SlideShare a Scribd company logo
1 of 46
Discussion
on
Reinforced Cement Concrete
Heals Developments Bangladesh
1
 Materials Required:
• MS Deformed Reinforcing Bars of
40/60 grade.
• Ordinary Portland Cement.
• Stone/Brick Chips (25 mm down
graded).
• Sylhet Sand (FM from 1.8 to 2.5).
• Coarse Sand (FM from 1.2 to 1.5).
2
 Clear Coverings:
• Footing 3”
• Grade Beam 2”
• Column
below Grade Beam 2½”
Above Grade Beam 1½”
• Beam 1½”
• Slab ¾”
• Stair 1”
• Under Ground Water Reservoir
Bottom Slab 2”
Vertical Wall 2”
Top Slab 1” 3
 Lap Lengths:
• Column 30 D
• Beam, Grade Beam, Slab35 D
(Where D is the Diameter of Rod)
4
 Equipments:
• Concrete Mixture Machine
• Vibrator with Nozzles (One 1½”
diameter and the other 2” diameter)
• Batching Box
• Slum Cone
• Cube Mold
• Water pump
5
 Items to be checked before
concreting:
A. Form Work
• Forms are cleaned and oiled.
• Horizontal and vertical level as well as
alignment.
• Spacing & size of planks and runner
(plank spacing maximum 7” c/c,
runner spacing 2’-0’ c/c)
6
• Peripheral forms are in same line and
level.
• Joints and leakages are properly
closed.
• Spacing of props is within 2’-0” to 2’-6”
c/c.
• Props are strong and properly tight.
7
B. Rebar
• Rebars are rust and straight.
• Size and spacing of rebars are as per
drawing.
• All crossing points are tightly fixed with
binding wire of 24 SWG.
• Extra tops are properly placed.
• Clear coverings and spacer blocks/
chairs are properly placed.
8
 Mix proportions:
Mix proportions which are normally
mentioned in the drawing by the
consultant must be maintained strictly
(usually mixing ratios are 1:1½:3 and
1:2:4).
9
 Admixture Mixing:
• If any leakage is found after casting of
UGWR and water meter pit then it will
be repaired by the grey cementitous
alloy.
• Before casting the same we have to mix
foam lub with cement – ½ Litre for 1
bag cement.
10
 Construction Joints:
Construction joints in grade beam,
beam or slab will not be left at the
support. It will be left at minimum shear
point of grade beam, beam or slab. Bar
schedule will be prepared before
fabrication of reinforcement. No
casting of any structural member can
be done with aggregates mixed with
foreign materials. At the same time
casting will not be allowed in any place
which is water logged.
11
 Curing for RCC Works:
1. RCC curing will be started after 24
hours of casting for normal condition.
2. If the weather is dry and hot, it may be
stared earlier.
3. The columns, walls and the footings
will be wrapped by the Hessian cloth.
12
4. The Hessian cloth will always remain
in wet condition by sprinkling water.
5. Slab top will be ponded with water
until curing period is over.
6. RCC surface will be cured for at least
21 days after casting.
13
 Materials Consumption :
 For 100 cft of RCC works (1:1½: 3),
requirement is as follows:
• Cement 22 Bags
• Sylhet Sand 21 Cft
• Medium coarse sand 21 Cft
• Stone chips/brick chips 84 Cft
14
 For 100 Cft of RCC works (1:2:4),
requirement is as follows:
• Cement 18 Bags
• Sylhet Sand 22 Cft
• Medium coarse sand 22 Cft
• Stone chips/brick chips 88 Cft
15
 For 100 Cft of RCC works (1:6:6),
requirement is as follows:
• Cement 12 Bags
• Sylhet Sand 22 Cft
• Medium coarse sand 22 Cft
• Stone chips/brick chips 90 Cft
16
 Test of construction materials:
 Slump Test :
Slump Test is a test of concrete which
determines the water cement ration in
the field. The test is performed with
slump cone. The following figure is an
illustration of the Slump Test
17
 Procedure of Slump Test :
1. Take a slump cone having top dia of
102 mm, bottom dia of 203 mm and
height of 305 mm. The base of 203 mm
dia is placed on a smooth surface.
Make the inner surface of the slump
cone clean and smooth.
2. Pour freshly prepared concrete into the
slump cone in three layers. Give at
least 25 blows for each layer with 4600
mm long and 16 mm dia plain rod.
During placing of concrete it should be
noticed that the cone is not disturbed.
18
3. Remove the cone and measure the
difference in heights between the
central tip of subsided concrete and top
level of the cone which is the slump.
19
 If the slump value is less than minimum,
then amount of water is to be
increased.
 If the slump value is more than the
maximum, then the amount of water is
to be reduced.
 Normally the water cement ratio (i. e.
w/e) is varied form 0.40 to 0.50 for RCC
slab, column etc. and above 0.60 for
pile casting.
20
 Cube Test:
1. Mould Assembly:
a) Separate mould assembly and clean
all interior face, base with scraper to
remove rust / cement coating.
b) Assemble cube moulds checking every
dimension with 15cm long MS flat bar.
c) Oil the interior surface of the mould
with mold releasing oil to prevent
adhesion of concrete. Don’t use
excess oil. 21
2. Sample Collection:
a) Sample should be the true
representative of concrete being used.
b) For site mixing, mixing time should be
at least one minute or 20 revolution of
the mixer from adding all aggregates
to obtain a homogeneous mix. For
