SlideShare a Scribd company logo
1 of 7
Download to read offline
Power Transformers in Generating Stations 
Relu Ilie, Israel Electric Corporation, and Isidor Kerszenbaum, Exponent, Inc. 
Issues to Consider when Substituting Large 
Power Transformers in Generating Stations 
Relu Ilie, Israel Electric Corporation, and Isidor Kerszenbaum, Exponent, Inc. 
EHV EHV/HV EHV 
62 גליון 46 , אוגוסט 2013 
Abstract—For availability reasons, many generating utilities 
keep in storage custom designed spare transformers, 
readily available and identical to their critical large power 
transformers. However, in case an exact replacement is not 
available, the only option the generating utility has is to search 
for a substitute transformer that, as a minimum, is able to offer 
a temporary solution. The purpose of this paper is to indicate 
the most important aspects to be considered when checking 
the interchangeability of such substitute transformer, based on 
authors’ experience and on various standards requirements. 
Index Terms—power plants, power transformers. 
I. Introduction THE power transformer is a reliable device, yet not failure-free. 
It has no moving parts, consequently neither the typical faults 
of rotating machines. On the other hand, the large transformers 
are oil-immersed and suffer from other faults, mainly chemically 
or electrically related. A transformer internal fault may be very 
difficult to locate and to repair. In many cases, the owner may 
decide that it is faster and cheaper to buy a new transformer than 
to repair an old damaged one. Even when the repair is worthwhile, 
it may last for many months. 
Almost all large transformers used in power plants are custom-designed. 
Keeping in storage suitable spare transformers is a 
common practice, for the purpose of avoiding long unplanned 
outages and high economic losses. In case an exact replacement 
is not available, the only option the generating utility has is to 
search for a substitute transformer that, as a minimum, is able to 
offer a temporary solution than may introduce some operational 
constraints. The goal of this paper is to mention the most important 
aspects to be considered when checking the interchangeability 
of such substitute transformer. The discussion is based on the 
various requirements included in relevant American and European 
standards. 
The most common generating station arrangements are shown 
in Fig. 1: a unit generator-transformer block configuration, and 
a unit generator-transformer with generator breaker. The vital 
large transformers in a power plant are the unit step-up/main/ 
generator transformer (UT), the auxiliary transformer (UAT) and 
the station service/reserve transformer (SST). A failure of any 
one of these transformers may lead to unit shutdown or start-up 
unavailability. 
II. General Layout 
The UT may consist of a single three-phase unit, two half-size 
three-phase units, or three single-phase units. This is the 
most evident aspect to consider when a substitute transformer is 
needed. 
When designing a new plant, the selection among these 
alternatives is generally based on consideration of some form 
of strategic reserve, as well as available space. Two half-size 
transformers may be selected in place of a single full-size 
transformer in order to reduce the cost of the spare. For similar 
reasons, a generator transformer may be made as a bank of single-phase 
units. Normally the cost, mass, and loss of such solutions 
are larger than for a single three-phase transformer; however, they 
may be preferable if transport size or weight limits apply. The 
three single-phase transformers provide independent magnetic 
circuits (see Section XI below), representing high magnetizing 
impedance for zero-sequence voltage components. Therefore, a 
delta equalizer winding is normally provided, implemented by 
external connection between phase units. 
Some layouts may pose other complications, like UAT with 
three-winding design. 
III. Dimensions and Weight 
Any physical size and weight limitations should be checked, 
for example for installation on an existing foundation. Special 
installation space restrictions may influence the insulation 
clearan 
ces and terminal locations on the transformer. 
 
