SlideShare a Scribd company logo
1 of 28
Project Charter
Week2
Table of Contents
Business
Case……………………………………………………………………
……..………….………….3
Project
Charter…….…………………………………………………..………
……………………………..6
Project Name
………………………………………………………………..………
………………………..6
Project
Description……………………………………………………………
……………….….…………6
Objectives………………………………………….…………………
……..…………………………………..8
Project
Outcome……………………….………………………………………
…….…….….……………..8
Requirements……………………………………..…….……………
…………………………………….….9
Project Success
Criteria………………………………………………………………
…………………..11
Project Assumptions and
Constraints……………………………………………………………
…13
Project Milestone Timeline
chart……………………………………………………………………
.14
Stakeholder
Register………………………………………………………………
……………….………15
Project Approval
Procedure…………………………………………..…………………
……..……...16
Business Case:
(Cooperative Milk Collecting Center)
Executive Summary
Several options were considered that will help address the
objectives of the project, which are the inadequate access to the
market by the dairy farmers, the milk spoilage problem, which
has a direct impact on the quality of the milk. The project will
sell the milk on behalf of the farmers either directly to the
consumers around, but there is a percentage that will be sold
through the cooperation will be determined later. Furthermore,
the project intends to provide storage facilities that will ensure
that milk is stored properly before it is delivered or sold.
Proponent Details
(a) Several employees- the project will require or employ 15
employees who will be involved either directly or indirectly in
the activities of the project.
(b) Major shareholders- the project will have five principal
shareholders who will directly discharge their duties to manage
the project.
Benefits of the Project
The project will be committed to the local community by
employing a local workforce and providing quality milk:
The project will have several benefits once it starts operations;
they include:
Creation of job opportunities- 15 local people will be employed
to work in the project. Moreover, the project also will achieve
the provision of secure market access for the farmers' dairy
products- the project intents to collect milk from the farmers
then sell the liquid on their behalf. Finally, Profit and revenue
for shareholders- shareholders will be able to get profit, once
the milk is sold, an automatic service charge will be deducted
from the farmers’ total amount (Melton, Yates, & Iles-Smith,
2011).
Time Frame
The earlier analysis indicates that the project will take
approximately one and a half years to be implemented; this is
exactly 24 months.
1. Preparing the Project Design and contractual documents of
the project with the farmers and get all the governmental
approvals related to milk collections and distribution. Also,
make all agreements with the selling points for milk to the
customers. –approximate inquired time around four months.
2. Site mobilization and preparation for starting to implement
the project works, Approximate 3months minimum.
3. Project Works Execution and Handing Over Approximate
10months.
4. Bring equipment and all the inquired refrigerators and fixed
them in preparation for the operation; this needs about three
months.
5. Commencement of operations of equipment, milk collection,
refilling, and distribution system for sales outlets. - The
approximate timeframe inquired for two months.
6. Completion of operations and Management staff Training and
starting up full capacity production – Approximate timeframe
two months.
Cost of the Project
the facility
cost
total cost
Land Purchasing
100,000
Design and Documentation
15,000
Construction work
160,000
20 Mechanical Refrigeration or Cooling Tanks
$1500/unit
$30,000
Packing System for milk in containers
suitable for distribution.
15,000
15 employee’s payrolls
salary per year
$75,000
Other Expenses (water, Electricity, telecommunication
services& Sterilize and cleaning)
$35,000
(a) The total estimated cost of investment- the project is likely
to cost an estimated as per the following:
In summary, the overall Budget of the Project is expected to be
$430,000.
(b) Purpose of investment funds- the main agenda is to help
farmers to get quick access to the market as well as earn profit
that will sustain the project.
Servicing Requirements
Several servicing requirements by the project will include
power supply, which will be provided by the Electricity
company, the water service board will provide water, other
services may consist of telecommunication services, among
others.
Expected Return on investment
The project does not assume any return in the first two years,
and this is because the first one and half a year, the project will
not have started its operation, and then the six months after will
enable the project to stabilize. The project, however, expects
650,000 return on investment in year three and an increase in
the subsequent years.
Risk
As for now, the project appears to be straight forward.
However, several risks may face the project later as it
progresses,
Several changes that may meet the project are:
(a) Market demand- a likely fall of Market demand
(b) Land- may be scanty and not enough for the expansion of
the project
(c) supplies- low supplies due to change in seasons and climate
change
(d) Operations- may be marred with a lack of adequate funds
(John & Oliver, 2015).
Environmental Impacts
The impact of the project on the environment will be positive,
and this is because cleanliness is the first element that will be
observed by the project. The purity of both the global climate as
well as the work environment. However, in the case of the
plastics container that may be thrown around by the users after
use, the project intends to address this by regular involvement
in the cleaning process.
Project Charter
Project Name:
Cooperative Milk Collecting Center (CMCC)- Product Name:
Golden Milk
Project Description:
The project is a profit-making organization which will be
headed by the CEO who will be hired from outside to avoid
conflict of interest, and every section will be directed by
managers to be in charge of other employees. Managers will be
one of the dairy farmers because they are the ones that
understand the challenges, but they must possess management
skills. In charge of the projects with a flat organizational
structure where machine operators and other staff will be
answerable directly to the manager. There will also be the board
of directors who will be monitoring the management team to
ensure that the interest of the shareholders is cared for. The
project is targeting thousands of dairy farmers so that it may
collect enough milk for value addition and processing.
The project aims to build milk processing machines that will
process the milk collected from different farmers to add value
and packages it before selling it to retail shops and supermarket.
Through processing, which adds value, the shelf life and prices
of milk increases, and this help in profit maximization. The
project will be particularly helpful and significant to the
smallholder dairy producers because it will be collecting milk
from the before processing. Payments that dairy farmers will be
getting will help them increase their income.
Furthermore, the project will facilitate several methods that
will assist in the improvement of milk safety, especially in the
small-scale dairying; this is because most of the farmers depend
on their dairy products they get from their dairy animals to sell
and at least earn a living from this activity. This project,
therefore, will enable farmers to eradicate milk spoilage, which
is estimated at the rate of 30% of the whole milk
produced(Ortuzar et al. 2018)and will further improve the
quality of the liquid. The project is specifically aimed at
solving Milk Spoilage Problem which we have observed
happening for quite some years now. The project targets to
reduce milk spoilage to about 10%, and it will be overcome
through However, offering storage facilities for the Milk
brought by the farmers and add value through processing, which
increases the shelf life. The project will facilitate transportation
of the milk to the market on behalf of the farmer's under
product name: Golden Milk.
Objectives
The project aims to help farmers get a quick market for their
dairy products since they will be supplying their milk to the
collection center and taken their money immediately without
facing any difficulty with how they can sale it and distributed it
in the market. Where the liquid will be packed and sold by the
(CMCC) to the market under product Name Golden Milk.
Market access will be measured in terms of the quantity of milk
sold by dairy farmers in liters. Secondly, the project also aims
at eradicating milk spoilage as storage facilities that will
effectively store milk will be offered. Milk spoilage will be
measured in percentage form where milk that is contaminated
by bacteria is divided by the whole quantity of milk produced
multiplied by 100 to get the rate of spoiled milk. Finally, the
project intends to ensure the quality of the milk as several
quality tests will be going on to ascertain the various milk
components also check for bacteria, pathogens among other
vital factors that may result in milk danger. Milk quality will be
measured as a dummy variable stating whether the mill is
contaminated with bacteria or not.
Moreover, quality testing of the milk will be done at the
collection center before the milk in stores and sold to the
consumers. Quality testing will mainly focus on determining the
microbial quality, water contamination, as well as the presence
of mastitis in the herd. Quality testing will provide a platform
where the farmers will be given individual advice regarding
how they should take care of their dairy animals to ensure high
and quality yields. All shareholders in the project will be
getting dividends after every financial year. Bonus will be
calculated based on the profit made after each fiscal year.
Project Outcome
The project will offer several services, the first service the
project intends to provide is the milk storage services in there
storage areas constructed specially for this purpose, and
equipped with all cooling devices according to the appropriate
cooling temperatures to save milk for long periods for more
than 4 weeks, until they are packaged in bottles intended for
this purpose for distribution in the local market and exported to
the rest of the United States. That will ensure milk does not go
wrong. According to the research we carried out, many farmers
