Entrepreneurship
Lecturer: Muhammad Imran,
PMP,BE,MS Management & Engineering, Torino, Italy.
Ex. Project Manager(Telecom), Etisalat, Abu Dhabi, UAE
Quaid I Azam University,
Islamabad , Pakistan
Department of Management Sciences.
Contacts:
Email:imrantlg@hotmail.com, Linkedin: Muhammad Imran, Twitter: imrantlg, Instagram: imrantlg, FB: imrantlg@hotmail.com,
Lecture-6
Phase-2
From Paper to
the Ground
Phase-1
From Mind
to the paper
Phase-3
Sustainable
Performance
1. Idea Generation
2. Idea assessment
3. Feasibility Analysis
4. Business Model
5. Business Plan
6. Strategic Plan
1. Project Initiation
 Project Charter
2. Project Planning
 Project Management Plan
i. Integration Mgm’t Plan
ii. Scope Mgm’t Plan
iii. Schedule Mgm’t Plan
iv. Cost Mgm’t Plan
v. Quality Mgm’t Plan
vi. Resource Mgm’t Plan
vii. Communications Mgm’t Plan
viii. Risk Mgm’t Plan
ix. Procurement Mgm’t Plan
x. Stakeholder Mgm’t Plan
3. Project Execution
4. Project Monitoring & Control
5. Project Closing
1. Operations Management
2. Marketing Management
3. Business Transformation
4. Ethical issues
Project Management Methodologies
Output : Business Plan
Output : Project Management Plan & Product
Output : Objective
and/or Money
Startup business- Life cycle
Engineering
Entrepreneurship
Management &
Commercialising
Management & Idea
Translation to Product
Innovation
Novel unique
Start Up
Project
Management
Uncertainty
Project Management
Process Groups: 5
Project Management
Knowledge Areas : 10
Various Tools and techniques
1. Expert judgment
2. Data gathering
o Brainstorming
o Checklists
o Focus groups
o Interviews
3. Data analysis
o Alternatives analysis
o Cost-benefit analysis
o Earned value
analysis
o Root cause analysis
o Trend analysis
o Variance analysis
o Regression analysis
4. Decision making
o Voting
o Autocratic decision
making
o Multi-criteria decision
Analysis
5. Estimation techniques
o Analogous estimating
o Parametric estimating
o Three-point
estimating
o Bottom-up estimating
6. Interpersonal and
team skills
o Conflict management
o Facilitation
o Meeting management
7. Scheduling Techniques
o Precedence diagramming
method
o Dependency determination
and integration
o Leads and lags
o Project management
information system
8. Miscellaneous
o Problem solving
o Prototypes
o Decomposition
o Rolling wave planning
Project Integration Management
includes the processes and activities to
identify, define, combine, unify, and
coordinate the various processes and
project management activities within
the Project Management Process
Groups.
Integration Management
Integration includes characteristics of
unification, consolidation, communication, and
interrelationship. These actions should be
applied from the start of the project through
completion.
Integration
Management
Processes
Process Important Output
4.1 Develop Project Charter Project charter
4.2 Develop Project Management Project management plan
4.3 Direct and Manage Project Deliverables
4.4 Manage Project Knowledge Lessons learned register
Monitor and Control Project 1 Work performance reports
2 Change requests
4.6 Perform Integrated Change 1.Approved change requests
2 Project management plan
4.7 Close Project Final report
Elements of Project Charter
Project purpose
Measurable project
objectives and related
success criteria
High-level requirements
High-level project
description, boundaries, and
key deliverables
Overall project risk
Summary milestone schedule
Preapproved financial
resources
Key stakeholder
Project approval requirements
(i.e., what constitutes success,
who decides the project is
successful, who signs off on the
project)
Project exit criteria (i.e., what
are the conditions to be met in
order to close or to cancel the
project or phase
Name and authority of the
sponsor or other person(s)
authorizing the project charter
 Assigned project manager,
responsibility, and authority
level
4.2 DEVELOP PROJECT MANAGEMENT PLAN
The project management plan
is defined as the document that
describes how the project will
be executed, monitored,
and controlled.
Develop Project Management Plan is
the process of defining, preparing,
and coordinating all plan components
and consolidating them into an
integrated project management plan.
The key benefit of this process is the
production of a comprehensive
document that defines the basis of
all project work and how the work
will be performed.
1. Scope management plan
2. Requirements management plan
3. Schedule management plan
4. Cost management plan
5. Quality management plan
6. Resource management plan
7. Communications management plan
8. Risk management plan
9. Procurement management plan
10. Stakeholder engagement plan
11. Change management plan
12. Configuration management plan
13. Scope baseline
14. Schedule baseline
15. Cost baseline
16. Performance measurement baseline
17. Project life cycle description
18. Development approach
Elements
Of
Project
Management
Plan
poor project management.mp4
PROJECT SCOPE MANAGEMENT
No Process Important out put
5.1 Plan Scope Scope management Plan
5.2 Collect Requirements Requirement Management Plan
5.3 Define Scope Scope statement
5.4 Create WBS Work Breakdown structure
5.5 Validate Scope
5.6 Control Scope
KEY CONCEPTS FOR
PROJECT SCOPE
MANAGEMENT
In the project context, the term “scope” can
refer to:
Product scope. The features and functions
that characterize a product, service, or
result.
Project scope. The work performed to
deliver a product, service, or result with the
specified features and
functions. The term “project scope” is
sometimes viewed as including product
scope.
SCOPE MANAGEMENT PLAN
scope management plan is a component of the
project management plan that describes how the
scope will be
defined, developed, monitored, controlled, and
validated. The components of a scope
management plan include:
 Process for preparing a project scope statement;
 Process that enables the creation of the WBS
from the detailed project scope statement;