Abstract—For availability reasons, many generating utilities 
keep in storage custom designed spare transformers, readily 
available and identical to their critical large power transformers. 
However, in case an exact replacement is not available, the only 
option the generating utility has is to search for a substitute 
transformer that, as a minimum, is able to offer a temporary 
solution. The purpose of this paper is to indicate the most 
important aspects to be considered when checking the 
interchangeability of such substitute transformer, based on 
authors' experience and on various standards requirements. 
Index Terms—power plants, power transformers. 
I. INTRODUCTION 
HE power transformer is a reliable device, yet not failure-free. 
It has no moving parts, consequently neither the 
typical faults of rotating machines. On the other hand, the 
large transformers are oil-immersed and suffer from other 
faults, mainly chemically or electrically related. A transformer 
internal fault may be very difficult to locate and to repair. In 
many cases, the owner may decide that it is faster and cheaper 
to buy a new transformer than to repair an old damaged one. 
Even when the repair is worthwhile, it may last for many 
months. 
Almost all large transformers used in power plants are 
custom-designed. Keeping in storage suitable spare 
transformers is a common practice, for the purpose of 
avoiding long unplanned outages and high economic losses. In 
case an exact replacement is not available, the only option the 
generating utility has is to search for a substitute transformer 
that, as a minimum, is able to offer a temporary solution than 
may introduce some operational constraints. The goal of this 
paper is to mention the most important aspects to be 
considered when checking the interchangeability of such 
substitute transformer. The discussion is based on the various 
requirements included in relevant American and European 
standards. 
The most common generating station arrangements are 
shown in Fig. 1: a unit generator-transformer block 
configuration, and a unit generator-transformer with generator 
breaker. The vital large transformers in a power plant are the 
unit step-up/main/generator transformer (UT), the auxiliary 
transformer (UAT) and the station service/reserve 
transformer (SST). A failure of any one of these transformers 
may lead to unit shutdown or start-up unavailability. 
II. GENERAL LAYOUT 
The UT may consist of a single three-phase unit, two half-size 
three-phase units, or three single-phase units. This is the 
most evident aspect to consider when a substitute transformer 
is needed. 
When designing a new plant, the selection among these 
alternatives is generally based on consideration of some form 
of strategic reserve, as well as available space. Two half-size 
transformers may be selected in place of a single full-size 
transformer in order to reduce the cost of the spare. For 
similar reasons, a generator transformer may be made as a 
bank of single-phase units. Normally the cost, mass, and loss 
of such solutions are larger than for a single three-phase 
transformer; however, they may be preferable if transport size 
or weight limits apply. The three single-phase transformers 
provide independent magnetic circuits (see Section XI below), 
representing high magnetizing impedance for zero-sequence 
voltage components. Therefore, a delta equalizer winding is 
normally provided, implemented by external connection 
between phase units. 
Some layouts may pose other complications, like UAT 
with three-winding design. 
III. DIMENSIONS AND WEIGHT 
Any physical size and weight limitations should be 
checked, for example for installation on an existing 
foundation. Special installation space restrictions may 
influence the insulation clearances and terminal locations on 
T 
a) Unit generator-transformer b) Unit generator-transformer 
block configuration with generator breaker 
Fig. 1. Common generating station arrangements. 
UAT 
MV 
UT UT 
UAT SST 
GCB 
MV MV 
UT and UAT are connected to the generator through isolated 
phase bus ducts. The high/extra high voltage terminals of the 
UT may be connected to gas insulated switchgear. The medium 
voltage connections to plant auxiliaries are also normally done via 
rigid, non-segregated phase bus bars or cables. All these aspects 
must be checked and solved when looking for a transformer 
replacement. 
IV. Rated Frequency 
In the unlikely situation a transformer designed for a different 
frequency is considered, the following applies. The rated frequency 
radically affects the transformer design and operation. The general 
formula of voltage e induced by a variable flux φ in a coil with N 
turns is e = -N dφ/dt. Assuming a sinusoidal flux φ = Φm cos ωt, the 
induced voltage becomes e = ω N Φm sin ωt. Its rms value will be, 
in terms of core cross section A and flux density Bm [1]: 
E = 2π/√2 f N Φm = 4.44 f N A Bm. (1)
According to (1), operating at 50 Hz a transformer designed for 
60 Hz means that the same voltage can be achieved only by a 
substantial increase in the flux density. The core iron will become 
heavily saturated, the excitation current will rise and also the 
hysteresis losses (proportional to the area of the hysteresis loop), 
which could severely overheat and damage the laminations. A 50 
Hz transformer needs roughly 12% more iron in its core than a 60 
Hz unit, and also more winding turns. 
When operating frequency is 60 Hz in contrast to a 50 Hz 
design, there is too much iron in the core. The hysteresis losses 
will be higher than the designed value (because iron volume and 
increased frequency), thus decreasing the efficiency. More im-portantly, 
the eddy currents losses will heat up the laminations, 
because they tend to increase as the square of the frequency. Op-eration 
of a 50 Hz rated transformer at 60 Hz may be sometime 
possible, but it may have to be derated from its nameplate MVA 
rating [2], depending on the new versus rated voltage. 
V. AMV Rating 
The substitute transformer rated MVA is obviously a first pa-rameter 
to consider. When a new plant is designed, the UT rating 
is chosen to ensure that it will not represent a bottleneck of unit 
capability, under any possible operating condition. However, a 
substitute UT poses a different perspective: using a smaller MVA 
rating than the original one means generating unit derating, nev-ertheless 
it is normally preferable to a complete shut-down, tak-ing 
into consideration the long time needed to obtain an exact 
replacement. 
In the case of a transformer (especially UT) substitution, it 
is essential to pay attention to the differences among the various 
standards about the definition of rated power. The IEC 60076-1 
[3] definition implies that rated MVA is the apparent input power, 
received when rated voltage is applied to the primary winding and 
rated current flows through the terminals of the secondary wind-ing; 
the output power is, in principle, the rated power minus the 
power consumption in the transformer (active and reactive losses). 
Differently, by the North America conventions (IEEE C57.12.80 
[4]), the rated MVA is the output power that can be delivered at 
rated secondary voltage. 
If the transformer nameplate mentions a certain rated power and 
if it was designed in conformity with the American standards, the 
significance is that its primary (connected to the generator) would 
be able to receive a higher than rated power. If for instance, the 
UT impedance is 15%, it should be able to accept a primary MVA 
higher up to about 15% than the rated one, including load and mag-netizing 
losses (in the worst conditions of lagging power factors). 
Exact values can be obtained by using the equivalent circuit of the 
transformer. Contrarily, such intrinsic capability will not be avail-able 
in transformer exhibiting the same rated MVA, but designed 
to IEC requirements. The situation inverts under leading power 
factors (Mvar absorbed from the system) but this is a less likely 
regime, especially when a substitute transformer is involved. 
A transformer may be able under some limitations to carry 
loads in excess of nameplate rating. In the case of a substitute 
transformer, the expected regime is a long-time emergency load-ing 
that may persist for months. Both IEEE and IEC have stan-dards 
specially dedicated to such loading aspects (IEC 60076-7 
[5], IEEE C57.91 [6]). The application of a load in excess of 
nameplate rating involves accelerated ageing and risk of prema-ture 
failure, for instance: deterioration at high temperatures of 
conductor insulation, other insulation parts and oil, overheating of 
metallic parts, increased gassing in the oil, high stresses in bush-ings, 
tap-changers, connections and current transformers, brittle-ness 
of gasket materials. In general, the larger the transformer the 
more vulnerable. 
Both above mentioned standards give similar maximum 
גליון 46 , אוגוסט 61 2013 
temperature limits that should not be exceeded in case of long– 
time loading beyond the nameplate rating: current 1.3 per-unit, 
winding hot-spot temperature 140 ºC (instead of 120 ºC at 
normal loading), top-oil temperature 110-115 ºC (instead of 105 
ºC at normal loading). The increased ageing rate due to a hot-spot 
temperature of 140 ºC is 17.2 times higher than normal for 
upgraded paper insulation and 128 times higher than normal for 
non-upgraded paper insulation [5]. 
VI. Rated Voltages 
Finding a substitute transformer with suitable primary and 
secondary rated voltages is a challenging task, difficult to be se-lected 
intuitively. Additionally, a transformer design for a certain 
voltage determines the size of the core and has a significant im-pact 
on the overall transformer size and cost. 
The system and transformer medium/high/extra high volt-age 
ratings are well standardized and correlated in ANSI C84.1 
[7] and IEC 60038 [8]. However, the generators standards do not 
specify standard series, neither preferable values for the rated sta-tor 
voltage. The generator stator voltage rating is normally fixed 
by agreement, and in many cases it is simply the generator manu-facturer 
decision, according to its available design. Therefore, it 
is quite difficult to match between UT/UAT primary rated voltage 
and generator rated voltage. 
Section VII deals in details with transformers having rated 
voltages lower than expected operational voltages. Contrarily, it 
may be possible to use transformers with rated voltages higher 
than the operational ones, providing that the rated current will not 
be exceeded. Practically in such case the substitute transformer 
might be oversized and then unsuitable, because of larger core 
size and longer insulation distances. 
Ideally, it is desirable for a generator to be able to absorb Mvar 
to its limit when the system voltage is at its highest expected level 
and to produce Mvar to its limit, when the system voltage is at 
its lowest expected level. This is seldom possible for a fixed tap 
setting in the UT, and thus a compromise may have to be made 
by selecting the appropriate tap rating to meet the most likely op-erating 
condition. It is important to note that the reactive power 
consumed by the UT will absorb a significant part of the generator 
Mvar output under most conditions. 
IEEE C57.116 [9] recommends selecting the main parameters 
of UT (rated voltages, rated MVA, impedance, and over-excita-tion) 
by portraying graphically their effect under various opera-tion 
conditions. While this method is mainly dedicated to a new 
plant project, it may be also used in case of a substitute transform-er. 
A typical graph (Fig. 2) shows the change in generator voltage 
with generator reactive load, for various constant transmission 
system voltages. The graph allows predicting the Mvar capability 
(both lead and lag) at any given system voltage, keeping the ±5% 
generator voltage limits, as required by IEEE C50.12 [10], IEEE 
C50.13 [11] and IEC 60034-1 [12]. 
The example in Fig. 2 was built on a spreadsheet using equations 
based on transformer phasors diagram [9]. For a potential substitute 
transformer, such graphs should be drawn for any available tap/ratio 
at anticipated MW, and analyzed in order to choose the most suitable 
tap voltages (according to the forecasted system voltage profile) that 
will pose minimum restrictions to unit operation: range of available 
Mvar, synchronization ability, etc. Of course, a substitute transformer 
may not allow a full range of loading; normally some limitations (e.g. 
in reactive capabilities) may be acceptable. 
References [13] and [14] propose other graphs, more complete 
but also more complex, which take in consideration additional 
restrictions, such as: generator maximum excitation limit, 
generator under-excited reactive ampere limit, UT limits (at lower 
than rated tap voltage), turbine MW limit, and auxiliary bus-bars 
(motors) voltage limits. Such graph shows the reactive power
3 
320 330 340 350 360 370 
320 330 340 350 360 370 
3 
60 גליון 46 , אוגוסט 2013 
transferred to/from the grid (at UT high voltage side) as a function 
of system voltage, and forecast the area of allowable operation. 
This graph can be also obtained in a spreadsheet using suitable 
equations (Fig. 3). 
VII. Overvoltage Limits 
The purpose of this section is to show how low the substitute-transformer 
rated voltages may be in order to withstand the high-est 
expected voltages on its terminals. 
The standards define the maximum winding voltage based 
on the insulation withstand capability (in IEC 60076-3 [15] it is 
called the highest voltage for equipment, while in ANSI C84.1 [7] 
it is the maximum system voltage). 
According to (1), the ratio between the voltage and frequency 
(V/Hz) of the system to which the transformer is connected de-termines 
the nominal flux density at which the transformer oper-ates 
(assuming the number of turns at a particular tap will remain 
constant). Normally, the transformer is economically designed to 
operate at as high as possible flux density, while avoiding satura-tion 
of the core. System frequency is normally controlled within 
close limits; thus, the system voltage is the main factor respon-sible 
for over-fluxing (over-excitation). When the V/Hz ratios are 
exceeded, saturation of the magnetic core of the transformers may 
occur, and stray flux may be induced in non-laminated compo-nents 
that are not designed to carry flux. This can cause severe 
localized overheating in the transformer and eventual breakdown 
of the core assembly and/or winding insulation. 
As mentioned before, the IEC 60076-1 [3] definitions imply 
that rated voltage is applied to primary winding, and the voltage 
across the secondary terminals differs from rated voltage (defined 
in no-load condition) by the voltage drop/rise in the transformer. 
Contrarily, by IEEE C57.12.00 [16] the rated output is delivered at 
rated secondary voltage; according to IEEE definition, allowance 
for voltage drop has to be made in the design so that the necessary 
primary voltage can be applied to the transformer (at a secondary 
load lagging power factor of 0.80 or higher). For instance, a UT 
with a impedance of 15% (typical range: 13–17%) designed ac-cording 
to IEEE shall withstand continuously primary voltages 
as high as 110% of the rated value when fully loaded at a power 
factor of 0.80 (value calculable using the transformer equivalent 
circuit). Such hidden capability will not be available in the case of 
a transformer which follows the IEC requirements. 
According to IEC 60076-1 [3], a transformer shall be capable 
of continuous operation up to 105% voltage or V/Hz (the standard 
meaning is per each winding). IEC 60076-8 [17] adds that this 
is not meant to be systematically utilized in normal service, but 
should be reserved for relatively rare cases of emergency service 
under limited periods of time. IEEE C57.12.00 [16] defines the 
over-flux capability in a different way: secondary voltage and V/ 
Hz up to 105% of rated values when load power factor is 0.80 
or higher (lagging). Taking into account the previous consider-ations, 
this additional requirement may result in 10-15% primary 
overvoltage (and over-excitation) for a fully loaded generator 
step-up transformer built under IEEE. Fortunately, generators are 
only capable of continuous operation until 5% above or 5% below 
their rated voltage, by [10]-[12] (i.e. V/Hz until 105% at generator 
base) so the above overvoltage capabilities are rarely exploited. 
For UAT and SST the impedance is usually smaller than for UT, 
they often work not fully loaded and the primary voltage will nor-mally 
not rise by more than a few percentage points for a second-ary 
increase of 5%. 
Another aspect related to an overvoltage condition is whether 
the UT and UAT will be subjected to load rejection. Sudden loss 
of load can subject these transformers to substantial overvoltage. 
If saturation occurs, substantial exciting current will flow, which 
may overheat the core and damage the transformer. A sudden 
unit unloading during a fault may be caused by the clearing of a 
system fault and, hence, the machine may be at the ceiling of its 
excitation system; the unit transformer may be excited with volt-ages 
exceeding 130% of normal [18], [19]. With the excitation 
control in service, the over-excitation will generally be reduced 
to safe limits in a few seconds; with the excitation control out of 
service, the over-excitation may be sustained and damage can oc-cur 
(unless dedicated V/Hz protection exists). Both IEC 60076-1 
[3] and IEEE C57.12.00 [16] allow continuous operation at no 
load at a voltage or V/Hz up to 110% of the rated values. For the 
particular case of transformers connected directly to generators 
between UT/UAT primary rated voltage and generator rated 
voltage. 
Section VII deals in details with transformers having rated 
voltages lower than expected operational voltages. Contrarily, 
it may be possible to use transformers with rated voltages 
higher than the operational ones, providing that the rated 
current will not be exceeded. Practically in such case the 
substitute transformer might be oversized and then unsuitable, 
because of larger core size and longer insulation distances. 
Ideally, it is desirable for a generator to be able to absorb 
Mvar to its limit when the system voltage is at its highest 
expected level and to produce Mvar to its limit, when the 
system voltage is at its lowest expected level. This is seldom 
possible for a fixed tap setting in the UT, and thus a 
compromise may have to be made by selecting the appropriate 
tap rating to meet the most likely operating condition. It is 
important to note that the reactive power consumed by the UT 
will absorb a significant part of the generator Mvar output 
under most conditions. 
IEEE C57.116 [9] recommends selecting the main 
parameters of UT (rated voltages, rated MVA, impedance, and 
over-excitation) by portraying graphically their effect under 
various operation conditions. While this method is mainly 
dedicated to a new plant project, it may be also used in case of 
a substitute transformer. A typical graph (Fig. 2) shows the 
change in generator voltage with generator reactive load, for 
various constant transmission system voltages. The graph 
allows predicting the Mvar capability (both lead and lag) at 
any given system voltage, keeping the ±5% generator voltage 
limits, as required by IEEE C50.12 [10], IEEE C50.13 [11] 
and IEC 60034-1 [12]. 
The example in Fig. 2 was built on a spreadsheet using 
equations based on transformer phasors diagram [9]. For a 
potential substitute transformer, such graphs should be drawn 
for any available tap/ratio at anticipated MW, and analyzed in 
order to choose the most suitable tap voltages (according to 
the forecasted system voltage profile) that will pose minimum 
restrictions to unit operation: range of available Mvar, 
synchronization ability, etc. Of course, a substitute 
transformer may not allow a full range of loading; normally 
some limitations (e.g. in reactive capabilities) may be 
acceptable. 
References [13] and [14] propose other graphs, more 
complete but also more complex, which take in consideration 
additional restrictions, such as: generator maximum excitation 
limit, generator under-excited reactive ampere limit, UT limits 
(at lower than rated tap voltage), turbine MW limit, and 
auxiliary bus-bars (motors) voltage limits. Such graph shows 
the reactive power transferred to/from the grid (at UT high 
voltage side) as a function of system voltage, and forecast the 
area of allowable operation. This graph can be also obtained 
in a spreadsheet using suitable equations (Fig. 3). 
VII. OVERVOLTAGE LIMITS 
The purpose of this section is to show how low the 
substitute-transformer rated voltages may be in order to 
withstand the highest expected voltages on its terminals. 
The standards define the maximum winding voltage based 
on the insulation withstand capability (in IEC 60076-3 [15] it 
is called the highest voltage for equipment, while in ANSI 
C84.1 [7] it is the maximum system voltage). 
According to (1), the ratio between the voltage and 
frequency (V/Hz) of the system to which the transformer is 
connected determines the nominal flux density at which the 
transformer operates (assuming the number of turns at a 
particular tap will remain constant). Normally, the transformer 
is economically designed to operate at as high as possible flux 
density, while avoiding saturation of the core. System 
frequency is normally controlled within close limits; thus, the 
system voltage is the main factor responsible for over-fluxing 
1200 
1200 
1100 
1100 
1000 
1000 
900 
900 
800 
800 
700 
700 
600 
600 
500 
500 
400 
400 
300 
300 
200 
200 
100 
100 
0 
0 
-100 
-100 
-200 
-200 
-300 
-300 
-400 
-400 
-500 
-500 
-600 
-600 
-700 
-700 
-800 
-800 
-900 
-900 
-1000 
-1000 
-1100 
-1100 
-1200 
System Voltage (kV) 
Reactive Power Transferred to (+) or from (-) System (Mvar) 
Generator Overexcited Limit 
Generator Unity Power Factor 
Generator Underexcited Limit 
Generator Voltage 105% 
Generator Voltage 100% 
Generator Voltage 95% 
Motors Voltage 110% 
Motors Voltage 90% 
UT Limits 
UNIT OPERATION LIMITS 
(shaded area) 
947 MVA UT Rated Power 
23.13 kV UT Primary Voltage 
345 kV UT Secondary Voltage 
9.17% UT Impedance 
1.585 kA UT Tap Current 
1006 MVA Gen. Rated Power 
854.9 MW Gen. Active Power 
530 Mvar Gen. Overex. Limit 
-346 Mvar Gen. Underex. Limit 
24 kV Gen. Rated Voltage 
60 MVA UAT Rated Power 
24 KV UAT Primary Voltage 
7.07 KV UAT Secondary Voltage 
7.50% UAT Impedance 
42.42 MW Unit Aux. Active Load 
30.71 Mvar Unit Aux. React. Load 
6.6 kV Motors Rated Voltage 
330 kV Syst. Volt. Lowest Limit 
362 KV Syst. Volt. Highest Limit 
UT Ratio 22 / 399 kV (Tap 5), Generator Net Output 576 MW 
UT Rating 650 MVA, UT Impedance 17%, Generator Rated Voltage 22 kV 
System Voltages: 
1.05 
1.05 
1.04 
1.04 
1.03 
1.03 
1.02 
1.02 
1.01 
1.01 
1.00 
1.00 
0.99 
0.99 
0.98 
0.98 
0.97 
0.97 
0.96 
0.96 
0.95 
-100 -80 -60 -40 -20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 
Generator Reactive Power Output Net Value 
Transferred to (+) or from (-) UT (Mvar) 
Generator Voltage (per-unit) 
420 kV 412 kV 
410 kV 
408 kV 
406 kV 
400 kV 
380 kV 
Fig. 2. Change in generator voltage with generator reactive load for various 
system voltages. 
Fig.3 Reactive power transferred to/from system as a function of system 
voltage (operation area limit). 
between UT/UAT primary rated voltage and generator rated 
voltage. 
Section VII deals in details with transformers having rated 
voltages lower than expected operational voltages. Contrarily, 
it may be possible to use transformers with rated voltages 
higher than the operational ones, providing that the rated 
current will not be exceeded. Practically in such case the 
substitute transformer might be oversized and then unsuitable, 
because of larger core size and longer insulation distances. 
Ideally, it is desirable for a generator to be able to absorb 
Mvar to its limit when the system voltage is at its highest 
expected level and to produce Mvar to its limit, when the 
system voltage is at its lowest expected level. This is seldom 
possible for a fixed tap setting in the UT, and thus a 
compromise may have to be made by selecting the appropriate 
tap rating to meet the most likely operating condition. It is 
important to note that the reactive power consumed by the UT 
will absorb a significant part of the generator Mvar output 
under most conditions. 
IEEE C57.116 [9] recommends selecting the main 
parameters of UT (rated voltages, rated MVA, impedance, and 
over-excitation) by portraying graphically their effect under 
various operation conditions. While this method is mainly 
dedicated to a new plant project, it may be also used in case of 
a substitute transformer. A typical graph (Fig. 2) shows the 
change in generator voltage with generator reactive load, for 
various constant transmission system voltages. The graph 
allows predicting the Mvar capability (both lead and lag) at 
any given system voltage, keeping the ±5% generator voltage 
limits, as required by IEEE C50.12 [10], IEEE C50.13 [11] 
and IEC 60034-1 [12]. 
The example in Fig. 2 was built on a spreadsheet using 
equations based on transformer phasors diagram [9]. For a 
potential substitute transformer, such graphs should be drawn 
for any available tap/ratio at anticipated MW, and analyzed in 
order to choose the most suitable tap voltages (according to 
the forecasted system voltage profile) that will pose minimum 