do not have milk storage facilities, and since milk is not
durable, as it only stays for hours and then goes terrible, so
many farmers incur lose when the milk goes wrong as they do
not have storage facilities. The project intends to provide
fridges that will assist in the storage and other milk storage
facilities. The storage facility is expected to store
approximately 50, 000 liters. It will be using cooling technology
to maintain milk temperature low. Deep freezers will also be
used as additional cooling equipment within the storage
building.
Secondly, the project also will focus on collecting the milk
from the farmers and pays them. Many farmers are not able to
get access to a quick market, and this is the main reason why
the milk spoilage rate is high, approximately 30%. Since we
have a direct link with the National Milk Corporation, we intend
to collect milk from the farmers and sell to the National Milk
Corporation immediately we get from the farmers, this will
ensure a quick market, and also the liquid won't stay for long
before getting to the market. At the same time, there are many
ideas to have our retail shops to sell our product named the
Golden Milk directly to the customers.
Requirements
There are several stakeholders' requirements for this project;
the stakeholders' demands for the project are:
Stakeholders need to support the project financially to enhance
its implementation. Some of the facilities that are required to
keep milk safe and in good quality are expensive. Therefore,
stakeholders must come in handy and help raise funds to acquire
those machines. Besides, they also need to assist in creating
awareness among the farmers. Farmers need to be informed
about these facilities that will be brought soon and how they
will help them.
Secondly, the Operations requirement- this stakeholder's
need takes into consideration the maintenance of the features of
the project. Furthermore. In this regard, the operational team
further fosters constraints, for instance, the ability activities in
the project.
The third stakeholder requirement is the customer's
stakeholder's requirement; this requirement – users, usually give
information regarding the product and services offered or
provided by the project. Lead users generally help in
contributing to the user stories as well as ideas regarding the
product and services quality as well as usability. It enables the
project to understand which area has to be improved (Eskerod &
Jepsen, 2013). Besides, they required the skill to help in the
process of the milk product so that wastages are minimized at
all costs. Also, they need the marketing skill that allows the
firm to sell its products to the final consumers.
The solution requirements include the ability to make farmers
earn the highest possible income and profit by selling the milk
directly to (CMCC) and at the same time taken a 25 %
percentage from their share as a member in CMCC to refer to
the milk quantities supplied to the Milk Collecting Center. This
is a result of reduced spoilage. The other requirement is about
enhanced consumer safety. Achievement of protection will be
realized as a result of the use of facilities that prevent the milk
from going bad quickly.
These project solution requirements include the equipment that
will be used to minimize milk spoilage while they are on transit
or storage to the final selling point. The other element is the
material used for packaging purposes to the quantities that will
be offered to the final consumer.
The project needs to uplift society and create employment.
Around the number of 15 employees will be hired to work in the
milk processing plant and thus creating jobs. Farmers will also
get the market for their milk and therefore make money, which
will raise their standards of living. On the other hand, the
project is required to lead to the development of the
neighboring areas. Other businesses are expected to come up in
the area where the cooperative will be built.
Quality requirements refer to specifications of the quality
of the products as well as services that are offered by the
project, it takes into consideration all the processes that take
place in the project as well as the entire environment
surrounding the project, including ensuring that the products
meet the required standards and keeping the high standards of
hygiene and cleanness. They are typically activities that may
result in the quality improvement of the product as well as
services. The quality requirements for this project include
customer experience- customer experience refers to activities
that may be able to contribute towards the pleasing of the
product as well as services.
Furthermore, maintainability requirements ensure that
everything works well, and things are easy to maintain (Pries &
Quigley, 2012).
Project Success Criteria:
Project success can be measured by the timeliness of the
project, such as meeting deadlines, budget utilization such as
staying within budget, and meeting requirements of the project.
The project was managed, organized, structured to meet the
goals and objectives of the plan is project success. If the
stakeholders and sponsors supported all decisions, this is
project success.
The real test of project success is the grand opening of the
CMCC on time with all team members there to support the
vision and mission of the project.
The several tangible measures of the success of this project
will be the completion of the projection within the specified
time of the two years. Every activity scheduled to be done
within this period has to be completed within this period. In
general, key factors that will determine the success of the
project include adherence to the Project Scope, Schedule as well
as customer satisfaction, among other tangible outcomes (Vida,
2012).
Various measures will indicate the success of the project. These
include an increase in the price of milk from farmers. The
cooperative will buy milk from the farmers at a reasonable
price. A survey will then be done to assess their satisfaction.
The other indicator is the reduction in loses of milk. This will
be shown by an increase in the amount of fluid supplied to the
cooperative. In addition to the equipment available in CMC
Center through which the milk is stored for long periods in a
considerable quantity, furthermore, to the milk filling system
and the quick transportation of the sale outlets for the arrival of
packaged milk to the consumer fresh daily as we are getting
other products extracted from milk such as cheese, cream, and
butter. The success criteria in this project include the
achievement of the high quality of the products when selling
them to the final consumers, obtaining the target sales in the
target market, and obtaining or achieving the producers'
satisfaction.
The other indicator of the project’s success will be through a
survey. Customers will be asked their opinion regarding the
performance of the cooperative. This will inform whether they
are satisfied with the operations being carried out. A survey
will also be done to determine the businesses that have come up
since the construction of the cooperative. This will be an
indicator of growth as a result of the project’s success.
Project Assumptions and Constraints:
Assumptions of the project refer to events that are expected to
take place during the life cycle of a project. Some of the
premises for this project are:
· Milk is the only product that will be handled by the project.
· Customers will be the local community around, and some
percentage of the milk will be supplied to the National
Creamery Corporation.
· The top management of the project will manage the project
and be responsible for ongoing operations.
· Milk Supplier deliveries will be arranged to ensure on-time
deliveries
Several constraints for this project include:
Resources- these include the various tools, equipment, as
well as material which have to be used during the project.
Resources also take into consideration the employees and
experts who will work on the project. Some of these resources
for this project will cover the refrigerators, cooling machines
for cooling milk, cleaning tools, among other devices. Other
constraints for the project are the Risk; proper preparations
should be put in place to manage any risk that is likely to arise.
Several Risks may occur during this project, and such Risks
include delays that may lead to spoilage of the milk or any
malfunctions that may lead to the interruption of the cooling
and packaging system and how to make plans to repair those
malfunctions as quickly as possible and develop alternative
solutions to avoid damage occurs to the milk. Milk is
perishable, and delays may result in spoilage hence losses. Risk
is arguably the critical project constraint.
Furthermore, Quality is another constraint for this project, since
this project requires strict quality of the milk, that the cost of
the project has to be high, in this regard. Therefore, quality
constraints usually affect the cost project constraint directly.
The provision of quality milk is thus aligned with the cost
constraints of the project (Haugan, 2016).
Project Milestone Timeline chart
· Provide investors with the necessary funding and
responsibilities for each of them.
· Preparing the project Design and contractual documents
· Site mobilization before starting work execution.
· Work execution
· Project Handing over
· Bring equipment and start the installation for refrigerators
· Commencement of operations for the computer and start-up all
systems.
· Completion of the operation phase and operation team
training.
Date
Activity
3rd October 2019
Kick-off meeting – with an investor to discuss the budget and
funds for the project.
10th October 2019 – 5 thFebruary 2020.
Preparing Design & Contractual document
10thFebruary 2020 - 9th May 2020
Site Mobilization
10thMay 2020 – 9th March 2021
Construction Work execution
10th March 2021 – 5th of May 2021
Bring equipment and start installations
6th May 2021- 7th July 2021
Commencing operations for project work& operation team
training
8thJuly 2021
Project Completion
Kick-off meeting would take place on 3rd October, the main
objective of the meeting will be to discuss all requirements of
the project, every consideration will be outlined during the
meeting including the sources of the finances as well as other
resources. Secondly, preparing a design and Contractual
document milestone is vital as essential information regarding
the geographical nature of the location where the project will be
set up will be identified. Furthermore, demographic information
