MEASUREMENT OF RC
FRAMED STRUCTURE
Framed concrete structure in building consists of the
following components:
1. Columns/Stiffeners
2. Floor/Roof beams
3. Floor/Roof Slab
2
COLUMNS
■ Items to be measured:
a. Concrete to column (VRC Grade 20 –30,
etc)
b. Formwork to sides of columns
c. Reinforcement
i) Main bar
ii) Links
3
COLUMNS
■ Measurement of the items above are similar to
the principles of measurements of column
stumps.
■ For the purpose of measurement, the height of
column is taken from the upper surface of
ground beam (upper surface of column stump)
to the upper surface of the floor/roof beams
above.
4
■ Starter bar must be added at (41d) from the
column height (if the measurement was not appeared in
drawings, however, this is not common with CAD drawings
provided nowadays).
■ Link bend formula (6d) for each bend x 4
(with bend cannot less than 900 angle), 4x6d
■ Note: Stirrups will end only at beam length.
Not in intersection area which only links will
be available in that area.
5
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Vibrated reinforced concrete
Grade 25 as described:
Columns m3
0.80
0.80
3.15
6
TK
Clause F3.1 &
F3.15
2.02
2
L
W
D TK
ALWAYS ADHERE TO
THIS PRINCIPLES OF
MEASUREMENT RULE
b. Formwork
■ Formwork is measured to sides of columns.
■ Formwork to column is measured in SQUARE
METRE (F.15.1 and F.15.4 and F.10.3).
7
8
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Sawn formwork Grade C timber as described
to:
Sides of columns
0.80
3.15
4
TK
m2
Clause (F.15.1 and F.15.4 and F.10.3)
TK
10.08
10
c. Reinforcement
■ Reinforcement to columns shall be measures in m which
later be converted to kg.
■ Consisting of two(2) types:
i) Main bars ( High tensile). (F8.4)-according to elements
ii) Links (Mild steel). (F8.3)
9
10
Study
reinforceme
nt layouts
according to
your building
technology
textbooks!
11
https://www.pinterest.com/pin/372250725434898988/
12
Link/stirrup
s
Main bars (check
diameter)
Measurement of links-
do this calculation on your side
cast.
■ Length of ONE link:
4/300
less 4/25 100 (cover)
1,100
add 4/6d (24d) 144 (say 6mm)
1,244
(4/6d also acceptable in links/stirrups bends which is equivalent to
24d)
(Ahmad Abdullah;2012)
13
Number of links in columns:
■ Assuming the height of column= 3.00 m
Centre to centre of links = 150 mm c/c
No. of link = 3,000 + 1
150
= 21 nos
14
Measurement of main bar
■ The length of main bar are measured based on the height
of column together with all laps and bends.
■ Normally, there are four(4) main bars in a columns and
high tensile steel are used.
15
16
17
18
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
20mm Diameter high tensile
reinforcement as described to:
Columns
3.60
5
TK
m
C5 (at 5
location),
marks
according
to grid in
drawings
TK
3.60
Convert to kg
after finish
measuring all
20mm dia for
columns
19
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
6mm Diameter mild steel reinforcement
as described to:
Links to columns
0.80
21
TK
m
Assuming the height of column= 3.00
m
Centre to centre of links = 150 mm c/c
No. of link = 3000 + 1
150
= 21 nos
5
84.00
Convert to kg
after finish
measuring all
6mm dia for
columns
FLOOR BEAM/ROOF BEAM
Items to be measured:
a. Concrete to floor/roof beams
■ Uses Vibrated Reinforced Concrete Grade 20 etc.
■ Measurement of concrete in beams is in CUBIC METRE
(volume) in accordance to F.3.1 and F.3.14.
■ Length is measured between the columns.
20
How to measure beam
length?
21
Column
Beam
Length of beam is taken between
columns
22
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Vibrated reinforced concrete Grade 25
as described:
Upper floor/roof beams
5.00
0.45
0.45
TK
m3
Clause F3.2, F3.14
L
W
D
Take note on the
arrangement of
dimension
placement,
arrangement
differs from
columns to beams
b. Formwork
■ Formwork are required at both sides and soffit of the
beam since it is suspended.
■ F.14.1 Formwork to sides and soffit of beam is measured
in SQUARE METRE according to the following
classification:
a. Horizontal
b. Sloping not exc. 150 from horizontal
c. Sloping over 150 from horizontal
23
b. Formwork
■ F.14.3 Formwork to secondary beam shall be measured up
to the sides of main beams but NO DEDUCTION shall be
made from the formwork of the main beam where the
secondary beam intersects it.
■ F.14.4 Formwork to beam which intersect with column
shall be measured up to them on all sides. (stop at end of
columns)
24
25
https://gharpedia.com/things-check-before-
concreting-beam-slab/
26
https://www.sgmedhat.com/en/product-list/modular-
formwork-system/beam-and-slam-formwork
27
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Sawn formwork Grade C timber as described:
To sides and soffit of floor/roof
beam
5.00
0.45
TK
m2
Clause F14.1
c. Reinforcement
i) Main bar – high tensile steel
■ Top main bar
■ Bottom main bar
ii) Stirrups – mild steel
■ Measurement of main bar and stirrups in floor/roof beams
are similar to the principles of measurement of
reinforcement in ground beams.
28
MEASUREMENT OF CONCRETE
SUSPENDED SLAB
Items to be measured:
a. Concrete to suspended floor slab.
