolwear.pptxtoolwear.pptx
toolwear.pptx
 
Report on Industrial visit at Aditya Auto products, Doddballapura, Bangalore.
Report on Industrial visit at Aditya Auto products, Doddballapura, Bangalore.Report on Industrial visit at Aditya Auto products, Doddballapura, Bangalore.
Report on Industrial visit at Aditya Auto products, Doddballapura, Bangalore.
 
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
IRJET- Development and Analysis of Special Purpose Machine (Peck Drilling Mac...
 
Ch23
Ch23Ch23
Ch23
 
Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga Bridge
 
Munger ganga bridge
Munger ganga bridgeMunger ganga bridge
Munger ganga bridge
 
Reading 1
Reading 1Reading 1
Reading 1
 
Machinability Study on Al-7si Alloy Subjected To Grain Refinement
Machinability Study on Al-7si Alloy Subjected To Grain RefinementMachinability Study on Al-7si Alloy Subjected To Grain Refinement
Machinability Study on Al-7si Alloy Subjected To Grain Refinement
 
DESIGN AND FABRICATION OF FATIGUE TESTING MACHINE
DESIGN AND FABRICATION OF FATIGUE TESTING MACHINEDESIGN AND FABRICATION OF FATIGUE TESTING MACHINE
DESIGN AND FABRICATION OF FATIGUE TESTING MACHINE
 
Ds34728732
Ds34728732Ds34728732
Ds34728732
 
Sheetmetaloperations 6 part a
Sheetmetaloperations 6 part aSheetmetaloperations 6 part a
Sheetmetaloperations 6 part a
 
Numerical simulation of friction stir butt welding processes for az91 magnesi...
Numerical simulation of friction stir butt welding processes for az91 magnesi...Numerical simulation of friction stir butt welding processes for az91 magnesi...
Numerical simulation of friction stir butt welding processes for az91 magnesi...
 
Numerical simulation of friction stir butt welding processes for az91 magnesi...
Numerical simulation of friction stir butt welding processes for az91 magnesi...Numerical simulation of friction stir butt welding processes for az91 magnesi...
Numerical simulation of friction stir butt welding processes for az91 magnesi...
 
MULTI-MATERIAL DED FOR HIGH-PERFORMANCE LOW-COST ADDITIVE MANUFACTURING
MULTI-MATERIAL DED FOR HIGH-PERFORMANCE LOW-COST ADDITIVE MANUFACTURINGMULTI-MATERIAL DED FOR HIGH-PERFORMANCE LOW-COST ADDITIVE MANUFACTURING
MULTI-MATERIAL DED FOR HIGH-PERFORMANCE LOW-COST ADDITIVE MANUFACTURING
 
200 tph crushing plant
200 tph crushing plant200 tph crushing plant
200 tph crushing plant
 
Pipelines welding handbook_welding_techn
Pipelines welding handbook_welding_technPipelines welding handbook_welding_techn
Pipelines welding handbook_welding_techn
 

Recently uploaded

BabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptxBabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptxolyaivanovalion
 
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service BhilaiLow Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service BhilaiSuhani Kapoor
 
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Delhi Call girls
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Invezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz1
 
BigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxBigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxolyaivanovalion
 
Market Analysis in the 5 Largest Economic Countries in Southeast Asia.pdf
Market Analysis in the 5 Largest Economic Countries in Southeast Asia.pdfMarket Analysis in the 5 Largest Economic Countries in Southeast Asia.pdf
Market Analysis in the 5 Largest Economic Countries in Southeast Asia.pdfRachmat Ramadhan H
 
04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationships04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationshipsccctableauusergroup
 
Mature dropshipping via API with DroFx.pptx
Mature dropshipping via API with DroFx.pptxMature dropshipping via API with DroFx.pptx
Mature dropshipping via API with DroFx.pptxolyaivanovalion
 
B2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxB2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxStephen266013
 
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一ffjhghh
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改atducpo
 
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingNeil Barnes
 
Data-Analysis for Chicago Crime Data 2023
Data-Analysis for Chicago Crime Data  2023Data-Analysis for Chicago Crime Data  2023
Data-Analysis for Chicago Crime Data 2023ymrp368
 
VidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxVidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxolyaivanovalion
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAroojKhan71
 
Edukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFxEdukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFxolyaivanovalion
 
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Callshivangimorya083
 

Recently uploaded (20)

BabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptxBabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptx
 
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service BhilaiLow Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
 
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
 
Invezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signals
 
BigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxBigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptx
 
Market Analysis in the 5 Largest Economic Countries in Southeast Asia.pdf
Market Analysis in the 5 Largest Economic Countries in Southeast Asia.pdfMarket Analysis in the 5 Largest Economic Countries in Southeast Asia.pdf
Market Analysis in the 5 Largest Economic Countries in Southeast Asia.pdf
 