will be gathered, and this information is critical for the
prosperity of the project. Thirdly, working out the plan include
all activities that will be carried out from the initial stages of
the project until completion; these activities may consist of
several constructions. Lastly, project run-up involves the last
phase of the project, and this event will include ensuring that
everything is ok before the project starts providing the required
services. By Commencement of operations of equipment, milk
collection, refilling, and distribution system for sales outlets.
Completion of activities and Management staff Training and
starting up full capacity production.
Stakeholder Register
Name
Organization
Title
Role
Internal/External
Gorge Stuard
Cooperative Milk Collecting Center (CMCC)
Head of Investors
Committee
Responsible for collecting funding for the project.
Internal
Jone Gowland
General Farmer Association
Manager for producer Division
Responsible for Supplying the milk to (CMCC)
External
Sam Smith
Texas State Government
Head of Permits for Industrial Establishment
Approved Licenses for project
External
Michel Saad
Cooperative Milk Collecting Center (CMCC)
Project Manager
Leads work Execution of the project.
Internal
Adam Abbas
General Farmer Association
Technical support Engineer
Approved all process from collecting the milk and storage it in
the refrigerators up to fill it in bottles to be ready for
distribution
External
Murad Nabiel
Cooperative Milk Collecting Center (CMCC)
Procurement Manager
Responsible for supply all equipment and prepare the system
for a start-up commissioning
Internal
Sarah Fouad
Cooperative Milk Collecting Center (CMCC)
Human Resources
Hiring employees and selecting qualified staff and withholding
training courses
Internal
Project Approval Procedure
Date
Activity
Approval
3rd October 2019
Kick-off meeting – with the investor to discuss the budget and
funds for the project.
Gorge Stuard
10th October 2019 – 5 thFebruary 2020.
Preparing Design & Contractual document
Sam Smith
10thFebruary 2020 - 9th May 2020
Site Mobilization
Michel Saad
10thMay 2020 – 9th March 2021
Construction Work execution
Michel Saad
10th March 2021 – 5th of May 2021
Bring equipment and start installations
Murad Nabiel
6th May 2021- 7th July 2021
Commencing operations for project work& operation team
training
Jone Gawland / Sara Fouad
8th July 2021
Project Completion
Michel Saad/ Jone Gowland
The project concept supported by investor committee after they
like the ideas that aimed at helping the Dairy farmers to get
easy access to the market and at the same time this investment
allows farmers benefit from proceeds of pensioner support fund,
the project concept approved by Mr. Gorge Stuard the Head of
Investors Committee. After that, the project manager Mr.
Michel Saaad begins to prepare the design drawing, including
all, inquired detailed, to execute the work with full
documentation with complete specification related to the
construction phase associated with other tasks like Electrical,
Mechanical and Plumbing works. All these documents will be
attached with the master plan for the project location and to be
submitted to the Permits for Industrial Establishment related to
the Texas State Government to get approval on it before
proceeding in to project implementation works, this will be
approved and signed by Mr. Sam Smith. Once we got the
necessary funds for the project and approval from Government
Authorities, the stage of preparing the site started with taking
all security safety measures to maintain the project staff
equipping all the tools needed by the project and developing the
temporary site offices this stage followed up and approved by
the project manager Mr. Michel said. Upon completion of this
stage, the project execution works will be started following the
time table set for this purpose and compatibility with the
investment strategy approved by Mr. Gorge Stuard, the Head of
Investor's committee. During the implementation of the project
Mr. Murad Nabil, Procurement manager ordered all the cooling
systems allocated to milk according to the design and
specifications approved previously, the arrival of the cooling
system will be on the specified time to begin installation in
cooperation with Mr. Adam Abass, the Technical Support
Engineer of the General Farmer Association. After that the next
stage to start the initial operation process of these systems to
make sure that they usually work and their ability to absorb the
necessary quantities of milk for storage and subsequent
packaging and distribution in market and points of sale, this is
under supervision of Mr. Jone Gawland ,Producer Division
Manager of General Farmer Association in cooperation with Ms.
Sarah Fouad, Director of Human Resources responsible for
holding training courses for staff operating these systems.
Finally, the project is completed after ensuring that (CMCC)
project is functioning efficiently at full operational capacity.
Accordingly, the project manager will hand over the project to
the production manager to follow up on the activities of the
(CMCC) after the approval of Mr. Gorge Stuard, the head of
investors committee.
References
Eskerod, P., & Jepsen, A. L. (2013). Project Stakeholder
Management.
Haugan, G. T. (2016). The New Triple Constraints for
Sustainable Projects, Programs, and Portfolios. Boca
Raton, FL: CRC Press.
Pries, K. H., & Quigley, J. M. (2012). Total Quality
Management for Project Management. Boca Raton, FL: CRC
Press.
Vida, K. P. (2012). The Project Management Handbook: A
Guide to Capital Improvements. Rowman & Littlefield.
15
1
Project
Charter
Week
2
1
Project Charter
Week2
Social Impact Assessment
(Project Name)
Student Name
Walden University
Date
Table of Contents
SIA Approach 3
Identify Social Impact(s) 3
Analyze Social Impact(s) 3
Social Impact(s) Response Plan 3
Monitor Social Impact(s) 3
A social impact assessment (SIA) identifies the potential impact
of a project on society (people), the environment (planet), and
economically (prosperity). Once identified, an assessment of
significant impacts must be analyzed, and plans for managing
each impact must be developed jointly with all appropriate
stakeholders.
SIA Approach
· Describe the approach that will be used to identify, analyze,
and monitor the social impacts of the project. (1 page)
Identify Social Impact(s)
· Identify and describe at least two potential social impacts of
the project in each area: society, environment, and
economically. (3–4 paragraphs)
Analyze Social Impact(s)
· Analyze each of the potential social impacts of the project. (1
page)
· Who will be impacted?
· Will the impact be positive or negative?
· How will positive impacts be enhanced?
· How will negative impacts be mitigated?
Monitor Social Impact(s)
· Explain how the social impacts of the project will be
monitored. (3–4 paragraphs)
· How often will the social conditions of the project be
reviewed?
· How will actual social impacts be assessed against the
potential social impacts identified earlier?
· How will stakeholders be involved in monitoring the social
impacts of the project?
©2018 Walden University 1
Project Scope
(Project Name)
Student Name
Walden University
Date
Table of Contents
Project Outcome 3
Requirements Traceability Matrix 3
Project Scope Statement 3
Work Breakdown Structure 4
Work Breakdown Structure Dictionary 5
Project Outcome
(Copy from Project Charter.)
Requirements Traceability Matrix
(Copy requirements from Project Charter.)
The requirements of a project are the conditions or capabilities
that the deliverables of a project must meet in order to satisfy
the project objectives. The requirements traceability matrix
explicitly shows the connections between the requirements, the
project objectives, and the deliverables.
· List each requirement for the project, the project objective
that each requirement addresses, and the deliverable that
satisfies each requirement.
Requirement
Project Objective
Deliverable
Project Scope Statement
Project scope defines all of the work that must be done to
deliver the expected outcome or product of the project. The
project scope statement describes precisely what is and what is
not included in the project. The scope of the project is derived
from project requirements and is used as input to create the
work breakdown structure.
Compose a project scope statement:
· Describe, in detail, the characteristics of the product, service,
or outcome that the project will produce. (3–4 paragraphs)
· Describe the incremental deliverables that must be produced to
create the final product, service, or outcome of the project. (3–4
paragraphs)
Example: For a house construction project, the concrete masons
must deliver the foundation before the carpenters can begin
framing the house. Excavating the ground and pouring the
concrete are tasks that must be performed to produce the
foundation which is the deliverable.
· Describe the exclusions from the scope of the project. (1–2
paragraphs)
©2018 Walden University 1
Work Breakdown Structure
The work breakdown structure (WBS) is used in project
management to depict the scope of a project. In addition, the
WBS is the primary source of information for the development
of the project schedule and network diagram, for the
determination of project resources, and is an important element
of performance measurement.
For the purposes of this assignment, the highest level of the
WBS represents the product, service, or outcome of the project.
The second level of the WBS represents the incremental
deliverables that must be produced to create the final product,
service, or outcome of the project. The third level of the WBS
represents the activities/tasks (called work packages) that must
be performed to produce the incremental deliverables.
Note: Depending on the nature of your project, you may need or
want to add levels. Just remember that only the lowest level
represents activities/tasks (work packages). All other levels
represent deliverables.
· Produce a work breakdown structure (WBS) decomposed to at
least three levels for the project. The WBS must include at least
three sub-deliverables and two activities/tasks for each sub-
deliverable.
Work Breakdown Structure Dictionary
· Complete this table for each work package in the WBS.
Project Title:
WBS Work Package ID:
WBS Work Package Task Name:
Description of Work:
Deliverable:
Activities (Verb Noun Format)
Labor Resources
(Name or Type)
Other Resources (Such as Equipment)
Expected Duration
Total Duration:
Acceptance Criteria:
Project CharterWeek2.docx