ready mix concrete, before collecting
concrete it should be mixed properly
in the mixer truck.
22
c) Sample collecting pan should be
near, clean and free from any loose
material. Collecting pan may be slightly
moist with water but staking of water
should be avoided.
d) At least one set (3cubes) sample
should be taken from the same batch /
mix.
23
3. Making Cubes:
a) Remix the sample thoroughly with
sampling scoop and trowel.
b) After remixing immediately fill the
mould in layers approximately 5 cm
deep (total 3 layers).
C) Each layer should be compacted with
the tamping each layer vibrate the
mould using rubber / wooden hammer
to remove air voids from concrete.
24
d) After Compacting the top layer, top
surface of the concrete shall be
finished level with the top of the mould,
using a trowel.
e) Store the cube moulds in a place
which is free from vibration and cover
the surface of the concrete with a piece
of damp sacking for initial 16 to 24
hours.
25
4. Striping Moulds and Curing of
Cubes:
a) After 24 hours of casting cubes,
remove cubes from moulds. For ready
mix concrete some times it may take
more than 24 hours to harden the
concrete in that case wait until
concrete gains sufficient hardness.
26
b) After removing from mould mark
casting date and name of structure for
which concrete being used on the
cubes with a permanent marker.
Submerge cubes under clean water
for curing.
27
5. Sending Cubes for Testing:
a) After 28 days take out cubes from
curing tank.
b) Send to laboratory / testing Authority
for test.
c) During transportation care should be
taken to avoid any damage (broken
edge) of cubes.
28
Expansion Joint has not done in Parapet at East Wall as per specification.
Picture as follows:
Expansion Joint has not done in Parapet at East Wall as per specification.
Picture as follows:
29
Expansion Joint hasn’t done in Parapet Wall at Roof Top [Length= 37 Rft (approx)]. Pictures as
follows:
Expansion Joint hasn’t done in Parapet Wall at Roof Top [Length= 37 Rft (approx)]. Pictures as
follows:
30
1”to 1.5” width (Approx.) Kobla have physically done into the wall plaster surface into
the Bed room due to beam alignment has not done properly during beam casting
period. which is odd looking. But those Kobla haven’t mentioned into the drawing.
Pictures are as follows:
1”to 1.5” width (Approx.) Kobla have physically done into the wall plaster surface into
the Bed room due to beam alignment has not done properly during beam casting
period. which is odd looking. But those Kobla haven’t mentioned into the drawing.
Pictures are as follows:
31
High Window lintel Level & door lintel level hasn’t done same level of S.Bath. For this
reason Tiles top level & high window bottom level has not similar. Detail pictures are
as follows:
High Window lintel Level & door lintel level hasn’t done same level of S.Bath. For this
reason Tiles top level & high window bottom level has not similar. Detail pictures are
as follows:
32
Honey comb has found in slab and rod also visible. Details picture is as below:Honey comb has found in slab and rod also visible. Details picture is as below:
33
Stair beam casting work was not properly done in the electric pipe area. Details
picture is as below:
Stair beam casting work was not properly done in the electric pipe area. Details
picture is as below:
34
Stair beam casting is not done properly of electric pipe area. Details pictures are as below:Stair beam casting is not done properly of electric pipe area. Details pictures are as below:
35
Door side column cut for Door frame fitting which is beyond our policy. Details picture is as
below:
Door side column cut for Door frame fitting which is beyond our policy. Details picture is as
below:
36
Column has been cut for door clamp fitting. Details pictures are as below:Column has been cut for door clamp fitting. Details pictures are as below:
COLUMN RODCOLUMN RODCOLUMN RODCOLUMN ROD
37
COLUMN ROD
38
39
Column have cut unfortunately for lintel casting. Even no extra rod has given before column
casting for lintel. Details pictures are as below:
Column have cut unfortunately for lintel casting. Even no extra rod has given before column
casting for lintel. Details pictures are as below:
40
Some improper casting of beam in the electric pipe area. Picture of honeycomb and casting area
are as below:
Some improper casting of beam in the electric pipe area. Picture of honeycomb and casting area
are as below:
41
Retaining wall casting out of alignment up to 3” to 4”. Detail picture is as follows:Retaining wall casting out of alignment up to 3” to 4”. Detail picture is as follows:
42
They didn’t keep MS Rod for veranda railing. Detail picture is as follows:They didn’t keep MS Rod for veranda railing. Detail picture is as follows:
43
COLUMN ROD HAS EXPOSED AT MACHINE ROOM TOP.COLUMN ROD HAS EXPOSED AT MACHINE ROOM TOP.
44
45
16 mm Rod (8” Length) has found on Parapet Wall at Roof Top. Picture as follows:16 mm Rod (8” Length) has found on Parapet Wall at Roof Top. Picture as follows:
46

