SlideShare a Scribd company logo
1 of 8
Download to read offline
1
Introduction
The ambition of the Beijing Olympics was to be “the green
games, the hi-tech games, and the peoples’ games”.
	 In the short time since its opening, the Water Cube
has become an icon of a ‘new Beijing’. The venue amazed
visitors and inspired athletes at the 2008 Olympic Games,
hosting the swimming, diving and water polo events.
	 Twenty-five world records were set in what is now the
fastest pool in world, Great Britain’s Rebecca Adlington
became a double Olympic Champion, and Michael Phelps
set a new Olympic landmark with eight gold medals.
	 The design was delivered from competition stage
through to a fully approved scheme in just 12 weeks, with
the fast-track programme continuing through to the official
opening of the Water Cube in January this year.
	 Arup received a glowing tribute from the client, Thomas Yi,
Vice General Manager of China Construction Design Institute
(CCDI); “With regard to Arup’s performance on the project we
felt that the design consortium did an amazing job. We were
deeply impressed by the professionalism of the Arup team,
who delivered the multi-disciplinary engineering services
required for this key venue for the 2008 Beijing Olympics.
The project was completed on time and within budget.”
Overseas Project of the Year 2008
Arup for The Water Cube, Beijing.
Category
Winner
Sponsor
The project
WINNER’S
CASE STUDY
APM Project Management Awards
2
	 APM’s judges agreed that the Water Cube made a
worthy winner; “Arup has managed to deliver, on time
and to budget, a truly inspirational and enduring project
for the Chinese people within a complex technical and
cultural management environment, by establishing a clear
vision and roadmap that all stakeholders aligned to. Clarity
of communication was essential and Arup mitigated this
key risk via interface management techniques aligned to
the technical and commercial interdependencies, in an
innovative manner.”
	 The scale of the project was neatly summed up by
Joanna Kennedy, Arup, who when accepting the award
on behalf of Arup’s Australasian practice, described it as
a “major collaboration” involving 20 different disciplines
over four different countries.
Background
The Water Cube was the result of an international design
competition with 10 short-listed participants, judged by a
panel of architects, engineers and pre-eminent Chinese
academics. The Arup + PTW + CCDI design was selected as
the clear winner of the competition both by the international
jury and the people of China themselves, although the
outcome could have been quite different but for some
tough decision-making by the Water Cube team.
	 The Aquatics Centre was required to be the best
Olympic swimming venue and then a popular and
well-used leisure and training facility after the games. It
was to cost no more than US$100M before the Olympics
and US$10M for its conversion to legacy mode.
	 The Olympic requirements included a 50metre
competition pool, a 33metre diving pool and a 50metre
warm up pool. The main pool hall was to have 17,000 seats
for the games and then be reduced to 7,000 seats with
other facilities added in order to make the Aquatics Centre
a viable long-term legacy. The construction was to start
before the end of 2003 and to be completed at least six
months before the Olympics to allow a sufficient period for
trial competitive events.
	 In 2003, as the fast track development program got
underway, the team from Arup, PTW Architects, and China
Construction Design International (CCDI) agreed that the
Aquatics Centre design should portray the way in which
humanity relates to water, and devoted half of the available
design competition period developing a design with a wave
shaped roof depicting the power of the surf.
	 Following the unveiling of the spectacular glowing
Bird’s Nest design for the National Stadium by the team
at Herzog & de Meuron and Arup just four weeks before
the competition deadline the Aquatics Centre team
realised their design could not win and made the difficult
decision to scrap the wave design and swiftly agreed the
component parts of the Water Cube concept.
	 The National Stadium is on the neighbouring site to the
Aquatics Centre, the two sites separated by a protected
historic axis to Beijing’s Forbidden City, factors that led the
team to develop a complimentary design to the Bird’s Nest.
They concluded that a cube concept would appeal to the
typical Chinese way of understanding beauty – a subtle,
thought-provoking design representing the beauty and
serenity of calm, untroubled water.
	 The two opposing shapes sit together in harmony;
the Water Cube is blue against the Stadium’s red, water
versus fire, square versus round, male versus female,
earth versus heaven.
WINNER’S
CASE STUDY
APM Project Management Awards
3
	 While the structural solution based on the formation
of soap bubbles is unique, other technical ambitions
contributed to its iconic form.
	 The Water Cube is an insulated greenhouse, which
maximises the use of solar energy for both heating
and lighting.
	 The use of ETFE (ethylene tetrafluoroethylene – a kind
of plastic) in lieu of glass creates a superior acoustic
environment, reduces the weight of material supported
by the structure, improves seismic performance, and is
self cleaning and recyclable. The roof collects and re-uses
all rainwater that falls on the building.
	 Despite the building’s apparent complexity because
the structure is based on a repetitive geometry, the
sub-components repeat across the building. There
are only four different nodal geometries, three typical
member lengths, and 22 different ETFE pillow shapes,
greatly reducing the time and costs of production and
installation.
	 The design sets a new precedent for engineering
approvals for the Chinese Olympic venues. Without