More Related Content

Similar to Project CharterWeek2.docx

Co operative business plan group-1
Co operative business plan group-1Co operative business plan group-1
Co operative business plan group-1Anoop K Mishra
 
Pre Construction Stages Work(procurement and tendering) Binod Patro
Pre Construction Stages Work(procurement and tendering)  Binod PatroPre Construction Stages Work(procurement and tendering)  Binod Patro
Pre Construction Stages Work(procurement and tendering) Binod PatroBBinodKumarPatro
 
3761 db7415 -_manideep_yellanki_assesment_2_55705_10041974
3761 db7415 -_manideep_yellanki_assesment_2_55705_100419743761 db7415 -_manideep_yellanki_assesment_2_55705_10041974
3761 db7415 -_manideep_yellanki_assesment_2_55705_10041974Manideep Yellanki
 
Project Proposal: Coca-Cola Green Vending Machine
Project Proposal: Coca-Cola Green Vending MachineProject Proposal: Coca-Cola Green Vending Machine
Project Proposal: Coca-Cola Green Vending MachineKarmesh Patel, CCS, CITP
 
Bulk milk cooling unit 5000 litr
Bulk milk cooling unit   5000 litrBulk milk cooling unit   5000 litr
Bulk milk cooling unit 5000 litrKaushik Chaudhury
 
Rice millersclusterkalady project report
Rice millersclusterkalady project reportRice millersclusterkalady project report
Rice millersclusterkalady project reportNandiishKumarBM1
 
Food park in patna b ihar
Food park in patna b ihar Food park in patna b ihar
Food park in patna b ihar Prakash Hinduja
 
Consumer-To-Consumer Food Delivery System on Salesforce.
Consumer-To-Consumer Food Delivery System on Salesforce.Consumer-To-Consumer Food Delivery System on Salesforce.
Consumer-To-Consumer Food Delivery System on Salesforce.Darshan Gorasiya
 
Project Management Report for Blue Bag Films (University Assignment)
Project Management Report for Blue Bag Films (University Assignment)Project Management Report for Blue Bag Films (University Assignment)
Project Management Report for Blue Bag Films (University Assignment)Yordan Dimitrov
 
Process Improvement Project official
Process Improvement Project officialProcess Improvement Project official
Process Improvement Project officialPhilip Spottswood
 
Operations Research & Methodology project report
Operations Research & Methodology  project reportOperations Research & Methodology  project report
Operations Research & Methodology project reportPankaj Kumar Dwivedi
 
sample dpr bakery-unit
sample dpr bakery-unitsample dpr bakery-unit
sample dpr bakery-unitMuditSharma126
 
Help With Scholarship Essa
Help With Scholarship EssaHelp With Scholarship Essa
Help With Scholarship EssaApril Smith
 
Production and operations management
Production and operations managementProduction and operations management
Production and operations managementdarious demus
 
Ebm internship report
Ebm internship reportEbm internship report
Ebm internship reportHamid Hussain
 
Scenario 1 (length as needed)You are considering auctioning a L.docx
Scenario 1 (length as needed)You are considering auctioning a L.docxScenario 1 (length as needed)You are considering auctioning a L.docx
Scenario 1 (length as needed)You are considering auctioning a L.docxkenjordan97598
 

Similar to Project CharterWeek2.docx (20)

Co operative business plan group-1
Co operative business plan group-1Co operative business plan group-1
Co operative business plan group-1
 
Pre Construction Stages Work(procurement and tendering) Binod Patro
Pre Construction Stages Work(procurement and tendering)  Binod PatroPre Construction Stages Work(procurement and tendering)  Binod Patro
Pre Construction Stages Work(procurement and tendering) Binod Patro
 
3761 db7415 -_manideep_yellanki_assesment_2_55705_10041974
3761 db7415 -_manideep_yellanki_assesment_2_55705_100419743761 db7415 -_manideep_yellanki_assesment_2_55705_10041974
3761 db7415 -_manideep_yellanki_assesment_2_55705_10041974
 
AHIDF.pdf
AHIDF.pdfAHIDF.pdf
AHIDF.pdf
 
Project Proposal: Coca-Cola Green Vending Machine
Project Proposal: Coca-Cola Green Vending MachineProject Proposal: Coca-Cola Green Vending Machine
Project Proposal: Coca-Cola Green Vending Machine
 
Bulk milk cooling unit 5000 litr
Bulk milk cooling unit   5000 litrBulk milk cooling unit   5000 litr
Bulk milk cooling unit 5000 litr
 
Rice millersclusterkalady project report
Rice millersclusterkalady project reportRice millersclusterkalady project report
Rice millersclusterkalady project report
 
Food park in patna b ihar
Food park in patna b ihar Food park in patna b ihar
Food park in patna b ihar
 
Consumer-To-Consumer Food Delivery System on Salesforce.
Consumer-To-Consumer Food Delivery System on Salesforce.Consumer-To-Consumer Food Delivery System on Salesforce.
Consumer-To-Consumer Food Delivery System on Salesforce.
 
Project Management Report for Blue Bag Films (University Assignment)
Project Management Report for Blue Bag Films (University Assignment)Project Management Report for Blue Bag Films (University Assignment)
Project Management Report for Blue Bag Films (University Assignment)
 
Process Improvement Project official
Process Improvement Project officialProcess Improvement Project official
Process Improvement Project official
 
Operations Research & Methodology project report
Operations Research & Methodology  project reportOperations Research & Methodology  project report
Operations Research & Methodology project report
 
Project pom 2
Project pom 2Project pom 2
Project pom 2
 
sample dpr bakery-unit
sample dpr bakery-unitsample dpr bakery-unit
sample dpr bakery-unit
 
Help With Scholarship Essa
Help With Scholarship EssaHelp With Scholarship Essa
Help With Scholarship Essa
 
Production and operations management
Production and operations managementProduction and operations management
Production and operations management
 
Ebm internship report
Ebm internship reportEbm internship report
Ebm internship report
 
Scenario 1 (length as needed)You are considering auctioning a L.docx
Scenario 1 (length as needed)You are considering auctioning a L.docxScenario 1 (length as needed)You are considering auctioning a L.docx
Scenario 1 (length as needed)You are considering auctioning a L.docx
 
Automatic bottle filling Machine
Automatic bottle filling Machine  Automatic bottle filling Machine
Automatic bottle filling Machine
 
Shaneka pob sba
Shaneka pob sbaShaneka pob sba
Shaneka pob sba
 

More from stilliegeorgiana

1. The Incident Command System (ICS) is a tool forA. Co.docx
1. The Incident Command System (ICS) is a tool forA. Co.docx1. The Incident Command System (ICS) is a tool forA. Co.docx
1. The Incident Command System (ICS) is a tool forA. Co.docxstilliegeorgiana
 
1. The Thirteenth Amendment effectively brought an end to slaver.docx
1. The Thirteenth Amendment effectively brought an end to slaver.docx1. The Thirteenth Amendment effectively brought an end to slaver.docx
1. The Thirteenth Amendment effectively brought an end to slaver.docxstilliegeorgiana
 
1. The Thirteenth Amendment effectively brought an end to slavery in.docx
1. The Thirteenth Amendment effectively brought an end to slavery in.docx1. The Thirteenth Amendment effectively brought an end to slavery in.docx
1. The Thirteenth Amendment effectively brought an end to slavery in.docxstilliegeorgiana
 
1. The Fight for a True Democracyhttpswww.nytimes.com201.docx
1. The Fight for a True Democracyhttpswww.nytimes.com201.docx1. The Fight for a True Democracyhttpswww.nytimes.com201.docx
1. The Fight for a True Democracyhttpswww.nytimes.com201.docxstilliegeorgiana
 
1. The article for week 8 described hip hop as a weapon. This weeks.docx
1. The article for week 8 described hip hop as a weapon. This weeks.docx1. The article for week 8 described hip hop as a weapon. This weeks.docx
1. The article for week 8 described hip hop as a weapon. This weeks.docxstilliegeorgiana
 