restrictions to unit operation: range of available Mvar, 
synchronization ability, etc. Of course, a substitute 
transformer may not allow a full range of loading; normally 
some limitations (e.g. in reactive capabilities) may be 
acceptable. 
References [13] and [14] propose other graphs, more 
complete but also more complex, which take in consideration 
additional restrictions, such as: generator maximum excitation 
limit, generator under-excited reactive ampere limit, UT limits 
(at lower than rated tap voltage), turbine MW limit, and 
auxiliary bus-bars (motors) voltage limits. Such graph shows 
the reactive power transferred to/from the grid (at UT high 
voltage side) as a function of system voltage, and forecast the 
area of allowable operation. This graph can be also obtained 
in a spreadsheet using suitable equations (Fig. 3). 
VII. OVERVOLTAGE LIMITS 
The purpose of this section is to show how low the 
substitute-transformer rated voltages may be in order to 
withstand the highest expected voltages on its terminals. 
The standards define the maximum winding voltage based 
on the insulation withstand capability (in IEC 60076-3 [15] it 
is called the highest voltage for equipment, while in ANSI 
C84.1 [7] it is the maximum system voltage). 
According to (1), the ratio between the voltage and 
frequency (V/Hz) of the system to which the transformer is 
connected determines the nominal flux density at which the 
transformer operates (assuming the number of turns at a 
particular tap will remain constant). Normally, the transformer 
is economically designed to operate at as high as possible flux 
density, while avoiding saturation of the core. System 
frequency is normally controlled within close limits; thus, the 
system voltage is the main factor responsible for over-fluxing 
-1200 
System Voltage (kV) 
Reactive Power Transferred to (+) or from (-) System (Mvar) 
Generator Overexcited Limit 
Generator Unity Power Factor 
Generator Underexcited Limit 
Generator Voltage 105% 
Generator Voltage 100% 
Generator Voltage 95% 
Motors Voltage 110% 
Motors Voltage 90% 
UT Limits 
UNIT OPERATION LIMITS 
(shaded area) 
947 MVA UT Rated Power 
23.13 kV UT Primary Voltage 
345 kV UT Secondary Voltage 
9.17% UT Impedance 
1.585 kA UT Tap Current 
1006 MVA Gen. Rated Power 
854.9 MW Gen. Active Power 
530 Mvar Gen. Overex. Limit 
-346 Mvar Gen. Underex. Limit 
24 kV Gen. Rated Voltage 
60 MVA UAT Rated Power 
24 KV UAT Primary Voltage 
7.07 KV UAT Secondary Voltage 
7.50% UAT Impedance 
42.42 MW Unit Aux. Active Load 
30.71 Mvar Unit Aux. React. Load 
6.6 kV Motors Rated Voltage 
330 kV Syst. Volt. Lowest Limit 
362 KV Syst. Volt. Highest Limit 
UT Ratio 22 / 399 kV (Tap 5), Generator Net Output 576 MW 
UT Rating 650 MVA, UT Impedance 17%, Generator Rated Voltage 22 kV 
System Voltages: 
0.95 
-100 -80 -60 -40 -20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 
Generator Reactive Power Output Net Value 
Transferred to (+) or from (-) UT (Mvar) 
Generator Voltage (per-unit) 
420 kV 412 kV 
410 kV 
408 kV 
406 kV 
400 kV 
380 kV 
Fig. 2. Change in generator voltage with generator reactive load for various 
system voltages. 
Fig.3 Reactive power transferred to/from system as a function of system 
voltage (operation area limit).
גליון 46 , אוגוסט 59 2013 
4 
(over-excitation). When the V/Hz ratios are exceeded, 
saturation of the magnetic core of the transformers may occur, 
and stray flux may be induced in non-laminated components 
that are not designed to carry flux. This can cause severe 
localized overheating in the transformer and eventual 
breakdown of the core assembly and/or winding insulation. 
As mentioned before, the IEC 60076-1 [3] definitions 
imply that rated voltage is applied to primary winding, and the 
voltage across the secondary terminals differs from rated 
voltage (defined in no-load condition) by the voltage drop/rise 
in the transformer. Contrarily, by IEEE C57.12.00 [16] the 
rated output is delivered at rated secondary voltage; according 
to IEEE definition, allowance for voltage drop has to be made 
in the design so that the necessary primary voltage can be 
applied to the transformer (at a secondary load lagging power 
factor of 0.80 or higher). For instance, a UT with a impedance 
of 15% (typical range: 13–17%) designed according to IEEE 
shall withstand continuously primary voltages as high as 
110% of the rated value when fully loaded at a power factor 
of 0.80 (value calculable using the transformer equivalent 
circuit). Such hidden capability will not be available in the 
case of a transformer which follows the IEC requirements. 
According to IEC 60076-1 [3], a transformer shall be 
capable of continuous operation up to 105% voltage or V/Hz 
(the standard meaning is per each winding). IEC 60076-8 [17] 
adds that this is not meant to be systematically utilized in 
normal service, but should be reserved for relatively rare cases 
of emergency service under limited periods of time. IEEE 
C57.12.00 [16] defines the over-flux capability in a different 
way: secondary voltage and V/Hz up to 105% of rated values 
when load power factor is 0.80 or higher (lagging). Taking 
into account the previous considerations, this additional 
requirement may result in 10-15% primary overvoltage (and 
over-excitation) for a fully loaded generator step-up 
transformer built under IEEE. Fortunately, generators are only 
capable of continuous operation until 5% above or 5% below 
their rated voltage, by [10]-[12] (i.e. V/Hz until 105% at 
generator base) so the above overvoltage capabilities are 
rarely exploited. For UAT and SST the impedance is usually 
smaller than for UT, they often work not fully loaded and the 
primary voltage will normally not rise by more than a few 
percentage points for a secondary increase of 5%. 
Another aspect related to an overvoltage condition is 
whether the UT and UAT will be subjected to load rejection. 
Sudden loss of load can subject these transformers to 
substantial overvoltage. If saturation occurs, substantial 
exciting current will flow, which may overheat the core and 
damage the transformer. A sudden unit unloading during a 
fault may be caused by the clearing of a system fault and, 
hence, the machine may be at the ceiling of its excitation 
system; the unit transformer may be excited with voltages 
exceeding 130% of normal [18], [19]. With the excitation 
control in service, the over-excitation will generally be 
reduced to safe limits in a few seconds; with the excitation 
control out of service, the over-excitation may be sustained 
and damage can occur (unless dedicated V/Hz protection 
exists). Both IEC 60076-1 [3] and IEEE C57.12.00 [16] allow 
continuous operation at no load at a voltage or V/Hz up to 
110% of the rated values. For the particular case of 
transformers connected directly to generators in such a way 
that they may be subjected to load rejection (i.e. 
configurations without generator breaker), [3] has an 
additional requirement: to be able to withstand 1.4 times rated 
primary voltage for 5 seconds. 
VIII. CONNECTION ARRANGEMENT AND PHASE 
DISPLACEMENT 
Normally the high voltage system is grounded, leading the 
UT’s high voltage windings to be star connected, with the 
neutral often solidly grounded. The reason for this is mainly 
related to equipment insulation level and system protection 
requirements. The significant consequence as regards the 
transformer high voltage windings is the possibility to use 
non-uniform, cheaper insulation systems (i.e. the neutral 
terminal insulation is designed with a lower insulation level 
than assigned for the line terminals). On the other hand, it is 
convenient to have the low voltage windings delta connected 
(the delta circuit provides a path for third-order harmonics of 
the magnetizing currents, thus reducing the voltage waveform 
distortion; it also stabilizes the neutral point potential in the 
case it is left ungrounded). The most common connection / 
angular (phase) displacement used for large UTs is YNd1 [9], 
[14], however YNd11 is also encountered (Fig. 4). 
For similar reasons, commonly the UAT primary windings 
(connected to the generator side) are delta connected, while 
the secondary ones are star connected through a current-limiting 
resistor. The most common connections used for 
UAT are Dyn11 [14] or Dyn1 [9] (Fig. 5). According to IEEE 
C57.12.00 [16], in Yd or Dy transformers the low voltage 
shall lag the high voltage by 30°; the connection Yd1 for step-up 
transformer matches this standard, while Dy11 for step-down 
transformers does not; however, a standard Dy1 UAT 
H0 H1 H2 H3 H0 H1 H2 H3 
H1 H1 
H0 H0 
H3 H2 H3 H2 
X1 X2 X3 X1 X1 X2 X3 
X2 
a) YNd1 b) YNd11 
Fig. 4 Most common connection/phase displacement used for UTs. 
X2 
X1 
SYSTEM SIDE 
GENERATOR 
SIDE 
X3 
X3 
H1 H2 H3 H1 H1 H2 H3 H1 
GENERATOR 
SIDE 
H3 H2 H3 H2 
X0 X1 X2 X3 X1 X0 X1 X2 X3 X1 
X0 
AUXILIARIES 
X2 SIDE X3 X0 
X3 X2 
a) Dyn11 b) Dyn1 
Fig. 5 Most common connection/phase displacement used for UATs. 
in such a way that they may be subjected to load rejection (i.e. 
configurations without generator breaker), [3] has an additional 
requirement: to be able to withstand 1.4 times rated primary volt-age 
for 5 seconds. 
VIII. Connection Arrangement and Phase Displacement 
Normally the high voltage system is grounded, leading the 
UT’s high voltage windings to be star connected, with the neutral 
often solidly grounded. The reason for this is mainly related to 
equipment insulation level and system protection requirements. 
The significant consequence as regards the transformer high 
voltage windings is the possibility to use non-uniform, cheaper 
insulation systems (i.e. the neutral terminal insulation is designed 
with a lower insulation level than assigned for the line terminals). 
On the other hand, it is convenient to have the low voltage windings 
delta connected (the delta circuit provides a path for third-order 
harmonics of the magnetizing currents, thus reducing the voltage 
waveform distortion; it also stabilizes the neutral point potential 
in the case it is left ungrounded). The most common connection 
/ angular phase) displacement used for large UTs is YNd1 [9], 
[14], however YNd11 is also encountered (Fig. 4). 
For similar reasons, commonly the UAT primary windings 
(connected to the generator side) are delta connected, while the 
secondary ones are star connected through a current-limiting 
resistor. The most common connections used for UAT are Dyn11 
[14] or Dyn1 [9] (Fig. 5). According to IEEE C57.12.00 [16], in 
Yd or Dy transformers the low voltage shall lag the high voltage 
by 30°; the connection Yd1 for step-up transformer matches 
this standard, while Dy11 for step-down transformers does not; 
however, a standard Dy1 UAT with phase sequence externally 
reversed on both sides, as explained below, is equal to Dy11. The 
IEC standards do not have such restrictions. 
If the UT is YNd1 and the UAT is Dyn11, the medium voltage 
auxiliary system has zero-phase shift compared with the high/ 
extra high voltage system (Fig. 1a). During unit start-up or shut-down, 
the medium voltage busses fed from the UAT and SST 
secondary windings are briefly paralleled (by the fast transfer 
scheme), so both must be in phase. Additionally, the high and 
extra high voltage systems are always in phase so the SST must 
produce zero-phase displacement and therefore, usually it is a 
star-star as YNyn0 transformer. In same cases it will have a delta-connected 
tertiary winding, for the reasons mentioned above. For 
modern transformers, it is matter of the grid configuration and/or 
protection requirements whether the SST is provided with a delta 
tertiary or not. 
The connection configurations and phasor groups are drawn 
in Fig. 4 and 5 according to IEC 60076-1 conventions [3]. Since 
that standard mentions that terminal marking on the transformers 
follows national practice, Fig. 4 and 5 use the American practice 
- IEEE C57.12.70 [20]. 
If the original transformer should be replaced by a non-identical 
substitute, matching the three-phase connections and phase-angle 
relations may be a complicated or even an impossible task. 
Normally it is not possible to substitute a UT or UAT having the 
vector group number 11 with a vector group number 1 transformer 
(or the opposite); the reason was explained above: these two 
transformers link between two rigid phasor systems. Only in the 
case of a unit equipped with generator breaker (Fig. 1b), it may be 
possible to use a YNd11 UT instead of a YNd1 one (or contrary) 
assuming no rapid transfer is performed to other auxiliary bus-bars. 
However, such substitution will affect the secondary circuits 
(at least the differential protection) and changes will be required 
in relays settings and/or matching by intermediate transformers. 
It is recommended to check also any potential influence on 
synchronizing circuits; it is a good practice to use supervision 
sync-check relay with two or three phase-sensing circuits. 
Theoretically, it is possible to keep the original vector group 
while using a different group transformer. For example, an UAT 
with vector group 11 may be used in place of an original device 
with vector group 1 (or inverse), by reversing the phase sequence 
on both sides of the transformer. Such change is shown in Fig. 
6a: as viewed from the external line connections, the Dy11 
transformer became a Dy1 one. Unfortunately, the rigid isolated 
phase bus bars on the generator side and non-segregated bars on 
medium voltage side will not allow such cross-connections in 
most cases. 
The substitution may be complicated by the transformer layout 
terminal marking and sequence. According to IEEE C57.12.70 
[20], the terminals are marked as in Fig. 7a, i.e. the H1 lead is 
brought out as the right-hand terminal as seen when facing the 
high voltage side. Other countries may use different standards; 
for instance, the English practice is to locate the high voltage 
terminals from left to right when facing that side [21]; the German 
DIN 42402 rule is the terminals are arranged from right to left as 
viewed from the low voltage side [22] (Fig. 7b). For instance, if 
an UAT designed according to the German standard with a vector 
group Dy11 is installed in place of an original UAT designed 
according to an American one, without any change in the external 
connections, it will externally appear as a Dy1 transformer (Fig. 
6 b). 
Taking in account both vector group and terminal sequence 
aspects, an Yd1 American transformer is interchangeable with a 
European Yd11, without any external modifications. 
IX. Taps and Tap-Changer 
The original transformer may be equipped with on-load tap-changer 
or de-energized tap-changer. Normally a substitution for 
a limited period of time with a fixed turns-ratio transformer will 
be possible in an emergency. When choosing the most suitable tap 
of the substitute transformer, it is indispensable to check whether 
it is a full-power tapping (e.g. suitable for a current equal to the 
rated power divided by the tap voltage).
58 גליון 46 , אוגוסט 2013 
By IEEE C57.12.00 [16], whenever a transformer is 
provided with de-energized taps, they shall be full capacity 
taps. Transformers with on-load tap-changer shall be capable of 
delivering rated MVA at the rated voltage and on all taps above 
rated voltage. However, for taps below the rated voltage, they shall 
be capable of just delivering the rated current related to the rated 
voltage (i.e. these taps may be of reduced MVA, unless specified 
otherwise). By IEC 60076-1 [3] all taps shall be full-power taps, 
except when specified otherwise. 
Almost all transformers used in power plants are at least 
equipped with de-energized tap-changers. Sometimes, especially 
in case of units equipped with generator breakers, it is difficult to 
ensure the unit auxiliaries suitable voltage under any operation 
regime. To overcome this problem, UAT with on-load tap-changer 
may be required. In some cases, UT or SST are equipped with on-load 
in place of de-energized taps to allow for large variations in 
transmission system voltage. 
X. Impedance 
When designing a new plant, the selection of transformer 
short-circuit impedance (in fact the reactance, the resistance 
being negligible for large transformers) is subject to conflicting 
demands: low enough to limit the voltage drop and to meet 
stability requirements, but also suitable high to set the system 
short circuit levels according to economic limitations of the 
switchgear and other connected plant. If a generator breaker is 
used, regulation of the UAT with the generator offline should 
also be considered. These aspects should be also considered for a 
replacement transformer. 
Since reactance is a result of leakage flux, low reactance is 
obtained by minimizing leakage flux and doing this requires a 
large core and an expensive transformer. Conversely, if high 
reactance can be tolerated, a smaller core can be provided and so 
a less expensive transformer. 
It should be noted that since the rated MVA (S) appears in 
the numerator of the expression for percentage impedance (z%) 
calculated from its ohmic value (Zohm), the value of percentage 
impedance tends to increase as the transformer rating increases: 
z% = Zohm x S / U2. (2) 
That means that large MVA at low impedances may require 
significant bulky transformers, and permissible transport limits of 
dimensions and weight may be reached. It is at this stage that the 
use of single-phase units may need to be considered. 
XI. Unbalance when Using Single Phase TU 
In addition to all the issues discussed in this paper that must be 
considered when selecting a substitute transformer, single-phase 
transformer replacement from a three-phase step-up unit introduces 
an additional concern: generator neutral current unbalance. 
Neutral current of the main generator is monitored in many 
power plants, in particular those with large generating units. 
Neutral current can be the result of a ground fault on the generator 
stator windings, on the circuit (isolated phase bus or cables) 
between the generator and UAT(s) and UT, or on the delta-connected 
windings of the UT or UATs. Upon exceeding certain 
amplitude, the generator neutral current alarms and might also trip 
the unit, by an overcurrent relay in the neutral circuit, or, by an 
overvoltage relay connected across the neutral resistor. 
A slightly different turns ratio and/or different impedance 
(resulting in different regulation) between the substituted 
transformer and the other two will result in voltage unbalance 
and thus, negative sequence voltages and currents. This condition 
will not lead to an increase in generator neutral current, although 
it introduces other problems discussed elsewhere in this paper. 
However, different winding capacitances to ground between the 
substituted and the other two transformers will result in an increase 
in neutral generator currents, with possible adverse impact on the 
protective scheme of the generator neutral. 
Fig. 8 shows the typical arrangement of a large generator 
grounded at the neutral via a single phase grounding transformer 
with a resistive load connected to the secondary winding, sized 
to reduce any fault current to about 15 to 25 Amps. The sizing 
of the neutral resistor is a simple calculation that can be found in 
any good book on generator protection or in the standard IEEE 
C62.92.2. It is mainly dependent on the value of the capacitance to 
ground of the generator as well as all other equipment connected 
to its stator leads. Fig. 8 shows the capacitances to ground of all 
windings and the isolated phase bus for each of the three phases. 
In the figure, the capacity to ground of the UT and UAT(s) are 
lumped in a single delta-connected component. 
Under normal conditions, all the capacitances to ground are 
balanced among the phases and the neutral current is very close to 
zero. However, if a substitute one-phase transformer is installed 
with different capacitance, the circuit becomes unbalanced, and 
the neutral current will grow. Finding the value of the unbalanced 
current requires solving the unbalanced circuit by any of several 
available methods. One such method requires the delta connection 
of capacitors to be replaced by its wye (star) equivalent. All series 
resistances and reactance are neglected. Then, Fig. 8 can be 
simplified to the circuit shown in Fig. 9. In the circuit, all the 
variables are vector quantities, with exception of Rr which is the 
grounding resistance referred to the primary side. Voltages are 
assumed balanced and generator / isolated phase bus capacitances 
to ground equal in each phase. Given that the capacitance 
reactance to ground is much higher than the series impedance of 
the windings/buses, these last are disregarded. Following, and 
using superposition, the total neutral current IN can be calculated 
by solving for each phase a circuit as shown in Fig. 10 (example 
for phase A) and then summing together. 
Following the calculation of the neutral unbalanced current, 
proper setting of the neutral protection can be done. 
XII. Overcurrent Considerations 
5 
sides, as 
standards do not 
medium 
compared with 
unit start-up 
from the 
paralleled (by 
in phase. 
systems are 
zero-phase 
as YNyn0 
connected 
For modern 
configuration and/or 
provided with a 
groups are 
conventions 
marking on the 
5 use the 
by a non-identical 
connections and 
even an 
substitute a UT 
a vector 
reason was 
between two 
equipped with 
a YNd11 
no rapid 
However, 
at least the 
in relays 
transformers. It is 
influence on 
supervision 
circuits. 
original vector 
example, 
place of an 
reversing 
transformer. Such 
external line 
Dy1 one. 
bars on the 
medium voltage 
cases. 
transformer 
to IEEE 
7a, i.e. the 
seen when 
different 
locate the 
that side 
[21]; the German DIN 42402 rule is the terminals are arranged 
from right to left as viewed from the low voltage side [22] 
(Fig. 7b). For instance, if an UAT designed according to the 
German standard with a vector group Dy11 is installed in 
place of an original UAT designed according to an American 
one, without any change in the external connections, it will 
externally appear as a Dy1 transformer (Fig. 6 b). 
Taking in account both vector group and terminal sequence 
aspects, an Yd1 American transformer is interchangeable with 
a European Yd11, without any external modifications. 
IX. TAPS AND TAP-CHANGER 
The original transformer may be equipped with on-load 
tap-changer or de-energized tap-changer. Normally a 
substitution for a limited period of time with a fixed turns-ratio 
transformer will be possible in an emergency. When 
choosing the most suitable tap of the substitute transformer, it 
is indispensable to check whether it is a full-power tapping 
(e.g. suitable for a current equal to the rated power divided by 
the tap voltage). 
By IEEE C57.12.00 [16], whenever a transformer is 
provided with de-energized taps, they shall be full capacity 
taps. Transformers with on-load tap-changer shall be capable 
of delivering rated MVA at the rated voltage and on all taps 
above rated voltage. However, for taps below the rated 
voltage, they shall be capable of just delivering the rated 
current related to the rated voltage (i.e. these taps may be of 
reduced MVA, unless specified otherwise). By IEC 60076-1 
[3] all taps shall be full-power taps, except when specified 
otherwise. 
Almost all transformers used in power plants are at least 
equipped with de-energized tap-changers. Sometimes, 
especially in case of units equipped with generator breakers, it 
is difficult to ensure the unit auxiliaries suitable voltage under 
any operation regime. To overcome this problem, UAT with 
A B C A B C 
H1 H2 H3 1V 1U 
A 1W 
A 
C B C B 
a b c a b c 
X1 X2 X3 a 2W 
2V 2U a 
c c 
b b 
a) Dy11→Dy1 b) Dy11→Dy1 
By reversing the phase sequence By using a substitute transformer 
on both sides of the transformer with different terminals layout 
Fig. 6. Modifications of transformer phase displacement. 
H0 H1 H2 H3 1W 1V 1U 1N 
X0 X1 X2 X3 2W 2V 2U 2N 
a) American practice (IEEE C57.12.70) b) German practice (DIN 42402) 
Fig. 7. Transformer layout terminal marking.
The mechanical force and the thermal short-circuit requirements 
described in transformer standards are normally satisfactory for 
UTs. 
However, the UAT must be designed to mechanically and 
thermally withstand the environment in which it operates. The 
standard requirements for network applications may be not 
be adequate for certain types of three-phase through-faults on 
the secondary of the UAT, because of the following: slower dc 
component decrement, longer short-circuit duration, possibility of 
higher primary voltage subsequent to breaker trip (load rejection) 
in block schemes [9]. 
Another eventuality is the fast transfer of load from UAT to 
SST (or vice-versa), which may lead, under certain conditions, 
to high-circulating currents flowing through the two transformers 
exceeding their mechanical design capability [9]. 
In general, examination of the aforementioned requires 
consulting with the manufacturer. 
XIII. Secondary Circuits 
When using a substitute transformer, the protection circuits 
may be required to be modified because the transformer’s rated 
power changed, and/or bushing current transformers have 
different turns ratio, and/or differing secondary current or burden 
capabilities, etc. 
Substitute-transformer’s bushing current transformers, with 
different rated secondary current, ratio or burden than those of 
the original one, may lead to saturation and wrong operation of 