performance-based fire engineering (a first for China)
the Water Cube as we know it would not exist. The
building is the result of integrating the technical
requirements of all the relevant engineering disciplines,
not the result of a single dominant one.
	 Due to its complexity (the structure consists of 22,000
steel members and 12,000 nodes), the entire project
had to be conceived and modelled during the last three
weeks of the design competition in three dimensions.
	 Numerous new techniques and pieces of software
were developed specifically for the Water Cube
project. This new software was used to generate the
geometry, create a physical prototype, optimise the
structural performance, analyse acoustics, smoke
spread, and pedestrian egress, and to provide
construction documentation in a fully automated
four dimensional sequence.
The challenges
In winning, the Arup team had created a significant
challenge for itself. The competition concept had
enormous wow-factor, and was based on solid engineering
principles, but many of the concepts were so cutting
edge that multiple streams of research and development
were still needed to prove the design both internally and
to design partners, and to sell technical aspects to the
Chinese approval authorities.
	 Despite the complexities involved, the Water Cube
always had one absolute given – a fixed end date. It was
up to Arup’s project management team to deal with major
timing issues along the way, most notably delivering the
physical venue design well in advance of knowing who
would operate the Water Cube before and after the games,
and how they may want to reconfigure the building.
	 There were no easy answers to these issues, however
the key to success was a combination of involving Arup’s
specialist designers and project managers with expertise
in Olympic sites. These specialists provided a real
understanding of how Olympic events will be operated,
how the many operational streams must be linked, how to
balance the needs of stakeholders, and how the venue sits
within the wider Olympic organisational framework.
	 The design and construction of the Water Cube, while
pushing back the boundaries of innovation, is essentially
business as usual for Arup. Arup is renowned for taking on
large and complex designs and bringing them to fruition.
However, the actual project management of an Olympic
venue for Arup is anything but business as usual.
Communication
The binding thread in the success of the Water Cube
project was the quality and depth of communication
both internally and externally. As well as day-to-day team
communication and information management processes,
Arup’s communication strategy established the vision and
key messages, and how these would be integrated into
daily project life.
	 The strategy produced by Arup’s project managers
went beyond planning the formal internal and external
methods of communication – it encompassed the need
for the continuous incorporation of lessons learnt in
dealing with stakeholders in a different location, and
with a different culture and language. In doing so it
provided a vehicle for relationship management and
stakeholder engagement.
	 At the implementation plan workshop, Arup’s project
management team focused initially on the need to articulate
and communicate a very clear project vision for the Water
Cube design. This was intended to have multiple benefits.
Most simply, the vision would provide improved clarity and
autonomy to the design team members.
	 This would help achieve a quality outcome in a very
short period of time, by allowing parallel streams of activity
to converge quickly and accurately. It was also hoped
that having a robust vision would greatly help achieve
alignment and buy-in from other project stakeholders.
International aspects
- the management
of difference
More challenging for Arup’s project management
team than the technical aspects of the Water Cube,
and ultimately far more rewarding, was learning and
understanding the business culture and context in China.
It was not only ‘foreign’ to Arup at the start of the project,
but also highly difficult to read, so they held some specific
internal sessions with Chinese team members to agree
WINNER’S
CASE STUDY
APM Project Management Awards
4
their approach to the early ‘management of difference’.
This partly focused on maintaining leverage over
commercial arrangements, but mainly looked at how to
minimise and manage the risks of the specific differences
in norms, practices and expectations through the project
lifecycle.
	 The complex and dynamic nature of the Chinese
market, particularly in the context of the Olympics, meant
that the risks associated with delivering the Water Cube
could not be underestimated. Beijing’s lack of regulatory
transparency and regional differences, as well as a
relationship-based business culture were among
the factors Arup identified that made China a challenging
project environment.
	 Arup’s project management team looked at a diverse
range of risks, trying to understand and plan their
approach to the project in the unfamiliar context of China’s
legal, social, cultural, economical and technological
environment. Other than the commercial risk of delayed
payment, the key risks identified were social – how
China’s business culture might affect the relationships and
dynamics within the international Water Cube team, and
with the external stakeholders involved in approving the
design concept.
	 Social risks such as cultural misunderstandings could
have completely derailed or significantly delayed the
Water Cube project. Relationship building is fundamental
in Chinese business, so understanding Guanxi – a form of
social networking – and how to authentically cultivate and
manage it was vital to the Arup project management team.
	 Other important factors in the approach included:
