The document discusses permit to work (PTW) procedures at an NGI training center. It defines what a PTW is, its purpose of ensuring work is planned and hazards identified, and that it is a legal document. It describes what types of work require a PTW, including hot work and cold work. It outlines the PTW process including initiation, authorization, cancellation. It defines roles and responsibilities of personnel involved in the PTW process. Finally, it discusses complementary permits that may be required for different types of work, such as electrical isolation or confined space entry.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Location / Area :
Panel No : Voltage:
Permit Validity:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
No: Checks Yes-No-NA Checks Yes-No-NA
ENERGIZATION (“Power On”) ISOLATION (“Power Off”)
1. Safety tool box briefing done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
2. Authorized personnel / operators available. ☐ ☐ ☐
Authorized personnel / operators available. ☐ ☐ ☐
3. Method statement/Risk assessment in place. ☐ ☐ ☐
Adjacent live areas protected. ☐ ☐ ☐
4. Safety Barriers in place and safety signage Displayed. ☐ ☐ ☐
PPE available, high voltage rubber gloves, Safety goggles and floor mat. ☐ ☐ ☐
5. Working area is well lighted. ☐ ☐ ☐
Isolation/Lock-out in place. ☐ ☐ ☐
6. Electrical instruments are available for any Purpose. ☐ ☐ ☐
Electrical circuits “proved” by calibrated Instrument and found out to be no power. ☐ ☐ ☐
7. Correct PPE available, high voltage rubber Gloves, safety goggles and floor mat. ☐ ☐ ☐
Unauthorized workers are cleared from the Area. ☐ ☐ ☐
8. Approved WIR for installation, testing and Termination are attached to the permit. ☐ ☐ ☐
Standby operatives in the event of contact With live circuits. ☐ ☐ ☐
9. Emergency light (Flashlight) available. ☐ ☐ ☐
Emergency light (Flashlight) available. ☐ ☐ ☐
10. Is live work absolutely necessary? ☐ ☐ ☐
Emergency response plan available ☐ ☐ ☐
11. Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☒ ☐ ☐
12. Power cable route from panel board to plant & equipment has been checked ☐ ☐ ☐
13 Emergency response plan available ☐ ☐ ☐
14 Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docxDwarika Bhushan Sharma
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Area / Location of edge protection or floor openings:
Purpose of removing:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Risk assessment/ method statement developed, approved and communicated? ☐ ☐ ☐
Availability of Fall protection arrangement (i.e. life line, etc.? ☐ ☐ ☐
Any high risk activity associated that requires PTW (i.e. hot work, Shaft Entry, CSE)? ☐ ☐ ☐
Adequate Lighting provided? ☐ ☐ ☐
Are all necessary Permit approved and displayed at work location? ☐ ☐ ☐
Availability of rescue procedure and equipment? ☐ ☐ ☐
Safe access / Working Platform provided? ☐ ☐ ☐
Mean of communication available? (Mobile, radio etc.) ☐ ☐ ☐
Availability of barricades/protection to prevent unauthorized or accidental entry? ☐ ☐ ☐
Helmet, Safety Shoes, Eye Protection, Hearing Protection and Cover All. ☐ ☐ ☐
Warning signs posted? ☐ ☐ ☐
Conduct Task Toolbox Talk prior to start the activity? ( TASK TBT TO BE ATTACHED) ☐ ☐ ☐
Exclusion zone for area below? ☐ ☐ ☐
Others (specify): ☐ ☐ ☐
Availability of Fall protection equipment (i.e. full body harness, etc.)? ☐ ☐ ☐
☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAhmadNadzir4
1. The document describes a work permit system which consists of standard procedures to ensure potentially hazardous routine and non-routine work is carried out safely.
2. A work permit specifies the work to be done, authorizes its start, and requires agreement of all concerned parties after reviewing safety measures.
3. A work permit is required for work involving hazards like oxygen deficiency, fires, chemicals, or confined spaces and for non-routine, hazardous routine works or those done by contractors.
The document discusses safe permits to work and provides examples of when they are required. It describes permits for hot work, confined space entry, excavations, and other hazardous jobs. Safe permits are used to identify hazards, require precautions, and protect workers from injury or accidents. Managers, supervisors and appointed persons are responsible for issuing permits and ensuring safety procedures are followed.
Work permit system, By Bimal Chandra Das, safety management, safety tips, sharing of safety knowledge, It is sharing of knowledge. By Bimal Chandra Das, Rtd. AGM (Safety), Bokaro Steel Plant,/ Bokaro. Kolkata
The document discusses the purpose and procedures of a work permit system. It is intended to ensure that all work is carried out safely by defining responsibilities, requiring appropriate training, and providing safety equipment. A work permit specifies the conditions and safety procedures that must be followed for particular jobs. It is required for non-routine and hazardous routine work, and when third parties are involved. A work permit must be prepared with relevant parties and approved before work begins to ensure all hazards are addressed.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Control Measures: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Method statement & Risk assessment developed, approved & communicated? ☐ ☐ ☐
Availability of rescue procedure and equipment? ☐ ☐ ☐
Operatives are trained and competent? ☐ ☐ ☐
Workplace appropriately illuminated ☐ ☐ ☐
Any high risk activity associated that requires PTW (i.e. hot work, CSE)? ☐ ☐ ☐
Forced ventilation provided? ☐ ☐ ☐
Are all necessary Permit approved and displayed at work location? ☐ ☐ ☐
Means of communication available? (Mobile, radio etc.) ☐ ☐ ☐
Safe access / Working Platform provided? ☐ ☐ ☐
Mandatory/specific good condition PPEs are available ☐ ☐ ☐
Availability of barricades/protection to prevent unauthorized or accidental entry? ☐ ☐ ☐
Life Line provided? ☐ ☐ ☐
Warning signs posted? ☐ ☐ ☐
Fall Protection equipment (e.g. full body harness) available? ☐ ☐ ☐
Availability of Fall protection arrangement? ☐ ☐ ☐
Other(s): ☐ ☐ ☐
Adequate Lighting provided? ☐ ☐ ☐
☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
The document discusses permit to work (PTW) procedures at an NGI training center. It defines what a PTW is, its purpose of ensuring work is planned and hazards identified, and that it is a legal document. It describes what types of work require a PTW, including hot work and cold work. It outlines the PTW process including initiation, authorization, cancellation. It defines roles and responsibilities of personnel involved in the PTW process. Finally, it discusses complementary permits that may be required for different types of work, such as electrical isolation or confined space entry.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Location / Area :
