This document contains a Gantt chart that outlines the tasks, durations, start/finish dates, and resources for a 34-day climate change segment project. Key tasks include drafting a creative brief and concepts, presenting concepts for sign-off, production which includes taping interviews and creating communication materials, post-production work such as editing and adding animations, reviews, legal review, and web development including metrics tracking and launch. The project runs from September 18 to November 2, 2007.
No Cookies No Problem - Steve Krull, Be Found Online
Climate change video project plan
1. ID Task Name Duration Start Finish Predecessors Resource Names
1 Climate Change Segment on Investment Implications 34 days Tue 9/18/07 Fri 11/2/07
2 Concept 10 days Tue 9/18/07 Mon 10/1/07
3 Draft Creative Brief 2 days Tue 9/18/07 Wed 9/19/07 VC-Project Mgmt
4 Draft Questions and Creative Concepts 6 days Thu 9/20/07 Thu 9/27/07 3 Writer
5 Present Questions and Concepts to Lew & Sign off 1 day Mon 10/1/07 Mon 10/1/07 J. Velgot
6 Public Relations 20 days Mon 10/1/07 Fri 10/26/07
7 Task TBD Meeting with John Meyers and Stephanie Giaramita 20 days Mon 10/1/07 Fri 10/26/07 PR Team
8 Production 1 day Mon 10/15/07 Mon 10/15/07
9 Tape: Lew, Amy and Nils 1 day Mon 10/15/07 Mon 10/15/07 VC-Multimedia
10 Communication Materials 7 days Tue 10/2/07 Wed 10/10/07
11 HTML Email production 7 days Tue 10/2/07 Wed 10/10/07 5 VC-Web
12 Player Production 7 days Tue 10/2/07 Wed 10/10/07 5 VC-Multimedia
13 Web Page Banner Ad 4 days Tue 10/2/07 Fri 10/5/07 5 VC-Web
14 Post Production Work 24 days Tue 10/2/07 Fri 11/2/07
15 Start work on Animations 4 days Tue 10/2/07 Fri 10/5/07 5
16 Send out for transcripts 2 days Tue 10/16/07 Wed 10/17/07 9 VC-Multimedia
17 Review video and mark time code edits 1 day Tue 10/16/07 Tue 10/16/07 9 Writer
18 Cut together tape with slides- not complete animations (draft 1) 3 days Wed 10/17/07 Fri 10/19/07 17 VC-Multimedia
19 Lew, Amy and Nils Review (draft 1) 2 days Mon 10/22/07 Tue 10/23/07 18 J. Velgot
20 Complete Animations 1 day Wed 10/24/07 Wed 10/24/07 19 VC-Multimedia
21 Cut together edits & insert animations (Final) 1 day Thu 10/25/07 Thu 10/25/07 20 VC-Multimedia
22 Lew, Amy and Nils Review (Final) 2 days Fri 10/26/07 Mon 10/29/07 21 J. Velgot
23 Legal Review 3 days Tue 10/30/07 Thu 11/1/07 22 Legal
24 Release to Press 1 day Fri 11/2/07 Fri 11/2/07 23 PR Team
25 Web Development 20 days Tue 10/2/07 Mon 10/29/07 5
26 Identify Metrics to Captured 7 days Tue 10/2/07 Wed 10/10/07 VC-Project Mgmt
27 Load Code to page/site for metrics 10 days Thu 10/11/07 Wed 10/24/07 26 WSG
28 Launch video & banners to public sites 3 days Thu 10/25/07 Mon 10/29/07 27 VC-Multimedia
Page 1