1. A P Goyal Shimla University
School of Architecture
End Term Examination, June, 2017
Course Name: Building Construction and Materials- II
Course Code: AGUAR 0202
Program: B.Arch Semester: 2nd
Duration: 3 Hours Max Marks: 40
1. In section A do any three questions out of four. (3×4=12 marks)
2. In section B do any three questions out of four. (3×6=18 marks)
3. In section C do all questions. (1×10=10 marks)
Section A
1. What are the characteristics of a good building stone. Sketch out a typical section to show a good
and bad construction in stone.
2. Discuss the importance of bamboo as a construction material. Discuss its advantages and
disadvantages.
3. What are various types of stones available to be used in flooring. Discuss in detail at least 4 such
stones and discuss their pros and cons.
4. Discuss the use, advantages and disadvantages of the following.
a. Terracotta
b. Stoneware
Section B
5. What is dressing of stones and state different types. Also discuss its use and importance
6. Make a typical wall sectionin stone masonry to explain all its components. Use appropriate scale.
7. What is Rubble masonry. State all the types and support the answer with sketches.
8. Make drawings for the following Clay products
a. Ridge Tile
b. Hip Tile
c. Spanish Tile
Section C
9. Show phase wise construction for an Earthquake resistant bamboo structure. Use appropriate
scale.
2. A P Goyal Shimla University
School of Architecture
End Term Examination, June, 2017
Course Name: Estimation, Costing and Specifications
Course Code: AGUAR 0607
Program: B.Arch Semester: 6th
Duration: 3 Hours Max Marks: 60
4. In section A do any four Questions out of five. (4×4=16 marks)
5. In section B do any three questions out of four. (3×8=24 marks)
6. In section C do all questions. (2×10=20 marks)
Section A
Q1.What are various types of Specifications.
Q2.
A. In centreline method of calculation junctions are applicable in both the corners and
cross walls True / False
B. In rate analysis ,contractor's profit percentage assumed to remain same in all items of
work True / False
C. Half brick thick brickwork is measured in ......... for calculation of quantities..
D. Brickwork in foundations is measured in ................... for calculation of quantities.
Q3.Discuss in brief the step by step procedure of building design till its completion while
emphasizing on the Estimation, costing and specifications of the materials
Q4.What do you understand by Rough Estimate and where it is used during the planning phase
of a project..
Q5. Explain Schedule of Rates. State their importance.
Section B
Q6.Write down a detailed specification for Ashlar masonry in c.m (1:3)
Q7.What is a detailed estimate and its importance. Discuss the various factors which affect the
preparation of detailed estimate.
Q8.Explain the various methods to take out quantities of brick walls. Give proper examples to
support your answer.
Q9.Write down rate analysis for the following.
a) Excavation for a depth of 1 meter
b) Cement Plaster in ratio 1:3
3. Section C
Q10. Estimate the detailed civil work cost of the following building drawing. Ensure
proper take off sheet for calculation and items of work. Assume any missing data.
Q11. Prepare an abstract of the same building to give a final cost of civil work including plumbing
and electrical costs along with the interior finishes and furniture (Assume the percentage
cost of allied works).
Also write brief specifications for the proposed flooring, false ceiling and wall paints.