	 Emphasising Arup’s international reputation and the
depth and diversity of its activities and locations.
	 Ensuring that all interactions with Chinese stakeholders
involved giving them the highest possible quality of
service, both in terms of the material issued and the
Arup staff directly involved with them.
	 It was important to involve well-respected senior
engineers from Arup’s Beijing and Hong Kong offices at
key stages of the approvals process. Their influence and
local knowledge of the Chinese legislation, coupled with
Arup’s involvement in other high profile Olympic projects
in Beijing, were leveraged to convince some conservative
authorities to accept a range of innovative approaches to
the engineering design that didn’t follow the prescriptive
rules of the Chinese building codes.
	 This was the number one risk in the early stages of the
project, and the formal approval of the engineering design
in early 2004 set a major precedent and direction for other
Olympic projects.
	 Arup’s specialist project managers were very specific
during contract negotiations to clearly define the scope of
services and the interfaces with Chinese design partners,
and were robust in contract negotiations that removed
some of the post-Olympic payment milestones that were
unrelated to Arup’s scope. The result was a financial
success despite the considerable risks of working on
such a fast track project, with international partners and
stakeholders, on a project involving such groundbreaking
design techniques and materials.
	 By deliberately resolving any potential conflicts early,
Arup were able to sign a contract and facilitate a smooth
and seamless handover to their Chinese partners with
clearly understood and accepted interfaces.
WINNER’S
CASE STUDY
APM Project Management Awards
5
Interface management
Some of the challenges faced included the integration and
the coordination of the many interfaces for the project
involving multiple stakeholders with conflicting demands.
Coordinating the requirements for athletes, officials,
VIPs, written press, broadcasters, workforce, sponsors,
spectators, and of course the operator, is complex and
requires delicate balance.
	 Arup’s project management team had the challenge of
coordinating 20 specialist Arup engineering disciplines,
ensuring they were properly integrated, and that the
complex interfaces of the Water Cube were properly
understood and documented.
	 Developing on previous Arup project management
work at London’s Heathrow Terminal 5, the project
management team introduced an interface management
strategy which divided component parts of the Water
Cube into volumes defined by physical and time
boundaries which were described in a project volume
register and each volume assigned an owner.
	 An interface occurred when anything touched or
crossed a boundary. Initially all high (key) and low level
interfaces were identified and captured on a register, and
regular interface management and coordination meetings
held involving all parties. The principle began working
very well internally, and was quickly expanded to include
external interfaces where Arup required information from
another team or third party – e.g. the interior designers, or
utility supplies from off site. These external interfaces were
classified as:
	 Physical – a point or plane common to two or more
parties at which a physical interdependency exists, e.g.
the location of an underground service or duct route.
	 Functional – a relationship between two parties at
which performance independency exists, eg power
requirements or data connectivity.
	 Organisational and contractual – a relationship between
two parties in which a delineation in scope or contractual
responsibility exists, e.g. the development of details by
Arup’s Chinese design partners CCDI based on Arup’s
scheme designs, or interfaces between civil engineering
and architectural landscaping documentation.
	 Operational – a relationship between two parties at
which delineation in operational responsibility exists,
e.g. maintenance for equipment under warranty with the
ongoing maintenance and replacement by the operator,
and the short term responsibilities for Olympic overlay
compared to pre-Olympics mode and then legacy mode.
The management of interfaces became one of the most
important functions of the project management team
during the Water Cube design and in the longer term,
Arup believes the results will also generate significant
savings in construction cost compared to current practice.
Safety in design
Measured by international standards, construction site
safety records in China are poor. At the implementation
plan workshop, Arup’s project management team made
a strong commitment to explore the risk-prone activities
likely to occur in the construction of the Water Cube,
and to potentially improve safety by following a ‘Safety in
Design’ approach. This included producing documentation
that would improve safety awareness, suggesting planned
and logical methods for construction and maintenance.
	 Using the UK Construction Design and Management
(CDM) Regulations, and draft NSW legislation, this
approach was intended to ensure that unusual hazards
and risks (such as post-Olympic alterations to the internal
fit-out, and working-at-height hazards involved in
maintenance of light fittings or adjusting broadcasting
equipment) were eliminated or controlled at the design
stage wherever possible.
	 The final hazard risk register was included with tender
documentation along with recommendations that it be
incorporated into the safety management plans for the
various package contractors on site.
The people factor
To remove potential pinch points from specific key staff
becoming overloaded, and to allow technical staff more
freedom, Arup’s project managers established
semi-independent teams with their own leadership,
to progress in parallel streams.
