SlideShare a Scribd company logo
1 of 20
Analysis Of Engineering Examples Of
Flat Space Frame Structure
Capital Airport A380 Hangar
Overview:
The A380 hangar is located on the north side of Terminal 3 of the Capital
Airport. The total construction area of the project is 64,000 m2, with 3
floors above ground and 1 underground floor. *176.3m, depth 110m, roof
elevation + 39.800m. After completion, it can accommodate 4 A380
Airbuses or 2 A380 and 4 B747 large passenger aircrafts at the same time.
It is currently the world's largest aircraft maintenance warehouse. The
roof structure is a three-layer welded spherical steel space frame with a
total area of 39,000 m2 and a total mass of about 7,000 tons. It adopts a
construction plan of ground assembly and an overall lifting in place, and
its one-time lifting area and weight can be called the world's largest . The
overall improvement of the roof structure in the construction of the
hangar is undoubtedly the biggest technical difficulty.
Floor plan:
The capital airport hangar can hold four Boeing 747 large passenger planes for
maintenance at the same time. Due to the special function of the hangar and
the special requirements for space, the layout adopts the layout of the large
space on one side and the auxiliary room on the other side of the hangar, so
that the large space of the hangar is made up.
Internal space:
The main space inside the hangar is
a large space for airplanes to dock,
and its height and span are larger
than those of ordinary buildings, and
it is required that there are no
obstacles such as pillar nets inside.
Facade modeling:
The overall shape of the
hangar is square, and the
facade is made of
transparent glass. With
structural features, the
whole building appears
light and simple.
Structural analysis:
• The roof structure design is the key to the design of a large-span hangar. The
formulation of the plan must meet the following requirements: According to the
height of the airport airspace, the highest point of the hangar roof should not
exceed 40m; the layout and size of the roof structure should meet the technical
use and setting The requirements of the suspension crane, the deformation of the
roof structure does not affect the normal operation of the suspension crane and
the hangar gate; the hangar can meet the seismic fortification requirements of an
8 degree earthquake; at the same time, it is also necessary to consider the
reasonable and reliable roof structure production, transportation, and hoisting.
Speed up the construction cycle. According to the above principles, after
comparing various schemes, a spatial structure system combining multi-layer
quadrangular pyramid space frame and bolt-welded steel bridge was selected.
Structural plan and
elevation:
The structure plan and elevation
of the hangar are shown in the
figure. The space frame side
beams at the gate of the hangar
are designed as a box-shaped
space truss with two-span
continuous steel beams with a
width of 9.5m and a height of
11.5m.
Structure plan
Structural elevation
Engineering difficulties:
• 1. The steel structure has a large span and area, which is the largest at
home and abroad: the steel structure of this project has a span of
352.60m, a depth of 114.5m, and a roof elevation of +39.800m. The roof
structure adopts three-layer obliquely placed quadrangular pyramid steel
space frame frame, supported by the lower chord, and the roof of the
hangar gate adopts a welded box-shaped steel truss, with a width of 9.5m
and a height of 11.5m. For the construction of such a large-span structure,
there is no domestic precedent and mature construction experience that
can be used for reference. The scientific construction plan is selected to
ensure the quality of the project, ensure the safety of the structure itself
and the construction safety, effectively control the construction progress,
and reasonably reduce the construction cost. The top priority of this
project and similar projects must be in-depth and detailed research.
Engineering difficulties:
• 2. High quality requirements for structural assembly: The steel structure of
this project adopts a three-layer obliquely placed quadrangular pyramid
steel space frame structure combined with a steel truss, with a span of
352.60m, a depth of 114.5m, and a complex structure. The measurement
of the plane control network during construction The accuracy
requirements are very high; how to take the correct assembly method,
assembly accuracy control measures according to the characteristics of
the structure itself, and how to ensure the final closure of the overall
structure after assembly requires careful study. In addition, the project has
a huge number of components and various on-site node forms. How to
combine structural span, depth, height and structural form characteristics,
take effective welding process and welding quality control measures to
ensure welding quality and overall structural assembly quality is the
difficulty of this project .
Engineering difficulties:
• 3. Heavy tasks and
tight schedule:
• The total construction period
for the four seats of the
Capital Airport is three years.
In order to meet the needs of
putting into use before the
Olympic Games, this project
shortened the conventional
36-month construction
period to 20 months.
Selection of construction plan:
• The existing construction schemes include high-altitude bulk
assembly, segmented hoisting and overall lifting, but
considering their respective advantages and disadvantages,
manpower and material resources, safety management and
other conditions, the overall lifting construction technology
was finally selected. The advantage is that a large amount of
work can be completed on the ground, reducing the amount
of tooling scaffolding, avoiding high-altitude operations, and
reducing the difficulty of project safety management. Due to
the large site area, multi-point and multi-face flow operations
can be formed, which speeds up the progress of ground
assembly and facilitates the control of engineering installation
accuracy.
Overall promotion technology:
• In order to meet the boundary conditions of the structural design to the
greatest extent and ensure the quality of the project; speed up the
progress of the project construction and create conditions for the follow-
up work; reduce the cost of the project; and ensure the safety of the
construction. For this project, a one-time overall lifting construction
technique is adopted. The one-time overall lifting structure has the
following advantages: the weight of the lifting structure can reach more
than 10,000 tons; the size, area and volume of the lifting structure are
large; computer control, high degree of automation; reducing the amount
of high-altitude work, the construction is safe, reliable, and lower
Construction risk; shorten the construction period and reduce the
construction cost. Based on the above analysis, we decided to adopt the
scheme of simultaneous lifting of the net frame and the truss.
Multi-point and multi-face ground assembly
work at the construction site
Improve the assembled spaceframe at one time
Summarize:
• Large span and high height have become the key to the
structure design of the hangar;
• Select the space structure system combining multi-layer
quadrangular pyramid space frame frame and bolt-welded
steel bridge;
• Capital Airport A380 hangar uses one-time overall lifting
technology to assemble the flat space frame structure;
• The shape is simple and light;