04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationships04242024_CCC TUG_Joins and Relationships
04242024_CCC TUG_Joins and Relationships
 
Mature dropshipping via API with DroFx.pptx
Mature dropshipping via API with DroFx.pptxMature dropshipping via API with DroFx.pptx
Mature dropshipping via API with DroFx.pptx
 
B2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxB2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docx
 
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
 
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data Storytelling
 
Data-Analysis for Chicago Crime Data 2023
Data-Analysis for Chicago Crime Data  2023Data-Analysis for Chicago Crime Data  2023
Data-Analysis for Chicago Crime Data 2023
 
VidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxVidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptx
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
 
Edukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFxEdukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFx
 
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
 

Steel Bridge for a construction of highway bridge in Nepal

  • 1. Cost Analysis for Fabrication and Erection of Steel Arch Bridges on East West Highway (H01)
  • 2. Item of Work: Steel Arch (Providing, Fabricating, assembling and erecting structural steel components/elements including nut, bolt, gusset plate ,including heavy zinc coat galvanization, facilities for inspection & test in gradual assembling as per approved design, shop drawings, technical specification and to the satisfaction of Engineer all complete) Total Quantity: 12,555,255.00 KG (Two Packages)
  • 3. Plan and Elevation of Bridge
  • 4. Total Weight of Bridges S.No Bridge Name Span No of Span Width max Height of bridge Steel Weight KG Nut Bolts Weight KG mtr mtr mtr Pack-x 1 b 79.5 2 13.95 13.5 1,506,740.00 41,362.40 2 k 87.6 4 13.95 14.9 3,353,504.00 90,809.36 3 n 79.5 2 13.95 13.5 1,506,740.00 41,362.40 6,366,984.00 173,534.16 Pack-y 4 B 79.5 2 13.95 14.6 1,506,740.00 41,362.40 5 L 85.25 2 18.65 14.6 1,820,800.00 54,588.37 6 R 87.6 3 18.65 14.9 2,860,731.00 82,093.13 6,188,271.00 178,043.90 Total Weight 12,555,255.00 351,578.06
  • 5. Maximum Sizes and Weights S.No Bridge Name Max Lifting Weight Max Length of single piece MT m Pack-x 1 b 14.6 11.6 2 k 15.5 12.4 3 n 14.6 11.6 Pack-y 4 B 14.6 11.6 5 L 15.3 11.8 6 R 15.6 12.4
  • 6. Quantity of Plates in Different Thickness (E410) Bridge Name Plate Thickness Total Qquantity 12mm 16mm 20mm 26mm 30mm 40mm B 166718 183102 304235 162301 687233 3149 1506738 K 366740 417795 696074 326,304 1539602 6990 3353505 N 166718 183102 304235 162301 687233 3149 1506738 B 166718 183102 304235 162301 687233 3149 1506738 L 232660 263298 351008 179947 790392 3495 1820800 R 359357 399288 539806 0 1557036 5243 2860730 Total MT 1458.911 1629.687 2499.593 993.154 5948.729 25.175 12555.249 Percentage by thickness 11.6% 13.0% 19.9% 7.9% 47.4% 0.2% 100% * Length Prefered 12.5m (minimum 12m) *Width prefered 2.0m to 3m
  • 7. Summary of Rate Analysis for 1MT of finished goods (for 1000 kg weight/5% waste considered) S. No Item Qty Unit Unit Rate Amount Assuming 6000 MT work) Amount Assuming 12000 MT work) 1 Steel landed cost 1050 Kg 137.00 143,850.00 143,850.00 (78 IC CIF*1.6+7.5%+2.5 transport Nepal) 2 Fabrication Consumables and Electricity 7,500.00 7,500.00 3 Fabrication Labour 9,000.00 9,000.00 4 Erection labour 9,000.00 9,000.00 5 Erection Consumable and tools 5,000.00 5,000.00 6 Galvanization 17,970.00 17,970.00 7 Transportation to site 3,500.00 3,500.00 8 Depreciation of Equipments/Capital Investment 29,683.33 18,266.67 225,503.33 214,086.67 OH Profit 7.50% 16,912.75 16,056.50 Rate/MT 242,416.08 230,143.17 Rate/Kg 242.42 230.14
  • 8. Capital Investment Cost per KG SN Items of Capital Investment Cost/Kg for 6000 MT in total Cost/Kg for 12000 MT in total 1 Fabrication Equipment 4.50 3.16 2 Erection Equipment 8.94 6.28 3 GI Structure and plant 7.42 4.41 4 Initial Zinc investment 8.82 4.41 Total 29.68 18.27
  • 9. A Fabrication Equipment Qty Unit Unit Rate Amount Cost/Kg for 6000 MT in total Cost/Kg for 12000 MT in total CNC cutting 2 Set 5,000,000.00 10,000,000.00 SAW 2 Set 2,000,000.00 4,000,000.00 Mig 10 Set 500,000.00 5,000,000.00 Crane 35 Mt 1 nos 17,500,000.00 17,500,000.00 Total 36,500,000.00 12% interest*2 years 24% 8,760,000.00 Recovery loses at the end of project 6000 MT Proj 50% 18,250,000.00 Recovery loses at the end of project 12000 MT Proj 80% 29,200,000.00 Total Effective Investment for 6000 MT Proj (intrest+rec. Loss) 27,010,000.00 4.50 Total Effective Investment for 12000 MT Proj (intrest+rec. Loss) 37,960,000.00 3.16 Sample Costing of Capital Investment (Fabrication Equipment)