Panel No : Voltage:
Permit Validity:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
No: Checks Yes-No-NA Checks Yes-No-NA
ENERGIZATION (“Power On”) ISOLATION (“Power Off”)
1. Safety tool box briefing done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
2. Authorized personnel / operators available. ☐ ☐ ☐
Authorized personnel / operators available. ☐ ☐ ☐
3. Method statement/Risk assessment in place. ☐ ☐ ☐
Adjacent live areas protected. ☐ ☐ ☐
4. Safety Barriers in place and safety signage Displayed. ☐ ☐ ☐
PPE available, high voltage rubber gloves, Safety goggles and floor mat. ☐ ☐ ☐
5. Working area is well lighted. ☐ ☐ ☐
Isolation/Lock-out in place. ☐ ☐ ☐
6. Electrical instruments are available for any Purpose. ☐ ☐ ☐
Electrical circuits “proved” by calibrated Instrument and found out to be no power. ☐ ☐ ☐
7. Correct PPE available, high voltage rubber Gloves, safety goggles and floor mat. ☐ ☐ ☐
Unauthorized workers are cleared from the Area. ☐ ☐ ☐
8. Approved WIR for installation, testing and Termination are attached to the permit. ☐ ☐ ☐
Standby operatives in the event of contact With live circuits. ☐ ☐ ☐
9. Emergency light (Flashlight) available. ☐ ☐ ☐
Emergency light (Flashlight) available. ☐ ☐ ☐
10. Is live work absolutely necessary? ☐ ☐ ☐
Emergency response plan available ☐ ☐ ☐
11. Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☒ ☐ ☐
12. Power cable route from panel board to plant & equipment has been checked ☐ ☐ ☐
13 Emergency response plan available ☐ ☐ ☐
14 Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docxDwarika Bhushan Sharma
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Area / Location of edge protection or floor openings:
Purpose of removing:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Risk assessment/ method statement developed, approved and communicated? ☐ ☐ ☐
Availability of Fall protection arrangement (i.e. life line, etc.? ☐ ☐ ☐
Any high risk activity associated that requires PTW (i.e. hot work, Shaft Entry, CSE)? ☐ ☐ ☐
Adequate Lighting provided? ☐ ☐ ☐
Are all necessary Permit approved and displayed at work location? ☐ ☐ ☐
Availability of rescue procedure and equipment? ☐ ☐ ☐
Safe access / Working Platform provided? ☐ ☐ ☐
Mean of communication available? (Mobile, radio etc.) ☐ ☐ ☐
Availability of barricades/protection to prevent unauthorized or accidental entry? ☐ ☐ ☐
Helmet, Safety Shoes, Eye Protection, Hearing Protection and Cover All. ☐ ☐ ☐
Warning signs posted? ☐ ☐ ☐
Conduct Task Toolbox Talk prior to start the activity? ( TASK TBT TO BE ATTACHED) ☐ ☐ ☐
Exclusion zone for area below? ☐ ☐ ☐
Others (specify): ☐ ☐ ☐
Availability of Fall protection equipment (i.e. full body harness, etc.)? ☐ ☐ ☐
☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAhmadNadzir4
1. The document describes a work permit system which consists of standard procedures to ensure potentially hazardous routine and non-routine work is carried out safely.
2. A work permit specifies the work to be done, authorizes its start, and requires agreement of all concerned parties after reviewing safety measures.
3. A work permit is required for work involving hazards like oxygen deficiency, fires, chemicals, or confined spaces and for non-routine, hazardous routine works or those done by contractors.
The document discusses safe permits to work and provides examples of when they are required. It describes permits for hot work, confined space entry, excavations, and other hazardous jobs. Safe permits are used to identify hazards, require precautions, and protect workers from injury or accidents. Managers, supervisors and appointed persons are responsible for issuing permits and ensuring safety procedures are followed.
Work permit system, By Bimal Chandra Das, safety management, safety tips, sharing of safety knowledge, It is sharing of knowledge. By Bimal Chandra Das, Rtd. AGM (Safety), Bokaro Steel Plant,/ Bokaro. Kolkata
The document discusses the purpose and procedures of a work permit system. It is intended to ensure that all work is carried out safely by defining responsibilities, requiring appropriate training, and providing safety equipment. A work permit specifies the conditions and safety procedures that must be followed for particular jobs. It is required for non-routine and hazardous routine work, and when third parties are involved. A work permit must be prepared with relevant parties and approved before work begins to ensure all hazards are addressed.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Control Measures: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Method statement & Risk assessment developed, approved & communicated? ☐ ☐ ☐
Availability of rescue procedure and equipment? ☐ ☐ ☐
Operatives are trained and competent? ☐ ☐ ☐
Workplace appropriately illuminated ☐ ☐ ☐
Any high risk activity associated that requires PTW (i.e. hot work, CSE)? ☐ ☐ ☐
Forced ventilation provided? ☐ ☐ ☐
Are all necessary Permit approved and displayed at work location? ☐ ☐ ☐
Means of communication available? (Mobile, radio etc.) ☐ ☐ ☐
Safe access / Working Platform provided? ☐ ☐ ☐
Mandatory/specific good condition PPEs are available ☐ ☐ ☐
Availability of barricades/protection to prevent unauthorized or accidental entry? ☐ ☐ ☐
Life Line provided? ☐ ☐ ☐
Warning signs posted? ☐ ☐ ☐
Fall Protection equipment (e.g. full body harness) available? ☐ ☐ ☐
Availability of Fall protection arrangement? ☐ ☐ ☐
Other(s): ☐ ☐ ☐
Adequate Lighting provided? ☐ ☐ ☐
☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
This document provides details about safety precautions during a planned annual turnaround (ATR) scheduled for March 2009 at KRIBHCO SHYAM Fertiliser Ltd's ammonia and urea plants. It outlines major jobs like equipment replacement and repairs to be completed during the 19.5 day shutdown. Planning processes for the ATR include developing job lists, assessing risks, scheduling contractor work, and ensuring availability of materials, tools and trained workers. Safety systems such as work permits, observer programs and emergency response arrangements will be reinforced during the shutdown. Procedures for isolating and purging equipment, inspection checklists and startup testing are also part of the ATR process.
The document discusses the key steps and requirements for closing out and turning over a construction project to the owner. These include completing all remaining work, creating a punch list of unfinished items, cleaning up the job site, obtaining necessary permits and certificates of completion, providing operation and maintenance manuals and as-built drawings, transferring warranties and guarantees, and formally turning over the keys to the owner. Project closeout is an important final phase that ensures all contract requirements are fulfilled before the owner accepts the completed work.
