CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
LOCATION:
CONTRACT/CWA #:
DOCUMENT DATE:
ESTIMATED START DATE:
INSTRUCTIONS: PG&E contractor project manager, safety representative, requestor etc. will complete this form and provide PG&E with a written safety
plan using this attached Project Specific Safety Plan Form that will document how the contractor and subcontractor, at any tier, will address any
anticipated and/or recognized hazards associated with their project/contract work.
This plan is an important step in the communication process to promote open communication between the contractor / subcontractors and PG&E on health
and safety expectations and related issues and/or concerns. Detailed plans such as environmental protection, oil management, lift plan, spill mitigation etc.
should be attached to this form separately, if applicable. This form along with its attachments, when completed, must be submitted to and approved by
PG&E before starting work.
1.0 General Information
Detailed Project Scope Summary (Be as specific as possible):
Risk Level of Work ☐ Medium ☐ High
Name(s) Email Contact #
PG&E
Contacts
Project Lead
Work Supervisor
Safety Representative
Contractor
Contacts
Safety Plan Author
Project Lead
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 1 of 18 Power Generation Template Rev. 1 Revised 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
1.1 Field Leadership and Safety Oversight Plan
Clearly identify the person(s) responsible for overseeing employees and subcontractors, including a plan for conducting observations and
safety meetings:
1.2 General Personal Protective Equipment (PPE) Requirements
Contractors are required to provide and ensure that workers use Personal Protective Equipment (PPE) as required by Cal/OSHA (California
Code of Regulations [CCR], Title 8, Section 3380) regulatory requirements to perform their work activities safely and when defined in their
safety plan, hazard analysis or when required to access a specific PG&E location.
Minimum Personal Protective Equipment required on jobsite (as required and pertinent to scope of work):
• Hard hat rated for the scope of work and conditions (ANSI Z89)
• Safety glasses with side shields (ANSI Z87)
• Class 2 or 3 high visibility traffic vest or retroreflective fabric shirt (Arc Rated if appropriate for scope of work)
• Long sleeve shirts and long pants (flame resistant as required & pertinent to scope of work)
• Appropriate footwear (ASTM F2413-05)
• Gloves (as required & pertinent to task)
• Hearing protection (as required at or above 85 Db)
• COVID-19 face protection (Flame resistant as required & pertinent to task)
• Any additional PPE as required by your company’s IIPP, PG&E contract, or pertinent industry regulations not covered in the above
bullets.
Additional PPE requirements must be evaluated when performing specific tasks and shall be identified in Section 3 of this document.
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 2 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
2.0 General Safety Checklist
Subject
Required
Contractor Description and Details
Yes No
LOCKOUT-TAGOUT (LOTO) ☐ N/A
Will LOTO be required? ☐ ☐
Inspect LOTO sources and ensure PG&E’s LOTO procedures and
applicable training are followed
PERSONAL PROTECTIVE EQUIPMENT (PPE) ☐ N/A
Will personnel be equipped with Fire Resistant or arc-rated
clothing and vests? ☐ ☐
Ensure compliance with PG&E jobsite PPE requirements.
Will respiratory protection be required? ☐ ☐
Will any other special PPE be required? ☐ ☐
Identify type:
Has personnel received training for special PPE
requirements? ☐ ☐
HOT WORK ☐ N/A
Will hot work activities be performed? (Any flame or spark
producing task) ☐ ☐
Will any special PPE be required? ☐ ☐
Will fire blankets/protective shields/screens be required? ☐ ☐
FALL PROTECTION, ELEVATED SURFACES,
SLOPES
☐ N/A
Will rope access be required? ☐ ☐
Provide competent person name, contact info and training verification:
Will fall protection be required? ☐ ☐
Has all fall protection equipment and fall arrest systems (e.g.
harnesses, lanyards, lifelines) been inspected? ☐ ☐
Provide competent person(s) name and contact information:
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 3 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
Subject
Are competent/qualified persons identified to perform system
and equipment inspections, identify hazards, and anchor
points as needed?
Required
Contractor Description and Details
Yes No
☐ ☐
CONFINED SPACES ☐ N/A
Will any confined space work be performed? ☐ ☐
Will any Confined Space Entry permits be required? ☐ ☐
Ensure compliance with PG&E permit-required confined space entry
procedures. Provide entry supervisor name and training verification:
Have affected personnel been trained for confined space
entry? ☐ ☐
Will a dedicated or external rescue team services be used? ☐ ☐
Identify rescue service provider:
Have all entry procedures been provided and documented? ☐ ☐
CRANE AND RIGGING ☐ N/A
Will crane operations be required? ☐ ☐
Attach lift plan and identify engineer approving (critical) plan as
applicable.
Will a PG&E overhead crane be used? ☐ ☐
Have all overhead lines and hazards been identified and the
locations appropriately communicated to personnel? ☐ ☐
Will a Qualified Electrical Worker (QEW) be assigned to
observe near electrical hazards? ☐ ☐
Will any special lifting devices be needed? ☐ ☐
Is all rigging in compliance with inspection requirements? ☐ ☐
Is all equipment appropriate for the task(s)? ☐ ☐
Have all required safety inspections been completed? ☐ ☐
Ensure inspection logs are completed for equipment/ lift devices
Will traffic control be provided (pedestrian and vehicular)? Provide flaggers’ name / training:
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 4 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
Subject
Required
Contractor Description and Details
Yes No
☐ ☐
SCAFFOLDING AND LADDERS ☐ N/A
Will ladders be required? ☐ ☐
Will scaffolding be required? ☐ ☐
Provide competent person name, contact info and training verification:
Will fall protection be required? ☐ ☐
List equipment to be used:
Will there be potential for dropped-object hazards? ☐ ☐
Will special structures or platforms be used or erected? ☐ ☐
Describe, in detail:
EXCAVATIONS ☐ N/A
Has a USA Ticket been obtained? ☐ ☐
Attach copy of ticket:
Will equipment be brought on site? Pleases specify type. ☐ ☐
Provide competent person name, contact info and training verification:
Will a trench box/shoring be needed? ☐ ☐
Ensure tabulated data for shoring/trench box is available onsite
Does fencing/barricade need to be installed? ☐ ☐