More Related Content

Similar to Analysis Of Engineering Examples Of Flat Space Frame Structure-Capital Airport A380 Hangar

case study of shanghai world finance centre.
case study of shanghai world finance centre.case study of shanghai world finance centre.
case study of shanghai world finance centre.Chiranjita Jibhkate
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Yee Len Wan
 
Structural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsStructural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsDP NITHIN
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard buildingBirukYared3
 
P.e.b. mini project report
P.e.b. mini project reportP.e.b. mini project report
P.e.b. mini project reportShubham Parab
 
Reconstruction of a 4 storey commercial building to a 5 story building
Reconstruction of a 4 storey commercial building to a 5 story buildingReconstruction of a 4 storey commercial building to a 5 story building
Reconstruction of a 4 storey commercial building to a 5 story buildingService_supportAssignment
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructionErankajKumar
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studiesSoumitra Smart
 
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...IRJET Journal
 
High rise archive research
High rise archive researchHigh rise archive research
High rise archive researchdenverdieza
 
calculation-sheet.docxProject DetailsDesignerDat.docx
calculation-sheet.docxProject DetailsDesignerDat.docxcalculation-sheet.docxProject DetailsDesignerDat.docx
calculation-sheet.docxProject DetailsDesignerDat.docxhumphrieskalyn
 
IRJET- Study of Pre-Engineered Building
IRJET-  	  Study of Pre-Engineered BuildingIRJET-  	  Study of Pre-Engineered Building
IRJET- Study of Pre-Engineered BuildingIRJET Journal
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfGourhariBiswas1
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimneyAxay Sharma
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
 

Similar to Analysis Of Engineering Examples Of Flat Space Frame Structure-Capital Airport A380 Hangar (20)

Industrial buildings
Industrial buildingsIndustrial buildings
Industrial buildings
 
case study of shanghai world finance centre.
case study of shanghai world finance centre.case study of shanghai world finance centre.
case study of shanghai world finance centre.
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
 
Structural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsStructural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methods
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Site report
Site reportSite report
Site report
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
P.e.b. mini project report
P.e.b. mini project reportP.e.b. mini project report
P.e.b. mini project report
 
Reconstruction of a 4 storey commercial building to a 5 story building
Reconstruction of a 4 storey commercial building to a 5 story buildingReconstruction of a 4 storey commercial building to a 5 story building
Reconstruction of a 4 storey commercial building to a 5 story building
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studies
 