 Process that establishes how the scope baseline
will be approved and maintained; and
 Process that specifies how formal acceptance of
the completed project deliverables will be
obtained.
The scope management plan can be formal or
informal, broadly framed or highly detailed, based
on the needs of the project.
REQUIREMENTS MANAGEMENT PLAN
The requirements management plan is a component
of the project management plan that describes how
project and product requirements will be analysed,
documented, and managed.
Components of the requirements management plan
can include but are not limited to:
 How requirements activities will be planned,
tracked, and reported;
 Configuration management activities such as:
how changes will be initiated; how impacts will
be analyzed; how they will be traced, tracked, and
reported; as well as the authorization levels
required to approve these changes;
 Requirements prioritization process;
 Metrics that will be used and the rationale for
using them; and
 Traceability structure that reflects the
requirement attributes captured on the
traceability matrix.
PROTOTYPES
Prototyping is a method of obtaining early
feedback on requirements by providing a
model of the expected product before actually
building it. Examples of prototypes are small-
scale products, computer generated 2D and
3D models, mock-ups, or simulations.
Prototypes allow stakeholders to experiment
with a model of the final product rather than
being limited to discussing abstract
representations of their requirements.
Prototypes support the concept of progressive
elaboration in iterative cycles of mock-up
creation, user experimentation, feedback
generation, and prototype revision.
When enough feedback cycles have been
performed, the requirements obtained from
the prototype are sufficiently complete to
move to a design or build phase.
5.4 CREATE WBS
Create WBS is the process of subdividing project deliverables
and project work into smaller, more manageable
components. The key benefit of this process is that it provides
a framework of what has to be delivered.
 The WBS is a hierarchical decomposition of the total scope of
work to be carried out by the project team to accomplish the
project objectives and create the required deliverables.
The WBS organizes and defines the total scope of the project and
represents the work specified in the current approved project scope
statement.
Project activities and overall
management
Spot the Project Manager
DECOMPOSITION
Decomposition is a technique used for
dividing and subdividing the project scope
and project deliverables into smaller, more
manageable parts.
WBS structure may be created through
various approaches. Some of the
popular methods include
 the top-down
approach, the use of organization-
specific guidelines, and the use of WBS
templates.
 A bottom-up approach can be used
to group subcomponents.
DATA ANALYSIS
Data analysis techniques that can be used in the Control Scope process
include but are not limited to:
Variance analysis. Variance analysis is used to compare the baseline to the
actual results and determine if the variance is within the threshold amount
or if corrective or preventive action is appropriate.
Trend analysis. Trend analysis examines project performance over time to
determine if performance is improving or deteriorating.
PROJECT SCHEDULE MANAGEMENT
Project Schedule Management includes the
processes required to manage the timely
completion of the project.
No Process Important out put
6.1 Plan Schedule Management Schedule management
plan
6.2 Define Activities Activity list
Activity attributes
6.3 Sequence Activities Project Schedule NW
Diagram
6.4 Estimate Activity Durations Duration estimates
6.5 Develop Schedule Project schedule
6.6 Control Schedule Schedule Forecasts
ROLLING WAVE PLANNING
Rolling wave planning is an iterative planning technique in which
the work to be accomplished in the near term is planned in detail,
while work further in the future is planned at a higher level.
SEQUENCE ACTIVITIES: TOOLS AND TECHNIQUES
PRECEDENCE DIAGRAMMING METHOD
The precedence diagramming method (PDM) is a technique used for constructing
a schedule model in which activities are represented by nodes and are graphically
linked by one or more logical relationships to show the sequence in which
the activities are to be performed.
 Finish-to-start (FS). A logical relationship in which a successor activity cannot start until a
predecessor activity has finished. For example, installing the operating system on a PC
(successor) cannot start until the PC hardware is assembled (predecessor).
 Finish-to-finish (FF). A logical relationship in which a successor activity cannot finish until a
predecessor activity has finished. For example, writing a document (predecessor) is required
to finish before editing the document (successor) can finish.
 Start-to-start (SS). A logical relationship in which a successor activity cannot start until a
predecessor activity has started. For example, level concrete (successor) cannot begin until
pour foundation (predecessor) begins.
 Start-to-finish (SF). A logical relationship in which a successor activity cannot finish until a
predecessor activity has started. For example, a new accounts payable system (successor)
has to start before the old accounts payable system can be shut down (predecessor).
LEADS AND LAGS
A lead is the amount of time a successor activity can be advanced with
respect to a predecessor activity
A lag is the amount of time a successor activity will be delayed with
respect to a predecessor activity.
ESTIMATE ACTIVITY DURATIONS: TOOLS AND TECHNIQUES
ANALOGOUS ESTIMATING
PARAMETRIC ESTIMATING
THREE-POINT ESTIMATING
Most likely (tM).
Optimistic (tO).
Pessimistic (tP).
, the expected duration, tE,
tE = (tO + tM + tP) / 3.
BOTTOM-UP ESTIMATING
Please join
https://www.facebook.com/Young-Managers-Leaders-Entrepreneurs-302010707304150