the differential protection. If the turns ratio or vector group of 
the alternative transformer is different from the original unit, it 
should be taken into account regarding current transformers ratio 
and connections. Some differential relays (mainly numerical) can 
internally accommodate the phase shift of the transformer, or 
differences in these ratios. Other relays (mainly electromechanical) 
do not have this versatility, and pose difficulties or need external 
auxiliary current transformers. 
In case of transformer replacement it is important to verify 
adequacy of the transformer over-excitation protection. Often, 
GENERATOR ISOLATED PH. BUS UT & UAT GEN. SIDE 
C GEN C IPB 
N1/N2 
R 
I N 
R r V CPH 
גליון 46 , אוגוסט 57 2013 
protection and output limiting functions are provided in the 
generator excitation equipment, but it is a good practice to apply 
additionally separate V/Hz protection. The curves that define 
generator and transformer V/Hz limits should be coordinated 
to properly protect both. When the transformer rated voltage is 
equal to the generator rated voltage, the same V/Hz relay that is 
protecting the generator may be set in such a way that also protects 
the transformer. In some cases, however, the rated transformer 
voltage is lower than the rated generator voltage and common 
protection may not be applicable; in such a case, it is desirable to 
provide supplementary protection for the transformer. 
XIV. Additional Considerations 
Additional aspects that should be checked when deciding for a 
transformer substitution are: 
- Details of type and arrangement of terminals, for example 
connections to overhead line, isolated phase bus, or cable box or 
gas insulated bus bar. 
- Isolated phase bus ducts with accompanying strong 
magnetic fields may cause high circulating currents in transformer 
tanks and covers which may result in excessive temperatures when 
corrective measures are not included in the design. 
- Unusual voltage conditions including transient over-voltages, 
resonance, switching surges, etc. which may require 
special consideration in insulation design. 
- Derating due to high harmonic load current. 
- Unusual environmental conditions (altitude, special cooling 
air temperature, explosive atmosphere, etc.). 
- Details of auxiliary supply voltage (for fans and pumps, 
tap-changer, alarms, etc.). 
- Sound-level restrictions. 
- Losses level (usually not relevant in case of an emergency 
situation transformer substitution). 
V APH 
I A 
R r C C 
CB CA 
XV. Conclusions 
I N 
The large transformers used in power plants have particular 
characteristics and specific custom designs. Keeping in stock 
spare transformers identical to the critical ones in operation is 
an expensive strategy; however it ensures the lowest risk. The 
advantageousness of this policy increases in the case of multiple 
standardized generating units (one example of interchangeable 
generator transformer is detailed in [23]). 
Checking the suitability of a different substitute transformer is 
a complex task. As a first feasibility check, confirm the transformer 
rated frequency fits your grid, preliminarily look for an available 
transformer ratio close to the ratio of secondary system voltage to 
generator rated voltage (about ±5%), and roughly appreciate the 
transformer largeness, heaviness and available power. 
Following is a partial list of the main parameters that must be 
checked: 
- UT secondary tap voltage should not be lower than 95% of 
the grid’s maximum expected voltage (this value typically equals 
the rated system voltage). 
- UT primary (low) voltage should not be lower than 95% 
of generator rated voltage for transformers designed according to 
IEEE C57.12.00, and not lower than generator rated voltage for 
6 
cases, UT or 
energized taps 
voltage. 
transformer 
resistance 
subject to 
drop and 
to set the 
limitations 
generator 
generator 
should be 
reactance is 
requires a 
Conversely, if high 
provided and 
appears in 
impedance (z%) 
percentage 
transformer rating 
(2) 
may require 
transport 
is at this 
need to be 
UT 
paper that 
transformer, 
phase step-up 
generator neutral 
monitored in many 
generating units. 
fault on the 
phase bus or 
or on the 
UATs. Upon 
neutral current 
overcurrent relay in 
connected 
impedance 
substituted 
unbalance 
currents. This 
generator neutral 
discussed 
elsewhere in this paper. However, different winding 
capacitances to ground between the substituted and the other 
two transformers will result in an increase in neutral generator 
currents, with possible adverse impact on the protective 
scheme of the generator neutral. 
Fig. 8 shows the typical arrangement of a large generator 
grounded at the neutral via a single phase grounding 
transformer with a resistive load connected to the secondary 
winding, sized to reduce any fault current to about 15 to 25 
Amps. The sizing of the neutral resistor is a simple calculation 
that can be found in any good book on generator protection or 
in the standard IEEE C62.92.2. It is mainly dependent on the 
value of the capacitance to ground of the generator as well as 
all other equipment connected to its stator leads. Fig. 8 shows 
the capacitances to ground of all windings and the isolated 
phase bus for each of the three phases. In the figure, the 
capacity to ground of the UT and UAT(s) are lumped in a 
single delta-connected component. 
Under normal conditions, all the capacitances to ground are 
balanced among the phases and the neutral current is very 
close to zero. However, if a substitute one-phase transformer 
is installed with different capacitance, the circuit becomes 
unbalanced, and the neutral current will grow. Finding the 
value of the unbalanced current requires solving the 
unbalanced circuit by any of several available methods. One 
such method requires the delta connection of capacitors to be 
replaced by its wye (star) equivalent. All series resistances and 
reactance are neglected. Then, Fig. 8 can be simplified to the 
circuit shown in Fig. 9. In the circuit, all the variables are 
vector quantities, with exception of Rr which is the grounding 
resistance referred to the primary side. Voltages are assumed 
balanced and generator / isolated phase bus capacitances to 
C LV1 
C LV3 
C LV2 
Fig. 8 Equivalent Circuit of the generator, isolated phase bus, and the delta-connected 
windings of the UT and UATs. 
I A 
I B 
I C 
C A 
C B 
C C 
V APH 
V BPH 
Fig. 9 Simplified circuit for calculating the unbalanced neutral current. 
requirements described in transformer standards are normally 
satisfactory for UTs. 
However, the UAT must be designed to mechanically and 
thermally withstand the environment in which it operates. The 
standard requirements for network applications may be not be 
adequate for certain types of three-phase through-faults on the 
secondary of the UAT, because of the following: slower dc 
component decrement, longer short-circuit duration, 
possibility of higher primary voltage subsequent to breaker 
trip (load rejection) in block schemes [9]. 
Another eventuality is the fast transfer of load from UAT 
to SST (or vice-versa), which may lead, under certain 
conditions, to high-circulating currents flowing through the 
two transformers exceeding their mechanical design capability 
[9]. 
In general, examination of the aforementioned requires 
consulting with the manufacturer. 
XIII. SECONDARY CIRCUITS 
When using a substitute transformer, the protection circuits 
may be required to be modified because the transformer’s 
rated power changed, and/or bushing current transformers 
have different turns ratio, and/or differing secondary current 
or burden capabilities, etc. 
Substitute-transformer’s bushing current transformers, with 
different rated secondary current, ratio or burden than those of 
the original one, may lead to saturation and wrong operation 
of the differential protection. If the turns ratio or vector group 
of the alternative transformer is different from the original 
unit, it should be taken into account regarding current 
transformers ratio and connections. Some differential relays 
(mainly numerical) can internally accommodate the phase 
shift of the transformer, or differences in these ratios. Other 
relays (mainly electromechanical) do not have this versatility, 
and pose difficulties or need external auxiliary current 
transformers. 
In case of transformer replacement it is important to verify 
adequacy of the transformer over-excitation protection. Often, 
supplementary Additional for a transformer - Details example cable - Isolated magnetic transformer temperatures design. 
- Unusual special - Derating - Unusual cooling - Details tap-changer, - Sound-- Losses emergency The characteristics spare an expensive advantageousness multiple interchangeable Checking transformer confirm preliminarily the ratio voltage largeness, Following be checked: 
- UT of the equals Fig. 10 One of the three circuits to be solved for calculating the neutral 
unbalance current.
8 
8 
56 גליון 46 , אוגוסט 2013 
transformers designed according to IEC 60076-1. 
- UAT primary voltage should normally match the rated 
generator voltage; a lower voltage (up to 95% of generator rating) 
may be possible only after investigation of the risk for over-excitation. 
- Check connection and phase displacement suitability. 
- Analyze MVA rating suitability. If taps below the rated 
voltage shall be used, check their MVA capability. 
- Transformer rated voltages higher than the expected 
operating ones mean mandatory reducing the MVA to avoid 
exceeding the rated current. 
- Check dimensions and weight suitability. 
- Analyze the unbalance that may be introduced when 
replacing a single-phase transformer from an UT made of three 
sing-phase transformers. 
- Estimate transformer short circuit impedance influences. 
- Confirm through fault and fast load transfer capability in 
case of UAT/SST replacement. 
- Verify the implications on secondary circuits (mainly 
protection and synchronizing). 
- Thoroughly analyze the synchronizing and loading 
capabilities for any available tap, under various operation 
conditions, using graphs as in Fig.2 or Fig.3. 
- In the eventuality of two units connected to the same bus, one 
of them having a substitute UT (with different MVA or ratio or 
impedance), the possible effect on generators different behavior 
should also be considered. 
XVI. References 
[1] M. G. Say, Alternating Current Machines, 4th edition, Wiley, 
1976, pp.14, 76. 
[2] B. Lawrie, “How does frequency affect transformer 
operation”, EC&M Magazine, Dec. 1992. 
[3] Power Transformers – Part 1: General, IEC Standard 60076- 
1, Ed. 3.0, April 2011. 
[4] IEEE Standard Terminology for Power and Distribution 
Transformers, IEEE Standard C57.12.80-2010, Dec. 2010. 
[5] Power Transformers – Part 7: Loading Guide for Oil- 
Immersed Power Transformers, IEC Standard 60076-7, First 
Ed., Dec. 2005. 
[6] IEEE Guide for Loading Mineral-Oil-Immersed Transformers 
and Step-Voltage Regulators, IEEE Standard C57.91-2011, 
March 2012. 
[7] American National Standard for Electric Power Systems 
and Equipment - Voltage Ratings (60 Hertz), ANSI Standard 
C84.1-2006, Dec. 2006. 
[8] IEC Standard Voltages, IEC Standard 60038, Ed. 6.2, July 
2002. 
[9] IEEE Guide for Transformers Directly Connected to 
Generators, IEEE Standard C57.116-1989, Sep. 1994. 
[10] IEEE Standard for Salient-Pole 50 Hz and 60 Hz Synchronous 
Generators and Generator/Motors for Hydraulic Turbine 
Applications Rated 5 MVA and Above, IEEE Standard 
C50.12-2005, Feb. 2006. 
[11] IEEE Standard for Cylindrical-Rotor 50 Hz and 60 Hz 
Synchronous Generators Rated 10 MVA and Above, IEEE 
Standard C50.13-2005, Feb. 2006. 
[12] Rotating electrical machines – Part 1: Rating and 
performance, IEC Standard 60034-1, Ed. 12.0, Feb. 2010. 
[13] A. W. Goldman, “Selection of Generator Step-up Transformer 
Ratings”, IEEE Trans. Power Apparatus and Systems, vol. 
PAS-100, No. 7, pp. 3425-3431, July 1981. 
[14] A. W. Goldman, C. G. Pebler, Power Plant Electrical 
Reference Series, Vol. 2, Power Transformers, EL-5036-V2, 
EPRI, 1987. 
[15] Power transformers – Part 3: Insulation levels, dielectric 
tests and external clearances in air, IEC Standard 60076-3, 
Second Ed., March 2000. 
[16] IEEE Standard for General Requirements for Liquid-immersed 
Distribution, Power, and Regulating Transformers, 
IEEE Standard C57.12.00-2010, Sep. 2010. 
[17] Power Transformers – Application Guide, IEC Standard 
60076-8, First Ed., Oct. 1997. 
[18] IEEE Guide Protecting Power Transformers, IEEE 
Standard C37.91- 2008, May 2008. 
[19] IEEE Guide for AC Generator Protection, IEEE Standard 
C37.102-2006, Feb. 2007. 
[20] IEEE Standard for Standard Terminal Markings and 
Connections for Distribution and Power Transformers, IEEE 
Standard C57.12.70-2011, Feb. 2012. 
[21] M. J. Heathcote, The J&P Transformer Book, 13th edition, 
Elsevier, 2007, p. 457. 
[22] ABB Switchgear Manual, 11th edition, Cornelsen, 2006, p. 
559. 
[23] Modern Power Station Practice, Vol. D Electrical Systems 
and Equipment, British Electricity International, Pergamon 
Press, 1992, pp.253-257. 
XVII. Biographies 
Relu Ilie received the MS degree in electrical 
engineering from the Technical University 
of Iaşi, Romania. He is in charge of Power 
Plant electrical systems and equipment for 
the Israel Electric Corporation. Relu Ilie 
has 30 years of experience in generation 
and transmission field, mostly dedicated to 
electrical machines issues: design and failure 
analysis, maintenance and inspections, 
monitoring and testing, technical specifications, life extension, 
condition assessment, etc. (email: reluilie@iec.co.il). 
Isidor “Izzy” Kerszenbaum received the 
BSc EE from the Technion – Israel Institute 
of Technology, and the MS and PhD (EE) 
from the University of the Witwatersrand. His 
employment experience includes working 
as large electric machines design engineer 
for GEC in South Africa, and manager of 
R&D for a power distribution transformer 
manufacturer (ITC) in California. He also worked as protection 
engineer and large apparatus consultant with three different 
utilities. He is a past chairman of the PES Electric Machines 
Committee. Currently Dr. Kerszenbaum is chairman of the IEEE 
Working Group 10 on Online Monitoring of Large Synchronous 
Generators.. He is a Fellow of the IEEE. Dr. Kerszenbaum spent 
2002 in the US House of Representatives as a IEEE-AAAS 
Science and Technology Fellow. 
- UT primary (low) voltage should not be lower than 95% 
of generator rated voltage for transformers designed according 
to IEEE C57.12.00, and not lower than generator rated voltage 
for transformers designed according to IEC 60076-1. 
- UAT primary voltage should normally match the rated 
generator voltage; a lower voltage (up to 95% of generator 
rating) may be possible only after investigation of the risk for 
over-excitation. 
- Check connection and phase displacement suitability. 
- Analyze MVA rating suitability. If taps below the rated 
voltage shall be used, check their MVA capability. 
- Transformer rated voltages higher than the expected 
operating ones mean mandatory reducing the MVA to avoid 
exceeding the rated current. 
- Check dimensions and weight suitability. 
- Analyze the unbalance that may be introduced when 
replacing a single-phase transformer from an UT made of 
three sing-phase transformers. 
- Estimate transformer short circuit impedance influences. 
- Confirm through fault and fast load transfer capability in 
case of UAT/SST replacement. 
- Verify the implications on secondary circuits (mainly 
protection and synchronizing). 
- Thoroughly analyze the synchronizing and loading 
capabilities for any available tap, under various operation 
conditions, using graphs as in Fig.2 or Fig.3. 
- In the eventuality of two units connected to the same bus, 
one of them having a substitute UT (with different MVA or 
ratio or impedance), the possible effect on generators different 
behavior should also be considered. 
XVI. REFERENCES 
[1] M. G. Say, Alternating Current Machines, 4th edition, Wiley, 1976, 
pp.14, 76. 
[2] B. Lawrie, "How does frequency affect transformer operation", EC&M 
Magazine, Dec. 1992. 
[3] Power Transformers – Part 1: General, IEC Standard 60076-1, Ed. 3.0, 
April 2011. 
[4] IEEE Standard Terminology for Power and Distribution Transformers, 
IEEE Standard C57.12.80-2010, Dec. 2010. 
[5] Power Transformers – Part 7: Loading Guide for Oil-Immersed Power 
Transformers, IEC Standard 60076-7, First Ed., Dec. 2005. 
[6] IEEE Guide for Loading Mineral-Oil-Immersed Transformers and Step- 
Voltage Regulators, IEEE Standard C57.91-2011, March 2012. 
[7] American National Standard for Electric Power Systems and Equipment 
- Voltage Ratings (60 Hertz), ANSI Standard C84.1-2006, Dec. 2006. 
[8] IEC Standard Voltages, IEC Standard 60038, Ed. 6.2, July 2002. 
[9] IEEE Guide for Transformers Directly Connected to Generators, IEEE 
Standard C57.116-1989, Sep. 1994. 
[10] IEEE Standard for Salient-Pole 50 Hz and 60 Hz Synchronous 
Generators and Generator/Motors for Hydraulic Turbine Applications 
Rated 5 MVA and Above, IEEE Standard C50.12-2005, Feb. 2006. 
[11] IEEE Standard for Cylindrical-Rotor 50 Hz and 60 Hz Synchronous 
Generators Rated 10 MVA and Above, IEEE Standard C50.13-2005, 
Feb. 2006. 
[12] Rotating electrical machines – Part 1: Rating and performance, IEC 
Standard 60034-1, Ed. 12.0, Feb. 2010. 
[13] A. W. Goldman, "Selection of Generator Step-up Transformer Ratings", 
IEEE Trans. Power Apparatus and Systems, vol. PAS-100, No. 7, pp. 
3425-3431, July 1981. 
[14] A. W. Goldman, C. G. Pebler, Power Plant Electrical Reference Series, 
Vol. 2, Power Transformers, EL-5036-V2, EPRI, 1987. 
[15] Power transformers – Part 3: Insulation levels, dielectric tests and 
external clearances in air, IEC Standard 60076-3, Second Ed., March 
2000. 
16] IEEE Standard for General Requirements for Liquid-immersed 
Distribution, Power, and Regulating Transformers, IEEE Standard 
C57.12.00-2010, Sep. 2010. 
[17] Power Transformers – Application Guide, IEC Standard 60076-8, First 
Ed., Oct. 1997. 
[18] IEEE Guide for Protecting Power Transformers, IEEE Standard C37.91- 
2008, May 2008. 
19] IEEE Guide for AC Generator Protection, IEEE Standard C37.102- 
2006, Feb. 2007. 
[20] IEEE Standard for Standard Terminal Markings and Connections for 
Distribution and Power Transformers, IEEE Standard C57.12.70-2011, 
Feb. 2012. 
[21] M. J. Heathcote, The J&P Transformer Book, 13th edition, Elsevier, 
2007, p. 457. 
[22] ABB Switchgear Manual, 11th edition, Cornelsen, 2006, p. 559. 
[23] Modern Power Station Practice, Vol. D Electrical Systems and 
Equipment, British Electricity International, Pergamon Press, 1992, 
pp.253-257. 
XVII. BIOGRAPHIES 
Relu Ilie received the MS degree in electrical 
engineering from the Technical University of Iaşi, 
Romania. He is in charge of Power Plant electrical 
systems and equipment for the Israel Electric 
Corporation. Relu Ilie has 30 years of experience in 
generation and transmission field, mostly dedicated 
to electrical machines issues: design and failure 
analysis, maintenance and inspections, monitoring 
and testing, technical specifications, life extension, 
condition assessment, etc. (email: reluilie@iec.co.il). 
Isidor “Izzy” Kerszenbaum received the BSc EE 
from the Technion – Israel Institute of Technology, 
and the MS and PhD (EE) from the University of the 
Witwatersrand. His employment experience includes 
working as large electric machines design engineer 
for GEC in South Africa, and manager of R&D for a 
power distribution transformer manufacturer (ITC) 
in California. He also worked as protection engineer 
and large apparatus consultant with three different 
utilities. He is a past chairman of the PES Electric 
Machines Committee. Currently Dr. Kerszenbaum is chairman of the IEEE 
Working Group 10 on Online Monitoring of Large Synchronous Generators.. 
He is a Fellow of the IEEE. Dr. Kerszenbaum spent 2002 in the US House of 
Representatives as a IEEE-AAAS Science and Technology Fellow. 
- UT primary (low) voltage should not be lower than 95% 
of generator rated voltage for transformers designed according 
to IEEE C57.12.00, and not lower than generator rated voltage 
for transformers designed according to IEC 60076-1. 
- UAT primary voltage should normally match the rated 
generator voltage; a lower voltage (up to 95% of generator 
rating) may be possible only after investigation of the risk for 
over-excitation. 
- Check connection and phase displacement suitability. 
- Analyze MVA rating suitability. If taps below the rated 
voltage shall be used, check their MVA capability. 
- Transformer rated voltages higher than the expected 
operating ones mean mandatory reducing the MVA to avoid 
exceeding the rated current. 
- Check dimensions and weight suitability. 
- Analyze the unbalance that may be introduced when 
replacing a single-phase transformer from an UT made of 
three sing-phase transformers. 
- Estimate transformer short circuit impedance influences. 
- Confirm through fault and fast load transfer capability in 
case of UAT/SST replacement. 
- Verify the implications on secondary circuits (mainly 
protection and synchronizing). 
- Thoroughly analyze the synchronizing and loading 
capabilities for any available tap, under various operation 
conditions, using graphs as in Fig.2 or Fig.3. 
- In the eventuality of two units connected to the same bus, 
one of them having a substitute UT (with different MVA or 
ratio or impedance), the possible effect on generators different 
behavior should also be considered. 
XVI. REFERENCES 
[1] M. G. Say, Alternating Current Machines, 4th edition, Wiley, 1976, 
pp.14, 76. 
[2] B. Lawrie, "How does frequency affect transformer operation", EC&M 
Magazine, Dec. 1992. 
[3] Power Transformers – Part 1: General, IEC Standard 60076-1, Ed. 3.0, 
April 2011. 
[4] IEEE Standard Terminology for Power and Distribution Transformers, 
IEEE Standard C57.12.80-2010, Dec. 2010. 
[5] Power Transformers – Part 7: Loading Guide for Oil-Immersed Power 
Transformers, IEC Standard 60076-7, First Ed., Dec. 2005. 
[6] IEEE Guide for Loading Mineral-Oil-Immersed Transformers and Step- 
Voltage Regulators, IEEE Standard C57.91-2011, March 2012. 
[7] American National Standard for Electric Power Systems and Equipment 
- Voltage Ratings (60 Hertz), ANSI Standard C84.1-2006, Dec. 2006. 
[8] IEC Standard Voltages, IEC Standard 60038, Ed. 6.2, July 2002. 
[9] IEEE Guide for Transformers Directly Connected to Generators, IEEE 
Standard C57.116-1989, Sep. 1994. 
[10] IEEE Standard for Salient-Pole 50 Hz and 60 Hz Synchronous 
Generators and Generator/Motors for Hydraulic Turbine Applications 
Rated 5 MVA and Above, IEEE Standard C50.12-2005, Feb. 2006. 
[11] IEEE Standard for Cylindrical-Rotor 50 Hz and 60 Hz Synchronous 
Generators Rated 10 MVA and Above, IEEE Standard C50.13-2005, 
Feb. 2006. 
[12] Rotating electrical machines – Part 1: Rating and performance, IEC 
Standard 60034-1, Ed. 12.0, Feb. 2010. 
[13] A. W. Goldman, "Selection of Generator Step-up Transformer Ratings", 
IEEE Trans. Power Apparatus and Systems, vol. PAS-100, No. 7, pp. 
3425-3431, July 1981. 
[14] A. W. Goldman, C. G. Pebler, Power Plant Electrical Reference Series, 
Vol. 2, Power Transformers, EL-5036-V2, EPRI, 1987. 
[15] Power transformers – Part 3: Insulation levels, dielectric tests and 
external clearances in air, IEC Standard 60076-3, Second Ed., March 
2000. 
16] IEEE Standard for General Requirements for Liquid-immersed 
Distribution, Power, and Regulating Transformers, IEEE Standard 
C57.12.00-2010, Sep. 2010. 
[17] Power Transformers – Application Guide, IEC Standard 60076-8, First 
Ed., Oct. 1997. 
[18] IEEE Guide for Protecting Power Transformers, IEEE Standard C37.91- 
2008, May 2008. 
[19] IEEE Guide for AC Generator Protection, IEEE Standard C37.102- 
2006, Feb. 2007. 
[20] IEEE Standard for Standard Terminal Markings and Connections for 
Distribution and Power Transformers, IEEE Standard C57.12.70-2011, 
Feb. 2012. 
[21] M. J. Heathcote, The J&P Transformer Book, 13th edition, Elsevier, 
2007, p. 457. 
[22] ABB Switchgear Manual, 11th edition, Cornelsen, 2006, p. 559. 
[23] Modern Power Station Practice, Vol. D Electrical Systems and 
Equipment, British Electricity International, Pergamon Press, 1992, 
pp.253-257. 
XVII. BIOGRAPHIES 
Relu Ilie received the MS degree in electrical 
engineering from the Technical University of Iaşi, 
Romania. He is in charge of Power Plant electrical 
systems and equipment for the Israel Electric 
Corporation. Relu Ilie has 30 years of experience in 
generation and transmission field, mostly dedicated 
to electrical machines issues: design and failure 
analysis, maintenance and inspections, monitoring 
and testing, technical specifications, life extension, 
condition assessment, etc. (email: reluilie@iec.co.il). 
Isidor “Izzy” Kerszenbaum received the BSc EE 
from the Technion – Israel Institute of Technology, 
and the MS and PhD (EE) from the University of the 
Witwatersrand. His employment experience includes 
working as large electric machines design engineer 
for GEC in South Africa, and manager of R&D for a 
power distribution transformer manufacturer (ITC) 
in California. He also worked as protection engineer 
and large apparatus consultant with three different 
utilities. He is a past chairman of the PES Electric 
Machines Committee. Currently Dr. Kerszenbaum is chairman of the IEEE 
Working Group 10 on Online Monitoring of Large Synchronous Generators.. 
He is a Fellow of the IEEE. Dr. Kerszenbaum spent 2002 in the US House of 
Representatives as a IEEE-AAAS Science and Technology Fellow.

