2. Areas for Project : Logistics Inward Logistics Outward Logistics TTAT Inventory Management Raw Material Finished Goods Consumables
3. Truck Turn Around Time (TTAT) Truck in factory Tare Weight Loading Gross Weight Preparation of Packing List Excise Formalities Security Check Truck Allowed to go out
4. PotentialAreas for Delay in TTAT Before Tare Weight Queue Time before Loading Waiting Time for Loading Actual Time Taken for Loading Queue Time for Gross Weight Weight Difference Excise Formalities
5. Major Areas of Delay Waiting Time for Loading Queue Time Priority given to export containers Actual Time for Loading Eye to Sky/ Eye to Wall Packing Delay due to Stacking Problem Manual Weighing of Individual Coils Material Handling Issues Excise Formalities
7. Conclusion Delay in TTAT due to Excise formalities is very high Excise formality are non controllable hence cannot be reduced Delay in TTAT due to Loading Process is significantly high Several factors in Loading Process are controllable, hence will have to reduce the time of loading related activities