MOBILE EQUIPMENT (POWERED FORK
TRUCKS, LIFTS, BOOMS ETC.)
☐ N/A
Will any mobile powered equipment be required? Type to be
rented or brought on site? ☐ ☐
Maintain daily/shift inspection logs on the equipment
Will any special attachments be used? jibs, manlifts, etc. ☐ ☐
Are operators trained / certified for operations of equipment? ☐ ☐
Attach verification of training (submitted before starting work):
POWDER ACTUATED TOOLS ☐ N/A
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 5 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
Subject
Required
Contractor Description and Details
Yes No
Are operators/personnel trained / licensed in use? ☐ ☐
Attach verification (submitted before starting work):
CHEMICAL, BIOLOGICAL, MATERIAL,
PHYSICAL HAZARDS
☐ N/A
Are all personnel trained in hazard communication / GHS? ☐ ☐
Are all SDS’s provided to PG&E and a copy easy to obtain at
job site? ☐ ☐
Are personnel trained to handle/use specific materials? ☐ ☐
Does storage and use meet all PG&E, NFPA, Fed and State
Regulations? ☐ ☐
Do personnel working with OSHA regulated chemicals have
proper training for job? (silica, asbestos, lead etc.) ☐ ☐
Does demo/abatement plans meet applicable standards? ☐ ☐
PAINTING, ADHESIVES AND EXPOXIES ☐ N/A
Are there any additional exhausts or fans needed during
application/curing time? ☐ ☐
Intrinsically safe exhaust fans are required for combustibles with low
flash points
Are there special PPE/precautions for this job? ☐ ☐
Will this require off-hours application? ☐ ☐
SIGNS, SIGNALS AND BARRICADES ☐ N/A
Will barricade tape be used? ☐ ☐
Ensure compliance with PG&E barricade tape policy
Will perimeter barricades be used? ☐ ☐
Will any caution/danger signs be needed? ☐ ☐
Will flammable gas/liquid labels be needed? Will material
labels (GHS) be needed? ☐ ☐
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 6 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
Subject
Required
Contractor Description and Details
Yes No
WORK PERMITS ☐ N/A
Will any pipe or vessel testing permits be required? ☐ ☐
Will any excavation permits be required? ☐ ☐
Will any utility interruption permits be required? ☐ ☐
Will Hot Work (welding/cutting/grinding/ soldering/electrical)
permits be required? ☐ ☐
Will any lead/asbestos permits be required? ☐ ☐
FLAMMABLE GASES / LIQUIDS ☐ N/A
Will any flammable gases and/or liquids be used? ☐ ☐
Have provisions for their storage been made? ☐ ☐
Will appropriate containers be utilized? ☐ ☐
Will secondary containment and spill kits be required? ☐ ☐
WASTE MANAGEMENT ☐ N/A
Is there a plan for waste disposal in place? ☐ ☐
Are all characterization, containerization, segregation,
storage and disposal requirements understood? ☐ ☐
Is there a plan for water/wastewater discharges in place? ☐ ☐
Attach plan:
Is there a spill plan in place? ☐ ☐
Ensure compliance with PG&E’s jobsite SPCC Plan, if applicable
WILDFIRE PREVENTION ☐ N/A
Have all contractor/subcontractor foreman, crew leads or site
representatives been trained on PG&E’s wildfire prevention
and mitigation program?
☐ ☐
Ensure compliance with Utility Standard: TD-1464S Preventing and
Mitigating Fires While Performing PG&E Work
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 7 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
Subject
Required
Contractor Description and Details
Yes No
HELICOPTER OPERATIONS ☐ N/A
Will helicopter operations be required? ☐ ☐
Attach helicopter operations plan:
MARINE AND UNDERWATER OPERATIONS ☐ N/A
Will dredging activities be performed? ☐ ☐
Will boats, rafts or pontoons be used? ☐ ☐
Will floating platforms or barges be used? ☐ ☐
Attach plan:
Are there diving operations, i.e. divers entering water? ☐ ☐
Attach dive operations plan:
Are divers trained / certified to dive? ☐ ☐
Attach verification of training (submitted before starting work):
OTHER, SPECIFY: ☐ N/A
☐ ☐
☐ ☐
2.1 Risk Assessment and Hazard Identification
HAZARD IDENTIFICATION: The hazards encountered as part of this scope could include, but are not limited to:
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 8 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
GENERAL HAZARDS PUBLIC SAFETY CRANE ELECTRICAL HAZARDS
• Uneven Ground/ Slips/ Trips & Falls • Distracted, Impaired, Unsafe Motorists • Crane Capacity • Clearance Procedures / LOTO /
Grounding
• Confined Spaces • Vehicular Traffic (Work Area Protection) • Crane Size
• Underground / Overhead Utilities
• Driving • Pedestrian Traffic • Load Weight
• Proximity to Energized Equipment
• Power Tool / Equipment Use • Proximity to Railroads • Lift Plans
• Induction
• Ergonomics • Neighboring Facilities/Homeowner Issues • Traffic / Transport
• Energized Work
Material
• Loading / Off-loading Equipment and • Setup/Access
• Stability / Terrain
EXCAVATION
• Unstable Ground Conditions / Slopes / • Rigging AVIATION
Uneven terrain • Cribbing
• Access / Proximity to Energized
• Safety-At-Heights / Scaffolding / Ladders Equipment Proximity to Energized • Dangerous Operations • External Cargo
• Cave-ins/ Excavating / Trenching / Circuits • Equipment Certification • Landing Zone Safety
Shoring • OH/UG Energized Lines • Rigging
• Operational Certification
• Welding / Oxy Acetylene / Grinding • Overhead Objects • Suspended Loads
• Electrical Hazards
• Hot work • Appropriate Tools & Equipment • Equipment Grounding • Flying in a Wire Environment
• Aggressive Animals / Dogs / Etc. • Equipment Certifications • Clearances
• High Crime Areas • Blasting Safety / Certification • Environmental issues
ENVIRONMENT HAZARDS
• Access • Confined Space • Suspended Loads
• No Cell Service • Open Excavation / Fall Restraint • Weather Conditions • Weather Conditions
• Night Operations • Soil Type / Conditions / Shoring / Sloping • Poison Oak
• Wildfire Safety • Slopes / Terrain • Animals / Insects
TRAFFIC CONTROL / FLAGGING
• Dropped Objects • Spoils Management • Heat Illness
• USAs • Environmental Conditions • Working Near / Over Water
• Non-Compliant Drivers
HEALTH HAZARDS
• Pedestrian Safety
GAS HAZARDS MOTOR VEHICLE SAFETY
• Chemical Exposure / Burns • Permits
• Noise Exposure • Oxygen Deficient Atmosphere • Public Safety • Driving
• Pesticides / Fumigation • Explosive Atmosphere - Burns / • Qualifications / Certifications • Backing
• PCB / Lead / Mercury Explosions • Site Specific Hazards • Mountainous Terrain
• Asbestos • Clearance Procedures / LOTO • Traffic Control Plan • Rural Roads
• Other Soil Contaminants • Dig-Ins / Line Strikes • Low Light Conditions • Traffic
• Hazardous Material Transportation • Unmarked or Mismarked Utilities • Weather • Transporting Loads/Cargo
• Hazardous Waste Transportation • Work Site Protection • Trailering/Towing
• Radioactive Exposure • Inclement Weather Driving
• Impaired Driving
• Distracted Driving
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
HAZARD MITIGATION: Using your Injury and Illness Prevention Program (IIPP) and the above sample tasks/activity table as a guide,
please complete the following JHA to capture actual hazards associated with each proposed activity. The specific hazard mitigation
measures used on PG&E work will typically include: (Add task, hazard, mitigation and required training below for each medium and/or high
risk major task performed on behalf of PG&E, including tasks performed by Subcontractors):
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 9 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
Task/Activity Description Hazard Description Contractor’s Mitigation Plan Required Training
New Hazards and Hazards not previously recognized shall be addressed upon discovery.
Changes shall be added to the Change Log in Section 8 of this document.
3.0 Hazard Communication/Right to Know
Conduct a complete survey to determine what hazardous substances are present on the project. Request necessary SDSs from the
manufacturer and keep a current SDS on hand for each hazardous substance used.
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 10 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
Chemical Onsite Location Storage Plan
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 11 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
4.0 Emergency Action Plan
Purpose: The following information shall be utilized to ensure effective and swift response to all emergencies. Please verify that location is still open and
it’s the closest to job site. An Emergency Action Plan must also be included on the daily JSSA/Tailboard for each jobsite/yard/meeting site.
Clinic (First Aid) Hospital
Name: * Name: *
Address: * Address: *
Phone #: * Phone #: *
Hours of Service: * Hours of Service: *
Fire Department Ambulance
Name: * Name: *
Address: Address:
Phone #: * Phone #: *
Hours of Service: Hours of Service:
Police/Sheriff 811 After Hours Emergency (click http://usanorth811.org/utility-operators/)
Name: * PG&E (Gas/Electric) (800) 743-5000
Address:
Phone #: *
First Aid Kit Location(s) *
AED Location(s) *
Fire Extinguisher Location(s) *
SDS Location(s) *
CPR Certified (who?) *
Cell Phone Reception? If no, provide
alternative communication method. *
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 12 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
(*) Denotes Required Field
Map View of Evacuation Plan – Print and Post
Show a map of the location with both primary and secondary meeting locations identified. Utilize Section 9 (Attachments) to provide additional maps as
needed
Map of A and B Meeting Location
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 13 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
Meeting Location A – please indicate on map (Primary) Meeting Location B – please indicate on map (Secondary)
Map View of Evacuation to Nearest Medical Facility – Print and Post
Show map with directions to the emergency center. Utilize Section 9 (Attachments) to provide additional maps as needed.
Directions to Medical Facility Map to Medical Facility
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 14 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
5.0 Certifications and Licenses
All contract employees, including Subcontractors, covered under this Safety Plan are trained and qualified to perform the task(s) they have
been assigned.
Contractors shall ensure that their personnel (including those of Subcontractors) have completed all training required by law and any
required PG&E specific courses, including the Contractor Safety Program Orientation (SAFE-0101) and any specific LOB required safety
orientations, prior to conducting work for PG&E.
Training qualifications shall be provided to PG&E for each contract employee prior to the start of work for PG&E.
Workers must carry their ISN ID cards at all times while working for PG&E and display to PG&E upon request.
All training materials must be made available to PG&E upon request that shall train all Contractor and Subcontractor personnel on all
PG&E’s Contractor Safety Program, Contractor’s safety program, all job related hazards, and Applicable Laws.
6.0 Managing Subcontractors No Subcontractors Anticipated
The Prime contractor shall ensure that all Subcontractors have an accepted hard copy of the Safety Plan on site at all times; the scope of
work conducted by all Subcontractors shall be covered in this Safety Plan. All Subcontractors shall also be added to Section 1A of the
contract.
Subcontractor Name Subcontractor Scope ISN ID # Risk Level
Subcontractor
Contact Name
Subcontractor
Contact Phone
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 15 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
7.0 Site Orientation
All site personnel, including subcontractors, are required to be introduced and trained on the content and hazard mitigation measures
included in this Safety Plan prior to beginning work on the project. Contractors shall document personnel who have completed a review of
this Safety Plan, including each worker’s name, signature, classification, company name and date. This record must be maintained by the
Prime contractor and available by request of PG&E.
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 16 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
8.0 Change Log
Indicate changes made on the Safety Plan in the table below. For each date a change is made, an additional section 8.0 will need to be
completed and shall be added as an additional page to the overall Safety Plan. Multiple changes may be required for each date, please copy
additional pages as needed.
Date Reason for Change Change Description Section(s)
Changed
PG&E Representative Who
Accepted Change
Once the crew has reviewed the changes above, please maintain a signed record that documents the review. This record must be
maintained by the Prime contractor and available by request of PG&E.
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 17 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)
CONTRACTOR PROJECT SPECIFIC SAFETY PLAN
PG&E PROJECT
CONTRACTOR:
9.0 Attachments
INCLUDED ATTACHMENTS:
Directions to medical facility*
Evacuation plans*
Parking / Laydown plans
Maps*
Other safety submittals, please specify:
(*) Denotes Required Field
© 2021 Pacific Gas & Electric. All Rights Reserved. Page: 18 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021
Template Link: Suppliers (pge.com)

More Related Content

Similar to ContractorSafetyProgram-Safety-Plan-Power-Generation-Template.pdf

HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docxHOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
Dwarika Bhushan Sharma
 
20060516 roles and_responsibilities_final
20060516 roles and_responsibilities_final20060516 roles and_responsibilities_final
20060516 roles and_responsibilities_final
twevans
 
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docxEDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
Dwarika Bhushan Sharma
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
Minh Bui Si
 
1.1. CHEVRON - ANGOLA LNG Job Description of JAGADEESAN Manicka A - Copy - Co...
1.1. CHEVRON - ANGOLA LNG Job Description of JAGADEESAN Manicka A - Copy - Co...1.1. CHEVRON - ANGOLA LNG Job Description of JAGADEESAN Manicka A - Copy - Co...
1.1. CHEVRON - ANGOLA LNG Job Description of JAGADEESAN Manicka A - Copy - Co...
JAGADEESAN MANICKA
 
MS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdfMS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdf
NajiRaheem2
 
Control Engineer-CV
Control Engineer-CVControl Engineer-CV
Control Engineer-CV
Ahmed Samir
 
Event infrastructure
Event infrastructure Event infrastructure
Event infrastructure
M. C.
 
update Khalid safety cv1
update Khalid safety cv1update Khalid safety cv1
update Khalid safety cv1
Khalid Deragun
 

Similar to ContractorSafetyProgram-Safety-Plan-Power-Generation-Template.pdf (20)

Practical assessment 3 - Install horizontal and vertical sheet panels
Practical assessment 3 - Install horizontal and vertical sheet panels Practical assessment 3 - Install horizontal and vertical sheet panels
Practical assessment 3 - Install horizontal and vertical sheet panels
 
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docxHOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
 
WHS_Practical Assessment.docx
WHS_Practical Assessment.docxWHS_Practical Assessment.docx
WHS_Practical Assessment.docx
 
Practical assessment 2 - Install horizontal weatherboards to internal corner
Practical assessment 2 - Install horizontal weatherboards to internal cornerPractical assessment 2 - Install horizontal weatherboards to internal corner
Practical assessment 2 - Install horizontal weatherboards to internal corner
 
20060516 roles and_responsibilities_final
20060516 roles and_responsibilities_final20060516 roles and_responsibilities_final
20060516 roles and_responsibilities_final
 
Abdulsaid CV 2016
Abdulsaid CV 2016Abdulsaid CV 2016
Abdulsaid CV 2016
 
Resume
ResumeResume
Resume
 
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docxEDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
 
Last updated Resume Jan 2017
Last updated Resume Jan 2017Last updated Resume Jan 2017
Last updated Resume Jan 2017
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
1.1. CHEVRON - ANGOLA LNG Job Description of JAGADEESAN Manicka A - Copy - Co...
1.1. CHEVRON - ANGOLA LNG Job Description of JAGADEESAN Manicka A - Copy - Co...1.1. CHEVRON - ANGOLA LNG Job Description of JAGADEESAN Manicka A - Copy - Co...
1.1. CHEVRON - ANGOLA LNG Job Description of JAGADEESAN Manicka A - Copy - Co...
 
Antony cv - 2
Antony cv - 2Antony cv - 2
Antony cv - 2
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
 
MS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdfMS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdf
 
Control Engineer-CV
Control Engineer-CVControl Engineer-CV
Control Engineer-CV
 
Event infrastructure
Event infrastructure Event infrastructure
Event infrastructure
 
AHU.pdf
AHU.pdfAHU.pdf
AHU.pdf
 
update Khalid safety cv1
update Khalid safety cv1update Khalid safety cv1
update Khalid safety cv1
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10
 

Recently uploaded

+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
Health
 
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
ZurliaSoop
 
Indian Call girl in Dubai 0508644382 Dubai Call girls
Indian Call girl in Dubai 0508644382 Dubai Call girlsIndian Call girl in Dubai 0508644382 Dubai Call girls
Indian Call girl in Dubai 0508644382 Dubai Call girls
Monica Sydney
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377087607
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377087607FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377087607
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377087607
dollysharma2066
 
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdfEnabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Smartinfologiks
 

Recently uploaded (15)

+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
 
How to structure your pitch - B4i template
How to structure your pitch - B4i templateHow to structure your pitch - B4i template
How to structure your pitch - B4i template
 
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
 
Dàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptxDàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptx
 
JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...
JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...
JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...
 
CARA BINA PENDAPATAN PASIF HARIAN RM9000 BERMODALKAN RM30 DI TDC
CARA BINA PENDAPATAN PASIF HARIAN RM9000 BERMODALKAN RM30 DI TDCCARA BINA PENDAPATAN PASIF HARIAN RM9000 BERMODALKAN RM30 DI TDC
CARA BINA PENDAPATAN PASIF HARIAN RM9000 BERMODALKAN RM30 DI TDC
 
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
 
Indian Call girl in Dubai 0508644382 Dubai Call girls
Indian Call girl in Dubai 0508644382 Dubai Call girlsIndian Call girl in Dubai 0508644382 Dubai Call girls
Indian Call girl in Dubai 0508644382 Dubai Call girls
 
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.inEV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
 
How Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptxHow Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptx
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377087607
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377087607FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377087607
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377087607
 
Famedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . FullsailFamedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . Fullsail
 
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdfEnabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
 
Supply Chain Location Decision and Management
Supply Chain Location Decision and ManagementSupply Chain Location Decision and Management
Supply Chain Location Decision and Management
 
EXPERIENCE THE FUTURE OF WORK FOR FUTURE OF BUSINESSES
EXPERIENCE  THE FUTURE OF WORK FOR FUTURE OF BUSINESSESEXPERIENCE  THE FUTURE OF WORK FOR FUTURE OF BUSINESSES
EXPERIENCE THE FUTURE OF WORK FOR FUTURE OF BUSINESSES
 

ContractorSafetyProgram-Safety-Plan-Power-Generation-Template.pdf

  • 1. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: LOCATION: CONTRACT/CWA #: DOCUMENT DATE: ESTIMATED START DATE: INSTRUCTIONS: PG&E contractor project manager, safety representative, requestor etc. will complete this form and provide PG&E with a written safety plan using this attached Project Specific Safety Plan Form that will document how the contractor and subcontractor, at any tier, will address any anticipated and/or recognized hazards associated with their project/contract work. This plan is an important step in the communication process to promote open communication between the contractor / subcontractors and PG&E on health and safety expectations and related issues and/or concerns. Detailed plans such as environmental protection, oil management, lift plan, spill mitigation etc. should be attached to this form separately, if applicable. This form along with its attachments, when completed, must be submitted to and approved by PG&E before starting work. 1.0 General Information Detailed Project Scope Summary (Be as specific as possible): Risk Level of Work ☐ Medium ☐ High Name(s) Email Contact # PG&E Contacts Project Lead Work Supervisor Safety Representative Contractor Contacts Safety Plan Author Project Lead © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 1 of 18 Power Generation Template Rev. 1 Revised 11/01/2021 Template Link: Suppliers (pge.com)
  • 2. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: 1.1 Field Leadership and Safety Oversight Plan Clearly identify the person(s) responsible for overseeing employees and subcontractors, including a plan for conducting observations and safety meetings: 1.2 General Personal Protective Equipment (PPE) Requirements Contractors are required to provide and ensure that workers use Personal Protective Equipment (PPE) as required by Cal/OSHA (California Code of Regulations [CCR], Title 8, Section 3380) regulatory requirements to perform their work activities safely and when defined in their safety plan, hazard analysis or when required to access a specific PG&E location. Minimum Personal Protective Equipment required on jobsite (as required and pertinent to scope of work): • Hard hat rated for the scope of work and conditions (ANSI Z89) • Safety glasses with side shields (ANSI Z87) • Class 2 or 3 high visibility traffic vest or retroreflective fabric shirt (Arc Rated if appropriate for scope of work) • Long sleeve shirts and long pants (flame resistant as required & pertinent to scope of work) • Appropriate footwear (ASTM F2413-05) • Gloves (as required & pertinent to task) • Hearing protection (as required at or above 85 Db) • COVID-19 face protection (Flame resistant as required & pertinent to task) • Any additional PPE as required by your company’s IIPP, PG&E contract, or pertinent industry regulations not covered in the above bullets. Additional PPE requirements must be evaluated when performing specific tasks and shall be identified in Section 3 of this document. © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 2 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 3. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: 2.0 General Safety Checklist Subject Required Contractor Description and Details Yes No LOCKOUT-TAGOUT (LOTO) ☐ N/A Will LOTO be required? ☐ ☐ Inspect LOTO sources and ensure PG&E’s LOTO procedures and applicable training are followed PERSONAL PROTECTIVE EQUIPMENT (PPE) ☐ N/A Will personnel be equipped with Fire Resistant or arc-rated clothing and vests? ☐ ☐ Ensure compliance with PG&E jobsite PPE requirements. Will respiratory protection be required? ☐ ☐ Will any other special PPE be required? ☐ ☐ Identify type: Has personnel received training for special PPE requirements? ☐ ☐ HOT WORK ☐ N/A Will hot work activities be performed? (Any flame or spark producing task) ☐ ☐ Will any special PPE be required? ☐ ☐ Will fire blankets/protective shields/screens be required? ☐ ☐ FALL PROTECTION, ELEVATED SURFACES, SLOPES ☐ N/A Will rope access be required? ☐ ☐ Provide competent person name, contact info and training verification: Will fall protection be required? ☐ ☐ Has all fall protection equipment and fall arrest systems (e.g. harnesses, lanyards, lifelines) been inspected? ☐ ☐ Provide competent person(s) name and contact information: © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 3 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 4. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: Subject Are competent/qualified persons identified to perform system and equipment inspections, identify hazards, and anchor points as needed? Required Contractor Description and Details Yes No ☐ ☐ CONFINED SPACES ☐ N/A Will any confined space work be performed? ☐ ☐ Will any Confined Space Entry permits be required? ☐ ☐ Ensure compliance with PG&E permit-required confined space entry procedures. Provide entry supervisor name and training verification: Have affected personnel been trained for confined space entry? ☐ ☐ Will a dedicated or external rescue team services be used? ☐ ☐ Identify rescue service provider: Have all entry procedures been provided and documented? ☐ ☐ CRANE AND RIGGING ☐ N/A Will crane operations be required? ☐ ☐ Attach lift plan and identify engineer approving (critical) plan as applicable. Will a PG&E overhead crane be used? ☐ ☐ Have all overhead lines and hazards been identified and the locations appropriately communicated to personnel? ☐ ☐ Will a Qualified Electrical Worker (QEW) be assigned to observe near electrical hazards? ☐ ☐ Will any special lifting devices be needed? ☐ ☐ Is all rigging in compliance with inspection requirements? ☐ ☐ Is all equipment appropriate for the task(s)? ☐ ☐ Have all required safety inspections been completed? ☐ ☐ Ensure inspection logs are completed for equipment/ lift devices Will traffic control be provided (pedestrian and vehicular)? Provide flaggers’ name / training: © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 4 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 5. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: Subject Required Contractor Description and Details Yes No ☐ ☐ SCAFFOLDING AND LADDERS ☐ N/A Will ladders be required? ☐ ☐ Will scaffolding be required? ☐ ☐ Provide competent person name, contact info and training verification: Will fall protection be required? ☐ ☐ List equipment to be used: Will there be potential for dropped-object hazards? ☐ ☐ Will special structures or platforms be used or erected? ☐ ☐ Describe, in detail: EXCAVATIONS ☐ N/A Has a USA Ticket been obtained? ☐ ☐ Attach copy of ticket: Will equipment be brought on site? Pleases specify type. ☐ ☐ Provide competent person name, contact info and training verification: Will a trench box/shoring be needed? ☐ ☐ Ensure tabulated data for shoring/trench box is available onsite Does fencing/barricade need to be installed? ☐ ☐ MOBILE EQUIPMENT (POWERED FORK TRUCKS, LIFTS, BOOMS ETC.) ☐ N/A Will any mobile powered equipment be required? Type to be rented or brought on site? ☐ ☐ Maintain daily/shift inspection logs on the equipment Will any special attachments be used? jibs, manlifts, etc. ☐ ☐ Are operators trained / certified for operations of equipment? ☐ ☐ Attach verification of training (submitted before starting work): POWDER ACTUATED TOOLS ☐ N/A © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 5 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 6. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: Subject Required Contractor Description and Details Yes No Are operators/personnel trained / licensed in use? ☐ ☐ Attach verification (submitted before starting work): CHEMICAL, BIOLOGICAL, MATERIAL, PHYSICAL HAZARDS ☐ N/A Are all personnel trained in hazard communication / GHS? ☐ ☐ Are all SDS’s provided to PG&E and a copy easy to obtain at job site? ☐ ☐ Are personnel trained to handle/use specific materials? ☐ ☐ Does storage and use meet all PG&E, NFPA, Fed and State Regulations? ☐ ☐ Do personnel working with OSHA regulated chemicals have proper training for job? (silica, asbestos, lead etc.) ☐ ☐ Does demo/abatement plans meet applicable standards? ☐ ☐ PAINTING, ADHESIVES AND EXPOXIES ☐ N/A Are there any additional exhausts or fans needed during application/curing time? ☐ ☐ Intrinsically safe exhaust fans are required for combustibles with low flash points Are there special PPE/precautions for this job? ☐ ☐ Will this require off-hours application? ☐ ☐ SIGNS, SIGNALS AND BARRICADES ☐ N/A Will barricade tape be used? ☐ ☐ Ensure compliance with PG&E barricade tape policy Will perimeter barricades be used? ☐ ☐ Will any caution/danger signs be needed? ☐ ☐ Will flammable gas/liquid labels be needed? Will material labels (GHS) be needed? ☐ ☐ © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 6 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 7. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: Subject Required Contractor Description and Details Yes No WORK PERMITS ☐ N/A Will any pipe or vessel testing permits be required? ☐ ☐ Will any excavation permits be required? ☐ ☐ Will any utility interruption permits be required? ☐ ☐ Will Hot Work (welding/cutting/grinding/ soldering/electrical) permits be required? ☐ ☐ Will any lead/asbestos permits be required? ☐ ☐ FLAMMABLE GASES / LIQUIDS ☐ N/A Will any flammable gases and/or liquids be used? ☐ ☐ Have provisions for their storage been made? ☐ ☐ Will appropriate containers be utilized? ☐ ☐ Will secondary containment and spill kits be required? ☐ ☐ WASTE MANAGEMENT ☐ N/A Is there a plan for waste disposal in place? ☐ ☐ Are all characterization, containerization, segregation, storage and disposal requirements understood? ☐ ☐ Is there a plan for water/wastewater discharges in place? ☐ ☐ Attach plan: Is there a spill plan in place? ☐ ☐ Ensure compliance with PG&E’s jobsite SPCC Plan, if applicable WILDFIRE PREVENTION ☐ N/A Have all contractor/subcontractor foreman, crew leads or site representatives been trained on PG&E’s wildfire prevention and mitigation program? ☐ ☐ Ensure compliance with Utility Standard: TD-1464S Preventing and Mitigating Fires While Performing PG&E Work © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 7 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 8. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: Subject Required Contractor Description and Details Yes No HELICOPTER OPERATIONS ☐ N/A Will helicopter operations be required? ☐ ☐ Attach helicopter operations plan: MARINE AND UNDERWATER OPERATIONS ☐ N/A Will dredging activities be performed? ☐ ☐ Will boats, rafts or pontoons be used? ☐ ☐ Will floating platforms or barges be used? ☐ ☐ Attach plan: Are there diving operations, i.e. divers entering water? ☐ ☐ Attach dive operations plan: Are divers trained / certified to dive? ☐ ☐ Attach verification of training (submitted before starting work): OTHER, SPECIFY: ☐ N/A ☐ ☐ ☐ ☐ 2.1 Risk Assessment and Hazard Identification HAZARD IDENTIFICATION: The hazards encountered as part of this scope could include, but are not limited to: © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 8 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 9. GENERAL HAZARDS PUBLIC SAFETY CRANE ELECTRICAL HAZARDS • Uneven Ground/ Slips/ Trips & Falls • Distracted, Impaired, Unsafe Motorists • Crane Capacity • Clearance Procedures / LOTO / Grounding • Confined Spaces • Vehicular Traffic (Work Area Protection) • Crane Size • Underground / Overhead Utilities • Driving • Pedestrian Traffic • Load Weight • Proximity to Energized Equipment • Power Tool / Equipment Use • Proximity to Railroads • Lift Plans • Induction • Ergonomics • Neighboring Facilities/Homeowner Issues • Traffic / Transport • Energized Work Material • Loading / Off-loading Equipment and • Setup/Access • Stability / Terrain EXCAVATION • Unstable Ground Conditions / Slopes / • Rigging AVIATION Uneven terrain • Cribbing • Access / Proximity to Energized • Safety-At-Heights / Scaffolding / Ladders Equipment Proximity to Energized • Dangerous Operations • External Cargo • Cave-ins/ Excavating / Trenching / Circuits • Equipment Certification • Landing Zone Safety Shoring • OH/UG Energized Lines • Rigging • Operational Certification • Welding / Oxy Acetylene / Grinding • Overhead Objects • Suspended Loads • Electrical Hazards • Hot work • Appropriate Tools & Equipment • Equipment Grounding • Flying in a Wire Environment • Aggressive Animals / Dogs / Etc. • Equipment Certifications • Clearances • High Crime Areas • Blasting Safety / Certification • Environmental issues ENVIRONMENT HAZARDS • Access • Confined Space • Suspended Loads • No Cell Service • Open Excavation / Fall Restraint • Weather Conditions • Weather Conditions • Night Operations • Soil Type / Conditions / Shoring / Sloping • Poison Oak • Wildfire Safety • Slopes / Terrain • Animals / Insects TRAFFIC CONTROL / FLAGGING • Dropped Objects • Spoils Management • Heat Illness • USAs • Environmental Conditions • Working Near / Over Water • Non-Compliant Drivers HEALTH HAZARDS • Pedestrian Safety GAS HAZARDS MOTOR VEHICLE SAFETY • Chemical Exposure / Burns • Permits • Noise Exposure • Oxygen Deficient Atmosphere • Public Safety • Driving • Pesticides / Fumigation • Explosive Atmosphere - Burns / • Qualifications / Certifications • Backing • PCB / Lead / Mercury Explosions • Site Specific Hazards • Mountainous Terrain • Asbestos • Clearance Procedures / LOTO • Traffic Control Plan • Rural Roads • Other Soil Contaminants • Dig-Ins / Line Strikes • Low Light Conditions • Traffic • Hazardous Material Transportation • Unmarked or Mismarked Utilities • Weather • Transporting Loads/Cargo • Hazardous Waste Transportation • Work Site Protection • Trailering/Towing • Radioactive Exposure • Inclement Weather Driving • Impaired Driving • Distracted Driving CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: HAZARD MITIGATION: Using your Injury and Illness Prevention Program (IIPP) and the above sample tasks/activity table as a guide, please complete the following JHA to capture actual hazards associated with each proposed activity. The specific hazard mitigation measures used on PG&E work will typically include: (Add task, hazard, mitigation and required training below for each medium and/or high risk major task performed on behalf of PG&E, including tasks performed by Subcontractors): © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 9 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 10. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: Task/Activity Description Hazard Description Contractor’s Mitigation Plan Required Training New Hazards and Hazards not previously recognized shall be addressed upon discovery. Changes shall be added to the Change Log in Section 8 of this document. 3.0 Hazard Communication/Right to Know Conduct a complete survey to determine what hazardous substances are present on the project. Request necessary SDSs from the manufacturer and keep a current SDS on hand for each hazardous substance used. © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 10 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 11. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: Chemical Onsite Location Storage Plan © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 11 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 12. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: 4.0 Emergency Action Plan Purpose: The following information shall be utilized to ensure effective and swift response to all emergencies. Please verify that location is still open and it’s the closest to job site. An Emergency Action Plan must also be included on the daily JSSA/Tailboard for each jobsite/yard/meeting site. Clinic (First Aid) Hospital Name: * Name: * Address: * Address: * Phone #: * Phone #: * Hours of Service: * Hours of Service: * Fire Department Ambulance Name: * Name: * Address: Address: Phone #: * Phone #: * Hours of Service: Hours of Service: Police/Sheriff 811 After Hours Emergency (click http://usanorth811.org/utility-operators/) Name: * PG&E (Gas/Electric) (800) 743-5000 Address: Phone #: * First Aid Kit Location(s) * AED Location(s) * Fire Extinguisher Location(s) * SDS Location(s) * CPR Certified (who?) * Cell Phone Reception? If no, provide alternative communication method. * © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 12 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 13. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: (*) Denotes Required Field Map View of Evacuation Plan – Print and Post Show a map of the location with both primary and secondary meeting locations identified. Utilize Section 9 (Attachments) to provide additional maps as needed Map of A and B Meeting Location © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 13 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 14. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: Meeting Location A – please indicate on map (Primary) Meeting Location B – please indicate on map (Secondary) Map View of Evacuation to Nearest Medical Facility – Print and Post Show map with directions to the emergency center. Utilize Section 9 (Attachments) to provide additional maps as needed. Directions to Medical Facility Map to Medical Facility © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 14 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 15. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: 5.0 Certifications and Licenses All contract employees, including Subcontractors, covered under this Safety Plan are trained and qualified to perform the task(s) they have been assigned. Contractors shall ensure that their personnel (including those of Subcontractors) have completed all training required by law and any required PG&E specific courses, including the Contractor Safety Program Orientation (SAFE-0101) and any specific LOB required safety orientations, prior to conducting work for PG&E. Training qualifications shall be provided to PG&E for each contract employee prior to the start of work for PG&E. Workers must carry their ISN ID cards at all times while working for PG&E and display to PG&E upon request. All training materials must be made available to PG&E upon request that shall train all Contractor and Subcontractor personnel on all PG&E’s Contractor Safety Program, Contractor’s safety program, all job related hazards, and Applicable Laws. 6.0 Managing Subcontractors No Subcontractors Anticipated The Prime contractor shall ensure that all Subcontractors have an accepted hard copy of the Safety Plan on site at all times; the scope of work conducted by all Subcontractors shall be covered in this Safety Plan. All Subcontractors shall also be added to Section 1A of the contract. Subcontractor Name Subcontractor Scope ISN ID # Risk Level Subcontractor Contact Name Subcontractor Contact Phone © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 15 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 16. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: 7.0 Site Orientation All site personnel, including subcontractors, are required to be introduced and trained on the content and hazard mitigation measures included in this Safety Plan prior to beginning work on the project. Contractors shall document personnel who have completed a review of this Safety Plan, including each worker’s name, signature, classification, company name and date. This record must be maintained by the Prime contractor and available by request of PG&E. © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 16 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 17. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: 8.0 Change Log Indicate changes made on the Safety Plan in the table below. For each date a change is made, an additional section 8.0 will need to be completed and shall be added as an additional page to the overall Safety Plan. Multiple changes may be required for each date, please copy additional pages as needed. Date Reason for Change Change Description Section(s) Changed PG&E Representative Who Accepted Change Once the crew has reviewed the changes above, please maintain a signed record that documents the review. This record must be maintained by the Prime contractor and available by request of PG&E. © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 17 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)
  • 18. CONTRACTOR PROJECT SPECIFIC SAFETY PLAN PG&E PROJECT CONTRACTOR: 9.0 Attachments INCLUDED ATTACHMENTS: Directions to medical facility* Evacuation plans* Parking / Laydown plans Maps* Other safety submittals, please specify: (*) Denotes Required Field © 2021 Pacific Gas & Electric. All Rights Reserved. Page: 18 of 18 Power Generation Template Rev. 1 Revised: 11/01/2021 Template Link: Suppliers (pge.com)