The document discusses the key steps and requirements for closing out and turning over a construction project to the owner. These include completing all remaining work, creating a punch list of unfinished items, cleaning up the job site, obtaining necessary permits and certificates of completion, providing operation and maintenance manuals and as-built drawings, transferring warranties and guarantees, and formally turning over the keys to the owner. Project closeout is an important final phase that ensures all contract requirements are fulfilled before the owner accepts the completed work.
Engineering plant facilities 12 mechanics building preventive maintenance and...Luis Cabrera
The document discusses facilities management and maintenance. It defines facilities management as maintaining commercial, institutional and manufacturing buildings. It outlines the benefits of outsourcing facilities management such as a healthy, safe and clean environment. It also describes various roles in facilities management including engineers, technicians and management. Standard procedures for work orders, preventative maintenance and inspections are also outlined.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
Type :
Work at height without guardrails
Work at height on fragile surfaces
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator) Yes-No-NA
Method Statement and Risk Assessment developed, approved and communicated? ☐ ☐ ☐
Area barricaded & proper signage are posted? ☐ ☐ ☐
Qualified and briefed workers? ☐ ☐ ☐
PPE of workers available & inspected as per MS/RA? ☐ ☐ ☐
Tools/Equipment inspected? ☐ ☐ ☐
Safe means of access/ Egress? ☐ ☐ ☐
Lifeline available and inspected? ☐ ☐ ☐
Fragile surface covered / work surface protected? ☐ ☐ ☐
Dimensions of platform and restrain lanyard match safety requirement? ☐ ☐ ☐
Harness with double lanyard provided and its use briefed to workforce? ☐ ☐ ☐
Harness anchorage point checked? ☐ ☐ ☐
Load bearing capacity of anchoring point checked? ☐ ☐ ☐
Load bearing capacity of fragile service checked? ☐ ☐ ☐
Emergency response procedure and rescue plan are developed & communicated? ☐ ☐ ☐
Others ( Specify) ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature : Time:
Ahmed Samir Abdelnaeem has applied for a position as a control engineer. He has over 10 years of experience working in instrumentation and control engineering. His experience includes working for GE and Alstom in various countries installing, maintaining and troubleshooting gas turbine control systems. He has a bachelor's degree in electronics and communication engineering and has received extensive training in gas turbine control systems.
Chk construction site_inspection-checklistimaduddin91
This document is a construction site inspection checklist. It lists various items that should be inspected on a construction site to ensure safety. The items include barricades isolating the work area from traffic, condition of steps and ladders, induction and sign-in of personnel, display of relevant documents, condition of electrical equipment and leads, emergency access and egress, use of residual current devices, condition of entrances and walkways, availability and condition of fire equipment, labeling and storage of chemicals, availability of first aid kits, awareness of safety procedures, use of correct safety gear, and condition of machinery and equipment. The inspector is to check each item and indicate with a check, x, or N/A if the item is satisfactory
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Area / Location of Mast Climber or Cradle:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
Serial No. of Mast Climber or Cradle: No. of persons working on Mast Climber or Cradle:
Safe Working Load of Mast Climber or Cradle:
Other(s):
3. Mast Climber or Cradle Operators Details: (To be filled by initiator/originator)
Operator Contact:
Rigger-1 Contact:
Rigger-2 Contact:
Rigger-3 Contact:
4. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Risk assessment/ method statement developed, approved and communicated? ☐ ☐ ☐
Area below mast climber or cradle free from personnel and barriers in place when working? ☐ ☐ ☐
Mast climber or cradle have a valid 3rd party certificate and displayed? ☐ ☐ ☐
All mast climber or cradle rigging points secure to building? ☐ ☐ ☐
Operator competent and certified? ☐ ☐ ☐
Are the mast climber or cradles brakes working? ☐ ☐ ☐
Wire ropes in good conditions? ☐ ☐ ☐
Proper barricade and signage are posted? ☐ ☐ ☐
Counterweights sufficient and properly anchored/secured? ☐ ☐ ☐
Mast climber or cradle SWL displayed?
☐ ☐ ☐
Electrical wires are in good conditions and free from obstructions? ☐ ☐ ☐
Access and egress will be on ground level? ☐ ☐ ☐
Anchor point for safety harness available and in good condition? ☐ ☐ ☐
Rescue plan available and communicated? ☐ ☐ ☐
Personnel working in mast climber cradle wearing safety harness and clipped on? ☐ ☐ ☐
Others (specify): ☐ ☐ ☐
5. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
6. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
7. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
The document discusses permit to work (PTW), which is a formal safety system used to control potentially hazardous work activities. It outlines the PTW process involving the permit applicant, responsible asset holder supervisor, asset holder site supervisor, and permit holder. The PTW contains details of the job, required documents like a job hazard analysis, and safety precautions. Certificates and personal protective equipment requirements are also specified. The validity, handover, and closure of the PTW are further described.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE TEST AND IS NOT EXTENDABLE
Description of Task:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
Design Pressure of Pipeline: Operating Pressure:
Testing Pressure: Pressure Time:
3. Pressure Testing Details: (To be filled by initiator/originator)
Type of Work Request ☐ Hydrostatic
☐ Pneumatic
☐ Gravity Testing
☐ Other :
Type of Equipment testing: ☐ Pipeline
☐ GRP ☐ AC ☐ others:
☐ Tanks
☐ Hose
☐ Other(s)
Dimensions: Pipeline/Tank/Hose
☐ Diameter:
☐ Thickness:
☐ Length:
☐ Other(s):
Attachment(s): ☐ Plan
☐ Sketch
☐ Drawing (approved)
☐ Method Statement & Risk Assessment
☐ Authority Approvals (NOCs)
☐ Road Traffic Approval (if applicable)
☐ Other(s)
4. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Is the segment of pipeline under testing isolated from service by closing nearest valves? ☐ ☐ ☐