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
 
High rise archive research
High rise archive researchHigh rise archive research
High rise archive research
 
calculation-sheet.docxProject DetailsDesignerDat.docx
calculation-sheet.docxProject DetailsDesignerDat.docxcalculation-sheet.docxProject DetailsDesignerDat.docx
calculation-sheet.docxProject DetailsDesignerDat.docx
 
Defense thesis
Defense thesisDefense thesis
Defense thesis
 
CCTVHeadquarters.pdf
CCTVHeadquarters.pdfCCTVHeadquarters.pdf
CCTVHeadquarters.pdf
 
IRJET- Study of Pre-Engineered Building
IRJET-  	  Study of Pre-Engineered BuildingIRJET-  	  Study of Pre-Engineered Building
IRJET- Study of Pre-Engineered Building
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 

More from wendy cai

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Philippine bolt ball space frame Power Plant.pdf
Philippine bolt ball space frame Power Plant.pdfPhilippine bolt ball space frame Power Plant.pdf
Philippine bolt ball space frame Power Plant.pdfwendy cai
 
Philippine steel space frame coal bunker.pdf
Philippine steel space frame coal bunker.pdfPhilippine steel space frame coal bunker.pdf
Philippine steel space frame coal bunker.pdfwendy cai
 
Several methods of surface treatment for structural steel fasteners
Several methods of surface treatment for structural steel fastenersSeveral methods of surface treatment for structural steel fasteners
Several methods of surface treatment for structural steel fastenerswendy cai
 
Nodal seismic construction requirements.pptx
Nodal seismic construction requirements.pptxNodal seismic construction requirements.pptx
Nodal seismic construction requirements.pptxwendy cai
 
Support nodes for large-span coal storage structures
Support nodes for large-span coal storage structuresSupport nodes for large-span coal storage structures
Support nodes for large-span coal storage structureswendy cai
 
Pipe Truss Coal Stroged Shed for Power Plants
Pipe Truss Coal Stroged Shed for Power PlantsPipe Truss Coal Stroged Shed for Power Plants
Pipe Truss Coal Stroged Shed for Power Plantswendy cai
 
How do you satisfy the length-to-finish ratio.pdf
How do you satisfy the length-to-finish ratio.pdfHow do you satisfy the length-to-finish ratio.pdf
How do you satisfy the length-to-finish ratio.pdfwendy cai
 
What are the advantages of dome glass roof
What are the advantages of dome glass roofWhat are the advantages of dome glass roof
What are the advantages of dome glass roofwendy cai
 
Which is more economical, steel or concrete construction?
Which is more economical, steel or concrete construction?Which is more economical, steel or concrete construction?
Which is more economical, steel or concrete construction?wendy cai
 
Which is better, steel or wood construction.pdf
Which is better, steel or wood construction.pdfWhich is better, steel or wood construction.pdf
Which is better, steel or wood construction.pdfwendy cai
 
Shopping mall dome roof.pdf
Shopping mall dome roof.pdfShopping mall dome roof.pdf
Shopping mall dome roof.pdfwendy cai
 
Abu Dhabi Armed Force Space Frame Project
Abu Dhabi Armed Force Space Frame ProjectAbu Dhabi Armed Force Space Frame Project
Abu Dhabi Armed Force Space Frame Projectwendy cai
 
Dome roof structure
Dome roof structureDome roof structure
Dome roof structurewendy cai
 
Space truss structure
Space truss structureSpace truss structure
Space truss structurewendy cai
 
Space frame structure shanghai stadium
Space frame structure shanghai stadiumSpace frame structure shanghai stadium
Space frame structure shanghai stadiumwendy cai
 

More from wendy cai (16)

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Philippine bolt ball space frame Power Plant.pdf
Philippine bolt ball space frame Power Plant.pdfPhilippine bolt ball space frame Power Plant.pdf
Philippine bolt ball space frame Power Plant.pdf
 
Philippine steel space frame coal bunker.pdf
Philippine steel space frame coal bunker.pdfPhilippine steel space frame coal bunker.pdf
Philippine steel space frame coal bunker.pdf
 