1. The Hatch Act defines prohibited activities of public employees. .docx
1. The Hatch Act defines prohibited activities of public employees. .docx1. The Hatch Act defines prohibited activities of public employees. .docx
1. The Hatch Act defines prohibited activities of public employees. .docxstilliegeorgiana
 
1. The Case for Reparations” by Ta-Nehisi Coates (604-19) in Rere.docx
1. The Case for Reparations” by Ta-Nehisi Coates (604-19) in Rere.docx1. The Case for Reparations” by Ta-Nehisi Coates (604-19) in Rere.docx
1. The Case for Reparations” by Ta-Nehisi Coates (604-19) in Rere.docxstilliegeorgiana
 
1. Some people say that chatbots are inferior for chatting.Others di.docx
1. Some people say that chatbots are inferior for chatting.Others di.docx1. Some people say that chatbots are inferior for chatting.Others di.docx
1. Some people say that chatbots are inferior for chatting.Others di.docxstilliegeorgiana
 
1. Some people say that chatbots are inferior for chatting.Other.docx
1. Some people say that chatbots are inferior for chatting.Other.docx1. Some people say that chatbots are inferior for chatting.Other.docx
1. Some people say that chatbots are inferior for chatting.Other.docxstilliegeorgiana
 
1. Some people say that chatbots are inferior for chatting. Others d.docx
1. Some people say that chatbots are inferior for chatting. Others d.docx1. Some people say that chatbots are inferior for chatting. Others d.docx
1. Some people say that chatbots are inferior for chatting. Others d.docxstilliegeorgiana
 
1. Tell us about yourself and your personal journey that has to .docx
1. Tell us about yourself and your personal journey that has to .docx1. Tell us about yourself and your personal journey that has to .docx
1. Tell us about yourself and your personal journey that has to .docxstilliegeorgiana
 
1. Tell us what characteristics of Loma Linda University are particu.docx
1. Tell us what characteristics of Loma Linda University are particu.docx1. Tell us what characteristics of Loma Linda University are particu.docx
1. Tell us what characteristics of Loma Linda University are particu.docxstilliegeorgiana
 
1. Tell us about yourself and your personal journey that has lea.docx
1. Tell us about yourself and your personal journey that has lea.docx1. Tell us about yourself and your personal journey that has lea.docx
1. Tell us about yourself and your personal journey that has lea.docxstilliegeorgiana
 
1. The Research paper will come in five parts. The instructions are.docx
1. The Research paper will come in five parts. The instructions are.docx1. The Research paper will come in five parts. The instructions are.docx
1. The Research paper will come in five parts. The instructions are.docxstilliegeorgiana
 
1. The minutiae points located on a fingerprint will help determine .docx
1. The minutiae points located on a fingerprint will help determine .docx1. The minutiae points located on a fingerprint will help determine .docx
1. The minutiae points located on a fingerprint will help determine .docxstilliegeorgiana
 
1. The initial post is to be posted first and have 300-500 words.docx
1. The initial post is to be posted first and have 300-500 words.docx1. The initial post is to be posted first and have 300-500 words.docx
1. The initial post is to be posted first and have 300-500 words.docxstilliegeorgiana
 
1. The key elements of supplier measurement are quality, delivery, a.docx
1. The key elements of supplier measurement are quality, delivery, a.docx1. The key elements of supplier measurement are quality, delivery, a.docx
1. The key elements of supplier measurement are quality, delivery, a.docxstilliegeorgiana
 
1. Search the Internet and locate an article that relates to the top.docx
1. Search the Internet and locate an article that relates to the top.docx1. Search the Internet and locate an article that relates to the top.docx
1. Search the Internet and locate an article that relates to the top.docxstilliegeorgiana
 
1. Text mining – Text mining or text data mining is a process to e.docx
1. Text mining – Text mining or text data mining is a process to e.docx1. Text mining – Text mining or text data mining is a process to e.docx
1. Text mining – Text mining or text data mining is a process to e.docxstilliegeorgiana
 
1. Students need to review 3 different social media platforms that a.docx
1. Students need to review 3 different social media platforms that a.docx1. Students need to review 3 different social media platforms that a.docx
1. Students need to review 3 different social media platforms that a.docxstilliegeorgiana
 

More from stilliegeorgiana (20)

1. The Incident Command System (ICS) is a tool forA. Co.docx
1. The Incident Command System (ICS) is a tool forA. Co.docx1. The Incident Command System (ICS) is a tool forA. Co.docx
1. The Incident Command System (ICS) is a tool forA. Co.docx
 
1. The Thirteenth Amendment effectively brought an end to slaver.docx
1. The Thirteenth Amendment effectively brought an end to slaver.docx1. The Thirteenth Amendment effectively brought an end to slaver.docx
1. The Thirteenth Amendment effectively brought an end to slaver.docx
 
1. The Thirteenth Amendment effectively brought an end to slavery in.docx
1. The Thirteenth Amendment effectively brought an end to slavery in.docx1. The Thirteenth Amendment effectively brought an end to slavery in.docx
1. The Thirteenth Amendment effectively brought an end to slavery in.docx
 
1. The Fight for a True Democracyhttpswww.nytimes.com201.docx
1. The Fight for a True Democracyhttpswww.nytimes.com201.docx1. The Fight for a True Democracyhttpswww.nytimes.com201.docx
1. The Fight for a True Democracyhttpswww.nytimes.com201.docx
 
1. The article for week 8 described hip hop as a weapon. This weeks.docx
1. The article for week 8 described hip hop as a weapon. This weeks.docx1. The article for week 8 described hip hop as a weapon. This weeks.docx
1. The article for week 8 described hip hop as a weapon. This weeks.docx
 
1. The Hatch Act defines prohibited activities of public employees. .docx
1. The Hatch Act defines prohibited activities of public employees. .docx1. The Hatch Act defines prohibited activities of public employees. .docx
1. The Hatch Act defines prohibited activities of public employees. .docx
 
1. The Case for Reparations” by Ta-Nehisi Coates (604-19) in Rere.docx
1. The Case for Reparations” by Ta-Nehisi Coates (604-19) in Rere.docx1. The Case for Reparations” by Ta-Nehisi Coates (604-19) in Rere.docx
1. The Case for Reparations” by Ta-Nehisi Coates (604-19) in Rere.docx
 
1. Some people say that chatbots are inferior for chatting.Others di.docx
1. Some people say that chatbots are inferior for chatting.Others di.docx1. Some people say that chatbots are inferior for chatting.Others di.docx
1. Some people say that chatbots are inferior for chatting.Others di.docx
 
1. Some people say that chatbots are inferior for chatting.Other.docx
1. Some people say that chatbots are inferior for chatting.Other.docx1. Some people say that chatbots are inferior for chatting.Other.docx
1. Some people say that chatbots are inferior for chatting.Other.docx
 
1. Some people say that chatbots are inferior for chatting. Others d.docx
1. Some people say that chatbots are inferior for chatting. Others d.docx1. Some people say that chatbots are inferior for chatting. Others d.docx
1. Some people say that chatbots are inferior for chatting. Others d.docx
 
1. Tell us about yourself and your personal journey that has to .docx
1. Tell us about yourself and your personal journey that has to .docx1. Tell us about yourself and your personal journey that has to .docx
1. Tell us about yourself and your personal journey that has to .docx
 
1. Tell us what characteristics of Loma Linda University are particu.docx
1. Tell us what characteristics of Loma Linda University are particu.docx1. Tell us what characteristics of Loma Linda University are particu.docx
1. Tell us what characteristics of Loma Linda University are particu.docx
 
1. Tell us about yourself and your personal journey that has lea.docx
1. Tell us about yourself and your personal journey that has lea.docx1. Tell us about yourself and your personal journey that has lea.docx
1. Tell us about yourself and your personal journey that has lea.docx
 
1. The Research paper will come in five parts. The instructions are.docx
1. The Research paper will come in five parts. The instructions are.docx1. The Research paper will come in five parts. The instructions are.docx
1. The Research paper will come in five parts. The instructions are.docx
 
1. The minutiae points located on a fingerprint will help determine .docx
1. The minutiae points located on a fingerprint will help determine .docx1. The minutiae points located on a fingerprint will help determine .docx
1. The minutiae points located on a fingerprint will help determine .docx
 
1. The initial post is to be posted first and have 300-500 words.docx
1. The initial post is to be posted first and have 300-500 words.docx1. The initial post is to be posted first and have 300-500 words.docx
1. The initial post is to be posted first and have 300-500 words.docx
 
