The document provides a progress update on valve chamber and thrust block construction for water pipeline projects. As of the date, 1307 of 2818 valve chambers are completed for rural water supply projects, with 872 remaining. For urban projects, 876 of 2021 valve chambers are completed, with 1145 remaining. A total of 2183 thrust blocks are scoped, with 475 completed and 51 remaining.