	 The four teams included design, product research,
stakeholder engagement and commercial issues such as
scope, contract and fees. For example, Arup established
clean interfaces that would allow the finalisation of the
structural geometry and research into the ETFE facade
performance to proceed without holding up the general
space planning of the building. Leadership for key
stakeholder meetings was separate from commercial
negotiations, so that one did not compromise the other.
	 Following the success of the Water Cube
implementation model, it has now become standard
practice on all of Arup’s major projects. Having specialist
project managers providing leadership, while still providing
freedom to technical staff, significantly improved the
design process and embedding project management into
the business was more easily accepted as the specialist
project managers on the Water Cube also had technical
engineering backgrounds. In this way the specialist project
managers were able to contribute at all levels, rather than
ever being perceived as a ‘non-technical’ overhead.
Developing the tools to deliver
The Water Cube was a catalyst for the development of
a range of bespoke project management planning and
monitoring tools. Such tools were needed to deliver such
WINNER’S
CASE STUDY
APM Project Management Awards
6
a large multidisciplinary project, delivered across different
offices, and with a program that demanded reporting,
monitoring and action to happen in real time.
	 A range of project management tools established
for the Water Cube have since been developed further
through internal funding and are now being rolled out on
all major Arup projects in the Australasia Region. These
include simple protocols for shared servers and email filing
between multiple offices, technical management of project
interfaces, safety in design and construction sequencing,
through to more complex programming applications that
interface with Arup’s global cost monitoring system to
provide detailed forecasting and performance reporting
capabilities such as resource management and earned
value management.
	 In fact, following on from the momentum and success
of the Water Cube, there is now a dedicated systems
development & integration team based within Arup’s
Brisbane project management team that services both
internal major projects and also successfully provides
these services direct to external clients, through licensing
agreements and tailored systems development.
Conclusions
Stretching with their involvement in the design competition
in 2003, through to the emerging dynamics of working
between Chinese and Australian teams, the Water
Cube has been an incredible learning and development
experience for Arup. The Water Cube has acted as catalyst
in advancing and codifying Arup’s approach to a number of
key areas of project management knowledge.
	 In particular, these included:
	 Establishing and leading winning teams,
	 Managing relationships with stakeholders across
cultures,
	 Project management processes required on major
multidisciplinary projects,
	 Technological improvements in modelling capability.
	 These have since been used to great effect on many
other Arup projects internationally. Watching the Olympic
events in the Water Cube has been a rewarding and
humbling experience for the Arup team. There is a genuine
sense of authorship with the team members, and there
have been many presentations and discussions about why
the project was so special.
	 Of all the key messages though, the one that has
emerged above all others is the total, equitable and
transparent partnership between Arup, PTW Architects,
and CCDI.
	 The Water Cube is a unique project brought about
by a set of circumstances that perhaps may never repeat
themselves. Olympic venues are always special, but the
nature of Beijing’s aspirations to emerge on the global
stage meant that the Water Cube became a representation
to four billion viewers of a new Beijing.
	 The fact that Beijing invited international designers to be
part of the Olympics at all was unusual, and set the tone for
a genuine collaboration on the Water Cube where western
and eastern perspectives worked together with mutual
respect and openness.
	 The project management of the Water Cube has created
a lasting legacy for Beijing, and a lasting legacy for Arup’s
project management team.
WINNER’S
CASE STUDY
APM Project Management Awards
7
The APM Project Management Awards have been celebrating
project management excellence since 1993 and the broad range
of categories is designed to make entry possible for projects and
companies of all sizes and complexity.
The awards reflect the invaluable contribution project managers
make in all sectors of society and the event provides an opportunity
for industry professionals to meet with colleagues and entertain
guests as well as celebrate at one of the year’s most exciting events.
Highly regarded in the project management industry, the awards
reflect the dedication and talent that helps to shape the project
management community and the world around us. The finalists,
winners and sponsors of the awards attract national publicity for
their achievement and involvement. Winning an award provides
invaluable recognition and kudos to the careers of winners.
WINNER’S
CASE STUDY
APM Project Management Awards
For more details on the awards and how to enter or attend, visit
www.apm.org.uk/awards.asp or email awards@apm.org.uk
Joana Kennedy OBE, Director
of Ove Arup & Partners Ltd
collecting the 2008 Overseas
Project of the Year Award for
the Watercube, Beijing
Ibis House, Regent Park
Summerleys Road
Princes Risborough
Buckinghamshire, HP27 9LE
Email	 info@apm.org.uk
Web	 www.apm.org.uk
Telephone	 0845 458 1944
International 	 +44 (0)1844 271640
Facsimile	 +44 (0)1844 274509
Association for Project Management