b. Formwork
i) To soffit of slab
ii) To edge of slab ( not associated to beams)
iii) To top of slab ( exc. 150 from horizontal)
c. Reinforcement
d. Expansion joint (if any)
29
Concrete to floor slab
■ Uses vibrated reinforced concrete Grade 20 etc.
■ Measured in CUBIC METRE which shall include thickening
but excludes upstands stating the thickness according to
F.2.1. (F.3.1 and F.3.9 ).
30
Concrete to upper floor
slab
■ If the slab is laid sloping, this shall be stated in the
description according to:
i) Sloping not exceeding 150 from horizontal
ii) Sloping over 150 from horizontal ( Refer F.1.7 )
■ Usually the measurement to find the area of slab is taken
ACROSS THE BEAM.
31
32
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Vibrated reinforced concrete Grade 25 as
described to:
Suspended floor slab exceeding 100
mm not exceeding 150 mm thick
25.00
10.00
0.15
TK
m3
Clause F.3.1 &
F.3.9
L
W
D
33
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Vibrated reinforced concrete Grade 25 as
described to:
Suspended floor slab exceeding 100
mm not exceeding 150 mm thick laid
sloping not exc. 150
25.00
10.00
0.15
TK
m3
Clause F.3.1 & F.3.14
Concrete to floor slab
Formwork
■ Formwork to soffit of slab is measured in SQUARE METRE and
classified as follows (F.12.1 ):
a. Horizontal
b. Sloping not exceeding 150 from horizontal
c. Sloping over 150 from horizontal.
34
Concrete to floor slab
■ Formwork to soffit of solid slab exceeding 200 mm thick
shall be measured separately in SQUARE METRE and the
thickness in stages of 100 mm ( F.12.2 ).
■ Formwork to upper sloping surfaces of slabs where more
than 150 from horizontal shall be measured in SQUARE
METRES (F.12.3 ).
35
Concrete to floor slab
Formwork to edges of slabs (not associated with
downstand beams or projecting eaves), shall be measured
in LINEAR METRE according the following categories
(F.12.5) :
■ Not exceeding 250 mm deep
■ 250 – 500 mm deep
Where exceeding 500 mm deep, the depth shall be
stated.
36
Concrete to floor slab
Formwork to ends and perimeter of openings exceeding
1.00m girth shall be measured in LINEAR METRE
according the following categories ( F.12.6):
– Not exceeding 250 mm wide
– 250 – 500 mm wide
Where exceeding 500 mm wide, the width shall be
stated.
37
Concrete to floor slab
Note:
■ F.10.9 Formwork to soffits or soffits of beams over 3.50 m
high shall be so described stating the height in further
stages of 1.50m.
■ If the soffit of floor slab exceeds 3.50m high then it is
subjected to this clause.
38
39
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Sawn formwork Grade C timber as
described to:
Soffit of suspended floor slab
exceeding 200 mm thick; exc. 3.50m
but not exc. 5.00m high
25.00
10.00
TK
m2
(Clause F.3.1, F10.9 &
F12.2)
Concrete to floor slab
Reinforcement
■ The type of reinforcement used in suspended slab are normally
high tensile bar reinforcement even though fabric
reinforcement can also be used.
■ F.8.4 Classification of bar reinforcement shall be as follows:
a. In foundation which shall include column bases (pad
foundation), ground beams, pile caps and the like.
b. In ground slab which shall include beds, roads, footpaths and
paving.
c. In suspended slab which shall include attached beams,
upstand, kerbs and lintels.
d. In walls which shall include columns.
40
Concrete to floor slab
■ Therefore based on F.8.4(c) , principally the
measurement of reinforcements in suspended slab should
be done together with the reinforcements for suspended
floor/roof beams.
■ Typical layout of reinforcement in suspended slab is as
shown in the following transparencies.
■ The most important thing to do before starting the
process of taking off is to understand the layout of the
reinforcements and if possible sketches of the layout be
made to avoid confusion due to the several layers of the
reinforcements.
41
Concrete to floor slab
■ Measurements if bar reinforcement follows the same
principles of other bar reinforcement according to:
i) Type of steel used
ii) Diameter of steel bar
42
Expansion joints
■ Expansion joint is sometimes incorporated
in the design of suspended slab for the
purpose for providing a mechanism to cater
for the expansion and compression of the
slab due to heat.
■ F.4.2 Designed joints including those
required to be a special profile or which
incorporate water stops, EXPANSION OR
COMPRESSION jointing materials which are
required in the formation of bays shall be
measured in LINEAR METRE.
43
44
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Sundries:
Expansion joint, 25mm wide in 100mm thick slab filled
with and approved non-shrinking grout and pointed on
both sides with aluminium strip 20mm x 4mm thick
including all necessary formwork and any necessary
treatment to the reinforcement
21.00
TK
m
Clause F4.3
Length
8,000
add 7,000
add 6,000
21,000
Side Cast
Concrete to floor slab
■ Particulars of the following shall be stated in the
description:
i. Any necessary formwork.
ii. Treatment of reinforcement crossing the joint.
iii. Water stop, expansion or compression jointing and
pointing materials.
45
46