1. The key elements of supplier measurement are quality, delivery, a.docx
1. The key elements of supplier measurement are quality, delivery, a.docx1. The key elements of supplier measurement are quality, delivery, a.docx
1. The key elements of supplier measurement are quality, delivery, a.docx
 
1. Search the Internet and locate an article that relates to the top.docx
1. Search the Internet and locate an article that relates to the top.docx1. Search the Internet and locate an article that relates to the top.docx
1. Search the Internet and locate an article that relates to the top.docx
 
1. Text mining – Text mining or text data mining is a process to e.docx
1. Text mining – Text mining or text data mining is a process to e.docx1. Text mining – Text mining or text data mining is a process to e.docx
1. Text mining – Text mining or text data mining is a process to e.docx
 
1. Students need to review 3 different social media platforms that a.docx
1. Students need to review 3 different social media platforms that a.docx1. Students need to review 3 different social media platforms that a.docx
1. Students need to review 3 different social media platforms that a.docx
 

Recently uploaded

Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 

Recently uploaded (20)

Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 

Project CharterWeek2.docx

  • 1. Project Charter Week2 Table of Contents Business Case…………………………………………………………………… ……..………….………….3 Project Charter…….…………………………………………………..………
  • 2. ……………………………..6 Project Name ………………………………………………………………..……… ………………………..6 Project Description…………………………………………………………… ……………….….…………6 Objectives………………………………………….………………… ……..…………………………………..8 Project Outcome……………………….……………………………………… …….…….….……………..8 Requirements……………………………………..…….…………… …………………………………….….9 Project Success Criteria……………………………………………………………… …………………..11 Project Assumptions and Constraints…………………………………………………………… …13 Project Milestone Timeline chart…………………………………………………………………… .14 Stakeholder Register……………………………………………………………… ……………….………15 Project Approval Procedure…………………………………………..………………… ……..……...16
  • 3. Business Case: (Cooperative Milk Collecting Center) Executive Summary Several options were considered that will help address the objectives of the project, which are the inadequate access to the market by the dairy farmers, the milk spoilage problem, which has a direct impact on the quality of the milk. The project will sell the milk on behalf of the farmers either directly to the consumers around, but there is a percentage that will be sold through the cooperation will be determined later. Furthermore, the project intends to provide storage facilities that will ensure that milk is stored properly before it is delivered or sold. Proponent Details (a) Several employees- the project will require or employ 15 employees who will be involved either directly or indirectly in the activities of the project. (b) Major shareholders- the project will have five principal shareholders who will directly discharge their duties to manage the project. Benefits of the Project The project will be committed to the local community by employing a local workforce and providing quality milk: The project will have several benefits once it starts operations; they include: Creation of job opportunities- 15 local people will be employed to work in the project. Moreover, the project also will achieve the provision of secure market access for the farmers' dairy
  • 4. products- the project intents to collect milk from the farmers then sell the liquid on their behalf. Finally, Profit and revenue for shareholders- shareholders will be able to get profit, once the milk is sold, an automatic service charge will be deducted from the farmers’ total amount (Melton, Yates, & Iles-Smith, 2011). Time Frame The earlier analysis indicates that the project will take approximately one and a half years to be implemented; this is exactly 24 months. 1. Preparing the Project Design and contractual documents of the project with the farmers and get all the governmental approvals related to milk collections and distribution. Also, make all agreements with the selling points for milk to the customers. –approximate inquired time around four months. 2. Site mobilization and preparation for starting to implement the project works, Approximate 3months minimum. 3. Project Works Execution and Handing Over Approximate 10months. 4. Bring equipment and all the inquired refrigerators and fixed them in preparation for the operation; this needs about three months. 5. Commencement of operations of equipment, milk collection, refilling, and distribution system for sales outlets. - The approximate timeframe inquired for two months. 6. Completion of operations and Management staff Training and starting up full capacity production – Approximate timeframe two months. Cost of the Project the facility cost
  • 5. total cost Land Purchasing 100,000 Design and Documentation 15,000 Construction work 160,000 20 Mechanical Refrigeration or Cooling Tanks $1500/unit $30,000 Packing System for milk in containers suitable for distribution. 15,000 15 employee’s payrolls salary per year $75,000 Other Expenses (water, Electricity, telecommunication services& Sterilize and cleaning) $35,000 (a) The total estimated cost of investment- the project is likely to cost an estimated as per the following: In summary, the overall Budget of the Project is expected to be $430,000. (b) Purpose of investment funds- the main agenda is to help farmers to get quick access to the market as well as earn profit that will sustain the project.
  • 6. Servicing Requirements Several servicing requirements by the project will include power supply, which will be provided by the Electricity company, the water service board will provide water, other services may consist of telecommunication services, among others. Expected Return on investment The project does not assume any return in the first two years, and this is because the first one and half a year, the project will not have started its operation, and then the six months after will enable the project to stabilize. The project, however, expects 650,000 return on investment in year three and an increase in the subsequent years. Risk As for now, the project appears to be straight forward. However, several risks may face the project later as it progresses, Several changes that may meet the project are: (a) Market demand- a likely fall of Market demand (b) Land- may be scanty and not enough for the expansion of the project (c) supplies- low supplies due to change in seasons and climate change (d) Operations- may be marred with a lack of adequate funds (John & Oliver, 2015). Environmental Impacts The impact of the project on the environment will be positive, and this is because cleanliness is the first element that will be observed by the project. The purity of both the global climate as well as the work environment. However, in the case of the plastics container that may be thrown around by the users after use, the project intends to address this by regular involvement
  • 7. in the cleaning process. Project Charter Project Name: Cooperative Milk Collecting Center (CMCC)- Product Name: Golden Milk Project Description: The project is a profit-making organization which will be headed by the CEO who will be hired from outside to avoid conflict of interest, and every section will be directed by managers to be in charge of other employees. Managers will be one of the dairy farmers because they are the ones that understand the challenges, but they must possess management skills. In charge of the projects with a flat organizational structure where machine operators and other staff will be answerable directly to the manager. There will also be the board of directors who will be monitoring the management team to ensure that the interest of the shareholders is cared for. The project is targeting thousands of dairy farmers so that it may collect enough milk for value addition and processing. The project aims to build milk processing machines that will process the milk collected from different farmers to add value and packages it before selling it to retail shops and supermarket. Through processing, which adds value, the shelf life and prices of milk increases, and this help in profit maximization. The project will be particularly helpful and significant to the smallholder dairy producers because it will be collecting milk from the before processing. Payments that dairy farmers will be getting will help them increase their income. Furthermore, the project will facilitate several methods that will assist in the improvement of milk safety, especially in the small-scale dairying; this is because most of the farmers depend on their dairy products they get from their dairy animals to sell and at least earn a living from this activity. This project, therefore, will enable farmers to eradicate milk spoilage, which is estimated at the rate of 30% of the whole milk
  • 8. produced(Ortuzar et al. 2018)and will further improve the quality of the liquid. The project is specifically aimed at solving Milk Spoilage Problem which we have observed happening for quite some years now. The project targets to reduce milk spoilage to about 10%, and it will be overcome through However, offering storage facilities for the Milk brought by the farmers and add value through processing, which increases the shelf life. The project will facilitate transportation of the milk to the market on behalf of the farmer's under product name: Golden Milk. Objectives The project aims to help farmers get a quick market for their dairy products since they will be supplying their milk to the collection center and taken their money immediately without facing any difficulty with how they can sale it and distributed it in the market. Where the liquid will be packed and sold by the (CMCC) to the market under product Name Golden Milk. Market access will be measured in terms of the quantity of milk sold by dairy farmers in liters. Secondly, the project also aims at eradicating milk spoilage as storage facilities that will effectively store milk will be offered. Milk spoilage will be measured in percentage form where milk that is contaminated by bacteria is divided by the whole quantity of milk produced multiplied by 100 to get the rate of spoiled milk. Finally, the project intends to ensure the quality of the milk as several quality tests will be going on to ascertain the various milk components also check for bacteria, pathogens among other vital factors that may result in milk danger. Milk quality will be measured as a dummy variable stating whether the mill is contaminated with bacteria or not. Moreover, quality testing of the milk will be done at the collection center before the milk in stores and sold to the consumers. Quality testing will mainly focus on determining the microbial quality, water contamination, as well as the presence of mastitis in the herd. Quality testing will provide a platform where the farmers will be given individual advice regarding