More Related Content

What's hot

Fuzzy control of shoot through time of single stage boost inverter with coupl...
Fuzzy control of shoot through time of single stage boost inverter with coupl...Fuzzy control of shoot through time of single stage boost inverter with coupl...
Fuzzy control of shoot through time of single stage boost inverter with coupl...IAEME Publication
 
How to reduce transformer losses
How to reduce transformer lossesHow to reduce transformer losses
How to reduce transformer losseskamal soni
 
TRANSFORMERS and LOSSES
TRANSFORMERS and LOSSESTRANSFORMERS and LOSSES
TRANSFORMERS and LOSSESPraveen Kumar
 
Basic electrical engineering (Autotransformer)
Basic electrical engineering (Autotransformer)Basic electrical engineering (Autotransformer)
Basic electrical engineering (Autotransformer)Home
 
On load tap changer in a.c. locomotive transformer & air blast circuit b...
On load tap changer in a.c. locomotive transformer  & air blast circuit b...On load tap changer in a.c. locomotive transformer  & air blast circuit b...
On load tap changer in a.c. locomotive transformer & air blast circuit b...vishalgohel12195
 
Power Transformer in DPL
Power Transformer in DPLPower Transformer in DPL
Power Transformer in DPLAbhishek Roy
 
How to reduced transformer losses report
How to reduced transformer losses reportHow to reduced transformer losses report
How to reduced transformer losses reportkamal soni
 
A Novel High Performance H-Bridge Converter Topology for 8/6 pole SRM Drive
A Novel High Performance H-Bridge Converter Topology for 8/6  pole SRM DriveA Novel High Performance H-Bridge Converter Topology for 8/6  pole SRM Drive
A Novel High Performance H-Bridge Converter Topology for 8/6 pole SRM DriveIJMER
 
Basics of Poly phase transformer _ppt
Basics of Poly phase transformer _pptBasics of Poly phase transformer _ppt
Basics of Poly phase transformer _pptAjay Balar
 
Design and Optimum Arrangement Of 3-phase Cascade Multilevel Inverter for Con...
Design and Optimum Arrangement Of 3-phase Cascade Multilevel Inverter for Con...Design and Optimum Arrangement Of 3-phase Cascade Multilevel Inverter for Con...
Design and Optimum Arrangement Of 3-phase Cascade Multilevel Inverter for Con...IOSR Journals
 
Voltage Control of Single-Phase Two Winding Self Excited Induction Generator ...
Voltage Control of Single-Phase Two Winding Self Excited Induction Generator ...Voltage Control of Single-Phase Two Winding Self Excited Induction Generator ...
Voltage Control of Single-Phase Two Winding Self Excited Induction Generator ...IJPEDS-IAES
 
All about motor
All about motorAll about motor
All about motoranil0943
 
Single phase compensated motor
Single phase compensated motorSingle phase compensated motor
Single phase compensated motorSayanSarkar55
 

What's hot (19)

Bee016 facts
Bee016 factsBee016 facts
Bee016 facts
 
Fuzzy control of shoot through time of single stage boost inverter with coupl...
Fuzzy control of shoot through time of single stage boost inverter with coupl...Fuzzy control of shoot through time of single stage boost inverter with coupl...
Fuzzy control of shoot through time of single stage boost inverter with coupl...
 
