1
Project Management
Work Breakdown Structure
(WBS)
GURUKUL KANGARI UNIVERSITY,HARIDWAR
SUBMITTED TO : SUBMITTED BY :
DR PANKAJ MADAN RAHUL SAINI
Title
Scope
(definition)
Project Management Processes
(Initiation)
Initiation
Cost
(estimates, …)
WBS
Time
(activity diagrams, …)
Human Resources
(RACI matrix, …)
• Also to consider: Quality, Risk,
Communication, Procurement, Integration
Project Charter
Project Management Plan
Project Scope
Statement
The Work Breakdown Structure
4
The Work Breakdown Structure (WBS)
• Used as a basis for a number of processes in
particular to produce the subsidiary plans of the
Project Management Plan.
• The WBS is a deliverable-oriented hierarchy of
decomposed project components that organises
and defines the total scope of the project. The WBS
is a representation of the detailed project scope
statement that specifies the work to be
accomplished by the project.
• The elements comprising the WBS assist the
stakeholders in viewing the end product of the
project.
• The work at the lowest-level WBS component is
estimated, scheduled, and tracked.
WBS
10.11.16
Marc Conrad
University of Bedfordshire 5
The Dictionary of the WBS
• A WBS dictionary is a companion document to the
WBS that describes each WBS element. For each WBS
element, the WBS dictionary includes a statement of
work, a list of associated activities, and a list of
milestones.
• Other information can include the responsible
organisation, start and end dates, resources required,
an estimate of cost, charge number, contract
information, quality requirements, and technical
references.
• WBS elements should be cross-referenced as
appropriate.
WBS
Marc Conrad
University of Bedfordshire 6
• Redecorate Room
♦ Prepare materials
 Buy paint
 Buy a ladder
 Buy brushes/rollers
 Buy wallpaper remover
♦ Prepare room
 Remove old wallpaper
 Remove detachable decorations
 Cover floor with old newspapers
 Cover electrical outlets/switches with tape
 Cover furniture with sheets
♦ Paint the room
♦ Clean up the room
 Dispose or store left over paint
 Clean brushes/rollers
 Dispose of old newspapers
 Remove covers
WBS
Example
WBS
7
Developing the WBS
• Divide the total work of the project into
major groups...
• ...then subdivide these groups into
tasks...
• ...then divide these tasks into sub-tasks
• Subtasks should be small enough to
permit adequate control and visibility
• But avoid excess bureaucracy!
WBS
Marc Conrad
University of Bedfordshire 8
Product Breakdown Structure
• Redecorated Room
♦ Removed old wallpaper
♦ Clean room
 Cover for furniture
 Cover for electrical
switches
 Newspapers to cover
floor.
♦ Paint
 Paint on wall
 Leftover paint
♦ Management products
 Ladder
 Brushes and rollers
• Focus on the product
to be delivered and not
on the work to do.
• Underpins PRINCE2®
“product-based”
approach.
PBS
9
“Scope Breakdown Structure”
(Max Wideman’s approach)
• Geographically discrete components
• Time based phases and stages
• Intermediate or final major deliverables
• Discrete structural, process, system or device
components
• Deliverable elements that can be associated
with distinctive types of people-skills or
resources
• After that, break down the work as in the WBS
SBS
Marc Conrad
University of Bedfordshire 10
Scope Breakdown Structure
(Max Wideman redecorates a room)
• Redecorated Room
♦ Painted wall
 Buy paint
 Buy ladder
 Buy brushes or rollers
 Paint room
♦ New curtains
 …
• Content Family
♦ A clean room
 Cover floor with old newspapers
 Cover electrical outlets/switches with tape
 Cover furniture with sheets
♦ Dinner in a restaurant
 …
♦ Decision on colours
 …
SBS
• Note the noun
phrases on the top
levels (scope
breakdown) and
the activities on
the lower levels!
11
Summary
• The WBS is used to define the
activities that are then further
managed.
• Consider alternatives:
♦ Work Breakdown Structure
♦ Product Breakdown Structure
♦ Scope Breakdown Structure
• Use Common Sense in Breakdown the
Project.