  • 9. how they should take care of their dairy animals to ensure high and quality yields. All shareholders in the project will be getting dividends after every financial year. Bonus will be calculated based on the profit made after each fiscal year. Project Outcome The project will offer several services, the first service the project intends to provide is the milk storage services in there storage areas constructed specially for this purpose, and equipped with all cooling devices according to the appropriate cooling temperatures to save milk for long periods for more than 4 weeks, until they are packaged in bottles intended for this purpose for distribution in the local market and exported to the rest of the United States. That will ensure milk does not go wrong. According to the research we carried out, many farmers do not have milk storage facilities, and since milk is not durable, as it only stays for hours and then goes terrible, so many farmers incur lose when the milk goes wrong as they do not have storage facilities. The project intends to provide fridges that will assist in the storage and other milk storage facilities. The storage facility is expected to store approximately 50, 000 liters. It will be using cooling technology to maintain milk temperature low. Deep freezers will also be used as additional cooling equipment within the storage building. Secondly, the project also will focus on collecting the milk from the farmers and pays them. Many farmers are not able to get access to a quick market, and this is the main reason why the milk spoilage rate is high, approximately 30%. Since we have a direct link with the National Milk Corporation, we intend to collect milk from the farmers and sell to the National Milk Corporation immediately we get from the farmers, this will ensure a quick market, and also the liquid won't stay for long before getting to the market. At the same time, there are many ideas to have our retail shops to sell our product named the Golden Milk directly to the customers. Requirements
  • 10. There are several stakeholders' requirements for this project; the stakeholders' demands for the project are: Stakeholders need to support the project financially to enhance its implementation. Some of the facilities that are required to keep milk safe and in good quality are expensive. Therefore, stakeholders must come in handy and help raise funds to acquire those machines. Besides, they also need to assist in creating awareness among the farmers. Farmers need to be informed about these facilities that will be brought soon and how they will help them. Secondly, the Operations requirement- this stakeholder's need takes into consideration the maintenance of the features of the project. Furthermore. In this regard, the operational team further fosters constraints, for instance, the ability activities in the project. The third stakeholder requirement is the customer's stakeholder's requirement; this requirement – users, usually give information regarding the product and services offered or provided by the project. Lead users generally help in contributing to the user stories as well as ideas regarding the product and services quality as well as usability. It enables the project to understand which area has to be improved (Eskerod & Jepsen, 2013). Besides, they required the skill to help in the process of the milk product so that wastages are minimized at all costs. Also, they need the marketing skill that allows the firm to sell its products to the final consumers. The solution requirements include the ability to make farmers earn the highest possible income and profit by selling the milk directly to (CMCC) and at the same time taken a 25 % percentage from their share as a member in CMCC to refer to the milk quantities supplied to the Milk Collecting Center. This is a result of reduced spoilage. The other requirement is about enhanced consumer safety. Achievement of protection will be realized as a result of the use of facilities that prevent the milk from going bad quickly. These project solution requirements include the equipment that
  • 11. will be used to minimize milk spoilage while they are on transit or storage to the final selling point. The other element is the material used for packaging purposes to the quantities that will be offered to the final consumer. The project needs to uplift society and create employment. Around the number of 15 employees will be hired to work in the milk processing plant and thus creating jobs. Farmers will also get the market for their milk and therefore make money, which will raise their standards of living. On the other hand, the project is required to lead to the development of the neighboring areas. Other businesses are expected to come up in the area where the cooperative will be built. Quality requirements refer to specifications of the quality of the products as well as services that are offered by the project, it takes into consideration all the processes that take place in the project as well as the entire environment surrounding the project, including ensuring that the products meet the required standards and keeping the high standards of hygiene and cleanness. They are typically activities that may result in the quality improvement of the product as well as services. The quality requirements for this project include customer experience- customer experience refers to activities that may be able to contribute towards the pleasing of the product as well as services. Furthermore, maintainability requirements ensure that everything works well, and things are easy to maintain (Pries & Quigley, 2012). Project Success Criteria: Project success can be measured by the timeliness of the project, such as meeting deadlines, budget utilization such as staying within budget, and meeting requirements of the project. The project was managed, organized, structured to meet the goals and objectives of the plan is project success. If the stakeholders and sponsors supported all decisions, this is project success.
  • 12. The real test of project success is the grand opening of the CMCC on time with all team members there to support the vision and mission of the project. The several tangible measures of the success of this project will be the completion of the projection within the specified time of the two years. Every activity scheduled to be done within this period has to be completed within this period. In general, key factors that will determine the success of the project include adherence to the Project Scope, Schedule as well as customer satisfaction, among other tangible outcomes (Vida, 2012). Various measures will indicate the success of the project. These include an increase in the price of milk from farmers. The cooperative will buy milk from the farmers at a reasonable price. A survey will then be done to assess their satisfaction. The other indicator is the reduction in loses of milk. This will be shown by an increase in the amount of fluid supplied to the cooperative. In addition to the equipment available in CMC Center through which the milk is stored for long periods in a considerable quantity, furthermore, to the milk filling system and the quick transportation of the sale outlets for the arrival of packaged milk to the consumer fresh daily as we are getting other products extracted from milk such as cheese, cream, and butter. The success criteria in this project include the achievement of the high quality of the products when selling them to the final consumers, obtaining the target sales in the target market, and obtaining or achieving the producers' satisfaction. The other indicator of the project’s success will be through a survey. Customers will be asked their opinion regarding the performance of the cooperative. This will inform whether they are satisfied with the operations being carried out. A survey will also be done to determine the businesses that have come up since the construction of the cooperative. This will be an indicator of growth as a result of the project’s success.
  • 13. Project Assumptions and Constraints: Assumptions of the project refer to events that are expected to take place during the life cycle of a project. Some of the premises for this project are: · Milk is the only product that will be handled by the project. · Customers will be the local community around, and some percentage of the milk will be supplied to the National Creamery Corporation. · The top management of the project will manage the project and be responsible for ongoing operations. · Milk Supplier deliveries will be arranged to ensure on-time deliveries Several constraints for this project include: Resources- these include the various tools, equipment, as well as material which have to be used during the project. Resources also take into consideration the employees and experts who will work on the project. Some of these resources for this project will cover the refrigerators, cooling machines for cooling milk, cleaning tools, among other devices. Other constraints for the project are the Risk; proper preparations should be put in place to manage any risk that is likely to arise. Several Risks may occur during this project, and such Risks include delays that may lead to spoilage of the milk or any malfunctions that may lead to the interruption of the cooling and packaging system and how to make plans to repair those malfunctions as quickly as possible and develop alternative solutions to avoid damage occurs to the milk. Milk is perishable, and delays may result in spoilage hence losses. Risk is arguably the critical project constraint. Furthermore, Quality is another constraint for this project, since this project requires strict quality of the milk, that the cost of the project has to be high, in this regard. Therefore, quality constraints usually affect the cost project constraint directly. The provision of quality milk is thus aligned with the cost constraints of the project (Haugan, 2016).
  • 14. Project Milestone Timeline chart · Provide investors with the necessary funding and responsibilities for each of them. · Preparing the project Design and contractual documents · Site mobilization before starting work execution. · Work execution · Project Handing over · Bring equipment and start the installation for refrigerators · Commencement of operations for the computer and start-up all systems. · Completion of the operation phase and operation team training. Date Activity 3rd October 2019 Kick-off meeting – with an investor to discuss the budget and funds for the project. 10th October 2019 – 5 thFebruary 2020. Preparing Design & Contractual document 10thFebruary 2020 - 9th May 2020 Site Mobilization 10thMay 2020 – 9th March 2021 Construction Work execution 10th March 2021 – 5th of May 2021 Bring equipment and start installations 6th May 2021- 7th July 2021 Commencing operations for project work& operation team training 8thJuly 2021 Project Completion Kick-off meeting would take place on 3rd October, the main objective of the meeting will be to discuss all requirements of the project, every consideration will be outlined during the meeting including the sources of the finances as well as other resources. Secondly, preparing a design and Contractual