Several methods of surface treatment for structural steel fasteners
Several methods of surface treatment for structural steel fastenersSeveral methods of surface treatment for structural steel fasteners
Several methods of surface treatment for structural steel fasteners
 
Nodal seismic construction requirements.pptx
Nodal seismic construction requirements.pptxNodal seismic construction requirements.pptx
Nodal seismic construction requirements.pptx
 
Support nodes for large-span coal storage structures
Support nodes for large-span coal storage structuresSupport nodes for large-span coal storage structures
Support nodes for large-span coal storage structures
 
Pipe Truss Coal Stroged Shed for Power Plants
Pipe Truss Coal Stroged Shed for Power PlantsPipe Truss Coal Stroged Shed for Power Plants
Pipe Truss Coal Stroged Shed for Power Plants
 
How do you satisfy the length-to-finish ratio.pdf
How do you satisfy the length-to-finish ratio.pdfHow do you satisfy the length-to-finish ratio.pdf
How do you satisfy the length-to-finish ratio.pdf
 
What are the advantages of dome glass roof
What are the advantages of dome glass roofWhat are the advantages of dome glass roof
What are the advantages of dome glass roof
 
Which is more economical, steel or concrete construction?
Which is more economical, steel or concrete construction?Which is more economical, steel or concrete construction?
Which is more economical, steel or concrete construction?
 
Which is better, steel or wood construction.pdf
Which is better, steel or wood construction.pdfWhich is better, steel or wood construction.pdf
Which is better, steel or wood construction.pdf
 
Shopping mall dome roof.pdf
Shopping mall dome roof.pdfShopping mall dome roof.pdf
Shopping mall dome roof.pdf
 
Abu Dhabi Armed Force Space Frame Project
Abu Dhabi Armed Force Space Frame ProjectAbu Dhabi Armed Force Space Frame Project
Abu Dhabi Armed Force Space Frame Project
 
Dome roof structure
Dome roof structureDome roof structure
Dome roof structure
 
Space truss structure
Space truss structureSpace truss structure
Space truss structure
 
Space frame structure shanghai stadium
Space frame structure shanghai stadiumSpace frame structure shanghai stadium
Space frame structure shanghai stadium
 

Recently uploaded

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 

Recently uploaded (20)

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 

Analysis Of Engineering Examples Of Flat Space Frame Structure-Capital Airport A380 Hangar