Risk assessment/ method statement developed, approved and communicated? ☐ ☐ ☐
Is the Liquid/Gas vented/removed from the pipeline? ☐ ☐ ☐
Testing & monitoring of the environment prior to entry? ☐ ☐ ☐
Test Head and End plug/end point are properly sealed/secured/tighten. ☐ ☐ ☐
Emergency response procedure and rescue plan are developed & communicated? ☐ ☐ ☐
Is Air vented completely by pumping and filling the water in the testing segment pipeline without pressurizing? ☐ ☐ ☐
Operatives are trained and competent? ☐ ☐ ☐
Pressure testing equipment in good condition with available safe guards ☐ ☐ ☐
Provision of vigilance supervision? ☐ ☐ ☐
Flexible pipe/hose are in good condition and connections are safely clamped ☐ ☐ ☐
Proper barricade and signage are posted? ☐ ☐ ☐
Pressure testing gauge have valid calibration. ☐ ☐ ☐
Safe means of access/egress provided? ☐ ☐ ☐
Pressure testing gauge/ valve are in safe & accessible place outside restricted/isolated area ☐ ☐ ☐
Means of communication available? ☐ ☐ ☐
Is the testing pipeline/vessel/tank are properly isolated ☐ ☐ ☐
Electrical equipment & connections safe? ☐ ☐ ☐
Is confined space PTW required & obtained? ☐ ☐ ☐
Other(s) ☐ ☐ ☐
5. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
6. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
The document outlines lock out tag out (LOTO) procedures for electrical work on the Opera Grand Tower Project in Downtown Dubai. It assigns responsibilities for the LOTO system and describes permit requirements and processes. Key elements include appointing authorized engineers and competent persons, implementing safe isolation procedures before work, maintaining a permit log book, and having emergency response plans and contact details. The goal is to ensure electrical hazards are controlled whenever employees or others could be exposed to risks like electric shock or burns during work.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Hot Work Details: (To be filled by initiator/originator)
Hot Work Operator Contact:
Fire Watcher Contact:
Type of Hot Work: ☐ Welding
☐ Oxy Acetylene ☐ Electric Arc
☐ Gas Cutting
☐ Oxy Acetylene ☐ LPG
☐ Grinding :
☐ Disc Cutting:
☐ Other:
Fire Fighting Equipment Required: ☐ Fire Extinguisher:
☐ Hose Reel:
☐ Fire Blanket:
☐ Water:
☐ Sand:
☐ Other(s):
Specific PPEs Required: ☐ Hearing Protection:
☐ Ear Plug ☐ Ear Muff
☐ Face Shield/ Visor:
☐ Welding Suit:
☐ Gloves (Type):
☐ Dark welding goggles with appropriate lens number: ____________ ☐ Mask
☐ Dust ☐ Chemical ☐ Respirator
☐ Safety Boots:
☐ Full Body Harness:
☐ Apron:
☐ Others: __________________
4. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Risk assessment/ method statement developed, approved and communicated? ☐ ☐ ☐
Arc welding machine is in good condition ☐ ☐ ☐
Operator is competent and certified ☐ ☐ ☐
welding cable, connector, clamp and rod holder are in good condition ☐ ☐ ☐
Stand-by fire watcher is trained & competent ☐ ☐ ☐
Cutting/Grinding machine discs fitted with guards ☐ ☐ ☐
Area immediately below the wok spot is cleared from all Combustible materials ☐ ☐ ☐
Power tools monthly inspection done and color coded ☐ ☐ ☐
All flammable materials/chemical cleared from the hot work area ☐ ☐ ☐
Power tools accessories available & in good condition (key, extension cord, sockets etc.) ☐ ☐ ☐
Firefighting equipment available at welding area ☐ ☐ ☐
Environmental aspect, impacts and control measures are in place ☐ ☐ ☐
Tin sheet/Fire blanket are provided to prevent sparks from spreading ☐ ☐ ☐
Provision of vigilance supervision ☐ ☐ ☐
Welding Area screening done to prevent UV rays ☐ ☐ ☐
Safe means of access/egress provided? ☐ ☐ ☐
Flask back arrester installed to the gas cylinders ☐ ☐ ☐
Proper barricade and signage are posted? ☐ ☐ ☐
Gas cylinders and fittings are free from cracks, grease etc. ☐ ☐ ☐
Is confined space PTW required & obtained? ☐ ☐ ☐
Gas cylinders are kept upright and secured ☐ ☐ ☐
Other(s) if Any
☐ ☐ ☐
5. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Excavation Details: (To be filled by initiator/originator)
Location of Excavation:
Click here to enter text.
Excavation Dimensions:
☐ Depth: Enter Depth
☐ Width: Enter Width
☐ Length: Enter Length
☐ Other(s): Enter Others
Type of Excavation: ☐ Ditches
☐ Trenches
☐ Shafts
☐ Tunneling (drilling /Boring)
☐ Well
☐ Post Driving
☐ Other(s): Enter Others
Excavation Tools/ Equipment ☐ Hand Shovel
☐ Pickaxe
☐ Excavator
☐ Shovel
☐ Skid steer Loader
☐ Backhoe Loader
☐ Other(s): Enter Others
Identified Underground Service(s): ☐ Electrical
☐ Sewer/ Water
☐ Drainage
☐ Communication/Data
☐ Gas
☐ Other(s): Enter Others
Underground Condition(s): ☐ Water Table, Depth: Enter Depth
☐ Tanks
☐ Vaults
☐ Wells
☐ Void & structure
☐ Chemicals
☐ Volatile Fuels
☐ Toxic Gases
☐ Other(s): Enter Others
Excavation Protection(s) By: ☐ Slope, (in degrees from horizontal) Enter Angle as per soil condition
☐ Benching
☐ Sheet, Waling, Strutting
☐ Soldier piling
☐ Void & structure
☐ Proprietary support system
☐ Other(s): Enter Others
Notification(s) given to( If Required): ☐ Relevant Authorities: Click here to enter text.
☐ Utility Service Provider(s): Click here to enter text.
☐ Owner Of Adjoining Properties :
☐ Other(s): Click here to enter text.
4. Control Measures: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Applicable NOCs available ☐ ☐ ☐
Safe means of access/egress provided ☐ ☐ ☐
Method statement & Risk assessment developed, approved & communicated? ☐ ☐ ☐
Ladder are secured, fixed & maintained ☐ ☐ ☐
Operatives are trained and competent? ☐ ☐ ☐
Workplace appropriately illuminated ☐ ☐ ☐
Site is surveyed correctly, marked and identified ☐ ☐ ☐
Ventilation means are available ☐ ☐ ☐
All underground services checked & validated ☐ ☐ ☐
Proper signage are posted ☐ ☐ ☐
Certified cable detector used to verify above ☐ ☐ ☐
Adequate barricade to prevent fall of person/vehicle ☐ ☐ ☐
Ground conditions are examined with bore/trial pit ☐ ☐ ☐
Flash light are fixed on the barricades ☐ ☐ ☐
Water table is located ☐ ☐ ☐
Trained flagman deputed to caution traffic ☐ ☐ ☐
Adjacent properties/services exist? Inspected? ☐ ☐ ☐
Adequate traffic diversion is provided ☐ ☐ ☐
Stability of adjacent property structure ensured/secured ☐ ☐ ☐
Trained banksman available for plants ☐ ☐ ☐
Adequate arrangement to prevent Cave-in ☐ ☐ ☐
Mandatory/specific good condition PPEs are available ☐ ☐ ☐
Dewatering arrangem
Dear Sir/ Madam,
Good day!