How to reduce transformer losses
How to reduce transformer lossesHow to reduce transformer losses
How to reduce transformer losses
 
TRANSFORMERS and LOSSES
TRANSFORMERS and LOSSESTRANSFORMERS and LOSSES
TRANSFORMERS and LOSSES
 
Basic electrical engineering (Autotransformer)
Basic electrical engineering (Autotransformer)Basic electrical engineering (Autotransformer)
Basic electrical engineering (Autotransformer)
 
On load tap changer in a.c. locomotive transformer & air blast circuit b...
On load tap changer in a.c. locomotive transformer  & air blast circuit b...On load tap changer in a.c. locomotive transformer  & air blast circuit b...
On load tap changer in a.c. locomotive transformer & air blast circuit b...
 
RGPV EX503 UNIT III
RGPV EX503 UNIT IIIRGPV EX503 UNIT III
RGPV EX503 UNIT III
 
Power Transformer in DPL
Power Transformer in DPLPower Transformer in DPL
Power Transformer in DPL
 
How to reduced transformer losses report
How to reduced transformer losses reportHow to reduced transformer losses report
How to reduced transformer losses report
 
Substation overview
Substation overviewSubstation overview
Substation overview
 
A Novel High Performance H-Bridge Converter Topology for 8/6 pole SRM Drive
A Novel High Performance H-Bridge Converter Topology for 8/6  pole SRM DriveA Novel High Performance H-Bridge Converter Topology for 8/6  pole SRM Drive
A Novel High Performance H-Bridge Converter Topology for 8/6 pole SRM Drive
 
Basics of Poly phase transformer _ppt
Basics of Poly phase transformer _pptBasics of Poly phase transformer _ppt
Basics of Poly phase transformer _ppt
 
40220140507002
4022014050700240220140507002
40220140507002
 
Transformer
Transformer Transformer
Transformer
 
Design and Optimum Arrangement Of 3-phase Cascade Multilevel Inverter for Con...
Design and Optimum Arrangement Of 3-phase Cascade Multilevel Inverter for Con...Design and Optimum Arrangement Of 3-phase Cascade Multilevel Inverter for Con...
Design and Optimum Arrangement Of 3-phase Cascade Multilevel Inverter for Con...
 
Voltage Control of Single-Phase Two Winding Self Excited Induction Generator ...
Voltage Control of Single-Phase Two Winding Self Excited Induction Generator ...Voltage Control of Single-Phase Two Winding Self Excited Induction Generator ...
Voltage Control of Single-Phase Two Winding Self Excited Induction Generator ...
 
All about motor
All about motorAll about motor
All about motor
 
Single phase compensated motor
Single phase compensated motorSingle phase compensated motor
Single phase compensated motor
 
Tpel.2005.854020
Tpel.2005.854020Tpel.2005.854020
Tpel.2005.854020
 

Similar to Power Transformer Substitution in Generating Stations

132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training reportMuntazir Mehdi
 
MV Transformer Replacement Decisions
MV Transformer Replacement DecisionsMV Transformer Replacement Decisions
MV Transformer Replacement DecisionsLeonardo ENERGY
 
Transformers pptxx.ppt
Transformers pptxx.pptTransformers pptxx.ppt
Transformers pptxx.pptjaajasnjkja
 
Electrical engineering-portal.com-mv circuit-breaker_or_vacuum_contactor_part_1
Electrical engineering-portal.com-mv circuit-breaker_or_vacuum_contactor_part_1Electrical engineering-portal.com-mv circuit-breaker_or_vacuum_contactor_part_1
Electrical engineering-portal.com-mv circuit-breaker_or_vacuum_contactor_part_1Abu Hashim
 
Why transformers fail_final
Why transformers fail_finalWhy transformers fail_final
Why transformers fail_finalSnehangshu Ghosh
 
Unique Role Of Wtsu Transformers
Unique Role Of Wtsu TransformersUnique Role Of Wtsu Transformers
Unique Role Of Wtsu Transformerspacificcresttrans
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...f95346
 
EDEC_Design of Transformer_part-1.pdf
EDEC_Design of Transformer_part-1.pdfEDEC_Design of Transformer_part-1.pdf
EDEC_Design of Transformer_part-1.pdfTanmoyMondal89
 
Transformer types
Transformer typesTransformer types
Transformer typeselprocus
 
Voltage regulators-vs-load-tap-changers-information-td225012en
Voltage regulators-vs-load-tap-changers-information-td225012enVoltage regulators-vs-load-tap-changers-information-td225012en
Voltage regulators-vs-load-tap-changers-information-td225012enKritika sharma
 
High voltage transformers
High voltage transformersHigh voltage transformers
High voltage transformersDr.Raja R
 
Cost savings by low-loss distribution transformers in wind power plants
Cost savings by low-loss distribution transformers in wind power plantsCost savings by low-loss distribution transformers in wind power plants
Cost savings by low-loss distribution transformers in wind power plantsLeonardo ENERGY
 
TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...
TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...
TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...eeiej_journal
 
Transformer report-Siemens
Transformer report-SiemensTransformer report-Siemens
Transformer report-SiemensMahmood Ali
 
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Low
 
About SOLID STATE TRANSFORMER
About SOLID STATE TRANSFORMERAbout SOLID STATE TRANSFORMER
About SOLID STATE TRANSFORMERBalaNaik2
 
What is the Importance of a Transformer in the Industrial Sector?
What is the Importance of a Transformer in the Industrial Sector?What is the Importance of a Transformer in the Industrial Sector?
What is the Importance of a Transformer in the Industrial Sector?Shakti Electronics
 

Similar to Power Transformer Substitution in Generating Stations (20)

132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report
 
MV Transformer Replacement Decisions
MV Transformer Replacement DecisionsMV Transformer Replacement Decisions
MV Transformer Replacement Decisions
 
Transformers pptxx.ppt
Transformers pptxx.pptTransformers pptxx.ppt
Transformers pptxx.ppt
 
TRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptxTRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptx
 
Electrical engineering-portal.com-mv circuit-breaker_or_vacuum_contactor_part_1
Electrical engineering-portal.com-mv circuit-breaker_or_vacuum_contactor_part_1Electrical engineering-portal.com-mv circuit-breaker_or_vacuum_contactor_part_1
Electrical engineering-portal.com-mv circuit-breaker_or_vacuum_contactor_part_1
 
Why transformers fail_final
Why transformers fail_finalWhy transformers fail_final
Why transformers fail_final
 
Unique Role Of Wtsu Transformers
Unique Role Of Wtsu TransformersUnique Role Of Wtsu Transformers
Unique Role Of Wtsu Transformers
 
G1-Distri-Transformer.pptx
G1-Distri-Transformer.pptxG1-Distri-Transformer.pptx
G1-Distri-Transformer.pptx
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
 
EDEC_Design of Transformer_part-1.pdf
EDEC_Design of Transformer_part-1.pdfEDEC_Design of Transformer_part-1.pdf
EDEC_Design of Transformer_part-1.pdf
 
Transformer types
Transformer typesTransformer types
Transformer types
 
Voltage regulators-vs-load-tap-changers-information-td225012en
Voltage regulators-vs-load-tap-changers-information-td225012enVoltage regulators-vs-load-tap-changers-information-td225012en
Voltage regulators-vs-load-tap-changers-information-td225012en
 
High voltage transformers
High voltage transformersHigh voltage transformers
High voltage transformers
 
Cost savings by low-loss distribution transformers in wind power plants
Cost savings by low-loss distribution transformers in wind power plantsCost savings by low-loss distribution transformers in wind power plants
Cost savings by low-loss distribution transformers in wind power plants
 
TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...
TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...
TCSC AND SVC OPTIMAL LOCATION TO IMPROVE THE PERFORMANCE OF POWER SYSTEM WITH...
 
Transformer report-Siemens
Transformer report-SiemensTransformer report-Siemens
Transformer report-Siemens
 
5 power house
5 power house5 power house
5 power house
 
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015
 
About SOLID STATE TRANSFORMER
About SOLID STATE TRANSFORMERAbout SOLID STATE TRANSFORMER
About SOLID STATE TRANSFORMER
 
What is the Importance of a Transformer in the Industrial Sector?
What is the Importance of a Transformer in the Industrial Sector?What is the Importance of a Transformer in the Industrial Sector?
What is the Importance of a Transformer in the Industrial Sector?
 

Recently uploaded

Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDGMarianaLemus7
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 

Recently uploaded (20)

Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDG
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
The transition to renewables in India.pdf
The transition to renewables in India.pdfThe transition to renewables in India.pdf
The transition to renewables in India.pdf
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 