  • 1. Analysis Of Engineering Examples Of Flat Space Frame Structure Capital Airport A380 Hangar
  • 2. Overview: The A380 hangar is located on the north side of Terminal 3 of the Capital Airport. The total construction area of the project is 64,000 m2, with 3 floors above ground and 1 underground floor. *176.3m, depth 110m, roof elevation + 39.800m. After completion, it can accommodate 4 A380 Airbuses or 2 A380 and 4 B747 large passenger aircrafts at the same time. It is currently the world's largest aircraft maintenance warehouse. The roof structure is a three-layer welded spherical steel space frame with a total area of 39,000 m2 and a total mass of about 7,000 tons. It adopts a construction plan of ground assembly and an overall lifting in place, and its one-time lifting area and weight can be called the world's largest . The overall improvement of the roof structure in the construction of the hangar is undoubtedly the biggest technical difficulty.
  • 3. Floor plan: The capital airport hangar can hold four Boeing 747 large passenger planes for maintenance at the same time. Due to the special function of the hangar and the special requirements for space, the layout adopts the layout of the large space on one side and the auxiliary room on the other side of the hangar, so that the large space of the hangar is made up.
  • 4. Internal space: The main space inside the hangar is a large space for airplanes to dock, and its height and span are larger than those of ordinary buildings, and it is required that there are no obstacles such as pillar nets inside.
  • 5. Facade modeling: The overall shape of the hangar is square, and the facade is made of transparent glass. With structural features, the whole building appears light and simple.
  • 6. Structural analysis: • The roof structure design is the key to the design of a large-span hangar. The formulation of the plan must meet the following requirements: According to the height of the airport airspace, the highest point of the hangar roof should not exceed 40m; the layout and size of the roof structure should meet the technical use and setting The requirements of the suspension crane, the deformation of the roof structure does not affect the normal operation of the suspension crane and the hangar gate; the hangar can meet the seismic fortification requirements of an 8 degree earthquake; at the same time, it is also necessary to consider the reasonable and reliable roof structure production, transportation, and hoisting. Speed up the construction cycle. According to the above principles, after comparing various schemes, a spatial structure system combining multi-layer quadrangular pyramid space frame and bolt-welded steel bridge was selected.
  • 7.
  • 8. Structural plan and elevation: The structure plan and elevation of the hangar are shown in the figure. The space frame side beams at the gate of the hangar are designed as a box-shaped space truss with two-span continuous steel beams with a width of 9.5m and a height of 11.5m. Structure plan Structural elevation
  • 9.
  • 10. Engineering difficulties: • 1. The steel structure has a large span and area, which is the largest at home and abroad: the steel structure of this project has a span of 352.60m, a depth of 114.5m, and a roof elevation of +39.800m. The roof structure adopts three-layer obliquely placed quadrangular pyramid steel space frame frame, supported by the lower chord, and the roof of the hangar gate adopts a welded box-shaped steel truss, with a width of 9.5m and a height of 11.5m. For the construction of such a large-span structure, there is no domestic precedent and mature construction experience that can be used for reference. The scientific construction plan is selected to ensure the quality of the project, ensure the safety of the structure itself and the construction safety, effectively control the construction progress, and reasonably reduce the construction cost. The top priority of this project and similar projects must be in-depth and detailed research.
  • 11. Engineering difficulties: • 2. High quality requirements for structural assembly: The steel structure of this project adopts a three-layer obliquely placed quadrangular pyramid steel space frame structure combined with a steel truss, with a span of 352.60m, a depth of 114.5m, and a complex structure. The measurement of the plane control network during construction The accuracy requirements are very high; how to take the correct assembly method, assembly accuracy control measures according to the characteristics of the structure itself, and how to ensure the final closure of the overall structure after assembly requires careful study. In addition, the project has a huge number of components and various on-site node forms. How to combine structural span, depth, height and structural form characteristics, take effective welding process and welding quality control measures to ensure welding quality and overall structural assembly quality is the difficulty of this project .
  • 12. Engineering difficulties: • 3. Heavy tasks and tight schedule: • The total construction period for the four seats of the Capital Airport is three years. In order to meet the needs of putting into use before the Olympic Games, this project shortened the conventional 36-month construction period to 20 months.
  • 13. Selection of construction plan: • The existing construction schemes include high-altitude bulk assembly, segmented hoisting and overall lifting, but considering their respective advantages and disadvantages, manpower and material resources, safety management and other conditions, the overall lifting construction technology was finally selected. The advantage is that a large amount of work can be completed on the ground, reducing the amount of tooling scaffolding, avoiding high-altitude operations, and reducing the difficulty of project safety management. Due to the large site area, multi-point and multi-face flow operations can be formed, which speeds up the progress of ground assembly and facilitates the control of engineering installation accuracy.
  • 14. Overall promotion technology: • In order to meet the boundary conditions of the structural design to the greatest extent and ensure the quality of the project; speed up the progress of the project construction and create conditions for the follow- up work; reduce the cost of the project; and ensure the safety of the construction. For this project, a one-time overall lifting construction technique is adopted. The one-time overall lifting structure has the following advantages: the weight of the lifting structure can reach more than 10,000 tons; the size, area and volume of the lifting structure are large; computer control, high degree of automation; reducing the amount of high-altitude work, the construction is safe, reliable, and lower Construction risk; shorten the construction period and reduce the construction cost. Based on the above analysis, we decided to adopt the scheme of simultaneous lifting of the net frame and the truss.
  • 15. Multi-point and multi-face ground assembly work at the construction site
  • 16. Improve the assembled spaceframe at one time
  • 17.
  • 18.
  • 19.
  • 20. Summarize: • Large span and high height have become the key to the structure design of the hangar; • Select the space structure system combining multi-layer quadrangular pyramid space frame frame and bolt-welded steel bridge; • Capital Airport A380 hangar uses one-time overall lifting technology to assemble the flat space frame structure; • The shape is simple and light;