More Related Content

What's hot

Space Studio Chennai - Architects and Interior Designers
Space Studio Chennai -  Architects and Interior DesignersSpace Studio Chennai -  Architects and Interior Designers
Space Studio Chennai - Architects and Interior DesignersShashi Rekha
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture IIAr. Mukunda K.S
 
Theory of architecture unit 03
Theory of architecture unit 03Theory of architecture unit 03
Theory of architecture unit 03Geeva Chandana
 
ARCHITECTURE PROFESSIONAL PRACTICE
ARCHITECTURE PROFESSIONAL PRACTICE ARCHITECTURE PROFESSIONAL PRACTICE
ARCHITECTURE PROFESSIONAL PRACTICE Gai3 Segar
 
Pneumatic structures
Pneumatic structuresPneumatic structures
Pneumatic structuresKrishnagnr
 
La interior design course
La interior design courseLa interior design course
La interior design courseCusen Systems
 
Lecture 2 - Organization of form and space
Lecture 2 - Organization of form and spaceLecture 2 - Organization of form and space
Lecture 2 - Organization of form and spaceYosef Yemane
 
5 Star Hotel Case study
5 Star Hotel Case study5 Star Hotel Case study
5 Star Hotel Case studyNamratha Bs
 
Sustainable architecture
Sustainable architectureSustainable architecture
Sustainable architectureTanzil Faraz
 
Geodesic Dome - History and Construction
Geodesic Dome - History and ConstructionGeodesic Dome - History and Construction
Geodesic Dome - History and ConstructionAzra Maliha
 