  • 15. document milestone is vital as essential information regarding the geographical nature of the location where the project will be set up will be identified. Furthermore, demographic information will be gathered, and this information is critical for the prosperity of the project. Thirdly, working out the plan include all activities that will be carried out from the initial stages of the project until completion; these activities may consist of several constructions. Lastly, project run-up involves the last phase of the project, and this event will include ensuring that everything is ok before the project starts providing the required services. By Commencement of operations of equipment, milk collection, refilling, and distribution system for sales outlets. Completion of activities and Management staff Training and starting up full capacity production. Stakeholder Register Name Organization Title Role Internal/External Gorge Stuard Cooperative Milk Collecting Center (CMCC) Head of Investors Committee Responsible for collecting funding for the project. Internal Jone Gowland General Farmer Association Manager for producer Division Responsible for Supplying the milk to (CMCC) External Sam Smith Texas State Government Head of Permits for Industrial Establishment Approved Licenses for project
  • 16. External Michel Saad Cooperative Milk Collecting Center (CMCC) Project Manager Leads work Execution of the project. Internal Adam Abbas General Farmer Association Technical support Engineer Approved all process from collecting the milk and storage it in the refrigerators up to fill it in bottles to be ready for distribution External Murad Nabiel Cooperative Milk Collecting Center (CMCC) Procurement Manager Responsible for supply all equipment and prepare the system for a start-up commissioning Internal Sarah Fouad Cooperative Milk Collecting Center (CMCC) Human Resources Hiring employees and selecting qualified staff and withholding training courses Internal Project Approval Procedure Date Activity Approval 3rd October 2019 Kick-off meeting – with the investor to discuss the budget and funds for the project. Gorge Stuard 10th October 2019 – 5 thFebruary 2020. Preparing Design & Contractual document
  • 17. Sam Smith 10thFebruary 2020 - 9th May 2020 Site Mobilization Michel Saad 10thMay 2020 – 9th March 2021 Construction Work execution Michel Saad 10th March 2021 – 5th of May 2021 Bring equipment and start installations Murad Nabiel 6th May 2021- 7th July 2021 Commencing operations for project work& operation team training Jone Gawland / Sara Fouad 8th July 2021 Project Completion Michel Saad/ Jone Gowland The project concept supported by investor committee after they like the ideas that aimed at helping the Dairy farmers to get easy access to the market and at the same time this investment allows farmers benefit from proceeds of pensioner support fund, the project concept approved by Mr. Gorge Stuard the Head of Investors Committee. After that, the project manager Mr. Michel Saaad begins to prepare the design drawing, including all, inquired detailed, to execute the work with full documentation with complete specification related to the construction phase associated with other tasks like Electrical, Mechanical and Plumbing works. All these documents will be attached with the master plan for the project location and to be submitted to the Permits for Industrial Establishment related to the Texas State Government to get approval on it before proceeding in to project implementation works, this will be approved and signed by Mr. Sam Smith. Once we got the
  • 18. necessary funds for the project and approval from Government Authorities, the stage of preparing the site started with taking all security safety measures to maintain the project staff equipping all the tools needed by the project and developing the temporary site offices this stage followed up and approved by the project manager Mr. Michel said. Upon completion of this stage, the project execution works will be started following the time table set for this purpose and compatibility with the investment strategy approved by Mr. Gorge Stuard, the Head of Investor's committee. During the implementation of the project Mr. Murad Nabil, Procurement manager ordered all the cooling systems allocated to milk according to the design and specifications approved previously, the arrival of the cooling system will be on the specified time to begin installation in cooperation with Mr. Adam Abass, the Technical Support Engineer of the General Farmer Association. After that the next stage to start the initial operation process of these systems to make sure that they usually work and their ability to absorb the necessary quantities of milk for storage and subsequent packaging and distribution in market and points of sale, this is under supervision of Mr. Jone Gawland ,Producer Division Manager of General Farmer Association in cooperation with Ms. Sarah Fouad, Director of Human Resources responsible for holding training courses for staff operating these systems. Finally, the project is completed after ensuring that (CMCC) project is functioning efficiently at full operational capacity. Accordingly, the project manager will hand over the project to the production manager to follow up on the activities of the (CMCC) after the approval of Mr. Gorge Stuard, the head of investors committee. References
  • 19. Eskerod, P., & Jepsen, A. L. (2013). Project Stakeholder Management. Haugan, G. T. (2016). The New Triple Constraints for Sustainable Projects, Programs, and Portfolios. Boca Raton, FL: CRC Press. Pries, K. H., & Quigley, J. M. (2012). Total Quality Management for Project Management. Boca Raton, FL: CRC Press. Vida, K. P. (2012). The Project Management Handbook: A Guide to Capital Improvements. Rowman & Littlefield. 15 1 Project Charter Week 2
  • 21. Social Impact Assessment (Project Name) Student Name Walden University Date Table of Contents SIA Approach 3 Identify Social Impact(s) 3 Analyze Social Impact(s) 3 Social Impact(s) Response Plan 3 Monitor Social Impact(s) 3 A social impact assessment (SIA) identifies the potential impact of a project on society (people), the environment (planet), and economically (prosperity). Once identified, an assessment of significant impacts must be analyzed, and plans for managing each impact must be developed jointly with all appropriate stakeholders. SIA Approach
  • 22. · Describe the approach that will be used to identify, analyze, and monitor the social impacts of the project. (1 page) Identify Social Impact(s) · Identify and describe at least two potential social impacts of the project in each area: society, environment, and economically. (3–4 paragraphs) Analyze Social Impact(s) · Analyze each of the potential social impacts of the project. (1 page) · Who will be impacted? · Will the impact be positive or negative? · How will positive impacts be enhanced? · How will negative impacts be mitigated? Monitor Social Impact(s) · Explain how the social impacts of the project will be monitored. (3–4 paragraphs) · How often will the social conditions of the project be reviewed? · How will actual social impacts be assessed against the potential social impacts identified earlier? · How will stakeholders be involved in monitoring the social impacts of the project? ©2018 Walden University 1 Project Scope (Project Name)
  • 23. Student Name Walden University Date Table of Contents Project Outcome 3 Requirements Traceability Matrix 3 Project Scope Statement 3 Work Breakdown Structure 4 Work Breakdown Structure Dictionary 5 Project Outcome (Copy from Project Charter.) Requirements Traceability Matrix (Copy requirements from Project Charter.) The requirements of a project are the conditions or capabilities that the deliverables of a project must meet in order to satisfy the project objectives. The requirements traceability matrix explicitly shows the connections between the requirements, the project objectives, and the deliverables. · List each requirement for the project, the project objective that each requirement addresses, and the deliverable that satisfies each requirement. Requirement Project Objective Deliverable
  • 24. Project Scope Statement Project scope defines all of the work that must be done to deliver the expected outcome or product of the project. The project scope statement describes precisely what is and what is not included in the project. The scope of the project is derived from project requirements and is used as input to create the work breakdown structure. Compose a project scope statement:
  • 25. · Describe, in detail, the characteristics of the product, service, or outcome that the project will produce. (3–4 paragraphs) · Describe the incremental deliverables that must be produced to create the final product, service, or outcome of the project. (3–4 paragraphs) Example: For a house construction project, the concrete masons must deliver the foundation before the carpenters can begin framing the house. Excavating the ground and pouring the concrete are tasks that must be performed to produce the foundation which is the deliverable. · Describe the exclusions from the scope of the project. (1–2 paragraphs) ©2018 Walden University 1 Work Breakdown Structure The work breakdown structure (WBS) is used in project management to depict the scope of a project. In addition, the WBS is the primary source of information for the development of the project schedule and network diagram, for the determination of project resources, and is an important element of performance measurement. For the purposes of this assignment, the highest level of the WBS represents the product, service, or outcome of the project. The second level of the WBS represents the incremental deliverables that must be produced to create the final product, service, or outcome of the project. The third level of the WBS represents the activities/tasks (called work packages) that must be performed to produce the incremental deliverables. Note: Depending on the nature of your project, you may need or want to add levels. Just remember that only the lowest level represents activities/tasks (work packages). All other levels represent deliverables.
  • 26. · Produce a work breakdown structure (WBS) decomposed to at least three levels for the project. The WBS must include at least three sub-deliverables and two activities/tasks for each sub- deliverable. Work Breakdown Structure Dictionary · Complete this table for each work package in the WBS. Project Title: WBS Work Package ID: WBS Work Package Task Name: Description of Work: Deliverable: Activities (Verb Noun Format) Labor Resources (Name or Type) Other Resources (Such as Equipment) Expected Duration