Hope my Mail finds you well, and greetings to your good-self and your respected family,
I am Manoj Kumar and i have 11 years of working experience in instrumentation and i have attached my CV and all scanned documents along with this mail kindly acknowledge me once you receive my mail.
Skype id : manojkumar2870
Notice Period: Immediate
Thanks With Best Regards,
Manoj Kumar
M: +917506966847
Email:manojk940@yahoo.com
This document is a permit to work form for Banu Mukhtar Contracting Pvt. Ltd. requesting permission to perform work at the Novatex Plant in Faisalabad, Pakistan for two weeks. The form details the type of work, location, hazards, required controls, permits, and personal protective equipment. Key personnel must sign off on the completed form before and after the authorized work is performed.
The document provides instructions and assessment requirements for students to develop a Safe Work Method Statement (SWMS) for removing and replacing gutters on a house. It includes templates for the SWMS, with sections to identify hazards, control measures, implementation details, and a review process. Students will be assessed on developing the SWMS that complies with relevant legislation and standards. They are allowed two attempts and must upload the completed SWMS into an online system.
The document is a curriculum vitae for a position of Safety Coordinator and Confined Space Assessor. It details the applicant's work experience over 15 years in safety roles on construction projects in Singapore. Responsibilities included conducting inspections, ensuring permits, monitoring safety compliance, and assessing confined spaces. Employers included developers, contractors, and companies in industries like oil and gas, utilities, and transportation.
This document is a contractor project specific safety plan for work being done for PG&E. It includes instructions for completing the form, general project information, leadership and oversight plans, personal protective equipment requirements, a general safety checklist covering various hazards and safety requirements, a risk assessment and hazard identification section, and a section on hazard communication and training requirements. The contractor must submit this completed plan to PG&E for approval before starting work on the project.
The document provides instructions and assessment materials for a student to develop a Safe Work Method Statement (SWMS) for removing and replacing gutters on a house. It includes:
- An overview of the assessment task and requirements
- A checklist for skills to be demonstrated in developing the SWMS
- Templates for the SWMS content covering work details, hazards identified and control measures
- Guidance on implementing and reviewing the SWMS
The goal is for the student to identify all risks and hazards of the work, and complete the SWMS ensuring compliance with relevant legislation and standards for working safely at heights.
This document provides instructions and guidelines for a student completing an assessment to develop a Safe Work Method Statement (SWMS) for working at heights. It includes details of the assessment such as allowing 2 hours to complete it, conducting it under teacher supervision, and being allowed two attempts. The document provides a checklist of skills to be demonstrated and feedback sections for the assessor. It also provides information on developing a SWMS, including consulting workers, identifying hazards and controls, and ensuring the SWMS is followed.
This document provides details about safety precautions during a planned annual turnaround (ATR) scheduled for March 2009 at KRIBHCO SHYAM Fertiliser Ltd's ammonia and urea plants. It outlines major jobs like equipment replacement and repairs to be completed during the 19.5 day shutdown. Planning processes for the ATR include developing job lists, assessing risks, scheduling contractor work, and ensuring availability of materials, tools and trained workers. Safety systems such as work permits, observer programs and emergency response arrangements will be reinforced during the shutdown. Procedures for isolating and purging equipment, inspection checklists and startup testing are also part of the ATR process.
The document discusses the key steps and requirements for closing out and turning over a construction project to the owner. These include completing all remaining work, creating a punch list of unfinished items, cleaning up the job site, obtaining necessary permits and certificates of completion, providing operation and maintenance manuals and as-built drawings, transferring warranties and guarantees, and formally turning over the keys to the owner. Project closeout is an important final phase that ensures all contract requirements are fulfilled before the owner accepts the completed work.
The document discusses the key steps and requirements for closing out and turning over a construction project to the owner. These include completing all remaining work, creating a punch list of unfinished items, cleaning up the job site, obtaining necessary permits and certificates of completion, providing operation and maintenance manuals and as-built drawings, transferring warranties and guarantees, and formally turning over the keys to the owner. Project closeout is an important final phase that ensures all contract requirements are fulfilled before the owner accepts the completed work.
Engineering plant facilities 12 mechanics building preventive maintenance and...Luis Cabrera
The document discusses facilities management and maintenance. It defines facilities management as maintaining commercial, institutional and manufacturing buildings. It outlines the benefits of outsourcing facilities management such as a healthy, safe and clean environment. It also describes various roles in facilities management including engineers, technicians and management. Standard procedures for work orders, preventative maintenance and inspections are also outlined.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
Type :
Work at height without guardrails
Work at height on fragile surfaces
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator) Yes-No-NA
Method Statement and Risk Assessment developed, approved and communicated? ☐ ☐ ☐
Area barricaded & proper signage are posted? ☐ ☐ ☐
Qualified and briefed workers? ☐ ☐ ☐
PPE of workers available & inspected as per MS/RA? ☐ ☐ ☐
Tools/Equipment inspected? ☐ ☐ ☐
Safe means of access/ Egress? ☐ ☐ ☐
Lifeline available and inspected? ☐ ☐ ☐
Fragile surface covered / work surface protected? ☐ ☐ ☐
Dimensions of platform and restrain lanyard match safety requirement? ☐ ☐ ☐
Harness with double lanyard provided and its use briefed to workforce? ☐ ☐ ☐
Harness anchorage point checked? ☐ ☐ ☐
Load bearing capacity of anchoring point checked? ☐ ☐ ☐
Load bearing capacity of fragile service checked? ☐ ☐ ☐
Emergency response procedure and rescue plan are developed & communicated? ☐ ☐ ☐
Others ( Specify) ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature : Time:
Ahmed Samir Abdelnaeem has applied for a position as a control engineer. He has over 10 years of experience working in instrumentation and control engineering. His experience includes working for GE and Alstom in various countries installing, maintaining and troubleshooting gas turbine control systems. He has a bachelor's degree in electronics and communication engineering and has received extensive training in gas turbine control systems.