More Related Content

What's hot

Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored PilesAhmed Zanaty
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Arissa Loh
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentationRahul bhatnagar
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structuresHariyali Pujara
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMSagar Shah
 
Raft foundations _design_and_analysis_with_a_practical_approach
Raft foundations _design_and_analysis_with_a_practical_approachRaft foundations _design_and_analysis_with_a_practical_approach
Raft foundations _design_and_analysis_with_a_practical_approachAlmotasem Darawish
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)Adib Ramli
 

What's hot (20)

Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored Piles
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
site report
site reportsite report
site report
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
Slipform
SlipformSlipform
Slipform
 
DESIGN OF FLAT SLABS
DESIGN OF FLAT SLABSDESIGN OF FLAT SLABS
DESIGN OF FLAT SLABS
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
 
Site possession
Site possessionSite possession
Site possession
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Morphology factors
Morphology factorsMorphology factors
Morphology factors
 
Formwork
FormworkFormwork
Formwork
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Raft foundations _design_and_analysis_with_a_practical_approach
Raft foundations _design_and_analysis_with_a_practical_approachRaft foundations _design_and_analysis_with_a_practical_approach
Raft foundations _design_and_analysis_with_a_practical_approach
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
Top down construction presentation
Top down construction presentationTop down construction presentation
Top down construction presentation
 

Similar to Reinforced Concrete Frame Structure

Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiUrsachi Răzvan
 
Flat plate slab design (10.01.03.052)
Flat plate slab design (10.01.03.052)Flat plate slab design (10.01.03.052)
Flat plate slab design (10.01.03.052)Yeasir Gerrard
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimateimaduddin91
 
Design example of a six storey building project report
Design example of a six storey building project reportDesign example of a six storey building project report
Design example of a six storey building project reportPraba Haran
 