More Related Content

Similar to Entra lecture6 PM1.pdf

Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptxFawadAfridi6
 
3 scope Management
3 scope Management 3 scope Management
3 scope Management Qussay Karam
 
Pm4 dev the_project_managment_processes
Pm4 dev the_project_managment_processesPm4 dev the_project_managment_processes
Pm4 dev the_project_managment_processesYemi Osinubi, CFA
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfHuyNguyen657394
 
The project-managment-processes
The project-managment-processesThe project-managment-processes
The project-managment-processesDavid Toyohashi
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time ManagementSabrinaScott22
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Renee Jones
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6Amit Gupta
 
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docxeugeniadean34240
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...Arlene Smith
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life CycleReema
 
Overall project management
Overall project managementOverall project management
Overall project managementDesh Kapoor
 
Project management professional (PMP)
Project management professional (PMP)Project management professional (PMP)
Project management professional (PMP)Saad Al Jabri
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_managementSAJID ALI RUK
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]OyetadeTobi
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxSabrinaScott22
 

Similar to Entra lecture6 PM1.pdf (20)

Project Management Methodologies
Project Management MethodologiesProject Management Methodologies
Project Management Methodologies
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
3 scope Management
3 scope Management 3 scope Management
3 scope Management
 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
 
Pm4 dev the_project_managment_processes
Pm4 dev the_project_managment_processesPm4 dev the_project_managment_processes
Pm4 dev the_project_managment_processes
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
 
The project-managment-processes
The project-managment-processesThe project-managment-processes
The project-managment-processes
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
 
Project Management V1
Project Management V1Project Management V1
Project Management V1
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
Overall project management
Overall project managementOverall project management
Overall project management
 
Project management professional (PMP)
Project management professional (PMP)Project management professional (PMP)
Project management professional (PMP)
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_management
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
 

Recently uploaded

ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxLigayaBacuel1
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationAadityaSharma884161
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 

Recently uploaded (20)

ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint Presentation
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 