Chk construction site_inspection-checklistimaduddin91
This document is a construction site inspection checklist. It lists various items that should be inspected on a construction site to ensure safety. The items include barricades isolating the work area from traffic, condition of steps and ladders, induction and sign-in of personnel, display of relevant documents, condition of electrical equipment and leads, emergency access and egress, use of residual current devices, condition of entrances and walkways, availability and condition of fire equipment, labeling and storage of chemicals, availability of first aid kits, awareness of safety procedures, use of correct safety gear, and condition of machinery and equipment. The inspector is to check each item and indicate with a check, x, or N/A if the item is satisfactory
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Area / Location of Mast Climber or Cradle:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
Serial No. of Mast Climber or Cradle: No. of persons working on Mast Climber or Cradle:
Safe Working Load of Mast Climber or Cradle:
Other(s):
3. Mast Climber or Cradle Operators Details: (To be filled by initiator/originator)
Operator Contact:
Rigger-1 Contact:
Rigger-2 Contact:
Rigger-3 Contact:
4. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Risk assessment/ method statement developed, approved and communicated? ☐ ☐ ☐
Area below mast climber or cradle free from personnel and barriers in place when working? ☐ ☐ ☐
Mast climber or cradle have a valid 3rd party certificate and displayed? ☐ ☐ ☐
All mast climber or cradle rigging points secure to building? ☐ ☐ ☐
Operator competent and certified? ☐ ☐ ☐
Are the mast climber or cradles brakes working? ☐ ☐ ☐
Wire ropes in good conditions? ☐ ☐ ☐
Proper barricade and signage are posted? ☐ ☐ ☐
Counterweights sufficient and properly anchored/secured? ☐ ☐ ☐
Mast climber or cradle SWL displayed?
☐ ☐ ☐
Electrical wires are in good conditions and free from obstructions? ☐ ☐ ☐
Access and egress will be on ground level? ☐ ☐ ☐
Anchor point for safety harness available and in good condition? ☐ ☐ ☐
Rescue plan available and communicated? ☐ ☐ ☐
Personnel working in mast climber cradle wearing safety harness and clipped on? ☐ ☐ ☐
Others (specify): ☐ ☐ ☐
5. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
6. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
7. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
The document discusses permit to work (PTW), which is a formal safety system used to control potentially hazardous work activities. It outlines the PTW process involving the permit applicant, responsible asset holder supervisor, asset holder site supervisor, and permit holder. The PTW contains details of the job, required documents like a job hazard analysis, and safety precautions. Certificates and personal protective equipment requirements are also specified. The validity, handover, and closure of the PTW are further described.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE TEST AND IS NOT EXTENDABLE
Description of Task:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
Design Pressure of Pipeline: Operating Pressure:
Testing Pressure: Pressure Time:
3. Pressure Testing Details: (To be filled by initiator/originator)
Type of Work Request ☐ Hydrostatic
☐ Pneumatic
☐ Gravity Testing
☐ Other :
Type of Equipment testing: ☐ Pipeline
☐ GRP ☐ AC ☐ others:
☐ Tanks
☐ Hose
☐ Other(s)
Dimensions: Pipeline/Tank/Hose
☐ Diameter:
☐ Thickness:
☐ Length:
☐ Other(s):
Attachment(s): ☐ Plan
☐ Sketch
☐ Drawing (approved)
☐ Method Statement & Risk Assessment
☐ Authority Approvals (NOCs)
☐ Road Traffic Approval (if applicable)
☐ Other(s)
4. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Is the segment of pipeline under testing isolated from service by closing nearest valves? ☐ ☐ ☐
Risk assessment/ method statement developed, approved and communicated? ☐ ☐ ☐
Is the Liquid/Gas vented/removed from the pipeline? ☐ ☐ ☐
Testing & monitoring of the environment prior to entry? ☐ ☐ ☐
Test Head and End plug/end point are properly sealed/secured/tighten. ☐ ☐ ☐
Emergency response procedure and rescue plan are developed & communicated? ☐ ☐ ☐
Is Air vented completely by pumping and filling the water in the testing segment pipeline without pressurizing? ☐ ☐ ☐
Operatives are trained and competent? ☐ ☐ ☐
Pressure testing equipment in good condition with available safe guards ☐ ☐ ☐
Provision of vigilance supervision? ☐ ☐ ☐
Flexible pipe/hose are in good condition and connections are safely clamped ☐ ☐ ☐
Proper barricade and signage are posted? ☐ ☐ ☐
Pressure testing gauge have valid calibration. ☐ ☐ ☐
Safe means of access/egress provided? ☐ ☐ ☐
Pressure testing gauge/ valve are in safe & accessible place outside restricted/isolated area ☐ ☐ ☐
Means of communication available? ☐ ☐ ☐
Is the testing pipeline/vessel/tank are properly isolated ☐ ☐ ☐
Electrical equipment & connections safe? ☐ ☐ ☐
Is confined space PTW required & obtained? ☐ ☐ ☐
Other(s) ☐ ☐ ☐
5. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
6. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
The document outlines lock out tag out (LOTO) procedures for electrical work on the Opera Grand Tower Project in Downtown Dubai. It assigns responsibilities for the LOTO system and describes permit requirements and processes. Key elements include appointing authorized engineers and competent persons, implementing safe isolation procedures before work, maintaining a permit log book, and having emergency response plans and contact details. The goal is to ensure electrical hazards are controlled whenever employees or others could be exposed to risks like electric shock or burns during work.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Hot Work Details: (To be filled by initiator/originator)
Hot Work Operator Contact:
Fire Watcher Contact:
Type of Hot Work: ☐ Welding
☐ Oxy Acetylene ☐ Electric Arc
☐ Gas Cutting
☐ Oxy Acetylene ☐ LPG
☐ Grinding :
☐ Disc Cutting:
☐ Other:
Fire Fighting Equipment Required: ☐ Fire Extinguisher:
☐ Hose Reel:
☐ Fire Blanket:
☐ Water:
☐ Sand:
☐ Other(s):
Specific PPEs Required: ☐ Hearing Protection:
☐ Ear Plug ☐ Ear Muff
☐ Face Shield/ Visor:
☐ Welding Suit:
☐ Gloves (Type):
☐ Dark welding goggles with appropriate lens number: ____________ ☐ Mask
☐ Dust ☐ Chemical ☐ Respirator
☐ Safety Boots:
☐ Full Body Harness:
☐ Apron:
☐ Others: __________________
4. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Risk assessment/ method statement developed, approved and communicated? ☐ ☐ ☐
Arc welding machine is in good condition ☐ ☐ ☐
Operator is competent and certified ☐ ☐ ☐
welding cable, connector, clamp and rod holder are in good condition ☐ ☐ ☐
Stand-by fire watcher is trained & competent ☐ ☐ ☐
Cutting/Grinding machine discs fitted with guards ☐ ☐ ☐
Area immediately below the wok spot is cleared from all Combustible materials ☐ ☐ ☐
Power tools monthly inspection done and color coded ☐ ☐ ☐
All flammable materials/chemical cleared from the hot work area ☐ ☐ ☐
Power tools accessories available & in good condition (key, extension cord, sockets etc.) ☐ ☐ ☐
Firefighting equipment available at welding area ☐ ☐ ☐
Environmental aspect, impacts and control measures are in place ☐ ☐ ☐
Tin sheet/Fire blanket are provided to prevent sparks from spreading ☐ ☐ ☐
Provision of vigilance supervision ☐ ☐ ☐
Welding Area screening done to prevent UV rays ☐ ☐ ☐
Safe means of access/egress provided? ☐ ☐ ☐
Flask back arrester installed to the gas cylinders ☐ ☐ ☐
Proper barricade and signage are posted? ☐ ☐ ☐
Gas cylinders and fittings are free from cracks, grease etc. ☐ ☐ ☐
Is confined space PTW required & obtained? ☐ ☐ ☐
Gas cylinders are kept upright and secured ☐ ☐ ☐
Other(s) if Any
☐ ☐ ☐
5. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Excavation Details: (To be filled by initiator/originator)
Location of Excavation:
Click here to enter text.
