Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
What can Developments of National Significance learn from the NSIP regime?
1. Planning Inspectorate Wales Stakeholder
Event
What can DNS learn from the NSIP
regime?
Elizabeth Dunn - Planning Partner
30 September 2015
2. Planning Inspectorate Wales
Stakeholder Event
Credentials
Burges Salmon are specialist planning and infrastructure lawyers
Advised on over 30 NSIPs to date, 20 for promoters: electricity
(nuclear, EfW, biomass, wind, grid), rail freight, highways, rail,
hazardous waste, pipelines, gas storage
Highlights include:
- advising on second ever NSIP application
- securing first NSIP DCO from DECC (3 consents in total)
- led or major participation in 8 Examinations
- third Highways Agency accepted application
- two consented schemes in construction
3. Planning Inspectorate Wales
Stakeholder Event
Credentials (2)
Extensive experience of planning for energy projects in
Wales including:
- 350MW Port Talbot biomass plant
- 299MW Pen y Cymoedd wind farm
- Brig y Cwm energy from waste facility
- Mid-Wales conjoined wind farm inquiry
- advising IACC on Wylfa new nuclear power station
- other application stage NSIPs
5. Planning Inspectorate Wales
Stakeholder Event
Overview of NSIP regime
In place since 2008 - has evolved and changed
Decisions by Ministers on recommendation from Examining Authority
Statutory time period for examination (6 months) and decision (3+3 months)
Applies to specific projects and thresholds, also voluntary regime
Supported by suite of PINS advice notes and CLG guidance notes
Underpinned by National Policy Statements approved by Westminster
Front-loaded regime and aim for “one-stop shop”
Consent is statutory instrument – power to amend and disapply legislation,
statutory nuisance defence, CPO and other powers available
In England may include “associated development” within application
Increased pre-application time, resource and cost vs certainty on timing and
framework for decision-making
6. Planning Inspectorate Wales
Stakeholder Event
Role of policy
To date:
- 41 NSIPs approved
- 2 refused (although Preesall underground gas storage
granted on re-determination)
- 7 challenges, only Preesall successful
7. Planning Inspectorate Wales
Stakeholder Event
Role of policy (2)
NSIPs supported by suite of National Policy Statements
(NPS)
Are principal policy for determination of NSIPs
Save for EN 6 (nuclear) are not location-specific
Recognise need – for new renewable energy projects this
is ‘urgent’
EN1 states a presumption in favour of granting consent to
energy NSIPs
Identify likely issues and impacts and approach to project
8. Planning Inspectorate Wales
Stakeholder Event
LPA Role in NSIPs
Prescribed consultee – “host” authority
Agreement of Statement of Community Consultation (SoCC)
Responses to pre-application statutory consultation
Adequacy of consultation response
Relevant representation
Local Impact Report
Engagement in examination, questions, SoCGs and hearings
In Wales – determining “associated development” applications
Planning performance agreement?
S106/community benefit/legacy considerations
Discharge “requirements” and enforcement
9. Planning Inspectorate Wales
Stakeholder Event
Challenges for NSIP regime
Not “business as usual”
Legalistic and prescriptive system that has needed amendment
Extensive guidance and advice notes and pro-active team at PINS
Expectation of front-loading – is it realistic for issues to be identified/resolved at pre-
application stage?
Engagement and resourcing from prescribed consultees – LPAs, SNCBs, other interest
groups
Accommodating the Rochdale Envelope approach – flexibility vs certainty for EIA and
consent
A document-heavy system – extensive application material, focus on written questions
and representations during examination
Autonomy and experience of Examiners
Does the system genuinely encourage public participation and engagement?
10. Planning Inspectorate Wales
Stakeholder Event
Key elements of DNS
Applies to specified projects and thresholds
Decisions by Welsh Ministers on recommendation of Inspector
Planning permission and (optional/call-in) secondary consents
Statutory maximum timescale of 36 weeks for determination
Pre-application advice must be given by WM and LPA upon request
Requirement for developer to undertake pre-application consultation
and submit report with application
Applications can be rejected if PINS considers inadequate
PINS determines examination process with focus on written
representations
12. Planning Inspectorate Wales
Stakeholder Event
DNS vs NSIP (2)
A hybrid NSIP system for Wales?
Positives
- Statutory timeframe for decisions
- Secondary consents, including highways, other
planning permissions, listed building consent
- Defining LPA role and prescribed timing of responses
- Frontloading S106 negotiations
13. Planning Inspectorate Wales
Stakeholder Event
DNS vs NSIP (3)
Potential issues
- Expectation that pre-application consultation is on full
draft application documents
- It is enough of a one-stop shop? – limited CPO
- Securing secondary consents
- Prescribed period from PINS notification to submission
- Increased fees – PINS, LPA and WM
14. Planning Inspectorate Wales
Stakeholder Event
DNS vs NSIP (4)
To be resolved?:
- Sufficient flexibility? No outline applications
- Post-acceptance representations
- Opportunities to amend application
- Examination process – will inspector fall back on
inquiry if difficult issues?
15. Planning Inspectorate Wales
Stakeholder Event
Opportunities and challenges
DNS system has potential to deliver consents and increase developer
confidence in planning in Wales
Important to learn lessons from development of NSIP system
Clarity and transparency regarding process is essential
Secondary consents will be challenging
Increased expectation on promoters to front-load, must be matched
with delivery to timescales
Engagement from LPAs, NRW and other stakeholders is key…
So is having sufficient resource in place to properly administer the
system
Need robust approach by WM to judicial challenges
16. Planning Inspectorate Wales
Stakeholder Event
This presentation gives general information only and is not intended to be an exhaustive statement of the law. Although we have taken care
over the information, you should not rely on it as legal advice. We do not accept any liability to anyone who does rely on its content.