More Related Content

What's hot

Building construction
Building constructionBuilding construction
Building constructionnhmurad
 
Mechanical Compaction of Concrete
Mechanical Compaction of Concrete Mechanical Compaction of Concrete
Mechanical Compaction of Concrete Abhishek Shah
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignUmer Farooq
 
1515-T_Drawings
1515-T_Drawings1515-T_Drawings
1515-T_DrawingsMark Daly
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of QuantityArissa Loh
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryAbhishek Shah
 
Concrete technology(methods of compaction)
Concrete technology(methods of compaction)Concrete technology(methods of compaction)
Concrete technology(methods of compaction)Bhargav Panchal
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their AdvantagesJay1997Singhania
 
Jointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & BlockworkJointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & BlockworkSteve Jarvis
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Chapter 4 (e) cavity walls
Chapter 4 (e) cavity wallsChapter 4 (e) cavity walls
Chapter 4 (e) cavity wallsKHUSHBU SHAH
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2Gali Suresh
 

What's hot (20)

Building construction
Building constructionBuilding construction
Building construction
 
Mechanical Compaction of Concrete
Mechanical Compaction of Concrete Mechanical Compaction of Concrete
Mechanical Compaction of Concrete
 
Form Work
Form Work Form Work
Form Work
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
1515-T_Drawings
1515-T_Drawings1515-T_Drawings
1515-T_Drawings
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
Control joints
Control jointsControl joints
Control joints
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Concrete technology(methods of compaction)
Concrete technology(methods of compaction)Concrete technology(methods of compaction)
Concrete technology(methods of compaction)
 
Formwork
FormworkFormwork
Formwork
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their Advantages
 
Jointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & BlockworkJointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & Blockwork
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Construction material in civil engineering
Construction material in civil engineeringConstruction material in civil engineering
Construction material in civil engineering
 
Chapter 4 (e) cavity walls
Chapter 4 (e) cavity wallsChapter 4 (e) cavity walls
Chapter 4 (e) cavity walls
 
FormWork
FormWork FormWork
FormWork
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 

Similar to Heals - structural presentation

Similar to Heals - structural presentation (20)

SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
 
General Specifications (Architecture)
General Specifications (Architecture)General Specifications (Architecture)
General Specifications (Architecture)
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Fresh Concrete.pdf
Fresh Concrete.pdfFresh Concrete.pdf
Fresh Concrete.pdf
 
Concrete
ConcreteConcrete
Concrete
 
Formwork
FormworkFormwork
Formwork
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil works
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitation
 
Construction & Management
Construction & ManagementConstruction & Management
Construction & Management
 
Concrete cube casting and Testing.
Concrete cube casting and Testing.Concrete cube casting and Testing.
Concrete cube casting and Testing.
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concrete
 
Production of concrete
Production of concreteProduction of concrete
Production of concrete
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixtures
 
Water tank 1
Water tank 1Water tank 1
Water tank 1
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Upload a presentation to download Space frame
Upload a presentation to download Space frameUpload a presentation to download Space frame
Upload a presentation to download Space frame
 
specifications of buildings.pptx
specifications of buildings.pptxspecifications of buildings.pptx
specifications of buildings.pptx
 
Compaction of concrete
Compaction of concreteCompaction of concrete
Compaction of concrete
 

Recently uploaded

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 

Recently uploaded (20)