  • 10. General Approaches to Carry Out the Project
  • 11. Cutting Method Tools/machine Explanation Plasma Cutting CNC Plasma Machine with 3.0m x13.0m table up to 30mm Plate cutting Capacity Used for any shape of cutting,( linear and curvilinear closed/open shape), specially for curbed/cambered web plates, polygonal gusset plates etc. Oxyfuel Cutting Pug Cutter with aluminium Track,cutting Capacity up to 50 mm thick plate Generally used for Linear straight cutting Hand cutting Tourch Used for rolled section cutting, Shearing Hydraulic Shearing machine up to 25mm and 2.5 m wide cutting Used for rectangular shaped plates cutting, e.g for splice plates, stiffner etc. Band saw machine Up to 300mm x300mm profile cutting Used for rolled section cutting,
  • 12. Drill Marking and Drilling Method Tools/machine Explanation CNC Marking The same machine used for cutting is used for centre mark of hole position Any pattern of hole positions can be marked on plates Core Drill Magnet Drill machine with core cutter bit , capacity from 14mm dia. Hole to 42mm dia. hole and up to 50 mm thick plate Used for plate and other section drilling at shop and site
  • 13. Edge Preparation Method Tools/machine Explanation Machined edge preparation Edge preparation Machine with beveling/camphering tools Used to prepare plate edge for welding where required as per specification Oxyfuel cutting for edge preparation Pug cutter with tilted cutting head adjustment facility. The same machine for plate cutting can be is used.
  • 14. Jiggs Assembly Method Tools/machine Explanation Different Components are arranged on jig and fixture to make single assembled unit at shop by welding. Jigs and fixture are product dependent and fabricated at shop according to size and shape of components to be assembled Jigs and fixtures are most essential to place each component at correct location/position and to control distortion due to welding
  • 15. Welding and Testing Method Tools/machine Explanation Arc Welding Autometic Submerge arc welding (track travelling type) For Heavy and continuous welding Manual Arc Welding For tack welding, small piece welding and for position where ASW can not be used MIG welding Track travelling type MIG welding machine For Heavy and contineous welding Manual MIG welding Machine For tack welding, small piece welding and for position where ASW can not be used Welding Tests: NDT X-ray, Altrasound welding testing machine, Chemical Penetration test Depends on size and shape, lot size, and specified on technical specification The defected welding is removed by grinding and re-welded and checked again .
  • 17. Factory Assembly and Checking Method Tools/machine Explanation Partly or whole bridge is assembled at shop to ensure the correctness of fabrication . Lifting crane/Hydra Temporary assembling bolts are used for bolted joints
  • 18. Corrosion Protection (Hot Dip Galvanizing) Method Tools/machine Explanation Pickling and rinsing Galvanizing plant with 12.5m long 1.5m wide and 2.5m deep zinc bath and other processing tanks shall be at least same capacity of zinc bath Pickling is to remove rust and other foreign material sticked on steel surface with the help of acid bath Fluxing is to make thin protection layer to prevent rusting before hot dipping process. Fluxing Hot dipping is to dip the well dried flux coated steel parts on zinc bath for zinc coating on surface. Hot dipping Quenching is to quench the hot steel immediate after hot dipping process Quenching Coating Testing Coating Meter The Thickness of zinc coat on steel surface is measured with the help of electronic coating meter to ensure the required thickness of coating. If the required thickness is less than specified the work piece is subjected to re galvanizing
  • 19. Erection Works at Site Method Tools/machine Explanation False Works: Metal False work is installed on filled and compacted ground below the true position of bridge at site Fabricated post ties and bracing, lifting crane up to 50 MT capacity The false work member shall be designed to withstand the load of steel bridge at construction phase, these supports are removed after fully tightening the bolts and placing bridge at bearing position Erection of Main Structure: Bottom member and floor beams are first placed at position maintaining required in place camber. Then Top Chord ,suspender and top lateral ties are installed Lifting Cranes 50 Tonne, Electrical Winches, Bolt tightening Wrench, Torque Wrench to ensure the tightening torque. The Bolt tightening torque value and tightening method shall be followed