Power Transformer Substitution in Generating Stations

  • 1. Power Transformers in Generating Stations Relu Ilie, Israel Electric Corporation, and Isidor Kerszenbaum, Exponent, Inc. Issues to Consider when Substituting Large Power Transformers in Generating Stations Relu Ilie, Israel Electric Corporation, and Isidor Kerszenbaum, Exponent, Inc. EHV EHV/HV EHV 62 גליון 46 , אוגוסט 2013 Abstract—For availability reasons, many generating utilities keep in storage custom designed spare transformers, readily available and identical to their critical large power transformers. However, in case an exact replacement is not available, the only option the generating utility has is to search for a substitute transformer that, as a minimum, is able to offer a temporary solution. The purpose of this paper is to indicate the most important aspects to be considered when checking the interchangeability of such substitute transformer, based on authors’ experience and on various standards requirements. Index Terms—power plants, power transformers. I. Introduction THE power transformer is a reliable device, yet not failure-free. It has no moving parts, consequently neither the typical faults of rotating machines. On the other hand, the large transformers are oil-immersed and suffer from other faults, mainly chemically or electrically related. A transformer internal fault may be very difficult to locate and to repair. In many cases, the owner may decide that it is faster and cheaper to buy a new transformer than to repair an old damaged one. Even when the repair is worthwhile, it may last for many months. Almost all large transformers used in power plants are custom-designed. Keeping in storage suitable spare transformers is a common practice, for the purpose of avoiding long unplanned outages and high economic losses. In case an exact replacement is not available, the only option the generating utility has is to search for a substitute transformer that, as a minimum, is able to offer a temporary solution than may introduce some operational constraints. The goal of this paper is to mention the most important aspects to be considered when checking the interchangeability of such substitute transformer. The discussion is based on the various requirements included in relevant American and European standards. The most common generating station arrangements are shown in Fig. 1: a unit generator-transformer block configuration, and a unit generator-transformer with generator breaker. The vital large transformers in a power plant are the unit step-up/main/ generator transformer (UT), the auxiliary transformer (UAT) and the station service/reserve transformer (SST). A failure of any one of these transformers may lead to unit shutdown or start-up unavailability. II. General Layout The UT may consist of a single three-phase unit, two half-size three-phase units, or three single-phase units. This is the most evident aspect to consider when a substitute transformer is needed. When designing a new plant, the selection among these alternatives is generally based on consideration of some form of strategic reserve, as well as available space. Two half-size transformers may be selected in place of a single full-size transformer in order to reduce the cost of the spare. For similar reasons, a generator transformer may be made as a bank of single-phase units. Normally the cost, mass, and loss of such solutions are larger than for a single three-phase transformer; however, they may be preferable if transport size or weight limits apply. The three single-phase transformers provide independent magnetic circuits (see Section XI below), representing high magnetizing impedance for zero-sequence voltage components. Therefore, a delta equalizer winding is normally provided, implemented by external connection between phase units. Some layouts may pose other complications, like UAT with three-winding design. III. Dimensions and Weight Any physical size and weight limitations should be checked, for example for installation on an existing foundation. Special installation space restrictions may influence the insulation clearan ces and terminal locations on the transformer.  Abstract—For availability reasons, many generating utilities keep in storage custom designed spare transformers, readily available and identical to their critical large power transformers. However, in case an exact replacement is not available, the only option the generating utility has is to search for a substitute transformer that, as a minimum, is able to offer a temporary solution. The purpose of this paper is to indicate the most important aspects to be considered when checking the interchangeability of such substitute transformer, based on authors' experience and on various standards requirements. Index Terms—power plants, power transformers. I. INTRODUCTION HE power transformer is a reliable device, yet not failure-free. It has no moving parts, consequently neither the typical faults of rotating machines. On the other hand, the large transformers are oil-immersed and suffer from other faults, mainly chemically or electrically related. A transformer internal fault may be very difficult to locate and to repair. In many cases, the owner may decide that it is faster and cheaper to buy a new transformer than to repair an old damaged one. Even when the repair is worthwhile, it may last for many months. Almost all large transformers used in power plants are custom-designed. Keeping in storage suitable spare transformers is a common practice, for the purpose of avoiding long unplanned outages and high economic losses. In case an exact replacement is not available, the only option the generating utility has is to search for a substitute transformer that, as a minimum, is able to offer a temporary solution than may introduce some operational constraints. The goal of this paper is to mention the most important aspects to be considered when checking the interchangeability of such substitute transformer. The discussion is based on the various requirements included in relevant American and European standards. The most common generating station arrangements are shown in Fig. 1: a unit generator-transformer block configuration, and a unit generator-transformer with generator breaker. The vital large transformers in a power plant are the unit step-up/main/generator transformer (UT), the auxiliary transformer (UAT) and the station service/reserve transformer (SST). A failure of any one of these transformers may lead to unit shutdown or start-up unavailability. II. GENERAL LAYOUT The UT may consist of a single three-phase unit, two half-size three-phase units, or three single-phase units. This is the most evident aspect to consider when a substitute transformer is needed. When designing a new plant, the selection among these alternatives is generally based on consideration of some form of strategic reserve, as well as available space. Two half-size transformers may be selected in place of a single full-size transformer in order to reduce the cost of the spare. For similar reasons, a generator transformer may be made as a bank of single-phase units. Normally the cost, mass, and loss of such solutions are larger than for a single three-phase transformer; however, they may be preferable if transport size or weight limits apply. The three single-phase transformers provide independent magnetic circuits (see Section XI below), representing high magnetizing impedance for zero-sequence voltage components. Therefore, a delta equalizer winding is normally provided, implemented by external connection between phase units. Some layouts may pose other complications, like UAT with three-winding design. III. DIMENSIONS AND WEIGHT Any physical size and weight limitations should be checked, for example for installation on an existing foundation. Special installation space restrictions may influence the insulation clearances and terminal locations on T a) Unit generator-transformer b) Unit generator-transformer block configuration with generator breaker Fig. 1. Common generating station arrangements. UAT MV UT UT UAT SST GCB MV MV UT and UAT are connected to the generator through isolated phase bus ducts. The high/extra high voltage terminals of the UT may be connected to gas insulated switchgear. The medium voltage connections to plant auxiliaries are also normally done via rigid, non-segregated phase bus bars or cables. All these aspects must be checked and solved when looking for a transformer replacement. IV. Rated Frequency In the unlikely situation a transformer designed for a different frequency is considered, the following applies. The rated frequency radically affects the transformer design and operation. The general formula of voltage e induced by a variable flux φ in a coil with N turns is e = -N dφ/dt. Assuming a sinusoidal flux φ = Φm cos ωt, the induced voltage becomes e = ω N Φm sin ωt. Its rms value will be, in terms of core cross section A and flux density Bm [1]: E = 2π/√2 f N Φm = 4.44 f N A Bm. (1)
  • 2. According to (1), operating at 50 Hz a transformer designed for 60 Hz means that the same voltage can be achieved only by a substantial increase in the flux density. The core iron will become heavily saturated, the excitation current will rise and also the hysteresis losses (proportional to the area of the hysteresis loop), which could severely overheat and damage the laminations. A 50 Hz transformer needs roughly 12% more iron in its core than a 60 Hz unit, and also more winding turns. When operating frequency is 60 Hz in contrast to a 50 Hz design, there is too much iron in the core. The hysteresis losses will be higher than the designed value (because iron volume and increased frequency), thus decreasing the efficiency. More im-portantly, the eddy currents losses will heat up the laminations, because they tend to increase as the square of the frequency. Op-eration of a 50 Hz rated transformer at 60 Hz may be sometime possible, but it may have to be derated from its nameplate MVA rating [2], depending on the new versus rated voltage. V. AMV Rating The substitute transformer rated MVA is obviously a first pa-rameter to consider. When a new plant is designed, the UT rating is chosen to ensure that it will not represent a bottleneck of unit capability, under any possible operating condition. However, a substitute UT poses a different perspective: using a smaller MVA rating than the original one means generating unit derating, nev-ertheless it is normally preferable to a complete shut-down, tak-ing into consideration the long time needed to obtain an exact replacement. In the case of a transformer (especially UT) substitution, it is essential to pay attention to the differences among the various standards about the definition of rated power. The IEC 60076-1 [3] definition implies that rated MVA is the apparent input power, received when rated voltage is applied to the primary winding and rated current flows through the terminals of the secondary wind-ing; the output power is, in principle, the rated power minus the power consumption in the transformer (active and reactive losses). Differently, by the North America conventions (IEEE C57.12.80 [4]), the rated MVA is the output power that can be delivered at rated secondary voltage. If the transformer nameplate mentions a certain rated power and if it was designed in conformity with the American standards, the significance is that its primary (connected to the generator) would be able to receive a higher than rated power. If for instance, the UT impedance is 15%, it should be able to accept a primary MVA higher up to about 15% than the rated one, including load and mag-netizing losses (in the worst conditions of lagging power factors). Exact values can be obtained by using the equivalent circuit of the transformer. Contrarily, such intrinsic capability will not be avail-able in transformer exhibiting the same rated MVA, but designed to IEC requirements. The situation inverts under leading power factors (Mvar absorbed from the system) but this is a less likely regime, especially when a substitute transformer is involved. A transformer may be able under some limitations to carry loads in excess of nameplate rating. In the case of a substitute transformer, the expected regime is a long-time emergency load-ing that may persist for months. Both IEEE and IEC have stan-dards specially dedicated to such loading aspects (IEC 60076-7 [5], IEEE C57.91 [6]). The application of a load in excess of nameplate rating involves accelerated ageing and risk of prema-ture failure, for instance: deterioration at high temperatures of conductor insulation, other insulation parts and oil, overheating of metallic parts, increased gassing in the oil, high stresses in bush-ings, tap-changers, connections and current transformers, brittle-ness of gasket materials. In general, the larger the transformer the more vulnerable. Both above mentioned standards give similar maximum גליון 46 , אוגוסט 61 2013 temperature limits that should not be exceeded in case of long– time loading beyond the nameplate rating: current 1.3 per-unit, winding hot-spot temperature 140 ºC (instead of 120 ºC at normal loading), top-oil temperature 110-115 ºC (instead of 105 ºC at normal loading). The increased ageing rate due to a hot-spot temperature of 140 ºC is 17.2 times higher than normal for upgraded paper insulation and 128 times higher than normal for non-upgraded paper insulation [5]. VI. Rated Voltages Finding a substitute transformer with suitable primary and secondary rated voltages is a challenging task, difficult to be se-lected intuitively. Additionally, a transformer design for a certain voltage determines the size of the core and has a significant im-pact on the overall transformer size and cost. The system and transformer medium/high/extra high volt-age ratings are well standardized and correlated in ANSI C84.1 [7] and IEC 60038 [8]. However, the generators standards do not specify standard series, neither preferable values for the rated sta-tor voltage. The generator stator voltage rating is normally fixed by agreement, and in many cases it is simply the generator manu-facturer decision, according to its available design. Therefore, it is quite difficult to match between UT/UAT primary rated voltage and generator rated voltage. Section VII deals in details with transformers having rated voltages lower than expected operational voltages. Contrarily, it may be possible to use transformers with rated voltages higher than the operational ones, providing that the rated current will not be exceeded. Practically in such case the substitute transformer might be oversized and then unsuitable, because of larger core size and longer insulation distances. Ideally, it is desirable for a generator to be able to absorb Mvar to its limit when the system voltage is at its highest expected level and to produce Mvar to its limit, when the system voltage is at its lowest expected level. This is seldom possible for a fixed tap setting in the UT, and thus a compromise may have to be made by selecting the appropriate tap rating to meet the most likely op-erating condition. It is important to note that the reactive power consumed by the UT will absorb a significant part of the generator Mvar output under most conditions. IEEE C57.116 [9] recommends selecting the main parameters of UT (rated voltages, rated MVA, impedance, and over-excita-tion) by portraying graphically their effect under various opera-tion conditions. While this method is mainly dedicated to a new plant project, it may be also used in case of a substitute transform-er. A typical graph (Fig. 2) shows the change in generator voltage with generator reactive load, for various constant transmission system voltages. The graph allows predicting the Mvar capability (both lead and lag) at any given system voltage, keeping the ±5% generator voltage limits, as required by IEEE C50.12 [10], IEEE C50.13 [11] and IEC 60034-1 [12]. The example in Fig. 2 was built on a spreadsheet using equations based on transformer phasors diagram [9]. For a potential substitute transformer, such graphs should be drawn for any available tap/ratio at anticipated MW, and analyzed in order to choose the most suitable tap voltages (according to the forecasted system voltage profile) that will pose minimum restrictions to unit operation: range of available Mvar, synchronization ability, etc. Of course, a substitute transformer may not allow a full range of loading; normally some limitations (e.g. in reactive capabilities) may be acceptable. References [13] and [14] propose other graphs, more complete but also more complex, which take in consideration additional restrictions, such as: generator maximum excitation limit, generator under-excited reactive ampere limit, UT limits (at lower than rated tap voltage), turbine MW limit, and auxiliary bus-bars (motors) voltage limits. Such graph shows the reactive power
  • 3. 3 320 330 340 350 360 370 320 330 340 350 360 370 3 60 גליון 46 , אוגוסט 2013 transferred to/from the grid (at UT high voltage side) as a function of system voltage, and forecast the area of allowable operation. This graph can be also obtained in a spreadsheet using suitable equations (Fig. 3). VII. Overvoltage Limits The purpose of this section is to show how low the substitute-transformer rated voltages may be in order to withstand the high-est expected voltages on its terminals. The standards define the maximum winding voltage based on the insulation withstand capability (in IEC 60076-3 [15] it is called the highest voltage for equipment, while in ANSI C84.1 [7] it is the maximum system voltage). According to (1), the ratio between the voltage and frequency (V/Hz) of the system to which the transformer is connected de-termines the nominal flux density at which the transformer oper-ates (assuming the number of turns at a particular tap will remain constant). Normally, the transformer is economically designed to operate at as high as possible flux density, while avoiding satura-tion of the core. System frequency is normally controlled within close limits; thus, the system voltage is the main factor respon-sible for over-fluxing (over-excitation). When the V/Hz ratios are exceeded, saturation of the magnetic core of the transformers may occur, and stray flux may be induced in non-laminated compo-nents that are not designed to carry flux. This can cause severe localized overheating in the transformer and eventual breakdown of the core assembly and/or winding insulation. As mentioned before, the IEC 60076-1 [3] definitions imply that rated voltage is applied to primary winding, and the voltage across the secondary terminals differs from rated voltage (defined in no-load condition) by the voltage drop/rise in the transformer. Contrarily, by IEEE C57.12.00 [16] the rated output is delivered at rated secondary voltage; according to IEEE definition, allowance for voltage drop has to be made in the design so that the necessary primary voltage can be applied to the transformer (at a secondary load lagging power factor of 0.80 or higher). For instance, a UT with a impedance of 15% (typical range: 13–17%) designed ac-cording to IEEE shall withstand continuously primary voltages as high as 110% of the rated value when fully loaded at a power factor of 0.80 (value calculable using the transformer equivalent circuit). Such hidden capability will not be available in the case of a transformer which follows the IEC requirements. According to IEC 60076-1 [3], a transformer shall be capable of continuous operation up to 105% voltage or V/Hz (the standard meaning is per each winding). IEC 60076-8 [17] adds that this is not meant to be systematically utilized in normal service, but should be reserved for relatively rare cases of emergency service under limited periods of time. IEEE C57.12.00 [16] defines the over-flux capability in a different way: secondary voltage and V/ Hz up to 105% of rated values when load power factor is 0.80 or higher (lagging). Taking into account the previous consider-ations, this additional requirement may result in 10-15% primary overvoltage (and over-excitation) for a fully loaded generator step-up transformer built under IEEE. Fortunately, generators are only capable of continuous operation until 5% above or 5% below their rated voltage, by [10]-[12] (i.e. V/Hz until 105% at generator base) so the above overvoltage capabilities are rarely exploited. For UAT and SST the impedance is usually smaller than for UT, they often work not fully loaded and the primary voltage will nor-mally not rise by more than a few percentage points for a second-ary increase of 5%. Another aspect related to an overvoltage condition is whether the UT and UAT will be subjected to load rejection. Sudden loss of load can subject these transformers to substantial overvoltage. If saturation occurs, substantial exciting current will flow, which may overheat the core and damage the transformer. A sudden unit unloading during a fault may be caused by the clearing of a system fault and, hence, the machine may be at the ceiling of its excitation system; the unit transformer may be excited with volt-ages exceeding 130% of normal [18], [19]. With the excitation control in service, the over-excitation will generally be reduced to safe limits in a few seconds; with the excitation control out of service, the over-excitation may be sustained and damage can oc-cur (unless dedicated V/Hz protection exists). Both IEC 60076-1 [3] and IEEE C57.12.00 [16] allow continuous operation at no load at a voltage or V/Hz up to 110% of the rated values. For the particular case of transformers connected directly to generators between UT/UAT primary rated voltage and generator rated voltage. Section VII deals in details with transformers having rated voltages lower than expected operational voltages. Contrarily, it may be possible to use transformers with rated voltages higher than the operational ones, providing that the rated current will not be exceeded. Practically in such case the substitute transformer might be oversized and then unsuitable, because of larger core size and longer insulation distances. Ideally, it is desirable for a generator to be able to absorb Mvar to its limit when the system voltage is at its highest expected level and to produce Mvar to its limit, when the system voltage is at its lowest expected level. This is seldom possible for a fixed tap setting in the UT, and thus a compromise may have to be made by selecting the appropriate tap rating to meet the most likely operating condition. It is important to note that the reactive power consumed by the UT will absorb a significant part of the generator Mvar output under most conditions. IEEE C57.116 [9] recommends selecting the main parameters of UT (rated voltages, rated MVA, impedance, and over-excitation) by portraying graphically their effect under various operation conditions. While this method is mainly dedicated to a new plant project, it may be also used in case of a substitute transformer. A typical graph (Fig. 2) shows the change in generator voltage with generator reactive load, for various constant transmission system voltages. The graph allows predicting the Mvar capability (both lead and lag) at any given system voltage, keeping the ±5% generator voltage limits, as required by IEEE C50.12 [10], IEEE C50.13 [11] and IEC 60034-1 [12]. The example in Fig. 2 was built on a spreadsheet using equations based on transformer phasors diagram [9]. For a potential substitute transformer, such graphs should be drawn for any available tap/ratio at anticipated MW, and analyzed in order to choose the most suitable tap voltages (according to the forecasted system voltage profile) that will pose minimum restrictions to unit operation: range of available Mvar, synchronization ability, etc. Of course, a substitute transformer may not allow a full range of loading; normally some limitations (e.g. in reactive capabilities) may be acceptable. References [13] and [14] propose other graphs, more complete but also more complex, which take in consideration additional restrictions, such as: generator maximum excitation limit, generator under-excited reactive ampere limit, UT limits (at lower than rated tap voltage), turbine MW limit, and auxiliary bus-bars (motors) voltage limits. Such graph shows the reactive power transferred to/from the grid (at UT high voltage side) as a function of system voltage, and forecast the area of allowable operation. This graph can be also obtained in a spreadsheet using suitable equations (Fig. 3). VII. OVERVOLTAGE LIMITS The purpose of this section is to show how low the substitute-transformer rated voltages may be in order to withstand the highest expected voltages on its terminals. The standards define the maximum winding voltage based on the insulation withstand capability (in IEC 60076-3 [15] it is called the highest voltage for equipment, while in ANSI C84.1 [7] it is the maximum system voltage). According to (1), the ratio between the voltage and frequency (V/Hz) of the system to which the transformer is connected determines the nominal flux density at which the transformer operates (assuming the number of turns at a particular tap will remain constant). Normally, the transformer is economically designed to operate at as high as possible flux density, while avoiding saturation of the core. System frequency is normally controlled within close limits; thus, the system voltage is the main factor responsible for over-fluxing 1200 1200 1100 1100 1000 1000 900 900 800 800 700 700 600 600 500 500 400 400 300 300 200 200 100 100 0 0 -100 -100 -200 -200 -300 -300 -400 -400 -500 -500 -600 -600 -700 -700 -800 -800 -900 -900 -1000 -1000 -1100 -1100 -1200 System Voltage (kV) Reactive Power Transferred to (+) or from (-) System (Mvar) Generator Overexcited Limit Generator Unity Power Factor Generator Underexcited Limit Generator Voltage 105% Generator Voltage 100% Generator Voltage 95% Motors Voltage 110% Motors Voltage 90% UT Limits UNIT OPERATION LIMITS (shaded area) 947 MVA UT Rated Power 23.13 kV UT Primary Voltage 345 kV UT Secondary Voltage 9.17% UT Impedance 1.585 kA UT Tap Current 1006 MVA Gen. Rated Power 854.9 MW Gen. Active Power 530 Mvar Gen. Overex. Limit -346 Mvar Gen. Underex. Limit 24 kV Gen. Rated Voltage 60 MVA UAT Rated Power 24 KV UAT Primary Voltage 7.07 KV UAT Secondary Voltage 7.50% UAT Impedance 42.42 MW Unit Aux. Active Load 30.71 Mvar Unit Aux. React. Load 6.6 kV Motors Rated Voltage 330 kV Syst. Volt. Lowest Limit 362 KV Syst. Volt. Highest Limit UT Ratio 22 / 399 kV (Tap 5), Generator Net Output 576 MW UT Rating 650 MVA, UT Impedance 17%, Generator Rated Voltage 22 kV System Voltages: 1.05 1.05 1.04 1.04 1.03 1.03 1.02 1.02 1.01 1.01 1.00 1.00 0.99 0.99 0.98 0.98 0.97 0.97 0.96 0.96 0.95 -100 -80 -60 -40 -20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 Generator Reactive Power Output Net Value Transferred to (+) or from (-) UT (Mvar) Generator Voltage (per-unit) 420 kV 412 kV 410 kV 408 kV 406 kV 400 kV 380 kV Fig. 2. Change in generator voltage with generator reactive load for various system voltages. Fig.3 Reactive power transferred to/from system as a function of system voltage (operation area limit). between UT/UAT primary rated voltage and generator rated voltage. Section VII deals in details with transformers having rated voltages lower than expected operational voltages. Contrarily, it may be possible to use transformers with rated voltages higher than the operational ones, providing that the rated current will not be exceeded. Practically in such case the substitute transformer might be oversized and then unsuitable, because of larger core size and longer insulation distances. Ideally, it is desirable for a generator to be able to absorb Mvar to its limit when the system voltage is at its highest expected level and to produce Mvar to its limit, when the system voltage is at its lowest expected level. This is seldom possible for a fixed tap setting in the UT, and thus a compromise may have to be made by selecting the appropriate tap rating to meet the most likely operating condition. It is important to note that the reactive power consumed by the UT will absorb a significant part of the generator Mvar output under most conditions. IEEE C57.116 [9] recommends selecting the main parameters of UT (rated voltages, rated MVA, impedance, and over-excitation) by portraying graphically their effect under various operation conditions. While this method is mainly dedicated to a new plant project, it may be also used in case of a substitute transformer. A typical graph (Fig. 2) shows the change in generator voltage with generator reactive load, for various constant transmission system voltages. The graph allows predicting the Mvar capability (both lead and lag) at any given system voltage, keeping the ±5% generator voltage limits, as required by IEEE C50.12 [10], IEEE C50.13 [11] and IEC 60034-1 [12]. The example in Fig. 2 was built on a spreadsheet using equations based on transformer phasors diagram [9]. For a potential substitute transformer, such graphs should be drawn for any available tap/ratio at anticipated MW, and analyzed in order to choose the most suitable tap voltages (according to the forecasted system voltage profile) that will pose minimum restrictions to unit operation: range of available Mvar, synchronization ability, etc. Of course, a substitute transformer may not allow a full range of loading; normally some limitations (e.g. in reactive capabilities) may be acceptable. References [13] and [14] propose other graphs, more complete but also more complex, which take in consideration additional restrictions, such as: generator maximum excitation limit, generator under-excited reactive ampere limit, UT limits (at lower than rated tap voltage), turbine MW limit, and auxiliary bus-bars (motors) voltage limits. Such graph shows the reactive power transferred to/from the grid (at UT high voltage side) as a function of system voltage, and forecast the area of allowable operation. This graph can be also obtained in a spreadsheet using suitable equations (Fig. 3). VII. OVERVOLTAGE LIMITS The purpose of this section is to show how low the substitute-transformer rated voltages may be in order to withstand the highest expected voltages on its terminals. The standards define the maximum winding voltage based on the insulation withstand capability (in IEC 60076-3 [15] it is called the highest voltage for equipment, while in ANSI C84.1 [7] it is the maximum system voltage). According to (1), the ratio between the voltage and frequency (V/Hz) of the system to which the transformer is connected determines the nominal flux density at which the transformer operates (assuming the number of turns at a particular tap will remain constant). Normally, the transformer is economically designed to operate at as high as possible flux density, while avoiding saturation of the core. System frequency is normally controlled within close limits; thus, the system voltage is the main factor responsible for over-fluxing -1200 System Voltage (kV) Reactive Power Transferred to (+) or from (-) System (Mvar) Generator Overexcited Limit Generator Unity Power Factor Generator Underexcited Limit Generator Voltage 105% Generator Voltage 100% Generator Voltage 95% Motors Voltage 110% Motors Voltage 90% UT Limits UNIT OPERATION LIMITS (shaded area) 947 MVA UT Rated Power 23.13 kV UT Primary Voltage 345 kV UT Secondary Voltage 9.17% UT Impedance 1.585 kA UT Tap Current 1006 MVA Gen. Rated Power 854.9 MW Gen. Active Power 530 Mvar Gen. Overex. Limit -346 Mvar Gen. Underex. Limit 24 kV Gen. Rated Voltage 60 MVA UAT Rated Power 24 KV UAT Primary Voltage 7.07 KV UAT Secondary Voltage 7.50% UAT Impedance 42.42 MW Unit Aux. Active Load 30.71 Mvar Unit Aux. React. Load 6.6 kV Motors Rated Voltage 330 kV Syst. Volt. Lowest Limit 362 KV Syst. Volt. Highest Limit UT Ratio 22 / 399 kV (Tap 5), Generator Net Output 576 MW UT Rating 650 MVA, UT Impedance 17%, Generator Rated Voltage 22 kV System Voltages: 0.95 -100 -80 -60 -40 -20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 Generator Reactive Power Output Net Value Transferred to (+) or from (-) UT (Mvar) Generator Voltage (per-unit) 420 kV 412 kV 410 kV 408 kV 406 kV 400 kV 380 kV Fig. 2. Change in generator voltage with generator reactive load for various system voltages. Fig.3 Reactive power transferred to/from system as a function of system voltage (operation area limit).
  • 4. גליון 46 , אוגוסט 59 2013 4 (over-excitation). When the V/Hz ratios are exceeded, saturation of the magnetic core of the transformers may occur, and stray flux may be induced in non-laminated components that are not designed to carry flux. This can cause severe localized overheating in the transformer and eventual breakdown of the core assembly and/or winding insulation. As mentioned before, the IEC 60076-1 [3] definitions imply that rated voltage is applied to primary winding, and the voltage across the secondary terminals differs from rated voltage (defined in no-load condition) by the voltage drop/rise in the transformer. Contrarily, by IEEE C57.12.00 [16] the rated output is delivered at rated secondary voltage; according to IEEE definition, allowance for voltage drop has to be made in the design so that the necessary primary voltage can be applied to the transformer (at a secondary load lagging power factor of 0.80 or higher). For instance, a UT with a impedance of 15% (typical range: 13–17%) designed according to IEEE shall withstand continuously primary voltages as high as 110% of the rated value when fully loaded at a power factor of 0.80 (value calculable using the transformer equivalent circuit). Such hidden capability will not be available in the case of a transformer which follows the IEC requirements. According to IEC 60076-1 [3], a transformer shall be capable of continuous operation up to 105% voltage or V/Hz (the standard meaning is per each winding). IEC 60076-8 [17] adds that this is not meant to be systematically utilized in normal service, but should be reserved for relatively rare cases of emergency service under limited periods of time. IEEE C57.12.00 [16] defines the over-flux capability in a different way: secondary voltage and V/Hz up to 105% of rated values when load power factor is 0.80 or higher (lagging). Taking into account the previous considerations, this additional requirement may result in 10-15% primary overvoltage (and over-excitation) for a fully loaded generator step-up transformer built under IEEE. Fortunately, generators are only capable of continuous operation until 5% above or 5% below their rated voltage, by [10]-[12] (i.e. V/Hz until 105% at generator base) so the above overvoltage capabilities are rarely exploited. For UAT and SST the impedance is usually smaller than for UT, they often work not fully loaded and the primary voltage will normally not rise by more than a few percentage points for a secondary increase of 5%. Another aspect related to an overvoltage condition is whether the UT and UAT will be subjected to load rejection. Sudden loss of load can subject these transformers to substantial overvoltage. If saturation occurs, substantial exciting current will flow, which may overheat the core and damage the transformer. A sudden unit unloading during a fault may be caused by the clearing of a system fault and, hence, the machine may be at the ceiling of its excitation system; the unit transformer may be excited with voltages exceeding 130% of normal [18], [19]. With the excitation control in service, the over-excitation will generally be reduced to safe limits in a few seconds; with the excitation control out of service, the over-excitation may be sustained and damage can occur (unless dedicated V/Hz protection exists). Both IEC 60076-1 [3] and IEEE C57.12.00 [16] allow continuous operation at no load at a voltage or V/Hz up to 110% of the rated values. For the particular case of transformers connected directly to generators in such a way that they may be subjected to load rejection (i.e. configurations without generator breaker), [3] has an additional requirement: to be able to withstand 1.4 times rated primary voltage for 5 seconds. VIII. CONNECTION ARRANGEMENT AND PHASE DISPLACEMENT Normally the high voltage system is grounded, leading the UT’s high voltage windings to be star connected, with the neutral often solidly grounded. The reason for this is mainly related to equipment insulation level and system protection requirements. The significant consequence as regards the transformer high voltage windings is the possibility to use non-uniform, cheaper insulation systems (i.e. the neutral terminal insulation is designed with a lower insulation level than assigned for the line terminals). On the other hand, it is convenient to have the low voltage windings delta connected (the delta circuit provides a path for third-order harmonics of the magnetizing currents, thus reducing the voltage waveform distortion; it also stabilizes the neutral point potential in the case it is left ungrounded). The most common connection / angular (phase) displacement used for large UTs is YNd1 [9], [14], however YNd11 is also encountered (Fig. 4). For similar reasons, commonly the UAT primary windings (connected to the generator side) are delta connected, while the secondary ones are star connected through a current-limiting resistor. The most common connections used for UAT are Dyn11 [14] or Dyn1 [9] (Fig. 5). According to IEEE C57.12.00 [16], in Yd or Dy transformers the low voltage shall lag the high voltage by 30°; the connection Yd1 for step-up transformer matches this standard, while Dy11 for step-down transformers does not; however, a standard Dy1 UAT H0 H1 H2 H3 H0 H1 H2 H3 H1 H1 H0 H0 H3 H2 H3 H2 X1 X2 X3 X1 X1 X2 X3 X2 a) YNd1 b) YNd11 Fig. 4 Most common connection/phase displacement used for UTs. X2 X1 SYSTEM SIDE GENERATOR SIDE X3 X3 H1 H2 H3 H1 H1 H2 H3 H1 GENERATOR SIDE H3 H2 H3 H2 X0 X1 X2 X3 X1 X0 X1 X2 X3 X1 X0 AUXILIARIES X2 SIDE X3 X0 X3 X2 a) Dyn11 b) Dyn1 Fig. 5 Most common connection/phase displacement used for UATs. in such a way that they may be subjected to load rejection (i.e. configurations without generator breaker), [3] has an additional requirement: to be able to withstand 1.4 times rated primary volt-age for 5 seconds. VIII. Connection Arrangement and Phase Displacement Normally the high voltage system is grounded, leading the UT’s high voltage windings to be star connected, with the neutral often solidly grounded. The reason for this is mainly related to equipment insulation level and system protection requirements. The significant consequence as regards the transformer high voltage windings is the possibility to use non-uniform, cheaper insulation systems (i.e. the neutral terminal insulation is designed with a lower insulation level than assigned for the line terminals). On the other hand, it is convenient to have the low voltage windings delta connected (the delta circuit provides a path for third-order harmonics of the magnetizing currents, thus reducing the voltage waveform distortion; it also stabilizes the neutral point potential in the case it is left ungrounded). The most common connection / angular phase) displacement used for large UTs is YNd1 [9], [14], however YNd11 is also encountered (Fig. 4). For similar reasons, commonly the UAT primary windings (connected to the generator side) are delta connected, while the secondary ones are star connected through a current-limiting resistor. The most common connections used for UAT are Dyn11 [14] or Dyn1 [9] (Fig. 5). According to IEEE C57.12.00 [16], in Yd or Dy transformers the low voltage shall lag the high voltage by 30°; the connection Yd1 for step-up transformer matches this standard, while Dy11 for step-down transformers does not; however, a standard Dy1 UAT with phase sequence externally reversed on both sides, as explained below, is equal to Dy11. The IEC standards do not have such restrictions. If the UT is YNd1 and the UAT is Dyn11, the medium voltage auxiliary system has zero-phase shift compared with the high/ extra high voltage system (Fig. 1a). During unit start-up or shut-down, the medium voltage busses fed from the UAT and SST secondary windings are briefly paralleled (by the fast transfer scheme), so both must be in phase. Additionally, the high and extra high voltage systems are always in phase so the SST must produce zero-phase displacement and therefore, usually it is a star-star as YNyn0 transformer. In same cases it will have a delta-connected tertiary winding, for the reasons mentioned above. For modern transformers, it is matter of the grid configuration and/or protection requirements whether the SST is provided with a delta tertiary or not. The connection configurations and phasor groups are drawn in Fig. 4 and 5 according to IEC 60076-1 conventions [3]. Since that standard mentions that terminal marking on the transformers follows national practice, Fig. 4 and 5 use the American practice - IEEE C57.12.70 [20]. If the original transformer should be replaced by a non-identical substitute, matching the three-phase connections and phase-angle relations may be a complicated or even an impossible task. Normally it is not possible to substitute a UT or UAT having the vector group number 11 with a vector group number 1 transformer (or the opposite); the reason was explained above: these two transformers link between two rigid phasor systems. Only in the case of a unit equipped with generator breaker (Fig. 1b), it may be possible to use a YNd11 UT instead of a YNd1 one (or contrary) assuming no rapid transfer is performed to other auxiliary bus-bars. However, such substitution will affect the secondary circuits (at least the differential protection) and changes will be required in relays settings and/or matching by intermediate transformers. It is recommended to check also any potential influence on synchronizing circuits; it is a good practice to use supervision sync-check relay with two or three phase-sensing circuits. Theoretically, it is possible to keep the original vector group while using a different group transformer. For example, an UAT with vector group 11 may be used in place of an original device with vector group 1 (or inverse), by reversing the phase sequence on both sides of the transformer. Such change is shown in Fig. 6a: as viewed from the external line connections, the Dy11 transformer became a Dy1 one. Unfortunately, the rigid isolated phase bus bars on the generator side and non-segregated bars on medium voltage side will not allow such cross-connections in most cases. The substitution may be complicated by the transformer layout terminal marking and sequence. According to IEEE C57.12.70 [20], the terminals are marked as in Fig. 7a, i.e. the H1 lead is brought out as the right-hand terminal as seen when facing the high voltage side. Other countries may use different standards; for instance, the English practice is to locate the high voltage terminals from left to right when facing that side [21]; the German DIN 42402 rule is the terminals are arranged from right to left as viewed from the low voltage side [22] (Fig. 7b). For instance, if an UAT designed according to the German standard with a vector group Dy11 is installed in place of an original UAT designed according to an American one, without any change in the external connections, it will externally appear as a Dy1 transformer (Fig. 6 b). Taking in account both vector group and terminal sequence aspects, an Yd1 American transformer is interchangeable with a European Yd11, without any external modifications. IX. Taps and Tap-Changer The original transformer may be equipped with on-load tap-changer or de-energized tap-changer. Normally a substitution for a limited period of time with a fixed turns-ratio transformer will be possible in an emergency. When choosing the most suitable tap of the substitute transformer, it is indispensable to check whether it is a full-power tapping (e.g. suitable for a current equal to the rated power divided by the tap voltage).