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 

Heals - structural presentation

  • 2.  Materials Required: • MS Deformed Reinforcing Bars of 40/60 grade. • Ordinary Portland Cement. • Stone/Brick Chips (25 mm down graded). • Sylhet Sand (FM from 1.8 to 2.5). • Coarse Sand (FM from 1.2 to 1.5). 2
  • 3.  Clear Coverings: • Footing 3” • Grade Beam 2” • Column below Grade Beam 2½” Above Grade Beam 1½” • Beam 1½” • Slab ¾” • Stair 1” • Under Ground Water Reservoir Bottom Slab 2” Vertical Wall 2” Top Slab 1” 3
  • 4.  Lap Lengths: • Column 30 D • Beam, Grade Beam, Slab35 D (Where D is the Diameter of Rod) 4
  • 5.  Equipments: • Concrete Mixture Machine • Vibrator with Nozzles (One 1½” diameter and the other 2” diameter) • Batching Box • Slum Cone • Cube Mold • Water pump 5
  • 6.  Items to be checked before concreting: A. Form Work • Forms are cleaned and oiled. • Horizontal and vertical level as well as alignment. • Spacing & size of planks and runner (plank spacing maximum 7” c/c, runner spacing 2’-0’ c/c) 6
  • 7. • Peripheral forms are in same line and level. • Joints and leakages are properly closed. • Spacing of props is within 2’-0” to 2’-6” c/c. • Props are strong and properly tight. 7
  • 8. B. Rebar • Rebars are rust and straight. • Size and spacing of rebars are as per drawing. • All crossing points are tightly fixed with binding wire of 24 SWG. • Extra tops are properly placed. • Clear coverings and spacer blocks/ chairs are properly placed. 8
  • 9.  Mix proportions: Mix proportions which are normally mentioned in the drawing by the consultant must be maintained strictly (usually mixing ratios are 1:1½:3 and 1:2:4). 9
  • 10.  Admixture Mixing: • If any leakage is found after casting of UGWR and water meter pit then it will be repaired by the grey cementitous alloy. • Before casting the same we have to mix foam lub with cement – ½ Litre for 1 bag cement. 10
  • 11.  Construction Joints: Construction joints in grade beam, beam or slab will not be left at the support. It will be left at minimum shear point of grade beam, beam or slab. Bar schedule will be prepared before fabrication of reinforcement. No casting of any structural member can be done with aggregates mixed with foreign materials. At the same time casting will not be allowed in any place which is water logged. 11
  • 12.  Curing for RCC Works: 1. RCC curing will be started after 24 hours of casting for normal condition. 2. If the weather is dry and hot, it may be stared earlier. 3. The columns, walls and the footings will be wrapped by the Hessian cloth. 12
  • 13. 4. The Hessian cloth will always remain in wet condition by sprinkling water. 5. Slab top will be ponded with water until curing period is over. 6. RCC surface will be cured for at least 21 days after casting. 13
  • 14.  Materials Consumption :  For 100 cft of RCC works (1:1½: 3), requirement is as follows: • Cement 22 Bags • Sylhet Sand 21 Cft • Medium coarse sand 21 Cft • Stone chips/brick chips 84 Cft 14
  • 15.  For 100 Cft of RCC works (1:2:4), requirement is as follows: • Cement 18 Bags • Sylhet Sand 22 Cft • Medium coarse sand 22 Cft • Stone chips/brick chips 88 Cft 15
  • 16.  For 100 Cft of RCC works (1:6:6), requirement is as follows: • Cement 12 Bags • Sylhet Sand 22 Cft • Medium coarse sand 22 Cft • Stone chips/brick chips 90 Cft 16
  • 17.  Test of construction materials:  Slump Test : Slump Test is a test of concrete which determines the water cement ration in the field. The test is performed with slump cone. The following figure is an illustration of the Slump Test 17
  • 18.  Procedure of Slump Test : 1. Take a slump cone having top dia of 102 mm, bottom dia of 203 mm and height of 305 mm. The base of 203 mm dia is placed on a smooth surface. Make the inner surface of the slump cone clean and smooth. 2. Pour freshly prepared concrete into the slump cone in three layers. Give at least 25 blows for each layer with 4600 mm long and 16 mm dia plain rod. During placing of concrete it should be noticed that the cone is not disturbed. 18
  • 19. 3. Remove the cone and measure the difference in heights between the central tip of subsided concrete and top level of the cone which is the slump. 19
  • 20.  If the slump value is less than minimum, then amount of water is to be increased.  If the slump value is more than the maximum, then the amount of water is to be reduced.  Normally the water cement ratio (i. e. w/e) is varied form 0.40 to 0.50 for RCC slab, column etc. and above 0.60 for pile casting. 20
  • 21.  Cube Test: 1. Mould Assembly: a) Separate mould assembly and clean all interior face, base with scraper to remove rust / cement coating. b) Assemble cube moulds checking every dimension with 15cm long MS flat bar. c) Oil the interior surface of the mould with mold releasing oil to prevent adhesion of concrete. Don’t use excess oil. 21
  • 22. 2. Sample Collection: a) Sample should be the true representative of concrete being used. b) For site mixing, mixing time should be at least one minute or 20 revolution of the mixer from adding all aggregates to obtain a homogeneous mix. For ready mix concrete, before collecting concrete it should be mixed properly in the mixer truck. 22