Entra lecture6 PM1.pdf

  • 1. Entrepreneurship Lecturer: Muhammad Imran, PMP,BE,MS Management & Engineering, Torino, Italy. Ex. Project Manager(Telecom), Etisalat, Abu Dhabi, UAE Quaid I Azam University, Islamabad , Pakistan Department of Management Sciences. Contacts: Email:imrantlg@hotmail.com, Linkedin: Muhammad Imran, Twitter: imrantlg, Instagram: imrantlg, FB: imrantlg@hotmail.com, Lecture-6
  • 2. Phase-2 From Paper to the Ground Phase-1 From Mind to the paper Phase-3 Sustainable Performance 1. Idea Generation 2. Idea assessment 3. Feasibility Analysis 4. Business Model 5. Business Plan 6. Strategic Plan 1. Project Initiation  Project Charter 2. Project Planning  Project Management Plan i. Integration Mgm’t Plan ii. Scope Mgm’t Plan iii. Schedule Mgm’t Plan iv. Cost Mgm’t Plan v. Quality Mgm’t Plan vi. Resource Mgm’t Plan vii. Communications Mgm’t Plan viii. Risk Mgm’t Plan ix. Procurement Mgm’t Plan x. Stakeholder Mgm’t Plan 3. Project Execution 4. Project Monitoring & Control 5. Project Closing 1. Operations Management 2. Marketing Management 3. Business Transformation 4. Ethical issues Project Management Methodologies Output : Business Plan Output : Project Management Plan & Product Output : Objective and/or Money Startup business- Life cycle
  • 3. Engineering Entrepreneurship Management & Commercialising Management & Idea Translation to Product Innovation Novel unique Start Up Project Management Uncertainty
  • 4. Project Management Process Groups: 5 Project Management Knowledge Areas : 10
  • 5. Various Tools and techniques 1. Expert judgment 2. Data gathering o Brainstorming o Checklists o Focus groups o Interviews 3. Data analysis o Alternatives analysis o Cost-benefit analysis o Earned value analysis o Root cause analysis o Trend analysis o Variance analysis o Regression analysis 4. Decision making o Voting o Autocratic decision making o Multi-criteria decision Analysis 5. Estimation techniques o Analogous estimating o Parametric estimating o Three-point estimating o Bottom-up estimating 6. Interpersonal and team skills o Conflict management o Facilitation o Meeting management 7. Scheduling Techniques o Precedence diagramming method o Dependency determination and integration o Leads and lags o Project management information system 8. Miscellaneous o Problem solving o Prototypes o Decomposition o Rolling wave planning
  • 6. Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. Integration Management Integration includes characteristics of unification, consolidation, communication, and interrelationship. These actions should be applied from the start of the project through completion.
  • 7. Integration Management Processes Process Important Output 4.1 Develop Project Charter Project charter 4.2 Develop Project Management Project management plan 4.3 Direct and Manage Project Deliverables 4.4 Manage Project Knowledge Lessons learned register Monitor and Control Project 1 Work performance reports 2 Change requests 4.6 Perform Integrated Change 1.Approved change requests 2 Project management plan 4.7 Close Project Final report
  • 8. Elements of Project Charter Project purpose Measurable project objectives and related success criteria High-level requirements High-level project description, boundaries, and key deliverables Overall project risk Summary milestone schedule Preapproved financial resources Key stakeholder Project approval requirements (i.e., what constitutes success, who decides the project is successful, who signs off on the project) Project exit criteria (i.e., what are the conditions to be met in order to close or to cancel the project or phase Name and authority of the sponsor or other person(s) authorizing the project charter  Assigned project manager, responsibility, and authority level
  • 9. 4.2 DEVELOP PROJECT MANAGEMENT PLAN The project management plan is defined as the document that describes how the project will be executed, monitored, and controlled. Develop Project Management Plan is the process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan. The key benefit of this process is the production of a comprehensive document that defines the basis of all project work and how the work will be performed.
  • 10. 1. Scope management plan 2. Requirements management plan 3. Schedule management plan 4. Cost management plan 5. Quality management plan 6. Resource management plan 7. Communications management plan 8. Risk management plan 9. Procurement management plan 10. Stakeholder engagement plan 11. Change management plan 12. Configuration management plan 13. Scope baseline 14. Schedule baseline 15. Cost baseline 16. Performance measurement baseline 17. Project life cycle description 18. Development approach Elements Of Project Management Plan
  • 12. PROJECT SCOPE MANAGEMENT No Process Important out put 5.1 Plan Scope Scope management Plan 5.2 Collect Requirements Requirement Management Plan 5.3 Define Scope Scope statement 5.4 Create WBS Work Breakdown structure 5.5 Validate Scope 5.6 Control Scope
  • 13. KEY CONCEPTS FOR PROJECT SCOPE MANAGEMENT In the project context, the term “scope” can refer to: Product scope. The features and functions that characterize a product, service, or result. Project scope. The work performed to deliver a product, service, or result with the specified features and functions. The term “project scope” is sometimes viewed as including product scope.