Excavation Dimensions:
☐ Depth: Enter Depth
☐ Width: Enter Width
☐ Length: Enter Length
☐ Other(s): Enter Others
Type of Excavation: ☐ Ditches
☐ Trenches
☐ Shafts
☐ Tunneling (drilling /Boring)
☐ Well
☐ Post Driving
☐ Other(s): Enter Others
Excavation Tools/ Equipment ☐ Hand Shovel
☐ Pickaxe
☐ Excavator
☐ Shovel
☐ Skid steer Loader
☐ Backhoe Loader
☐ Other(s): Enter Others
Identified Underground Service(s): ☐ Electrical
☐ Sewer/ Water
☐ Drainage
☐ Communication/Data
☐ Gas
☐ Other(s): Enter Others
Underground Condition(s): ☐ Water Table, Depth: Enter Depth
☐ Tanks
☐ Vaults
☐ Wells
☐ Void & structure
☐ Chemicals
☐ Volatile Fuels
☐ Toxic Gases
☐ Other(s): Enter Others
Excavation Protection(s) By: ☐ Slope, (in degrees from horizontal) Enter Angle as per soil condition
☐ Benching
☐ Sheet, Waling, Strutting
☐ Soldier piling
☐ Void & structure
☐ Proprietary support system
☐ Other(s): Enter Others
Notification(s) given to( If Required): ☐ Relevant Authorities: Click here to enter text.
☐ Utility Service Provider(s): Click here to enter text.
☐ Owner Of Adjoining Properties :
☐ Other(s): Click here to enter text.
4. Control Measures: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Applicable NOCs available ☐ ☐ ☐
Safe means of access/egress provided ☐ ☐ ☐
Method statement & Risk assessment developed, approved & communicated? ☐ ☐ ☐
Ladder are secured, fixed & maintained ☐ ☐ ☐
Operatives are trained and competent? ☐ ☐ ☐
Workplace appropriately illuminated ☐ ☐ ☐
Site is surveyed correctly, marked and identified ☐ ☐ ☐
Ventilation means are available ☐ ☐ ☐
All underground services checked & validated ☐ ☐ ☐
Proper signage are posted ☐ ☐ ☐
Certified cable detector used to verify above ☐ ☐ ☐
Adequate barricade to prevent fall of person/vehicle ☐ ☐ ☐
Ground conditions are examined with bore/trial pit ☐ ☐ ☐
Flash light are fixed on the barricades ☐ ☐ ☐
Water table is located ☐ ☐ ☐
Trained flagman deputed to caution traffic ☐ ☐ ☐
Adjacent properties/services exist? Inspected? ☐ ☐ ☐
Adequate traffic diversion is provided ☐ ☐ ☐
Stability of adjacent property structure ensured/secured ☐ ☐ ☐
Trained banksman available for plants ☐ ☐ ☐
Adequate arrangement to prevent Cave-in ☐ ☐ ☐
Mandatory/specific good condition PPEs are available ☐ ☐ ☐
Dewatering arrangem
Dear Sir/ Madam,
Good day!
Hope my Mail finds you well, and greetings to your good-self and your respected family,
I am Manoj Kumar and i have 11 years of working experience in instrumentation and i have attached my CV and all scanned documents along with this mail kindly acknowledge me once you receive my mail.
Skype id : manojkumar2870
Notice Period: Immediate
Thanks With Best Regards,
Manoj Kumar
M: +917506966847
Email:manojk940@yahoo.com
This document is a permit to work form for Banu Mukhtar Contracting Pvt. Ltd. requesting permission to perform work at the Novatex Plant in Faisalabad, Pakistan for two weeks. The form details the type of work, location, hazards, required controls, permits, and personal protective equipment. Key personnel must sign off on the completed form before and after the authorized work is performed.
The document provides instructions and assessment requirements for students to develop a Safe Work Method Statement (SWMS) for removing and replacing gutters on a house. It includes templates for the SWMS, with sections to identify hazards, control measures, implementation details, and a review process. Students will be assessed on developing the SWMS that complies with relevant legislation and standards. They are allowed two attempts and must upload the completed SWMS into an online system.
The document is a curriculum vitae for a position of Safety Coordinator and Confined Space Assessor. It details the applicant's work experience over 15 years in safety roles on construction projects in Singapore. Responsibilities included conducting inspections, ensuring permits, monitoring safety compliance, and assessing confined spaces. Employers included developers, contractors, and companies in industries like oil and gas, utilities, and transportation.
This document is a contractor project specific safety plan for work being done for PG&E. It includes instructions for completing the form, general project information, leadership and oversight plans, personal protective equipment requirements, a general safety checklist covering various hazards and safety requirements, a risk assessment and hazard identification section, and a section on hazard communication and training requirements. The contractor must submit this completed plan to PG&E for approval before starting work on the project.
The document provides instructions and assessment materials for a student to develop a Safe Work Method Statement (SWMS) for removing and replacing gutters on a house. It includes:
- An overview of the assessment task and requirements
- A checklist for skills to be demonstrated in developing the SWMS
- Templates for the SWMS content covering work details, hazards identified and control measures
- Guidance on implementing and reviewing the SWMS
The goal is for the student to identify all risks and hazards of the work, and complete the SWMS ensuring compliance with relevant legislation and standards for working safely at heights.
This document provides instructions and guidelines for a student completing an assessment to develop a Safe Work Method Statement (SWMS) for working at heights. It includes details of the assessment such as allowing 2 hours to complete it, conducting it under teacher supervision, and being allowed two attempts. The document provides a checklist of skills to be demonstrated and feedback sections for the assessor. It also provides information on developing a SWMS, including consulting workers, identifying hazards and controls, and ensuring the SWMS is followed.
