2. Aim of the task .
Time Planned for the task .
Actual time elapsed .
Number of workers , Percentage of each
worker.
3. To get rid of the falling materials.
To control dust emission
To increase the efficiency of the burner.
To improve the dryer interface.
4. Date shift Task
19/6/2104
Day • Dismantle the old body
• install the new body
Night Weld the new body
20/6/2014
Day • Complete welding of the new body
• start the installation of thermal coating
Night Complete the installation of coating
5. Shift Tasks completed Workers name
day • Dismantle the old body
• install the new body
# Saeed Sad
# Alaa Nasr
# Ibrahim Metwally
# Hassan Kamel
# Hamdy Abd el Rehim
# Ashraf Ali
night Start welding of the new body # Saeed Sad
# Alaa Nasr
# Ibrahim Metwally
# Hassan Kamel
day • Complete welding
• start the installation of thermal coating
# Saeed Sad
# Alaa Nasr
# Hamdy Abel Rehim
# Mohamed Eltekky
# Abead Hamed
# Taha Ibrahim