Memo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-patternMemo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-patternS.s. Lee
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
Important Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignImportant Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignRoshni Ramakrishnan
 
Heals - structural presentation
Heals -  structural presentationHeals -  structural presentation
Heals - structural presentationTanvir Khan
 
Design-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdfDesign-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdfAsifHameed33
 
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0CSAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0CSunit Dhingra
 
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxDSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxADITYAPILLAI29
 
Design of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdfDesign of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdfmohamed abdo
 
Design Of Flat Slab
Design Of Flat Slab Design Of Flat Slab
Design Of Flat Slab Abdul Sahid
 

Similar to Reinforced Concrete Frame Structure (20)

Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
 
Stepped footing
Stepped footingStepped footing
Stepped footing
 
slabs.ppt
slabs.pptslabs.ppt
slabs.ppt
 
Flat plate slab design (10.01.03.052)
Flat plate slab design (10.01.03.052)Flat plate slab design (10.01.03.052)
Flat plate slab design (10.01.03.052)
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimate
 
Design example of a six storey building project report
Design example of a six storey building project reportDesign example of a six storey building project report
Design example of a six storey building project report
 
Rectangular tank
Rectangular tankRectangular tank
Rectangular tank
 
Memo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-patternMemo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-pattern
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
 
ppt.pptx
ppt.pptxppt.pptx
ppt.pptx
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
Important Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignImportant Technical Terms in Concrete Design
Important Technical Terms in Concrete Design
 
Heals - structural presentation
Heals -  structural presentationHeals -  structural presentation
Heals - structural presentation
 
Design-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdfDesign-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdf
 
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0CSAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
 
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxDSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
 
Design of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdfDesign of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdf
 
ACE special structures
ACE special structuresACE special structures
ACE special structures
 
Design Of Flat Slab
Design Of Flat Slab Design Of Flat Slab
Design Of Flat Slab
 
Camber design
Camber designCamber design
Camber design
 

Recently uploaded

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 

Recently uploaded (20)

Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 

Reinforced Concrete Frame Structure

  • 2. MEASUREMENT OF RC FRAMED STRUCTURE Framed concrete structure in building consists of the following components: 1. Columns/Stiffeners 2. Floor/Roof beams 3. Floor/Roof Slab 2
  • 3. COLUMNS ■ Items to be measured: a. Concrete to column (VRC Grade 20 –30, etc) b. Formwork to sides of columns c. Reinforcement i) Main bar ii) Links 3
  • 4. COLUMNS ■ Measurement of the items above are similar to the principles of measurements of column stumps. ■ For the purpose of measurement, the height of column is taken from the upper surface of ground beam (upper surface of column stump) to the upper surface of the floor/roof beams above. 4
  • 5. ■ Starter bar must be added at (41d) from the column height (if the measurement was not appeared in drawings, however, this is not common with CAD drawings provided nowadays). ■ Link bend formula (6d) for each bend x 4 (with bend cannot less than 900 angle), 4x6d ■ Note: Stirrups will end only at beam length. Not in intersection area which only links will be available in that area. 5
  • 6. Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Vibrated reinforced concrete Grade 25 as described: Columns m3 0.80 0.80 3.15 6 TK Clause F3.1 & F3.15 2.02 2 L W D TK ALWAYS ADHERE TO THIS PRINCIPLES OF MEASUREMENT RULE
  • 7. b. Formwork ■ Formwork is measured to sides of columns. ■ Formwork to column is measured in SQUARE METRE (F.15.1 and F.15.4 and F.10.3). 7
  • 8. 8 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Sawn formwork Grade C timber as described to: Sides of columns 0.80 3.15 4 TK m2 Clause (F.15.1 and F.15.4 and F.10.3) TK 10.08 10
  • 9. c. Reinforcement ■ Reinforcement to columns shall be measures in m which later be converted to kg. ■ Consisting of two(2) types: i) Main bars ( High tensile). (F8.4)-according to elements ii) Links (Mild steel). (F8.3) 9
  • 10. 10 Study reinforceme nt layouts according to your building technology textbooks!
  • 13. Measurement of links- do this calculation on your side cast. ■ Length of ONE link: 4/300 less 4/25 100 (cover) 1,100 add 4/6d (24d) 144 (say 6mm) 1,244 (4/6d also acceptable in links/stirrups bends which is equivalent to 24d) (Ahmad Abdullah;2012) 13
  • 14. Number of links in columns: ■ Assuming the height of column= 3.00 m Centre to centre of links = 150 mm c/c No. of link = 3,000 + 1 150 = 21 nos 14
  • 15. Measurement of main bar ■ The length of main bar are measured based on the height of column together with all laps and bends. ■ Normally, there are four(4) main bars in a columns and high tensile steel are used. 15
  • 16. 16
  • 17. 17
  • 18. 18 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate 20mm Diameter high tensile reinforcement as described to: Columns 3.60 5 TK m C5 (at 5 location), marks according to grid in drawings TK 3.60 Convert to kg after finish measuring all 20mm dia for columns
  • 19. 19 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate 6mm Diameter mild steel reinforcement as described to: Links to columns 0.80 21 TK m Assuming the height of column= 3.00 m Centre to centre of links = 150 mm c/c No. of link = 3000 + 1 150 = 21 nos 5 84.00 Convert to kg after finish measuring all 6mm dia for columns
  • 20. FLOOR BEAM/ROOF BEAM Items to be measured: a. Concrete to floor/roof beams ■ Uses Vibrated Reinforced Concrete Grade 20 etc. ■ Measurement of concrete in beams is in CUBIC METRE (volume) in accordance to F.3.1 and F.3.14. ■ Length is measured between the columns. 20
  • 21. How to measure beam length? 21 Column Beam Length of beam is taken between columns
  • 22. 22 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Vibrated reinforced concrete Grade 25 as described: Upper floor/roof beams 5.00 0.45 0.45 TK m3 Clause F3.2, F3.14 L W D Take note on the arrangement of dimension placement, arrangement differs from columns to beams
  • 23. b. Formwork ■ Formwork are required at both sides and soffit of the beam since it is suspended. ■ F.14.1 Formwork to sides and soffit of beam is measured in SQUARE METRE according to the following classification: a. Horizontal b. Sloping not exc. 150 from horizontal c. Sloping over 150 from horizontal 23
  • 24. b. Formwork ■ F.14.3 Formwork to secondary beam shall be measured up to the sides of main beams but NO DEDUCTION shall be made from the formwork of the main beam where the secondary beam intersects it. ■ F.14.4 Formwork to beam which intersect with column shall be measured up to them on all sides. (stop at end of columns) 24
  • 27. 27 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Sawn formwork Grade C timber as described: To sides and soffit of floor/roof beam 5.00 0.45 TK m2 Clause F14.1
  • 28. c. Reinforcement i) Main bar – high tensile steel ■ Top main bar ■ Bottom main bar ii) Stirrups – mild steel ■ Measurement of main bar and stirrups in floor/roof beams are similar to the principles of measurement of reinforcement in ground beams. 28
  • 29. MEASUREMENT OF CONCRETE SUSPENDED SLAB Items to be measured: a. Concrete to suspended floor slab. b. Formwork i) To soffit of slab ii) To edge of slab ( not associated to beams) iii) To top of slab ( exc. 150 from horizontal) c. Reinforcement d. Expansion joint (if any) 29