  • 5. 58 גליון 46 , אוגוסט 2013 By IEEE C57.12.00 [16], whenever a transformer is provided with de-energized taps, they shall be full capacity taps. Transformers with on-load tap-changer shall be capable of delivering rated MVA at the rated voltage and on all taps above rated voltage. However, for taps below the rated voltage, they shall be capable of just delivering the rated current related to the rated voltage (i.e. these taps may be of reduced MVA, unless specified otherwise). By IEC 60076-1 [3] all taps shall be full-power taps, except when specified otherwise. Almost all transformers used in power plants are at least equipped with de-energized tap-changers. Sometimes, especially in case of units equipped with generator breakers, it is difficult to ensure the unit auxiliaries suitable voltage under any operation regime. To overcome this problem, UAT with on-load tap-changer may be required. In some cases, UT or SST are equipped with on-load in place of de-energized taps to allow for large variations in transmission system voltage. X. Impedance When designing a new plant, the selection of transformer short-circuit impedance (in fact the reactance, the resistance being negligible for large transformers) is subject to conflicting demands: low enough to limit the voltage drop and to meet stability requirements, but also suitable high to set the system short circuit levels according to economic limitations of the switchgear and other connected plant. If a generator breaker is used, regulation of the UAT with the generator offline should also be considered. These aspects should be also considered for a replacement transformer. Since reactance is a result of leakage flux, low reactance is obtained by minimizing leakage flux and doing this requires a large core and an expensive transformer. Conversely, if high reactance can be tolerated, a smaller core can be provided and so a less expensive transformer. It should be noted that since the rated MVA (S) appears in the numerator of the expression for percentage impedance (z%) calculated from its ohmic value (Zohm), the value of percentage impedance tends to increase as the transformer rating increases: z% = Zohm x S / U2. (2) That means that large MVA at low impedances may require significant bulky transformers, and permissible transport limits of dimensions and weight may be reached. It is at this stage that the use of single-phase units may need to be considered. XI. Unbalance when Using Single Phase TU In addition to all the issues discussed in this paper that must be considered when selecting a substitute transformer, single-phase transformer replacement from a three-phase step-up unit introduces an additional concern: generator neutral current unbalance. Neutral current of the main generator is monitored in many power plants, in particular those with large generating units. Neutral current can be the result of a ground fault on the generator stator windings, on the circuit (isolated phase bus or cables) between the generator and UAT(s) and UT, or on the delta-connected windings of the UT or UATs. Upon exceeding certain amplitude, the generator neutral current alarms and might also trip the unit, by an overcurrent relay in the neutral circuit, or, by an overvoltage relay connected across the neutral resistor. A slightly different turns ratio and/or different impedance (resulting in different regulation) between the substituted transformer and the other two will result in voltage unbalance and thus, negative sequence voltages and currents. This condition will not lead to an increase in generator neutral current, although it introduces other problems discussed elsewhere in this paper. However, different winding capacitances to ground between the substituted and the other two transformers will result in an increase in neutral generator currents, with possible adverse impact on the protective scheme of the generator neutral. Fig. 8 shows the typical arrangement of a large generator grounded at the neutral via a single phase grounding transformer with a resistive load connected to the secondary winding, sized to reduce any fault current to about 15 to 25 Amps. The sizing of the neutral resistor is a simple calculation that can be found in any good book on generator protection or in the standard IEEE C62.92.2. It is mainly dependent on the value of the capacitance to ground of the generator as well as all other equipment connected to its stator leads. Fig. 8 shows the capacitances to ground of all windings and the isolated phase bus for each of the three phases. In the figure, the capacity to ground of the UT and UAT(s) are lumped in a single delta-connected component. Under normal conditions, all the capacitances to ground are balanced among the phases and the neutral current is very close to zero. However, if a substitute one-phase transformer is installed with different capacitance, the circuit becomes unbalanced, and the neutral current will grow. Finding the value of the unbalanced current requires solving the unbalanced circuit by any of several available methods. One such method requires the delta connection of capacitors to be replaced by its wye (star) equivalent. All series resistances and reactance are neglected. Then, Fig. 8 can be simplified to the circuit shown in Fig. 9. In the circuit, all the variables are vector quantities, with exception of Rr which is the grounding resistance referred to the primary side. Voltages are assumed balanced and generator / isolated phase bus capacitances to ground equal in each phase. Given that the capacitance reactance to ground is much higher than the series impedance of the windings/buses, these last are disregarded. Following, and using superposition, the total neutral current IN can be calculated by solving for each phase a circuit as shown in Fig. 10 (example for phase A) and then summing together. Following the calculation of the neutral unbalanced current, proper setting of the neutral protection can be done. XII. Overcurrent Considerations 5 sides, as standards do not medium compared with unit start-up from the paralleled (by in phase. systems are zero-phase as YNyn0 connected For modern configuration and/or provided with a groups are conventions marking on the 5 use the by a non-identical connections and even an substitute a UT a vector reason was between two equipped with a YNd11 no rapid However, at least the in relays transformers. It is influence on supervision circuits. original vector example, place of an reversing transformer. Such external line Dy1 one. bars on the medium voltage cases. transformer to IEEE 7a, i.e. the seen when different locate the that side [21]; the German DIN 42402 rule is the terminals are arranged from right to left as viewed from the low voltage side [22] (Fig. 7b). For instance, if an UAT designed according to the German standard with a vector group Dy11 is installed in place of an original UAT designed according to an American one, without any change in the external connections, it will externally appear as a Dy1 transformer (Fig. 6 b). Taking in account both vector group and terminal sequence aspects, an Yd1 American transformer is interchangeable with a European Yd11, without any external modifications. IX. TAPS AND TAP-CHANGER The original transformer may be equipped with on-load tap-changer or de-energized tap-changer. Normally a substitution for a limited period of time with a fixed turns-ratio transformer will be possible in an emergency. When choosing the most suitable tap of the substitute transformer, it is indispensable to check whether it is a full-power tapping (e.g. suitable for a current equal to the rated power divided by the tap voltage). By IEEE C57.12.00 [16], whenever a transformer is provided with de-energized taps, they shall be full capacity taps. Transformers with on-load tap-changer shall be capable of delivering rated MVA at the rated voltage and on all taps above rated voltage. However, for taps below the rated voltage, they shall be capable of just delivering the rated current related to the rated voltage (i.e. these taps may be of reduced MVA, unless specified otherwise). By IEC 60076-1 [3] all taps shall be full-power taps, except when specified otherwise. Almost all transformers used in power plants are at least equipped with de-energized tap-changers. Sometimes, especially in case of units equipped with generator breakers, it is difficult to ensure the unit auxiliaries suitable voltage under any operation regime. To overcome this problem, UAT with A B C A B C H1 H2 H3 1V 1U A 1W A C B C B a b c a b c X1 X2 X3 a 2W 2V 2U a c c b b a) Dy11→Dy1 b) Dy11→Dy1 By reversing the phase sequence By using a substitute transformer on both sides of the transformer with different terminals layout Fig. 6. Modifications of transformer phase displacement. H0 H1 H2 H3 1W 1V 1U 1N X0 X1 X2 X3 2W 2V 2U 2N a) American practice (IEEE C57.12.70) b) German practice (DIN 42402) Fig. 7. Transformer layout terminal marking.
  • 6. The mechanical force and the thermal short-circuit requirements described in transformer standards are normally satisfactory for UTs. However, the UAT must be designed to mechanically and thermally withstand the environment in which it operates. The standard requirements for network applications may be not be adequate for certain types of three-phase through-faults on the secondary of the UAT, because of the following: slower dc component decrement, longer short-circuit duration, possibility of higher primary voltage subsequent to breaker trip (load rejection) in block schemes [9]. Another eventuality is the fast transfer of load from UAT to SST (or vice-versa), which may lead, under certain conditions, to high-circulating currents flowing through the two transformers exceeding their mechanical design capability [9]. In general, examination of the aforementioned requires consulting with the manufacturer. XIII. Secondary Circuits When using a substitute transformer, the protection circuits may be required to be modified because the transformer’s rated power changed, and/or bushing current transformers have different turns ratio, and/or differing secondary current or burden capabilities, etc. Substitute-transformer’s bushing current transformers, with different rated secondary current, ratio or burden than those of the original one, may lead to saturation and wrong operation of the differential protection. If the turns ratio or vector group of the alternative transformer is different from the original unit, it should be taken into account regarding current transformers ratio and connections. Some differential relays (mainly numerical) can internally accommodate the phase shift of the transformer, or differences in these ratios. Other relays (mainly electromechanical) do not have this versatility, and pose difficulties or need external auxiliary current transformers. In case of transformer replacement it is important to verify adequacy of the transformer over-excitation protection. Often, GENERATOR ISOLATED PH. BUS UT & UAT GEN. SIDE C GEN C IPB N1/N2 R I N R r V CPH גליון 46 , אוגוסט 57 2013 protection and output limiting functions are provided in the generator excitation equipment, but it is a good practice to apply additionally separate V/Hz protection. The curves that define generator and transformer V/Hz limits should be coordinated to properly protect both. When the transformer rated voltage is equal to the generator rated voltage, the same V/Hz relay that is protecting the generator may be set in such a way that also protects the transformer. In some cases, however, the rated transformer voltage is lower than the rated generator voltage and common protection may not be applicable; in such a case, it is desirable to provide supplementary protection for the transformer. XIV. Additional Considerations Additional aspects that should be checked when deciding for a transformer substitution are: - Details of type and arrangement of terminals, for example connections to overhead line, isolated phase bus, or cable box or gas insulated bus bar. - Isolated phase bus ducts with accompanying strong magnetic fields may cause high circulating currents in transformer tanks and covers which may result in excessive temperatures when corrective measures are not included in the design. - Unusual voltage conditions including transient over-voltages, resonance, switching surges, etc. which may require special consideration in insulation design. - Derating due to high harmonic load current. - Unusual environmental conditions (altitude, special cooling air temperature, explosive atmosphere, etc.). - Details of auxiliary supply voltage (for fans and pumps, tap-changer, alarms, etc.). - Sound-level restrictions. - Losses level (usually not relevant in case of an emergency situation transformer substitution). V APH I A R r C C CB CA XV. Conclusions I N The large transformers used in power plants have particular characteristics and specific custom designs. Keeping in stock spare transformers identical to the critical ones in operation is an expensive strategy; however it ensures the lowest risk. The advantageousness of this policy increases in the case of multiple standardized generating units (one example of interchangeable generator transformer is detailed in [23]). Checking the suitability of a different substitute transformer is a complex task. As a first feasibility check, confirm the transformer rated frequency fits your grid, preliminarily look for an available transformer ratio close to the ratio of secondary system voltage to generator rated voltage (about ±5%), and roughly appreciate the transformer largeness, heaviness and available power. Following is a partial list of the main parameters that must be checked: - UT secondary tap voltage should not be lower than 95% of the grid’s maximum expected voltage (this value typically equals the rated system voltage). - UT primary (low) voltage should not be lower than 95% of generator rated voltage for transformers designed according to IEEE C57.12.00, and not lower than generator rated voltage for 6 cases, UT or energized taps voltage. transformer resistance subject to drop and to set the limitations generator generator should be reactance is requires a Conversely, if high provided and appears in impedance (z%) percentage transformer rating (2) may require transport is at this need to be UT paper that transformer, phase step-up generator neutral monitored in many generating units. fault on the phase bus or or on the UATs. Upon neutral current overcurrent relay in connected impedance substituted unbalance currents. This generator neutral discussed elsewhere in this paper. However, different winding capacitances to ground between the substituted and the other two transformers will result in an increase in neutral generator currents, with possible adverse impact on the protective scheme of the generator neutral. Fig. 8 shows the typical arrangement of a large generator grounded at the neutral via a single phase grounding transformer with a resistive load connected to the secondary winding, sized to reduce any fault current to about 15 to 25 Amps. The sizing of the neutral resistor is a simple calculation that can be found in any good book on generator protection or in the standard IEEE C62.92.2. It is mainly dependent on the value of the capacitance to ground of the generator as well as all other equipment connected to its stator leads. Fig. 8 shows the capacitances to ground of all windings and the isolated phase bus for each of the three phases. In the figure, the capacity to ground of the UT and UAT(s) are lumped in a single delta-connected component. Under normal conditions, all the capacitances to ground are balanced among the phases and the neutral current is very close to zero. However, if a substitute one-phase transformer is installed with different capacitance, the circuit becomes unbalanced, and the neutral current will grow. Finding the value of the unbalanced current requires solving the unbalanced circuit by any of several available methods. One such method requires the delta connection of capacitors to be replaced by its wye (star) equivalent. All series resistances and reactance are neglected. Then, Fig. 8 can be simplified to the circuit shown in Fig. 9. In the circuit, all the variables are vector quantities, with exception of Rr which is the grounding resistance referred to the primary side. Voltages are assumed balanced and generator / isolated phase bus capacitances to C LV1 C LV3 C LV2 Fig. 8 Equivalent Circuit of the generator, isolated phase bus, and the delta-connected windings of the UT and UATs. I A I B I C C A C B C C V APH V BPH Fig. 9 Simplified circuit for calculating the unbalanced neutral current. requirements described in transformer standards are normally satisfactory for UTs. However, the UAT must be designed to mechanically and thermally withstand the environment in which it operates. The standard requirements for network applications may be not be adequate for certain types of three-phase through-faults on the secondary of the UAT, because of the following: slower dc component decrement, longer short-circuit duration, possibility of higher primary voltage subsequent to breaker trip (load rejection) in block schemes [9]. Another eventuality is the fast transfer of load from UAT to SST (or vice-versa), which may lead, under certain conditions, to high-circulating currents flowing through the two transformers exceeding their mechanical design capability [9]. In general, examination of the aforementioned requires consulting with the manufacturer. XIII. SECONDARY CIRCUITS When using a substitute transformer, the protection circuits may be required to be modified because the transformer’s rated power changed, and/or bushing current transformers have different turns ratio, and/or differing secondary current or burden capabilities, etc. Substitute-transformer’s bushing current transformers, with different rated secondary current, ratio or burden than those of the original one, may lead to saturation and wrong operation of the differential protection. If the turns ratio or vector group of the alternative transformer is different from the original unit, it should be taken into account regarding current transformers ratio and connections. Some differential relays (mainly numerical) can internally accommodate the phase shift of the transformer, or differences in these ratios. Other relays (mainly electromechanical) do not have this versatility, and pose difficulties or need external auxiliary current transformers. In case of transformer replacement it is important to verify adequacy of the transformer over-excitation protection. Often, supplementary Additional for a transformer - Details example cable - Isolated magnetic transformer temperatures design. - Unusual special - Derating - Unusual cooling - Details tap-changer, - Sound-- Losses emergency The characteristics spare an expensive advantageousness multiple interchangeable Checking transformer confirm preliminarily the ratio voltage largeness, Following be checked: - UT of the equals Fig. 10 One of the three circuits to be solved for calculating the neutral unbalance current.
  • 7. 8 8 56 גליון 46 , אוגוסט 2013 transformers designed according to IEC 60076-1. - UAT primary voltage should normally match the rated generator voltage; a lower voltage (up to 95% of generator rating) may be possible only after investigation of the risk for over-excitation. - Check connection and phase displacement suitability. - Analyze MVA rating suitability. If taps below the rated voltage shall be used, check their MVA capability. - Transformer rated voltages higher than the expected operating ones mean mandatory reducing the MVA to avoid exceeding the rated current. - Check dimensions and weight suitability. - Analyze the unbalance that may be introduced when replacing a single-phase transformer from an UT made of three sing-phase transformers. - Estimate transformer short circuit impedance influences. - Confirm through fault and fast load transfer capability in case of UAT/SST replacement. - Verify the implications on secondary circuits (mainly protection and synchronizing). - Thoroughly analyze the synchronizing and loading capabilities for any available tap, under various operation conditions, using graphs as in Fig.2 or Fig.3. - In the eventuality of two units connected to the same bus, one of them having a substitute UT (with different MVA or ratio or impedance), the possible effect on generators different behavior should also be considered. XVI. References [1] M. G. Say, Alternating Current Machines, 4th edition, Wiley, 1976, pp.14, 76. [2] B. Lawrie, “How does frequency affect transformer operation”, EC&M Magazine, Dec. 1992. [3] Power Transformers – Part 1: General, IEC Standard 60076- 1, Ed. 3.0, April 2011. [4] IEEE Standard Terminology for Power and Distribution Transformers, IEEE Standard C57.12.80-2010, Dec. 2010. [5] Power Transformers – Part 7: Loading Guide for Oil- Immersed Power Transformers, IEC Standard 60076-7, First Ed., Dec. 2005. [6] IEEE Guide for Loading Mineral-Oil-Immersed Transformers and Step-Voltage Regulators, IEEE Standard C57.91-2011, March 2012. [7] American National Standard for Electric Power Systems and Equipment - Voltage Ratings (60 Hertz), ANSI Standard C84.1-2006, Dec. 2006. [8] IEC Standard Voltages, IEC Standard 60038, Ed. 6.2, July 2002. [9] IEEE Guide for Transformers Directly Connected to Generators, IEEE Standard C57.116-1989, Sep. 1994. [10] IEEE Standard for Salient-Pole 50 Hz and 60 Hz Synchronous Generators and Generator/Motors for Hydraulic Turbine Applications Rated 5 MVA and Above, IEEE Standard C50.12-2005, Feb. 2006. [11] IEEE Standard for Cylindrical-Rotor 50 Hz and 60 Hz Synchronous Generators Rated 10 MVA and Above, IEEE Standard C50.13-2005, Feb. 2006. [12] Rotating electrical machines – Part 1: Rating and performance, IEC Standard 60034-1, Ed. 12.0, Feb. 2010. [13] A. W. Goldman, “Selection of Generator Step-up Transformer Ratings”, IEEE Trans. Power Apparatus and Systems, vol. PAS-100, No. 7, pp. 3425-3431, July 1981. [14] A. W. Goldman, C. G. Pebler, Power Plant Electrical Reference Series, Vol. 2, Power Transformers, EL-5036-V2, EPRI, 1987. [15] Power transformers – Part 3: Insulation levels, dielectric tests and external clearances in air, IEC Standard 60076-3, Second Ed., March 2000. [16] IEEE Standard for General Requirements for Liquid-immersed Distribution, Power, and Regulating Transformers, IEEE Standard C57.12.00-2010, Sep. 2010. [17] Power Transformers – Application Guide, IEC Standard 60076-8, First Ed., Oct. 1997. [18] IEEE Guide Protecting Power Transformers, IEEE Standard C37.91- 2008, May 2008. [19] IEEE Guide for AC Generator Protection, IEEE Standard C37.102-2006, Feb. 2007. [20] IEEE Standard for Standard Terminal Markings and Connections for Distribution and Power Transformers, IEEE Standard C57.12.70-2011, Feb. 2012. [21] M. J. Heathcote, The J&P Transformer Book, 13th edition, Elsevier, 2007, p. 457. [22] ABB Switchgear Manual, 11th edition, Cornelsen, 2006, p. 559. [23] Modern Power Station Practice, Vol. D Electrical Systems and Equipment, British Electricity International, Pergamon Press, 1992, pp.253-257. XVII. Biographies Relu Ilie received the MS degree in electrical engineering from the Technical University of Iaşi, Romania. He is in charge of Power Plant electrical systems and equipment for the Israel Electric Corporation. Relu Ilie has 30 years of experience in generation and transmission field, mostly dedicated to electrical machines issues: design and failure analysis, maintenance and inspections, monitoring and testing, technical specifications, life extension, condition assessment, etc. (email: reluilie@iec.co.il). Isidor “Izzy” Kerszenbaum received the BSc EE from the Technion – Israel Institute of Technology, and the MS and PhD (EE) from the University of the Witwatersrand. His employment experience includes working as large electric machines design engineer for GEC in South Africa, and manager of R&D for a power distribution transformer manufacturer (ITC) in California. He also worked as protection engineer and large apparatus consultant with three different utilities. He is a past chairman of the PES Electric Machines Committee. Currently Dr. Kerszenbaum is chairman of the IEEE Working Group 10 on Online Monitoring of Large Synchronous Generators.. He is a Fellow of the IEEE. Dr. Kerszenbaum spent 2002 in the US House of Representatives as a IEEE-AAAS Science and Technology Fellow. - UT primary (low) voltage should not be lower than 95% of generator rated voltage for transformers designed according to IEEE C57.12.00, and not lower than generator rated voltage for transformers designed according to IEC 60076-1. - UAT primary voltage should normally match the rated generator voltage; a lower voltage (up to 95% of generator rating) may be possible only after investigation of the risk for over-excitation. - Check connection and phase displacement suitability. - Analyze MVA rating suitability. If taps below the rated voltage shall be used, check their MVA capability. - Transformer rated voltages higher than the expected operating ones mean mandatory reducing the MVA to avoid exceeding the rated current. - Check dimensions and weight suitability. - Analyze the unbalance that may be introduced when replacing a single-phase transformer from an UT made of three sing-phase transformers. - Estimate transformer short circuit impedance influences. - Confirm through fault and fast load transfer capability in case of UAT/SST replacement. - Verify the implications on secondary circuits (mainly protection and synchronizing). - Thoroughly analyze the synchronizing and loading capabilities for any available tap, under various operation conditions, using graphs as in Fig.2 or Fig.3. - In the eventuality of two units connected to the same bus, one of them having a substitute UT (with different MVA or ratio or impedance), the possible effect on generators different behavior should also be considered. XVI. REFERENCES [1] M. G. Say, Alternating Current Machines, 4th edition, Wiley, 1976, pp.14, 76. [2] B. Lawrie, "How does frequency affect transformer operation", EC&M Magazine, Dec. 1992. [3] Power Transformers – Part 1: General, IEC Standard 60076-1, Ed. 3.0, April 2011. [4] IEEE Standard Terminology for Power and Distribution Transformers, IEEE Standard C57.12.80-2010, Dec. 2010. [5] Power Transformers – Part 7: Loading Guide for Oil-Immersed Power Transformers, IEC Standard 60076-7, First Ed., Dec. 2005. [6] IEEE Guide for Loading Mineral-Oil-Immersed Transformers and Step- Voltage Regulators, IEEE Standard C57.91-2011, March 2012. [7] American National Standard for Electric Power Systems and Equipment - Voltage Ratings (60 Hertz), ANSI Standard C84.1-2006, Dec. 2006. [8] IEC Standard Voltages, IEC Standard 60038, Ed. 6.2, July 2002. [9] IEEE Guide for Transformers Directly Connected to Generators, IEEE Standard C57.116-1989, Sep. 1994. [10] IEEE Standard for Salient-Pole 50 Hz and 60 Hz Synchronous Generators and Generator/Motors for Hydraulic Turbine Applications Rated 5 MVA and Above, IEEE Standard C50.12-2005, Feb. 2006. [11] IEEE Standard for Cylindrical-Rotor 50 Hz and 60 Hz Synchronous Generators Rated 10 MVA and Above, IEEE Standard C50.13-2005, Feb. 2006. [12] Rotating electrical machines – Part 1: Rating and performance, IEC Standard 60034-1, Ed. 12.0, Feb. 2010. [13] A. W. Goldman, "Selection of Generator Step-up Transformer Ratings", IEEE Trans. Power Apparatus and Systems, vol. PAS-100, No. 7, pp. 3425-3431, July 1981. [14] A. W. Goldman, C. G. Pebler, Power Plant Electrical Reference Series, Vol. 2, Power Transformers, EL-5036-V2, EPRI, 1987. [15] Power transformers – Part 3: Insulation levels, dielectric tests and external clearances in air, IEC Standard 60076-3, Second Ed., March 2000. 16] IEEE Standard for General Requirements for Liquid-immersed Distribution, Power, and Regulating Transformers, IEEE Standard C57.12.00-2010, Sep. 2010. [17] Power Transformers – Application Guide, IEC Standard 60076-8, First Ed., Oct. 1997. [18] IEEE Guide for Protecting Power Transformers, IEEE Standard C37.91- 2008, May 2008. 19] IEEE Guide for AC Generator Protection, IEEE Standard C37.102- 2006, Feb. 2007. [20] IEEE Standard for Standard Terminal Markings and Connections for Distribution and Power Transformers, IEEE Standard C57.12.70-2011, Feb. 2012. [21] M. J. Heathcote, The J&P Transformer Book, 13th edition, Elsevier, 2007, p. 457. [22] ABB Switchgear Manual, 11th edition, Cornelsen, 2006, p. 559. [23] Modern Power Station Practice, Vol. D Electrical Systems and Equipment, British Electricity International, Pergamon Press, 1992, pp.253-257. XVII. BIOGRAPHIES Relu Ilie received the MS degree in electrical engineering from the Technical University of Iaşi, Romania. He is in charge of Power Plant electrical systems and equipment for the Israel Electric Corporation. Relu Ilie has 30 years of experience in generation and transmission field, mostly dedicated to electrical machines issues: design and failure analysis, maintenance and inspections, monitoring and testing, technical specifications, life extension, condition assessment, etc. (email: reluilie@iec.co.il). Isidor “Izzy” Kerszenbaum received the BSc EE from the Technion – Israel Institute of Technology, and the MS and PhD (EE) from the University of the Witwatersrand. His employment experience includes working as large electric machines design engineer for GEC in South Africa, and manager of R&D for a power distribution transformer manufacturer (ITC) in California. He also worked as protection engineer and large apparatus consultant with three different utilities. He is a past chairman of the PES Electric Machines Committee. Currently Dr. Kerszenbaum is chairman of the IEEE Working Group 10 on Online Monitoring of Large Synchronous Generators.. He is a Fellow of the IEEE. Dr. Kerszenbaum spent 2002 in the US House of Representatives as a IEEE-AAAS Science and Technology Fellow. - UT primary (low) voltage should not be lower than 95% of generator rated voltage for transformers designed according to IEEE C57.12.00, and not lower than generator rated voltage for transformers designed according to IEC 60076-1. - UAT primary voltage should normally match the rated generator voltage; a lower voltage (up to 95% of generator rating) may be possible only after investigation of the risk for over-excitation. - Check connection and phase displacement suitability. - Analyze MVA rating suitability. If taps below the rated voltage shall be used, check their MVA capability. - Transformer rated voltages higher than the expected operating ones mean mandatory reducing the MVA to avoid exceeding the rated current. - Check dimensions and weight suitability. - Analyze the unbalance that may be introduced when replacing a single-phase transformer from an UT made of three sing-phase transformers. - Estimate transformer short circuit impedance influences. - Confirm through fault and fast load transfer capability in case of UAT/SST replacement. - Verify the implications on secondary circuits (mainly protection and synchronizing). - Thoroughly analyze the synchronizing and loading capabilities for any available tap, under various operation conditions, using graphs as in Fig.2 or Fig.3. - In the eventuality of two units connected to the same bus, one of them having a substitute UT (with different MVA or ratio or impedance), the possible effect on generators different behavior should also be considered. XVI. REFERENCES [1] M. G. Say, Alternating Current Machines, 4th edition, Wiley, 1976, pp.14, 76. [2] B. Lawrie, "How does frequency affect transformer operation", EC&M Magazine, Dec. 1992. [3] Power Transformers – Part 1: General, IEC Standard 60076-1, Ed. 3.0, April 2011. [4] IEEE Standard Terminology for Power and Distribution Transformers, IEEE Standard C57.12.80-2010, Dec. 2010. [5] Power Transformers – Part 7: Loading Guide for Oil-Immersed Power Transformers, IEC Standard 60076-7, First Ed., Dec. 2005. [6] IEEE Guide for Loading Mineral-Oil-Immersed Transformers and Step- Voltage Regulators, IEEE Standard C57.91-2011, March 2012. [7] American National Standard for Electric Power Systems and Equipment - Voltage Ratings (60 Hertz), ANSI Standard C84.1-2006, Dec. 2006. [8] IEC Standard Voltages, IEC Standard 60038, Ed. 6.2, July 2002. [9] IEEE Guide for Transformers Directly Connected to Generators, IEEE Standard C57.116-1989, Sep. 1994. [10] IEEE Standard for Salient-Pole 50 Hz and 60 Hz Synchronous Generators and Generator/Motors for Hydraulic Turbine Applications Rated 5 MVA and Above, IEEE Standard C50.12-2005, Feb. 2006. [11] IEEE Standard for Cylindrical-Rotor 50 Hz and 60 Hz Synchronous Generators Rated 10 MVA and Above, IEEE Standard C50.13-2005, Feb. 2006. [12] Rotating electrical machines – Part 1: Rating and performance, IEC Standard 60034-1, Ed. 12.0, Feb. 2010. [13] A. W. Goldman, "Selection of Generator Step-up Transformer Ratings", IEEE Trans. Power Apparatus and Systems, vol. PAS-100, No. 7, pp. 3425-3431, July 1981. [14] A. W. Goldman, C. G. Pebler, Power Plant Electrical Reference Series, Vol. 2, Power Transformers, EL-5036-V2, EPRI, 1987. [15] Power transformers – Part 3: Insulation levels, dielectric tests and external clearances in air, IEC Standard 60076-3, Second Ed., March 2000. 16] IEEE Standard for General Requirements for Liquid-immersed Distribution, Power, and Regulating Transformers, IEEE Standard C57.12.00-2010, Sep. 2010. [17] Power Transformers – Application Guide, IEC Standard 60076-8, First Ed., Oct. 1997. [18] IEEE Guide for Protecting Power Transformers, IEEE Standard C37.91- 2008, May 2008. [19] IEEE Guide for AC Generator Protection, IEEE Standard C37.102- 2006, Feb. 2007. [20] IEEE Standard for Standard Terminal Markings and Connections for Distribution and Power Transformers, IEEE Standard C57.12.70-2011, Feb. 2012. [21] M. J. Heathcote, The J&P Transformer Book, 13th edition, Elsevier, 2007, p. 457. [22] ABB Switchgear Manual, 11th edition, Cornelsen, 2006, p. 559. [23] Modern Power Station Practice, Vol. D Electrical Systems and Equipment, British Electricity International, Pergamon Press, 1992, pp.253-257. XVII. BIOGRAPHIES Relu Ilie received the MS degree in electrical engineering from the Technical University of Iaşi, Romania. He is in charge of Power Plant electrical systems and equipment for the Israel Electric Corporation. Relu Ilie has 30 years of experience in generation and transmission field, mostly dedicated to electrical machines issues: design and failure analysis, maintenance and inspections, monitoring and testing, technical specifications, life extension, condition assessment, etc. (email: reluilie@iec.co.il). Isidor “Izzy” Kerszenbaum received the BSc EE from the Technion – Israel Institute of Technology, and the MS and PhD (EE) from the University of the Witwatersrand. His employment experience includes working as large electric machines design engineer for GEC in South Africa, and manager of R&D for a power distribution transformer manufacturer (ITC) in California. He also worked as protection engineer and large apparatus consultant with three different utilities. He is a past chairman of the PES Electric Machines Committee. Currently Dr. Kerszenbaum is chairman of the IEEE Working Group 10 on Online Monitoring of Large Synchronous Generators.. He is a Fellow of the IEEE. Dr. Kerszenbaum spent 2002 in the US House of Representatives as a IEEE-AAAS Science and Technology Fellow.