  • 14. SCOPE MANAGEMENT PLAN scope management plan is a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated. The components of a scope management plan include:  Process for preparing a project scope statement;  Process that enables the creation of the WBS from the detailed project scope statement;  Process that establishes how the scope baseline will be approved and maintained; and  Process that specifies how formal acceptance of the completed project deliverables will be obtained. The scope management plan can be formal or informal, broadly framed or highly detailed, based on the needs of the project.
  • 15. REQUIREMENTS MANAGEMENT PLAN The requirements management plan is a component of the project management plan that describes how project and product requirements will be analysed, documented, and managed. Components of the requirements management plan can include but are not limited to:  How requirements activities will be planned, tracked, and reported;  Configuration management activities such as: how changes will be initiated; how impacts will be analyzed; how they will be traced, tracked, and reported; as well as the authorization levels required to approve these changes;  Requirements prioritization process;  Metrics that will be used and the rationale for using them; and  Traceability structure that reflects the requirement attributes captured on the traceability matrix.
  • 16. PROTOTYPES Prototyping is a method of obtaining early feedback on requirements by providing a model of the expected product before actually building it. Examples of prototypes are small- scale products, computer generated 2D and 3D models, mock-ups, or simulations. Prototypes allow stakeholders to experiment with a model of the final product rather than being limited to discussing abstract representations of their requirements. Prototypes support the concept of progressive elaboration in iterative cycles of mock-up creation, user experimentation, feedback generation, and prototype revision. When enough feedback cycles have been performed, the requirements obtained from the prototype are sufficiently complete to move to a design or build phase.
  • 17. 5.4 CREATE WBS Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable components. The key benefit of this process is that it provides a framework of what has to be delivered.  The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. The WBS organizes and defines the total scope of the project and represents the work specified in the current approved project scope statement.
  • 18. Project activities and overall management Spot the Project Manager
  • 19. DECOMPOSITION Decomposition is a technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts. WBS structure may be created through various approaches. Some of the popular methods include  the top-down approach, the use of organization- specific guidelines, and the use of WBS templates.  A bottom-up approach can be used to group subcomponents.
  • 20.
  • 21. DATA ANALYSIS Data analysis techniques that can be used in the Control Scope process include but are not limited to: Variance analysis. Variance analysis is used to compare the baseline to the actual results and determine if the variance is within the threshold amount or if corrective or preventive action is appropriate. Trend analysis. Trend analysis examines project performance over time to determine if performance is improving or deteriorating.
  • 22. PROJECT SCHEDULE MANAGEMENT Project Schedule Management includes the processes required to manage the timely completion of the project. No Process Important out put 6.1 Plan Schedule Management Schedule management plan 6.2 Define Activities Activity list Activity attributes 6.3 Sequence Activities Project Schedule NW Diagram 6.4 Estimate Activity Durations Duration estimates 6.5 Develop Schedule Project schedule 6.6 Control Schedule Schedule Forecasts
  • 23. ROLLING WAVE PLANNING Rolling wave planning is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level.
  • 24. SEQUENCE ACTIVITIES: TOOLS AND TECHNIQUES PRECEDENCE DIAGRAMMING METHOD The precedence diagramming method (PDM) is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
  • 25.  Finish-to-start (FS). A logical relationship in which a successor activity cannot start until a predecessor activity has finished. For example, installing the operating system on a PC (successor) cannot start until the PC hardware is assembled (predecessor).  Finish-to-finish (FF). A logical relationship in which a successor activity cannot finish until a predecessor activity has finished. For example, writing a document (predecessor) is required to finish before editing the document (successor) can finish.  Start-to-start (SS). A logical relationship in which a successor activity cannot start until a predecessor activity has started. For example, level concrete (successor) cannot begin until pour foundation (predecessor) begins.  Start-to-finish (SF). A logical relationship in which a successor activity cannot finish until a predecessor activity has started. For example, a new accounts payable system (successor) has to start before the old accounts payable system can be shut down (predecessor).
  • 26. LEADS AND LAGS A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity A lag is the amount of time a successor activity will be delayed with respect to a predecessor activity.
  • 27.
  • 28. ESTIMATE ACTIVITY DURATIONS: TOOLS AND TECHNIQUES ANALOGOUS ESTIMATING PARAMETRIC ESTIMATING THREE-POINT ESTIMATING Most likely (tM). Optimistic (tO). Pessimistic (tP). , the expected duration, tE, tE = (tO + tM + tP) / 3. BOTTOM-UP ESTIMATING