Summary
12
THANK YOU

Work breakdownstructure

  • 1.
    1 Project Management Work BreakdownStructure (WBS) GURUKUL KANGARI UNIVERSITY,HARIDWAR SUBMITTED TO : SUBMITTED BY : DR PANKAJ MADAN RAHUL SAINI Title
  • 2.
    Scope (definition) Project Management Processes (Initiation) Initiation Cost (estimates,…) WBS Time (activity diagrams, …) Human Resources (RACI matrix, …) • Also to consider: Quality, Risk, Communication, Procurement, Integration Project Charter Project Management Plan Project Scope Statement
  • 3.
  • 4.
    4 The Work BreakdownStructure (WBS) • Used as a basis for a number of processes in particular to produce the subsidiary plans of the Project Management Plan. • The WBS is a deliverable-oriented hierarchy of decomposed project components that organises and defines the total scope of the project. The WBS is a representation of the detailed project scope statement that specifies the work to be accomplished by the project. • The elements comprising the WBS assist the stakeholders in viewing the end product of the project. • The work at the lowest-level WBS component is estimated, scheduled, and tracked. WBS
  • 5.
    10.11.16 Marc Conrad University ofBedfordshire 5 The Dictionary of the WBS • A WBS dictionary is a companion document to the WBS that describes each WBS element. For each WBS element, the WBS dictionary includes a statement of work, a list of associated activities, and a list of milestones. • Other information can include the responsible organisation, start and end dates, resources required, an estimate of cost, charge number, contract information, quality requirements, and technical references. • WBS elements should be cross-referenced as appropriate. WBS
  • 6.
    Marc Conrad University ofBedfordshire 6 • Redecorate Room ♦ Prepare materials  Buy paint  Buy a ladder  Buy brushes/rollers  Buy wallpaper remover ♦ Prepare room  Remove old wallpaper  Remove detachable decorations  Cover floor with old newspapers  Cover electrical outlets/switches with tape  Cover furniture with sheets ♦ Paint the room ♦ Clean up the room  Dispose or store left over paint  Clean brushes/rollers  Dispose of old newspapers  Remove covers WBS Example WBS
  • 7.
    7 Developing the WBS •Divide the total work of the project into major groups... • ...then subdivide these groups into tasks... • ...then divide these tasks into sub-tasks • Subtasks should be small enough to permit adequate control and visibility • But avoid excess bureaucracy! WBS
  • 8.
    Marc Conrad University ofBedfordshire 8 Product Breakdown Structure • Redecorated Room ♦ Removed old wallpaper ♦ Clean room  Cover for furniture  Cover for electrical switches  Newspapers to cover floor. ♦ Paint  Paint on wall  Leftover paint ♦ Management products  Ladder  Brushes and rollers • Focus on the product to be delivered and not on the work to do. • Underpins PRINCE2® “product-based” approach. PBS
  • 9.
    9 “Scope Breakdown Structure” (MaxWideman’s approach) • Geographically discrete components • Time based phases and stages • Intermediate or final major deliverables • Discrete structural, process, system or device components • Deliverable elements that can be associated with distinctive types of people-skills or resources • After that, break down the work as in the WBS SBS
  • 10.
    Marc Conrad University ofBedfordshire 10 Scope Breakdown Structure (Max Wideman redecorates a room) • Redecorated Room ♦ Painted wall  Buy paint  Buy ladder  Buy brushes or rollers  Paint room ♦ New curtains  … • Content Family ♦ A clean room  Cover floor with old newspapers  Cover electrical outlets/switches with tape  Cover furniture with sheets ♦ Dinner in a restaurant  … ♦ Decision on colours  … SBS • Note the noun phrases on the top levels (scope breakdown) and the activities on the lower levels!
  • 11.
    11 Summary • The WBSis used to define the activities that are then further managed. • Consider alternatives: ♦ Work Breakdown Structure ♦ Product Breakdown Structure ♦ Scope Breakdown Structure • Use Common Sense in Breakdown the Project. Summary
  • 12.