This document introduces Mr. X, the director of an SME company that has been in existence since 1963. It describes some of the challenges the company was facing, including delayed deliveries, cash flow pressure, and delayed vendor payments. It then outlines how the company worked with Yagna to apply Theory of Constraints (TOC) thinking to identify constraints, exploit them by ensuring full kit compliance and visibility, and subordinate all other activities. As a result of these changes, the company saw significant improvements over one year, with project sales increasing 60%, throughput increasing 70%, and product sales increasing 30%. Overall throughput doubled from the agreed baseline.