  • 23. c) Sample collecting pan should be near, clean and free from any loose material. Collecting pan may be slightly moist with water but staking of water should be avoided. d) At least one set (3cubes) sample should be taken from the same batch / mix. 23
  • 24. 3. Making Cubes: a) Remix the sample thoroughly with sampling scoop and trowel. b) After remixing immediately fill the mould in layers approximately 5 cm deep (total 3 layers). C) Each layer should be compacted with the tamping each layer vibrate the mould using rubber / wooden hammer to remove air voids from concrete. 24
  • 25. d) After Compacting the top layer, top surface of the concrete shall be finished level with the top of the mould, using a trowel. e) Store the cube moulds in a place which is free from vibration and cover the surface of the concrete with a piece of damp sacking for initial 16 to 24 hours. 25
  • 26. 4. Striping Moulds and Curing of Cubes: a) After 24 hours of casting cubes, remove cubes from moulds. For ready mix concrete some times it may take more than 24 hours to harden the concrete in that case wait until concrete gains sufficient hardness. 26
  • 27. b) After removing from mould mark casting date and name of structure for which concrete being used on the cubes with a permanent marker. Submerge cubes under clean water for curing. 27
  • 28. 5. Sending Cubes for Testing: a) After 28 days take out cubes from curing tank. b) Send to laboratory / testing Authority for test. c) During transportation care should be taken to avoid any damage (broken edge) of cubes. 28
  • 29. Expansion Joint has not done in Parapet at East Wall as per specification. Picture as follows: Expansion Joint has not done in Parapet at East Wall as per specification. Picture as follows: 29
  • 30. Expansion Joint hasn’t done in Parapet Wall at Roof Top [Length= 37 Rft (approx)]. Pictures as follows: Expansion Joint hasn’t done in Parapet Wall at Roof Top [Length= 37 Rft (approx)]. Pictures as follows: 30
  • 31. 1”to 1.5” width (Approx.) Kobla have physically done into the wall plaster surface into the Bed room due to beam alignment has not done properly during beam casting period. which is odd looking. But those Kobla haven’t mentioned into the drawing. Pictures are as follows: 1”to 1.5” width (Approx.) Kobla have physically done into the wall plaster surface into the Bed room due to beam alignment has not done properly during beam casting period. which is odd looking. But those Kobla haven’t mentioned into the drawing. Pictures are as follows: 31
  • 32. High Window lintel Level & door lintel level hasn’t done same level of S.Bath. For this reason Tiles top level & high window bottom level has not similar. Detail pictures are as follows: High Window lintel Level & door lintel level hasn’t done same level of S.Bath. For this reason Tiles top level & high window bottom level has not similar. Detail pictures are as follows: 32
  • 33. Honey comb has found in slab and rod also visible. Details picture is as below:Honey comb has found in slab and rod also visible. Details picture is as below: 33
  • 34. Stair beam casting work was not properly done in the electric pipe area. Details picture is as below: Stair beam casting work was not properly done in the electric pipe area. Details picture is as below: 34
  • 35. Stair beam casting is not done properly of electric pipe area. Details pictures are as below:Stair beam casting is not done properly of electric pipe area. Details pictures are as below: 35
  • 36. Door side column cut for Door frame fitting which is beyond our policy. Details picture is as below: Door side column cut for Door frame fitting which is beyond our policy. Details picture is as below: 36
  • 37. Column has been cut for door clamp fitting. Details pictures are as below:Column has been cut for door clamp fitting. Details pictures are as below: COLUMN RODCOLUMN RODCOLUMN RODCOLUMN ROD 37
  • 39. 39
  • 40. Column have cut unfortunately for lintel casting. Even no extra rod has given before column casting for lintel. Details pictures are as below: Column have cut unfortunately for lintel casting. Even no extra rod has given before column casting for lintel. Details pictures are as below: 40
  • 41. Some improper casting of beam in the electric pipe area. Picture of honeycomb and casting area are as below: Some improper casting of beam in the electric pipe area. Picture of honeycomb and casting area are as below: 41
  • 42. Retaining wall casting out of alignment up to 3” to 4”. Detail picture is as follows:Retaining wall casting out of alignment up to 3” to 4”. Detail picture is as follows: 42
  • 43. They didn’t keep MS Rod for veranda railing. Detail picture is as follows:They didn’t keep MS Rod for veranda railing. Detail picture is as follows: 43
  • 44. COLUMN ROD HAS EXPOSED AT MACHINE ROOM TOP.COLUMN ROD HAS EXPOSED AT MACHINE ROOM TOP. 44
  • 45. 45
  • 46. 16 mm Rod (8” Length) has found on Parapet Wall at Roof Top. Picture as follows:16 mm Rod (8” Length) has found on Parapet Wall at Roof Top. Picture as follows: 46