  • 30. Concrete to floor slab ■ Uses vibrated reinforced concrete Grade 20 etc. ■ Measured in CUBIC METRE which shall include thickening but excludes upstands stating the thickness according to F.2.1. (F.3.1 and F.3.9 ). 30
  • 31. Concrete to upper floor slab ■ If the slab is laid sloping, this shall be stated in the description according to: i) Sloping not exceeding 150 from horizontal ii) Sloping over 150 from horizontal ( Refer F.1.7 ) ■ Usually the measurement to find the area of slab is taken ACROSS THE BEAM. 31
  • 32. 32 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Vibrated reinforced concrete Grade 25 as described to: Suspended floor slab exceeding 100 mm not exceeding 150 mm thick 25.00 10.00 0.15 TK m3 Clause F.3.1 & F.3.9 L W D
  • 33. 33 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Vibrated reinforced concrete Grade 25 as described to: Suspended floor slab exceeding 100 mm not exceeding 150 mm thick laid sloping not exc. 150 25.00 10.00 0.15 TK m3 Clause F.3.1 & F.3.14
  • 34. Concrete to floor slab Formwork ■ Formwork to soffit of slab is measured in SQUARE METRE and classified as follows (F.12.1 ): a. Horizontal b. Sloping not exceeding 150 from horizontal c. Sloping over 150 from horizontal. 34
  • 35. Concrete to floor slab ■ Formwork to soffit of solid slab exceeding 200 mm thick shall be measured separately in SQUARE METRE and the thickness in stages of 100 mm ( F.12.2 ). ■ Formwork to upper sloping surfaces of slabs where more than 150 from horizontal shall be measured in SQUARE METRES (F.12.3 ). 35
  • 36. Concrete to floor slab Formwork to edges of slabs (not associated with downstand beams or projecting eaves), shall be measured in LINEAR METRE according the following categories (F.12.5) : ■ Not exceeding 250 mm deep ■ 250 – 500 mm deep Where exceeding 500 mm deep, the depth shall be stated. 36
  • 37. Concrete to floor slab Formwork to ends and perimeter of openings exceeding 1.00m girth shall be measured in LINEAR METRE according the following categories ( F.12.6): – Not exceeding 250 mm wide – 250 – 500 mm wide Where exceeding 500 mm wide, the width shall be stated. 37
  • 38. Concrete to floor slab Note: ■ F.10.9 Formwork to soffits or soffits of beams over 3.50 m high shall be so described stating the height in further stages of 1.50m. ■ If the soffit of floor slab exceeds 3.50m high then it is subjected to this clause. 38
  • 39. 39 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Sawn formwork Grade C timber as described to: Soffit of suspended floor slab exceeding 200 mm thick; exc. 3.50m but not exc. 5.00m high 25.00 10.00 TK m2 (Clause F.3.1, F10.9 & F12.2)
  • 40. Concrete to floor slab Reinforcement ■ The type of reinforcement used in suspended slab are normally high tensile bar reinforcement even though fabric reinforcement can also be used. ■ F.8.4 Classification of bar reinforcement shall be as follows: a. In foundation which shall include column bases (pad foundation), ground beams, pile caps and the like. b. In ground slab which shall include beds, roads, footpaths and paving. c. In suspended slab which shall include attached beams, upstand, kerbs and lintels. d. In walls which shall include columns. 40
  • 41. Concrete to floor slab ■ Therefore based on F.8.4(c) , principally the measurement of reinforcements in suspended slab should be done together with the reinforcements for suspended floor/roof beams. ■ Typical layout of reinforcement in suspended slab is as shown in the following transparencies. ■ The most important thing to do before starting the process of taking off is to understand the layout of the reinforcements and if possible sketches of the layout be made to avoid confusion due to the several layers of the reinforcements. 41
  • 42. Concrete to floor slab ■ Measurements if bar reinforcement follows the same principles of other bar reinforcement according to: i) Type of steel used ii) Diameter of steel bar 42
  • 43. Expansion joints ■ Expansion joint is sometimes incorporated in the design of suspended slab for the purpose for providing a mechanism to cater for the expansion and compression of the slab due to heat. ■ F.4.2 Designed joints including those required to be a special profile or which incorporate water stops, EXPANSION OR COMPRESSION jointing materials which are required in the formation of bays shall be measured in LINEAR METRE. 43
  • 44. 44 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Sundries: Expansion joint, 25mm wide in 100mm thick slab filled with and approved non-shrinking grout and pointed on both sides with aluminium strip 20mm x 4mm thick including all necessary formwork and any necessary treatment to the reinforcement 21.00 TK m Clause F4.3 Length 8,000 add 7,000 add 6,000 21,000 Side Cast
  • 45. Concrete to floor slab ■ Particulars of the following shall be stated in the description: i. Any necessary formwork. ii. Treatment of reinforcement crossing the joint. iii. Water stop, expansion or compression jointing and pointing materials. 45
  • 46. 46