Similar to Work at Heights_BMU_ Work Permisdfdsfsdfdsft.pdf (20)
Welcome to ASP Cranes, your trusted partner for crane solutions in Raipur, Chhattisgarh! With years of experience and a commitment to excellence, we offer a comprehensive range of crane services tailored to meet your lifting and material handling needs.
At ASP Cranes, we understand the importance of reliable and efficient crane operations in various industries, from construction and manufacturing to logistics and infrastructure development. That's why we strive to deliver top-notch solutions that enhance productivity, safety, and cost-effectiveness for our clients.
Our services include:
Crane Rental: Whether you need a crawler crane for heavy lifting or a hydraulic crane for versatile operations, we have a diverse fleet of well-maintained cranes available for rent. Our rental options are flexible and can be customized to suit your project requirements.
Crane Sales: Looking to invest in a crane for your business? We offer a wide selection of new and used cranes from leading manufacturers, ensuring you find the perfect equipment to match your needs and budget.
Crane Maintenance and Repair: To ensure optimal performance and safety, regular maintenance and timely repairs are essential for cranes. Our team of skilled technicians provides comprehensive maintenance and repair services to keep your equipment running smoothly and minimize downtime.
Crane Operator Training: Proper training is crucial for safe and efficient crane operation. We offer specialized training programs conducted by certified instructors to equip operators with the skills and knowledge they need to handle cranes effectively.
Custom Solutions: We understand that every project is unique, which is why we offer custom crane solutions tailored to your specific requirements. Whether you need modifications, attachments, or specialized equipment, we can design and implement solutions that meet your needs.
At ASP Cranes, customer satisfaction is our top priority. We are dedicated to delivering reliable, cost-effective, and innovative crane solutions that exceed expectations. Contact us today to learn more about our services and how we can support your project in Raipur, Chhattisgarh, and beyond. Let ASP Cranes be your trusted partner for all your crane needs!
Ever been troubled by the blinking sign and didn’t know what to do?
Here’s a handy guide to dashboard symbols so that you’ll never be confused again!
Save them for later and save the trouble!
What Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill RoadsSprinter Gurus
Unlock the secrets behind your Mercedes Sprinter's uphill power loss with our comprehensive presentation. From fuel filter blockages to turbocharger troubles, we uncover the culprits and empower you to reclaim your vehicle's peak performance. Conquer every ascent with confidence and ensure a thrilling journey every time.
Understanding Catalytic Converter Theft:
What is a Catalytic Converter?: Learn about the function of catalytic converters in vehicles and why they are targeted by thieves.
Why are They Stolen?: Discover the valuable metals inside catalytic converters (such as platinum, palladium, and rhodium) that make them attractive to criminals.
Steps to Prevent Catalytic Converter Theft:
Parking Strategies: Tips on where and how to park your vehicle to reduce the risk of theft, such as parking in well-lit areas or secure garages.
Protective Devices: Overview of various anti-theft devices available, including catalytic converter locks, shields, and alarms.
Etching and Marking: The benefits of etching your vehicle’s VIN on the catalytic converter or using a catalytic converter marking kit to make it traceable and less appealing to thieves.
Surveillance and Monitoring: Recommendations for using security cameras and motion-sensor lights to deter thieves.
Statistics and Insights:
Theft Rates by Borough: Analysis of data to determine which borough in NYC experiences the highest rate of catalytic converter thefts.
Recent Trends: Current trends and patterns in catalytic converter thefts to help you stay aware of emerging hotspots and tactics used by thieves.
Benefits of This Presentation:
Awareness: Increase your awareness about catalytic converter theft and its impact on vehicle owners.
Practical Tips: Gain actionable insights and tips to effectively prevent catalytic converter theft.
Local Insights: Understand the specific risks in different NYC boroughs, helping you take targeted preventive measures.
This presentation aims to equip you with the knowledge and tools needed to protect your vehicle from catalytic converter theft, ensuring you are prepared and proactive in safeguarding your property.
Expanding Access to Affordable At-Home EV Charging by Vanessa WarheitForth
Vanessa Warheit, Co-Founder of EV Charging for All, gave this presentation at the Forth Addressing The Challenges of Charging at Multi-Family Housing webinar on June 11, 2024.
EV Charging at MFH Properties by Whitaker JamiesonForth
Whitaker Jamieson, Senior Specialist at Forth, gave this presentation at the Forth Addressing The Challenges of Charging at Multi-Family Housing webinar on June 11, 2024.
Implementing ELDs or Electronic Logging Devices is slowly but surely becoming the norm in fleet management. Why? Well, integrating ELDs and associated connected vehicle solutions like fleet tracking devices lets businesses and their in-house fleet managers reap several benefits. Check out the post below to learn more.
1. HSE Documents 1
Work at Heights Permit
Building Maintenance Units (BMU)
Ref. No:
Project Engineer:
Issue Date: Project Manager:
Permit Number: Date:
Site:
Location:
Contractor/
Employee:
Phone:
This permit is valid from: am/pm On:
This permit is valid until: am/pm On:
Description of works:
A Safe Work Method Statement (SWMS), Job Safety Analysis (JSA) and/or Safe Work Procedure (SWP)
has been provided and is attached to this ‘work permit’ Yes No
Note: The following section of this permit must be completed and signed by the authorized
person(s) before work is to proceed and only work listed above may be completed.
The following equipment will be used during the works (all equipment to be used is in good working order and is fit for
use):
Elevated work platform
(i.e. scissor lift)
Roof and/or ladder anchor
points
Ropes and harness
Step ladder Extension ladder Edge protection
Mobile scaffold Appropriate footwear Safety net
Other (please specify): BMU
The following services have been isolated for the duration of the works:
Smoke / thermal detectors Pipes, tanks and valves
Electrical Outlets /
appliances
Other (please specify):
The following control measures have been implemented for the duration of the works:
Barricades Signage Spotter
Other (please specify):
CENTRAL OFFICE USE ONLY
/ /2020
2. HSE Documents 2
The following environmental factors have been assessed and are suitable for the works:
Weather/wind Stored material/vegetation
Other (please specify):
This permit should be prominently displayed at the worksite
Authorization
Permit Issued To:
(Print name) (Signature) (Date)
Permit Issued By:
(Print name) (Signature) (Date)
Cancellation/completion of the permit
Permit cancelled/returned by:
(Print name) (Signature)
Cancelled/returned at: am/pm On:
Reason for cancellation :
Final Sign Off
The work site has been inspected by me at the cancellation/completion of the work at heights and declared safe for
normal operations to resume.
Azhar
(Print name) (Signature) (Date)
Official use only:
Project Manager Signatures:
Project Engineer: Signatures:
HSE Officer: Signatures: