SlideShare a Scribd company logo
A case study into the effects of wind
loading on pushing and pulling manual
handling operations
James McCann
2015
A study into the use and operations of manually operated gates from a shop floor perspective
.
Introduction .
A Manager when asked, whatthe safe wind speed would be for safe operations of manually operated gates, did
not know! Nor did the manager know how much force was required to put the gate into motion even without the
effects of wind. As it would only require the wind to exert a force greater than that needed to set the gate in
motion and if uncontrolled to accelerate possibly to a dangerous extent, this should be or ought to be regarded as
a significant finding in a risk assessment. The Risk Assessments that were carried out indeed mention 'windy
conditions' however failed to further amplify what was meant by windy conditions, In any manual handling
operation it is the responsibility of those carrying out the work to carry out a Risk Assessment prior to
commencement of the work. This begs the question as to how the operators can carry out a dynammic risk
assessment prior to the operating of a manually operated gate, in windy conditions, that is 'adequate and
sufficient' if they do not have the information or tools needed to make the assessment? Or indeed what the safe
parameters are after the assessment. One suggestion that was made, was for theoperators to 'test' whether or not
they can operate the gate safely! This would be akin to testing whether a gun was loaded by pulling the trigger.
Operators have complained of aches and pains after prolonged use, there have also been a number of accidents
and near miss reports involving 'windy conditions' as being a contributory factor that have not been taken into
consideration
The HSE guidance regarding Risk Factors to be considered TILE;- TASK, INDIVIDUAL, LOAD &
ENVIRONMENT appears to underplay the influence of wind as a significant hazard to manual handling
operations seemingly sending the wrong measage regarding communication of risk. Manual handling injuries
reportedly contribute to one third of all 3 day absence, one wonders to what extent wind played as a factor in
these manual handling injuries?
A further suggestion that if in doubt, another person will be asked to help. None of the gates examined in this
study were found to be suited for 'team' operating and it is doubtful that the HSE guidanceof "2/3 the combined
capacity" would be appropriate for any gate operations as the positioning of adequate handles would
undoubtedly make coordination difficult and increase therisk of serious injury. None of the gates looked at have
extra handles for 'team operation' and in some cases are not been fitted with any handles!
It has been observed that gates are frequently used as convenient places to place site information notices, this
practice increases the effect of wind loading on the gate by increasing the effective surface area exposed to the
wind.
Accidents; In simple terms, when the wind acts on a gate, the gateacts like a sail. The magnitude of the wind
pressure will be at its greatestwhen acting perpendicularly to the gateand willdecrease proportionally as the
gate opens or closes, to use a sailing analogy 'luffing' or depowering of a sail. If the initial impetus from the sum
of the wind and human force is greater than the force required to keep thegate in motion then thegate will
accelerate and require an equal and opposite force to stop the momentum. If this force is greater than can be
controlled by the operator they willeither be dragged or willlet go and the gatewill swing out of control until it
reaches a solid object that will absorb or disperse the kinetic energy . The greater themass of the gate the
greater the kinetic energy and thegreater thecrash. When the wind strength is gusting and the area of the gate is
large enough then the force exerted by the wind maybesudden and overwhelming for the operator, in tests a
2000 kg gate reqired an impetus of 9kgf and a continuous force of 5kgf to maintain a walking pace of 3mph
however a gust of wind recorded an increase to 21.5kgf requiring theoperator to exert an equal and opposite
force (pulling) to bring thegate safely to a halt, simmilarly when closing the gate the operator experienced an
increase in effort to the same magnitude increasing to 21.5kgf (pushing) over a distance of 7m in this case the
greatest magnitude was at the end of the travel distance and theoperator now had to change sidesand hold the
gate with one hand inorder to secure the retaining bolt. This operation being repeated several times in a one hour
period.. Other environmental conditions included: heavy rain, cold, poor ,lighting and night shift, dressed in full
ppe of high visability jacket and over trousers on top of a uniform.
In one reportable (over 3 days) accident which involved opening and closing a 1500kg gate 4 x 4m in a full
force eight gale to allow upto 12 pedestrians access between 0700 and 0800 unaware that the securing hook had
not engaged properly the guard moved towards a pedestrian to check their id passes and was hit from behind
and catapulted into the opposite gate leaf and trapped by the closing leaf, he sustained damage to three vertebrae
and a chipped thigh bone. The cause of this accident was investigated from an office and declared as an operator
error, on inspection of the risk assessment there was no mention of wind, although mentioned in the assessment,
the reason a pedestrian gate or automation were not put in place (although the electrical controls were fitted),
was that it was not cost effective? how this computation was made is unclear. Not cost effective is simply
another way of saying 'notreasonably practicable' The test here would be 'Edwards v. The National Coal Board'
and in Coltness Iron Co v Sharp. Lord Atkin said: "The time of non-protection is so short, and
the time, trouble and expense of any other form of protection is so disproportionate that I
think the defence is proved." This shows that in every case it is the risk that has to be weighed
against the measures necessary to eliminate the risk. The greater the risk, no doubt, the less
will be the weight to be given to the factor of cost.
There would appear to be a number of conflicting 'risk perceptions' at work here or perhaps one of the many
myths surrunding risk , Sven Ove Hanssson Philosophy Unit RIT Stockholm et al . The risk to the individual
and the risk to security. Empirical v. Intelegence
There appears to be little or no empirical data available for manual handling of large single or double leafed
gates and the effects that wind loading has on them, this is probably as a result of increased automation
C RR 248/1999. AK Weyman & CJ Kelly In their Repor t highlight the many Risk Per ception & R isk
C ommunication Theor ies. One particular comentary stood out "However, the degree of consensu s
r egarding the precise nature of the influence of organisational role on per ception of r isk appear s to be
limited Lee et al (1993) for example, pr ovide findings which indicate that managers and supervisor s tend
to be mor e cautious in their appr oaches to r isk than workmen. By contrast other stu dies have shown that
supervisor s ar e poor sour ces of risk information and have a tendency to und erestimate r isk, r eportedly
they ar e 'too far r emoved from operations to make meaningful assessments, R osner & Markowitz (1995)
or mor e exposed to pr oduction pr essur es than other staff, Ostber g (1980) .
There are of course many other reasons and theories suggesting reasons for poor risk communication, perhaps
the expression ' aquila non capit muscas' may have some resonance whereby opening of gates is generally a
security function carried out by low skilled staff and health and safety is percieved to be a low priority over
security and perhaps it is only for those in the lowest levels of organisations that the cost of automation "is not
cost effective". This came into sharpe focus recently, The BBC Reported that a security officer in India was
murdered by being run over, for, "not opening a security gate fast enough" Other communication failures have
come to light whereby security officers failed to express their reasoning for having a security gate open " the
gate was too heavy" theresponse " no heavier than yesterday, now get it closed" the difference between the days
in question was that the previous day there was no wind on the next a gale force 8 was blowing!. From first
hand experience the higher the security risk the less health safety or welfare are considered! The less authority
within an organisation the less likely to challenge poor decission making by those with authority, this manifests
it's self in statements ' just get on with it' and ' you will have to put in a business plan' before changes can be
made. This becomes more evident when on closer inspection many of the gates were found to be below
industry standards to the point of being extremely dangerous. Fig 3, 1, 2, 3 5, 6, 7 & 8
It is regognised that gates come in different sizes, mass and drag coefficient making it difficult to give a more
accurate estimate compared with other push/ pulling manual handling operations, however it is believed that
sufficient data can be obtained that will allow guidance to be given as to the effects of wind loading to enable a
risk assessment to be made that is adequate and sufficient to reduce the risks to ALARP or indeed to justify
automation. Many of the gates looked at were installed prior to much of the regulations now inforce and only
recently brought into operation or back into operational use after many years of restricted use.. The imperative
to bring back these gates would appear to override safety issues or that the risks to security justifies the means,
this attidudinal disconect from policy which "inextricably linked H&S to security" manifest it's self in
comments by managers and supervisors to "just get on with it" neither empirical or epidemiological evidence
being considered, risk assessments apparently downplaying risk or ignoring wind as a significanthazard
Manual handling of loads, pushing and pulling, this type of operation is discused in HSE RR526 Fig 1 giving
data on frequency of pushing and pulling loads, giving guidance estimates of safe loads over distance and time/
frequency of pushing and pulling activities and is a usefulstart point.
The data collected and reproduced in RR526 was however obtained under laboratory conditions and were not
influenced by other contributory environmental factors or conditions such as wind loading. Although air
movement is mentioned as a contributory factor, contextually, 'draughts' only refer to an indoor environmental
condition and would not have sufficient energy to be regarded as significant to the load being pushed or pulled
but may have an effect on the operator I.e. Comfort.
There is also the problem of how to work out the math involved e.g. angular momentum/ torque the sum of the
forces, with or against the wind force, both positive or negative and measuring angles / vectors e.t.c. This is
complicated enough but becomes almost imposible where the wind force is unpradictable and variable, to
complicate matters the designs or where construction materials and dimentions differ make it unrealistic that
'generic' Risk Assessments would be sufficient Fig2 demonstrates the generic type risk/hazard identification
associated with gates.
There are two elements of risk associated with wind loading, first, the increase/decrease in load force for the
operator and second, the uncontrolled acceleration caused by wind loading. Unlike other manual handling
operations, pushing and pulling of gates or loads are often subject to sudden increase and or decrease of load
from the effects of wind . The analogy here would be pushing and pulling a load using a trolly, where, sudden
and unpredictable varying degrees of slopes appeared out of nowhere. Opening a gate or moving a load maybe
easier with the wind however converslely closing or changing direction would be subject to an increase in effort
from the effect of the wind acting against the gate or load. Gusting winds are more difficult to contend with, the
increased pressure may be sudden and overwhelming or again conversely a sudden drop in wind pressure may
be difficult to compensate for and control resulting in an increase likelyhood of serious injury.. These problems
are exacerbated by the lack of suitable handles often only one being fitted on one side of a gate or the only
handle thatis available is fitted on a slide bolt, often only a short metal bar.
The HSE, through examination of reported accidents, have determined that 11% musculoskeletal injuries
resulting from manual handling operations are associated with pushing or pulling loads, however it is unclear
whether any of the reported incidents included wind loading as a contributory factor.
Wind loading is recognised in many other areas of Health and Safety I.e crane operations and also plays a major
role in structural engineering
There is little to no wind loading information available in Gate Manufacturers Data sheets e.g. Pitts Security
Gates, Barriers, Blockers and Bollards PAS 68 Range, et al. British Standards BS EN 13241-2003, BS EN
12635-2002 BS EN 12605, BS EN 13849 - 2008 Although some of these Standards reference automated gates,
many of these gates can be disconected from their power source and can be operated manually when necessary.
Swing type security barriers found in e.g. Carparks, were the subjectof a HSE warning alert after a number of
accidents being reported (HSE Advice on horizontal swing carpark barriers) A number of simmilarities are
apparent, human intervention, locking mechenisms, the effects of wind and poor lighting and safety marking.
It is doubtful that mechanical dampening devices would be beneficial as they would only control sudden
changes in force however thepush pullforces would remain.or indeed be increased.
OBJECTIVES The purpose of this study is to examinethe effects of wind loading on manually operated gates.
Recognising that the operators would not have access to measuring devices inorder to carryout adequate or
sufficient risk assessments prior to operating the gates. To give managers and operators guidance on the safe
perameters for manually operating gates thatare simple and easy to understand
Examine if wind loading increases the load above the accepted limits 20kgf for men 15 kgf for women, 10 kgf
and 7 kgf respectively for keeping the load in motion. The HSE advise " that even for a minority of fit well
trained individuals under faverable conditions, may if the operation guideline limits are exceeded by a factor of
2 or more may be at risk of serious injury"
Determine the operationalloads in stillair
Determine wind speeds above which wind loading would increase the likelyhood of serious injury
Devise a graphicmanual handling toolthat willgive clearly understood inform
Determining risk factors for inclusion in the graphicmanual handling tool
l Provide estimates of impact(kinetic energy) forces from the gates whilst in motion
l We will be looking at the effects of wind loading on gates as they affect the manual operation and not the
structural integrity or design of the gates themselves but concentrating on the generality of the effects that
wind loading may have and to prepare guidance on contributory risk
l For ease of calculation a number of assumptions are being made, area of the gates in question will be
regarded as solid flat surfaces this will give an absolute maximum for wind pressure acting on the gate.
Angular movement/acceleration will be regarded as non vector or torque for simplicity of calculation as
wind direction is complex and variable therefor willbe calculated as perpendicular to thegate, again giving
a maximum for wind loading. It will be assumed that the greatest area of danger for the operator is at the
furthest from the hinge and refered to as the impact zone (IZ) . For the purpose of these calculations it is
not necessary for a higher degree of accuracy however if a higher degree of accuracy is required this may
be achieved by using the data and appropriate non linear formulas. The angle of wind direction relative to
thegate willbe recorded for those that wish to make more accurate assessments.
l As the most important factor will be that of wind pressure acting on the gates and not the capabilities of
the opperators, it is intended to make direct measurements under a range of wind conditions and compare
them to those taken under still air conditions this will give a direct comparison of increased loading on
gates of different dimensions and construction under different environmentalconditions
l Wind speed = m/s
l Acceleration =m/s^2
l Mass = kg
l Wind pressure = kg/m^2 = N/m^2
l Force, pushing or pulling required to control the gatein motion = kgf
Fig 1
Fig 1 It would be tempting for managers not to consider wind as a significant hazard. For managers,
RR526 Although "other environmentalfactors" have to be considered it is believed thatthisreport missed the
significance of the effects of wind on high risk push pull operations being carried out
Figure 2
Fig 2 . For the average person, carrying out the mathmatics prior to a manual handling
operation (push pull) would be wholly unreasonable and like an Inspector "who do not
typically pocess objective force measuring equipement " RR562 Executive
Recommendations, et al, would be unrealistic
Figure 3 Typical layout for identifying risk areas on gates
Note that the forces required to operate the gate or frequency of use (push pull manual
handling) handles and fittings are absent nor is wind identified as a significant factor. The
'weight' of the gate is supported by the hinges and load bearing style however the mass of the
gate is independent of how the weight is supported.
Fig 4a Guidance to the increase in force required to control the loading
Figure 4a A suggested diagram of the extra force needed to carryout push pull opperations.
where wind is a significant factor. For simplicity and ease of use this diagram uses the same
'traffic signal' format and should be used in conjunction with the load diagram Fig 1. The
combination of wind pressure in N/m^2 and the bodily force in kgf to control the gate whilst
in motion
Fig 4b
Fig 4b Wind force conversion
Figure 5. Suggested data for inclusion
Figure 5 Data collection
Data collection
Details of the gates, construction, dimensions and approximate mass..
Number of hinges and fittings
Orientation I.e 270°-90° = East / West. 0° - 180° = North / South
Wind speed and direction (from perpendicular to the gate) 0° = perpendicular .
Defects
Environmental conditions, day, night, rain, lighting etc.

More Related Content

What's hot

Square footing design
Square footing designSquare footing design
Square footing design
Southern University Bangladesh
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017
John Newquist
 
Separation distances and containment requirements for tanks nfpa 30 2008
Separation distances and containment requirements for tanks nfpa 30 2008Separation distances and containment requirements for tanks nfpa 30 2008
Separation distances and containment requirements for tanks nfpa 30 2008zaheer sajid
 
AISC - Steel Construction Manual-American Institute of Steel Construction (20...
AISC - Steel Construction Manual-American Institute of Steel Construction (20...AISC - Steel Construction Manual-American Institute of Steel Construction (20...
AISC - Steel Construction Manual-American Institute of Steel Construction (20...
AlejandraGalvis18
 
Scaffold classes and duties (cals)
Scaffold classes and duties (cals)Scaffold classes and duties (cals)
Scaffold classes and duties (cals)robadet
 
Fatigue behaviour of reinforced concrete beams with corroded
Fatigue behaviour of reinforced concrete beams with corrodedFatigue behaviour of reinforced concrete beams with corroded
Fatigue behaviour of reinforced concrete beams with corrodedkmpmanoj
 
Analysis of T-Beam
Analysis of T-BeamAnalysis of T-Beam
Analysis of T-Beam
01008828934
 
Subpart T - Demolition
Subpart T -  DemolitionSubpart T -  Demolition
Subpart T - DemolitionFFSafety
 
Wind Load of Wind Turbine Tower
Wind Load of Wind Turbine TowerWind Load of Wind Turbine Tower
Wind Load of Wind Turbine Tower
Henry Kurniadi
 
Cold-Formed-Steel Design And Construction ( Steel Structure )
Cold-Formed-Steel Design And Construction ( Steel Structure )Cold-Formed-Steel Design And Construction ( Steel Structure )
Cold-Formed-Steel Design And Construction ( Steel Structure )
Hossam Shafiq I
 
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined PilecapPile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
azhar ahmad
 
HSE_TM_06_Material handling Safety.pptx
HSE_TM_06_Material handling Safety.pptxHSE_TM_06_Material handling Safety.pptx
HSE_TM_06_Material handling Safety.pptx
johnraj44
 
Rt acceptance criteria by zas
Rt acceptance  criteria by zasRt acceptance  criteria by zas
Rt acceptance criteria by zas
zaheer sajid
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
AHMED NADIM JILANI
 
Design of compression members
Design of compression membersDesign of compression members
Design of compression members
Sabna Thilakan
 
Dynamic Response
Dynamic ResponseDynamic Response
Dynamic Response
AIT Solutions
 
New Life Steel Structures, Mumbai, Sheds and Steel Structures
 New Life Steel Structures, Mumbai, Sheds and Steel Structures New Life Steel Structures, Mumbai, Sheds and Steel Structures
New Life Steel Structures, Mumbai, Sheds and Steel Structures
IndiaMART InterMESH Limited
 
Steel Bridge Dr.Metwally
Steel Bridge Dr.MetwallySteel Bridge Dr.Metwally
Steel Bridge Dr.Metwally
Bahzad5
 

What's hot (20)

Square footing design
Square footing designSquare footing design
Square footing design
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017
 
Separation distances and containment requirements for tanks nfpa 30 2008
Separation distances and containment requirements for tanks nfpa 30 2008Separation distances and containment requirements for tanks nfpa 30 2008
Separation distances and containment requirements for tanks nfpa 30 2008
 
AISC - Steel Construction Manual-American Institute of Steel Construction (20...
AISC - Steel Construction Manual-American Institute of Steel Construction (20...AISC - Steel Construction Manual-American Institute of Steel Construction (20...
AISC - Steel Construction Manual-American Institute of Steel Construction (20...
 
Scaffold classes and duties (cals)
Scaffold classes and duties (cals)Scaffold classes and duties (cals)
Scaffold classes and duties (cals)
 
Fatigue behaviour of reinforced concrete beams with corroded
Fatigue behaviour of reinforced concrete beams with corrodedFatigue behaviour of reinforced concrete beams with corroded
Fatigue behaviour of reinforced concrete beams with corroded
 
Analysis of T-Beam
Analysis of T-BeamAnalysis of T-Beam
Analysis of T-Beam
 
Subpart T - Demolition
Subpart T -  DemolitionSubpart T -  Demolition
Subpart T - Demolition
 
Wind Load of Wind Turbine Tower
Wind Load of Wind Turbine TowerWind Load of Wind Turbine Tower
Wind Load of Wind Turbine Tower
 
Cold-Formed-Steel Design And Construction ( Steel Structure )
Cold-Formed-Steel Design And Construction ( Steel Structure )Cold-Formed-Steel Design And Construction ( Steel Structure )
Cold-Formed-Steel Design And Construction ( Steel Structure )
 
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined PilecapPile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
 
HSE_TM_06_Material handling Safety.pptx
HSE_TM_06_Material handling Safety.pptxHSE_TM_06_Material handling Safety.pptx
HSE_TM_06_Material handling Safety.pptx
 
Rt acceptance criteria by zas
Rt acceptance  criteria by zasRt acceptance  criteria by zas
Rt acceptance criteria by zas
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
 
Design of compression members
Design of compression membersDesign of compression members
Design of compression members
 
Dimension torque threads
Dimension torque   threadsDimension torque   threads
Dimension torque threads
 
Wall type
Wall typeWall type
Wall type
 
Dynamic Response
Dynamic ResponseDynamic Response
Dynamic Response
 
New Life Steel Structures, Mumbai, Sheds and Steel Structures
 New Life Steel Structures, Mumbai, Sheds and Steel Structures New Life Steel Structures, Mumbai, Sheds and Steel Structures
New Life Steel Structures, Mumbai, Sheds and Steel Structures
 
Steel Bridge Dr.Metwally
Steel Bridge Dr.MetwallySteel Bridge Dr.Metwally
Steel Bridge Dr.Metwally
 

Similar to Wind loading on gates

Enclosed Space Operations - Do We Understand the risks
Enclosed Space Operations - Do We Understand the risksEnclosed Space Operations - Do We Understand the risks
Enclosed Space Operations - Do We Understand the risksNippin Anand
 
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Nippin Anand
 
Accident investigations at Sea: Learning from Failure or Failure to Learn?
Accident investigations at Sea: Learning from Failure or Failure to Learn?Accident investigations at Sea: Learning from Failure or Failure to Learn?
Accident investigations at Sea: Learning from Failure or Failure to Learn?
Nippin Anand
 
assignment 2
assignment 2assignment 2
assignment 2Kai Guan
 
Technology Encourages Employees To Promote Facility Safety
Technology Encourages Employees To Promote Facility SafetyTechnology Encourages Employees To Promote Facility Safety
Technology Encourages Employees To Promote Facility Safety
Garrett Foley
 
Running Head SAFETY IN AVIATION .docx
Running Head SAFETY IN AVIATION                                  .docxRunning Head SAFETY IN AVIATION                                  .docx
Running Head SAFETY IN AVIATION .docx
charisellington63520
 
Running Head SAFETY IN AVIATION .docx
Running Head SAFETY IN AVIATION                                  .docxRunning Head SAFETY IN AVIATION                                  .docx
Running Head SAFETY IN AVIATION .docx
todd521
 
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
DigitalPower
 
Expensive ergonomics
Expensive ergonomicsExpensive ergonomics
Expensive ergonomics
Mert Daggecen
 
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH. 7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
Abdul Shukor
 
'Risk Culture' - The missing link in Safety Culture?
'Risk Culture' - The missing link in Safety Culture?'Risk Culture' - The missing link in Safety Culture?
'Risk Culture' - The missing link in Safety Culture?
Cranfield University
 
Analyzing The Near Miss: Are companies overlooking crucial data?
Analyzing The Near Miss: Are companies overlooking crucial data?Analyzing The Near Miss: Are companies overlooking crucial data?
Analyzing The Near Miss: Are companies overlooking crucial data?
Garrett Foley
 
arriers thatd due to lackm factorsthese causalent ca.docx
arriers thatd due to lackm factorsthese causalent ca.docxarriers thatd due to lackm factorsthese causalent ca.docx
arriers thatd due to lackm factorsthese causalent ca.docx
davezstarr61655
 
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docxRunning head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
SUBHI7
 
5 steps prior erecting a scaffold
5 steps prior erecting a scaffold5 steps prior erecting a scaffold
5 steps prior erecting a scaffold
ASK EHS Engineering & Consultants
 
Angharad Boyson dissertation
Angharad Boyson dissertationAngharad Boyson dissertation
Angharad Boyson dissertationAngharad Boyson
 
Pace IT - Introduction to Safety Procedures
Pace IT - Introduction to Safety ProceduresPace IT - Introduction to Safety Procedures
Pace IT - Introduction to Safety Procedures
Pace IT at Edmonds Community College
 

Similar to Wind loading on gates (20)

Risk Assessment
Risk AssessmentRisk Assessment
Risk Assessment
 
Enclosed Space Operations - Do We Understand the risks
Enclosed Space Operations - Do We Understand the risksEnclosed Space Operations - Do We Understand the risks
Enclosed Space Operations - Do We Understand the risks
 
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
 
Accident investigations at Sea: Learning from Failure or Failure to Learn?
Accident investigations at Sea: Learning from Failure or Failure to Learn?Accident investigations at Sea: Learning from Failure or Failure to Learn?
Accident investigations at Sea: Learning from Failure or Failure to Learn?
 
assignment 2
assignment 2assignment 2
assignment 2
 
Technology Encourages Employees To Promote Facility Safety
Technology Encourages Employees To Promote Facility SafetyTechnology Encourages Employees To Promote Facility Safety
Technology Encourages Employees To Promote Facility Safety
 
Running Head SAFETY IN AVIATION .docx
Running Head SAFETY IN AVIATION                                  .docxRunning Head SAFETY IN AVIATION                                  .docx
Running Head SAFETY IN AVIATION .docx
 
Running Head SAFETY IN AVIATION .docx
Running Head SAFETY IN AVIATION                                  .docxRunning Head SAFETY IN AVIATION                                  .docx
Running Head SAFETY IN AVIATION .docx
 
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
 
Near miss mgt. in chemical process
Near miss mgt. in chemical processNear miss mgt. in chemical process
Near miss mgt. in chemical process
 
Expensive ergonomics
Expensive ergonomicsExpensive ergonomics
Expensive ergonomics
 
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH. 7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
 
'Risk Culture' - The missing link in Safety Culture?
'Risk Culture' - The missing link in Safety Culture?'Risk Culture' - The missing link in Safety Culture?
'Risk Culture' - The missing link in Safety Culture?
 
Analyzing The Near Miss: Are companies overlooking crucial data?
Analyzing The Near Miss: Are companies overlooking crucial data?Analyzing The Near Miss: Are companies overlooking crucial data?
Analyzing The Near Miss: Are companies overlooking crucial data?
 
arriers thatd due to lackm factorsthese causalent ca.docx
arriers thatd due to lackm factorsthese causalent ca.docxarriers thatd due to lackm factorsthese causalent ca.docx
arriers thatd due to lackm factorsthese causalent ca.docx
 
Safety Matters Fall 2015
Safety Matters Fall 2015Safety Matters Fall 2015
Safety Matters Fall 2015
 
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docxRunning head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
 
5 steps prior erecting a scaffold
5 steps prior erecting a scaffold5 steps prior erecting a scaffold
5 steps prior erecting a scaffold
 
Angharad Boyson dissertation
Angharad Boyson dissertationAngharad Boyson dissertation
Angharad Boyson dissertation
 
Pace IT - Introduction to Safety Procedures
Pace IT - Introduction to Safety ProceduresPace IT - Introduction to Safety Procedures
Pace IT - Introduction to Safety Procedures
 

More from James McCann

For decades the question of how good and evil originate and manifest in us wa...
For decades the question of how good and evil originate and manifest in us wa...For decades the question of how good and evil originate and manifest in us wa...
For decades the question of how good and evil originate and manifest in us wa...
James McCann
 
Accident investigation full version
Accident investigation full versionAccident investigation full version
Accident investigation full version
James McCann
 
Promoting a positive health and safety culture
Promoting a positive health and safety culturePromoting a positive health and safety culture
Promoting a positive health and safety culture
James McCann
 
Full moon fallacy.pptx2
Full moon fallacy.pptx2Full moon fallacy.pptx2
Full moon fallacy.pptx2
James McCann
 
Managing disability 5
Managing disability 5Managing disability 5
Managing disability 5
James McCann
 
Health safety and disability
Health safety and disabilityHealth safety and disability
Health safety and disability
James McCann
 
BACK TO THE FLOOR
BACK TO THE FLOORBACK TO THE FLOOR
BACK TO THE FLOOR
James McCann
 
Floodprobe factsheet-casestudy-gloucester
Floodprobe factsheet-casestudy-gloucesterFloodprobe factsheet-casestudy-gloucester
Floodprobe factsheet-casestudy-gloucester
James McCann
 
Presentation globalisation & Health and Safety
Presentation globalisation & Health and SafetyPresentation globalisation & Health and Safety
Presentation globalisation & Health and Safety
James McCann
 
Shift work
Shift workShift work
Shift work
James McCann
 
Health and safety_is_just_common_sense...
Health and safety_is_just_common_sense...Health and safety_is_just_common_sense...
Health and safety_is_just_common_sense...
James McCann
 
Work At Height
Work At HeightWork At Height
Work At Height
James McCann
 
First Aid Slides
First Aid SlidesFirst Aid Slides
First Aid Slides
James McCann
 
D Part 2 H & S Regulations
D  Part 2 H & S RegulationsD  Part 2 H & S Regulations
D Part 2 H & S Regulations
James McCann
 
D Part 3 Health Safety Revision By J Mc Cann
D  Part 3 Health Safety Revision By J Mc CannD  Part 3 Health Safety Revision By J Mc Cann
D Part 3 Health Safety Revision By J Mc Cann
James McCann
 
D Part 4 Hswa Revision Law
D  Part 4 Hswa  Revision LawD  Part 4 Hswa  Revision Law
D Part 4 Hswa Revision Law
James McCann
 
D Part 7 Section 2 Hswa Revision
D  Part 7 Section 2 Hswa RevisionD  Part 7 Section 2 Hswa Revision
D Part 7 Section 2 Hswa Revision
James McCann
 
D Part 8 Hseoh Conference 2005
D  Part 8 Hseoh Conference 2005D  Part 8 Hseoh Conference 2005
D Part 8 Hseoh Conference 2005
James McCann
 
D Part 9 H & S Regs Revision By J Mc Cann
D  Part 9 H & S Regs Revision By J Mc CannD  Part 9 H & S Regs Revision By J Mc Cann
D Part 9 H & S Regs Revision By J Mc Cann
James McCann
 
D Part 5 Revision 6 Pack
D  Part 5 Revision 6 PackD  Part 5 Revision 6 Pack
D Part 5 Revision 6 Pack
James McCann
 

More from James McCann (20)

For decades the question of how good and evil originate and manifest in us wa...
For decades the question of how good and evil originate and manifest in us wa...For decades the question of how good and evil originate and manifest in us wa...
For decades the question of how good and evil originate and manifest in us wa...
 
Accident investigation full version
Accident investigation full versionAccident investigation full version
Accident investigation full version
 
Promoting a positive health and safety culture
Promoting a positive health and safety culturePromoting a positive health and safety culture
Promoting a positive health and safety culture
 
Full moon fallacy.pptx2
Full moon fallacy.pptx2Full moon fallacy.pptx2
Full moon fallacy.pptx2
 
Managing disability 5
Managing disability 5Managing disability 5
Managing disability 5
 
Health safety and disability
Health safety and disabilityHealth safety and disability
Health safety and disability
 
BACK TO THE FLOOR
BACK TO THE FLOORBACK TO THE FLOOR
BACK TO THE FLOOR
 
Floodprobe factsheet-casestudy-gloucester
Floodprobe factsheet-casestudy-gloucesterFloodprobe factsheet-casestudy-gloucester
Floodprobe factsheet-casestudy-gloucester
 
Presentation globalisation & Health and Safety
Presentation globalisation & Health and SafetyPresentation globalisation & Health and Safety
Presentation globalisation & Health and Safety
 
Shift work
Shift workShift work
Shift work
 
Health and safety_is_just_common_sense...
Health and safety_is_just_common_sense...Health and safety_is_just_common_sense...
Health and safety_is_just_common_sense...
 
Work At Height
Work At HeightWork At Height
Work At Height
 
First Aid Slides
First Aid SlidesFirst Aid Slides
First Aid Slides
 
D Part 2 H & S Regulations
D  Part 2 H & S RegulationsD  Part 2 H & S Regulations
D Part 2 H & S Regulations
 
D Part 3 Health Safety Revision By J Mc Cann
D  Part 3 Health Safety Revision By J Mc CannD  Part 3 Health Safety Revision By J Mc Cann
D Part 3 Health Safety Revision By J Mc Cann
 
D Part 4 Hswa Revision Law
D  Part 4 Hswa  Revision LawD  Part 4 Hswa  Revision Law
D Part 4 Hswa Revision Law
 
D Part 7 Section 2 Hswa Revision
D  Part 7 Section 2 Hswa RevisionD  Part 7 Section 2 Hswa Revision
D Part 7 Section 2 Hswa Revision
 
D Part 8 Hseoh Conference 2005
D  Part 8 Hseoh Conference 2005D  Part 8 Hseoh Conference 2005
D Part 8 Hseoh Conference 2005
 
D Part 9 H & S Regs Revision By J Mc Cann
D  Part 9 H & S Regs Revision By J Mc CannD  Part 9 H & S Regs Revision By J Mc Cann
D Part 9 H & S Regs Revision By J Mc Cann
 
D Part 5 Revision 6 Pack
D  Part 5 Revision 6 PackD  Part 5 Revision 6 Pack
D Part 5 Revision 6 Pack
 

Recently uploaded

Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 

Recently uploaded (20)

Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 

Wind loading on gates

  • 1. A case study into the effects of wind loading on pushing and pulling manual handling operations James McCann 2015
  • 2. A study into the use and operations of manually operated gates from a shop floor perspective . Introduction . A Manager when asked, whatthe safe wind speed would be for safe operations of manually operated gates, did not know! Nor did the manager know how much force was required to put the gate into motion even without the effects of wind. As it would only require the wind to exert a force greater than that needed to set the gate in motion and if uncontrolled to accelerate possibly to a dangerous extent, this should be or ought to be regarded as a significant finding in a risk assessment. The Risk Assessments that were carried out indeed mention 'windy conditions' however failed to further amplify what was meant by windy conditions, In any manual handling operation it is the responsibility of those carrying out the work to carry out a Risk Assessment prior to commencement of the work. This begs the question as to how the operators can carry out a dynammic risk assessment prior to the operating of a manually operated gate, in windy conditions, that is 'adequate and sufficient' if they do not have the information or tools needed to make the assessment? Or indeed what the safe parameters are after the assessment. One suggestion that was made, was for theoperators to 'test' whether or not they can operate the gate safely! This would be akin to testing whether a gun was loaded by pulling the trigger. Operators have complained of aches and pains after prolonged use, there have also been a number of accidents and near miss reports involving 'windy conditions' as being a contributory factor that have not been taken into consideration The HSE guidance regarding Risk Factors to be considered TILE;- TASK, INDIVIDUAL, LOAD & ENVIRONMENT appears to underplay the influence of wind as a significant hazard to manual handling operations seemingly sending the wrong measage regarding communication of risk. Manual handling injuries reportedly contribute to one third of all 3 day absence, one wonders to what extent wind played as a factor in these manual handling injuries? A further suggestion that if in doubt, another person will be asked to help. None of the gates examined in this study were found to be suited for 'team' operating and it is doubtful that the HSE guidanceof "2/3 the combined capacity" would be appropriate for any gate operations as the positioning of adequate handles would undoubtedly make coordination difficult and increase therisk of serious injury. None of the gates looked at have extra handles for 'team operation' and in some cases are not been fitted with any handles! It has been observed that gates are frequently used as convenient places to place site information notices, this practice increases the effect of wind loading on the gate by increasing the effective surface area exposed to the wind. Accidents; In simple terms, when the wind acts on a gate, the gateacts like a sail. The magnitude of the wind pressure will be at its greatestwhen acting perpendicularly to the gateand willdecrease proportionally as the gate opens or closes, to use a sailing analogy 'luffing' or depowering of a sail. If the initial impetus from the sum of the wind and human force is greater than the force required to keep thegate in motion then thegate will accelerate and require an equal and opposite force to stop the momentum. If this force is greater than can be controlled by the operator they willeither be dragged or willlet go and the gatewill swing out of control until it reaches a solid object that will absorb or disperse the kinetic energy . The greater themass of the gate the greater the kinetic energy and thegreater thecrash. When the wind strength is gusting and the area of the gate is large enough then the force exerted by the wind maybesudden and overwhelming for the operator, in tests a 2000 kg gate reqired an impetus of 9kgf and a continuous force of 5kgf to maintain a walking pace of 3mph however a gust of wind recorded an increase to 21.5kgf requiring theoperator to exert an equal and opposite force (pulling) to bring thegate safely to a halt, simmilarly when closing the gate the operator experienced an increase in effort to the same magnitude increasing to 21.5kgf (pushing) over a distance of 7m in this case the
  • 3. greatest magnitude was at the end of the travel distance and theoperator now had to change sidesand hold the gate with one hand inorder to secure the retaining bolt. This operation being repeated several times in a one hour period.. Other environmental conditions included: heavy rain, cold, poor ,lighting and night shift, dressed in full ppe of high visability jacket and over trousers on top of a uniform. In one reportable (over 3 days) accident which involved opening and closing a 1500kg gate 4 x 4m in a full force eight gale to allow upto 12 pedestrians access between 0700 and 0800 unaware that the securing hook had not engaged properly the guard moved towards a pedestrian to check their id passes and was hit from behind and catapulted into the opposite gate leaf and trapped by the closing leaf, he sustained damage to three vertebrae and a chipped thigh bone. The cause of this accident was investigated from an office and declared as an operator error, on inspection of the risk assessment there was no mention of wind, although mentioned in the assessment, the reason a pedestrian gate or automation were not put in place (although the electrical controls were fitted), was that it was not cost effective? how this computation was made is unclear. Not cost effective is simply another way of saying 'notreasonably practicable' The test here would be 'Edwards v. The National Coal Board' and in Coltness Iron Co v Sharp. Lord Atkin said: "The time of non-protection is so short, and the time, trouble and expense of any other form of protection is so disproportionate that I think the defence is proved." This shows that in every case it is the risk that has to be weighed against the measures necessary to eliminate the risk. The greater the risk, no doubt, the less will be the weight to be given to the factor of cost. There would appear to be a number of conflicting 'risk perceptions' at work here or perhaps one of the many myths surrunding risk , Sven Ove Hanssson Philosophy Unit RIT Stockholm et al . The risk to the individual and the risk to security. Empirical v. Intelegence There appears to be little or no empirical data available for manual handling of large single or double leafed gates and the effects that wind loading has on them, this is probably as a result of increased automation C RR 248/1999. AK Weyman & CJ Kelly In their Repor t highlight the many Risk Per ception & R isk C ommunication Theor ies. One particular comentary stood out "However, the degree of consensu s r egarding the precise nature of the influence of organisational role on per ception of r isk appear s to be limited Lee et al (1993) for example, pr ovide findings which indicate that managers and supervisor s tend to be mor e cautious in their appr oaches to r isk than workmen. By contrast other stu dies have shown that supervisor s ar e poor sour ces of risk information and have a tendency to und erestimate r isk, r eportedly they ar e 'too far r emoved from operations to make meaningful assessments, R osner & Markowitz (1995) or mor e exposed to pr oduction pr essur es than other staff, Ostber g (1980) . There are of course many other reasons and theories suggesting reasons for poor risk communication, perhaps the expression ' aquila non capit muscas' may have some resonance whereby opening of gates is generally a security function carried out by low skilled staff and health and safety is percieved to be a low priority over security and perhaps it is only for those in the lowest levels of organisations that the cost of automation "is not cost effective". This came into sharpe focus recently, The BBC Reported that a security officer in India was murdered by being run over, for, "not opening a security gate fast enough" Other communication failures have come to light whereby security officers failed to express their reasoning for having a security gate open " the gate was too heavy" theresponse " no heavier than yesterday, now get it closed" the difference between the days in question was that the previous day there was no wind on the next a gale force 8 was blowing!. From first hand experience the higher the security risk the less health safety or welfare are considered! The less authority
  • 4. within an organisation the less likely to challenge poor decission making by those with authority, this manifests it's self in statements ' just get on with it' and ' you will have to put in a business plan' before changes can be made. This becomes more evident when on closer inspection many of the gates were found to be below industry standards to the point of being extremely dangerous. Fig 3, 1, 2, 3 5, 6, 7 & 8 It is regognised that gates come in different sizes, mass and drag coefficient making it difficult to give a more accurate estimate compared with other push/ pulling manual handling operations, however it is believed that sufficient data can be obtained that will allow guidance to be given as to the effects of wind loading to enable a risk assessment to be made that is adequate and sufficient to reduce the risks to ALARP or indeed to justify automation. Many of the gates looked at were installed prior to much of the regulations now inforce and only recently brought into operation or back into operational use after many years of restricted use.. The imperative to bring back these gates would appear to override safety issues or that the risks to security justifies the means, this attidudinal disconect from policy which "inextricably linked H&S to security" manifest it's self in comments by managers and supervisors to "just get on with it" neither empirical or epidemiological evidence being considered, risk assessments apparently downplaying risk or ignoring wind as a significanthazard Manual handling of loads, pushing and pulling, this type of operation is discused in HSE RR526 Fig 1 giving data on frequency of pushing and pulling loads, giving guidance estimates of safe loads over distance and time/ frequency of pushing and pulling activities and is a usefulstart point. The data collected and reproduced in RR526 was however obtained under laboratory conditions and were not influenced by other contributory environmental factors or conditions such as wind loading. Although air movement is mentioned as a contributory factor, contextually, 'draughts' only refer to an indoor environmental condition and would not have sufficient energy to be regarded as significant to the load being pushed or pulled but may have an effect on the operator I.e. Comfort. There is also the problem of how to work out the math involved e.g. angular momentum/ torque the sum of the forces, with or against the wind force, both positive or negative and measuring angles / vectors e.t.c. This is complicated enough but becomes almost imposible where the wind force is unpradictable and variable, to complicate matters the designs or where construction materials and dimentions differ make it unrealistic that 'generic' Risk Assessments would be sufficient Fig2 demonstrates the generic type risk/hazard identification associated with gates. There are two elements of risk associated with wind loading, first, the increase/decrease in load force for the operator and second, the uncontrolled acceleration caused by wind loading. Unlike other manual handling operations, pushing and pulling of gates or loads are often subject to sudden increase and or decrease of load from the effects of wind . The analogy here would be pushing and pulling a load using a trolly, where, sudden and unpredictable varying degrees of slopes appeared out of nowhere. Opening a gate or moving a load maybe easier with the wind however converslely closing or changing direction would be subject to an increase in effort from the effect of the wind acting against the gate or load. Gusting winds are more difficult to contend with, the increased pressure may be sudden and overwhelming or again conversely a sudden drop in wind pressure may be difficult to compensate for and control resulting in an increase likelyhood of serious injury.. These problems are exacerbated by the lack of suitable handles often only one being fitted on one side of a gate or the only handle thatis available is fitted on a slide bolt, often only a short metal bar. The HSE, through examination of reported accidents, have determined that 11% musculoskeletal injuries resulting from manual handling operations are associated with pushing or pulling loads, however it is unclear whether any of the reported incidents included wind loading as a contributory factor.
  • 5. Wind loading is recognised in many other areas of Health and Safety I.e crane operations and also plays a major role in structural engineering There is little to no wind loading information available in Gate Manufacturers Data sheets e.g. Pitts Security Gates, Barriers, Blockers and Bollards PAS 68 Range, et al. British Standards BS EN 13241-2003, BS EN 12635-2002 BS EN 12605, BS EN 13849 - 2008 Although some of these Standards reference automated gates, many of these gates can be disconected from their power source and can be operated manually when necessary. Swing type security barriers found in e.g. Carparks, were the subjectof a HSE warning alert after a number of accidents being reported (HSE Advice on horizontal swing carpark barriers) A number of simmilarities are apparent, human intervention, locking mechenisms, the effects of wind and poor lighting and safety marking. It is doubtful that mechanical dampening devices would be beneficial as they would only control sudden changes in force however thepush pullforces would remain.or indeed be increased. OBJECTIVES The purpose of this study is to examinethe effects of wind loading on manually operated gates. Recognising that the operators would not have access to measuring devices inorder to carryout adequate or sufficient risk assessments prior to operating the gates. To give managers and operators guidance on the safe perameters for manually operating gates thatare simple and easy to understand Examine if wind loading increases the load above the accepted limits 20kgf for men 15 kgf for women, 10 kgf and 7 kgf respectively for keeping the load in motion. The HSE advise " that even for a minority of fit well trained individuals under faverable conditions, may if the operation guideline limits are exceeded by a factor of 2 or more may be at risk of serious injury" Determine the operationalloads in stillair Determine wind speeds above which wind loading would increase the likelyhood of serious injury Devise a graphicmanual handling toolthat willgive clearly understood inform Determining risk factors for inclusion in the graphicmanual handling tool l Provide estimates of impact(kinetic energy) forces from the gates whilst in motion l We will be looking at the effects of wind loading on gates as they affect the manual operation and not the structural integrity or design of the gates themselves but concentrating on the generality of the effects that wind loading may have and to prepare guidance on contributory risk l For ease of calculation a number of assumptions are being made, area of the gates in question will be regarded as solid flat surfaces this will give an absolute maximum for wind pressure acting on the gate. Angular movement/acceleration will be regarded as non vector or torque for simplicity of calculation as wind direction is complex and variable therefor willbe calculated as perpendicular to thegate, again giving a maximum for wind loading. It will be assumed that the greatest area of danger for the operator is at the furthest from the hinge and refered to as the impact zone (IZ) . For the purpose of these calculations it is not necessary for a higher degree of accuracy however if a higher degree of accuracy is required this may be achieved by using the data and appropriate non linear formulas. The angle of wind direction relative to thegate willbe recorded for those that wish to make more accurate assessments. l As the most important factor will be that of wind pressure acting on the gates and not the capabilities of the opperators, it is intended to make direct measurements under a range of wind conditions and compare them to those taken under still air conditions this will give a direct comparison of increased loading on gates of different dimensions and construction under different environmentalconditions l Wind speed = m/s
  • 6. l Acceleration =m/s^2 l Mass = kg l Wind pressure = kg/m^2 = N/m^2 l Force, pushing or pulling required to control the gatein motion = kgf Fig 1 Fig 1 It would be tempting for managers not to consider wind as a significant hazard. For managers, RR526 Although "other environmentalfactors" have to be considered it is believed thatthisreport missed the significance of the effects of wind on high risk push pull operations being carried out
  • 7. Figure 2 Fig 2 . For the average person, carrying out the mathmatics prior to a manual handling operation (push pull) would be wholly unreasonable and like an Inspector "who do not typically pocess objective force measuring equipement " RR562 Executive Recommendations, et al, would be unrealistic
  • 8. Figure 3 Typical layout for identifying risk areas on gates Note that the forces required to operate the gate or frequency of use (push pull manual handling) handles and fittings are absent nor is wind identified as a significant factor. The 'weight' of the gate is supported by the hinges and load bearing style however the mass of the gate is independent of how the weight is supported.
  • 9. Fig 4a Guidance to the increase in force required to control the loading Figure 4a A suggested diagram of the extra force needed to carryout push pull opperations. where wind is a significant factor. For simplicity and ease of use this diagram uses the same 'traffic signal' format and should be used in conjunction with the load diagram Fig 1. The combination of wind pressure in N/m^2 and the bodily force in kgf to control the gate whilst in motion
  • 10. Fig 4b Fig 4b Wind force conversion Figure 5. Suggested data for inclusion
  • 11. Figure 5 Data collection Data collection Details of the gates, construction, dimensions and approximate mass.. Number of hinges and fittings Orientation I.e 270°-90° = East / West. 0° - 180° = North / South Wind speed and direction (from perpendicular to the gate) 0° = perpendicular . Defects Environmental conditions, day, night, rain, lighting etc.