Principles of composition -Theory of Architecture
Principles of composition  -Theory of ArchitecturePrinciples of composition  -Theory of Architecture
Principles of composition -Theory of ArchitectureAnupama holla
 
leed certified buildings examplsPresentation team work
leed certified buildings examplsPresentation team workleed certified buildings examplsPresentation team work
leed certified buildings examplsPresentation team workgatti Teja
 

What's hot (20)

Space Studio Chennai - Architects and Interior Designers
Space Studio Chennai -  Architects and Interior DesignersSpace Studio Chennai -  Architects and Interior Designers
Space Studio Chennai - Architects and Interior Designers
 
CPAD UNIT 2.ppsx
CPAD UNIT 2.ppsxCPAD UNIT 2.ppsx
CPAD UNIT 2.ppsx
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture II
 
ANA - Company profile
ANA - Company profileANA - Company profile
ANA - Company profile
 
Folded plates
Folded platesFolded plates
Folded plates
 
Biophilic architecture
Biophilic architectureBiophilic architecture
Biophilic architecture
 
Theory of architecture unit 03
Theory of architecture unit 03Theory of architecture unit 03
Theory of architecture unit 03
 
ARCHITECTURE PROFESSIONAL PRACTICE
ARCHITECTURE PROFESSIONAL PRACTICE ARCHITECTURE PROFESSIONAL PRACTICE
ARCHITECTURE PROFESSIONAL PRACTICE
 
Urban Design - functional dimension
Urban Design - functional  dimension Urban Design - functional  dimension
Urban Design - functional dimension
 
Professional practice
Professional practiceProfessional practice
Professional practice
 
Pneumatic structures
Pneumatic structuresPneumatic structures
Pneumatic structures
 
La interior design course
La interior design courseLa interior design course
La interior design course
 
Lecture 2 - Organization of form and space
Lecture 2 - Organization of form and spaceLecture 2 - Organization of form and space
Lecture 2 - Organization of form and space
 
5 Star Hotel Case study
5 Star Hotel Case study5 Star Hotel Case study
5 Star Hotel Case study
 
Sustainable architecture
Sustainable architectureSustainable architecture
Sustainable architecture
 
Architectural Concept
Architectural Concept Architectural Concept
Architectural Concept
 
Geodesic Dome - History and Construction
Geodesic Dome - History and ConstructionGeodesic Dome - History and Construction
Geodesic Dome - History and Construction
 
Principles of composition -Theory of Architecture
Principles of composition  -Theory of ArchitecturePrinciples of composition  -Theory of Architecture
Principles of composition -Theory of Architecture
 
Concepts in Architecture
Concepts in ArchitectureConcepts in Architecture
Concepts in Architecture
 
leed certified buildings examplsPresentation team work
leed certified buildings examplsPresentation team workleed certified buildings examplsPresentation team work
leed certified buildings examplsPresentation team work
 

Similar to The Water Cube, Beijing.pdf

rocess, Physical Distribution, and Logistics Consulting Services.docx
rocess, Physical Distribution, and Logistics Consulting Services.docxrocess, Physical Distribution, and Logistics Consulting Services.docx
rocess, Physical Distribution, and Logistics Consulting Services.docxdaniely50
 
COTE Top Ten: Intelligent Design for a Restorative Future
COTE Top Ten: Intelligent Design for a Restorative FutureCOTE Top Ten: Intelligent Design for a Restorative Future
COTE Top Ten: Intelligent Design for a Restorative Futurejuliekannai
 
RHDHV Buildings Architecture 2008-18
RHDHV Buildings Architecture 2008-18RHDHV Buildings Architecture 2008-18
RHDHV Buildings Architecture 2008-18Mauritz Kruger
 
LG Magazine Auckland's Green Plans for Parks Nov16
LG Magazine Auckland's Green Plans for Parks Nov16LG Magazine Auckland's Green Plans for Parks Nov16
LG Magazine Auckland's Green Plans for Parks Nov16Mark Bowater
 
PanAm Sports Cov&SampleSpread_SM
PanAm Sports Cov&SampleSpread_SMPanAm Sports Cov&SampleSpread_SM
PanAm Sports Cov&SampleSpread_SMPamela Young
 
ESTHER_DESIGN PORTFOLIO_UPDATED.ppt
ESTHER_DESIGN PORTFOLIO_UPDATED.pptESTHER_DESIGN PORTFOLIO_UPDATED.ppt
ESTHER_DESIGN PORTFOLIO_UPDATED.pptEsther Wong
 
Long Beach Community College District Bond Construction Program
Long Beach Community College District Bond Construction ProgramLong Beach Community College District Bond Construction Program
Long Beach Community College District Bond Construction ProgramCordoba Corp
 
Science Demonstrator Session: Social and Earth Sciences
Science Demonstrator Session: Social and Earth SciencesScience Demonstrator Session: Social and Earth Sciences
Science Demonstrator Session: Social and Earth SciencesEOSCpilot .eu
 
SteveHerron-Portfolio_160208
SteveHerron-Portfolio_160208SteveHerron-Portfolio_160208
SteveHerron-Portfolio_160208Steven Herron
 
LohYewCheng-Portfolio-20160405
LohYewCheng-Portfolio-20160405LohYewCheng-Portfolio-20160405
LohYewCheng-Portfolio-20160405Yew Cheng Loh
 
Tubine foundation design
Tubine foundation designTubine foundation design
Tubine foundation designniketmahajan
 
IRJET- Design and Optimization of Carbonized Liquids in a Filling Bottle ...
IRJET-  	  Design and Optimization of Carbonized Liquids in a Filling Bottle ...IRJET-  	  Design and Optimization of Carbonized Liquids in a Filling Bottle ...
IRJET- Design and Optimization of Carbonized Liquids in a Filling Bottle ...IRJET Journal
 
AECOM Design Overview
AECOM Design OverviewAECOM Design Overview
AECOM Design Overviewjlohnes
 
Nikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural PortfolioNikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural Portfolionikoladakic
 
Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16Carige Andrew
 
Eurohull LTD presentation
Eurohull LTD presentationEurohull LTD presentation
Eurohull LTD presentationEUROHULL LTD
 

Similar to The Water Cube, Beijing.pdf (20)

rocess, Physical Distribution, and Logistics Consulting Services.docx
rocess, Physical Distribution, and Logistics Consulting Services.docxrocess, Physical Distribution, and Logistics Consulting Services.docx
rocess, Physical Distribution, and Logistics Consulting Services.docx
 
COTE Top Ten: Intelligent Design for a Restorative Future
COTE Top Ten: Intelligent Design for a Restorative FutureCOTE Top Ten: Intelligent Design for a Restorative Future
COTE Top Ten: Intelligent Design for a Restorative Future
 
Academic Portfolio
Academic PortfolioAcademic Portfolio
Academic Portfolio
 
slides
slidesslides
slides
 
RHDHV Buildings Architecture 2008-18
RHDHV Buildings Architecture 2008-18RHDHV Buildings Architecture 2008-18
RHDHV Buildings Architecture 2008-18
 
LG Magazine Auckland's Green Plans for Parks Nov16
LG Magazine Auckland's Green Plans for Parks Nov16LG Magazine Auckland's Green Plans for Parks Nov16
LG Magazine Auckland's Green Plans for Parks Nov16
 
PanAm Sports Cov&SampleSpread_SM
PanAm Sports Cov&SampleSpread_SMPanAm Sports Cov&SampleSpread_SM
PanAm Sports Cov&SampleSpread_SM
 
ESTHER_DESIGN PORTFOLIO_UPDATED.ppt
ESTHER_DESIGN PORTFOLIO_UPDATED.pptESTHER_DESIGN PORTFOLIO_UPDATED.ppt
ESTHER_DESIGN PORTFOLIO_UPDATED.ppt
 
Long Beach Community College District Bond Construction Program
Long Beach Community College District Bond Construction ProgramLong Beach Community College District Bond Construction Program
Long Beach Community College District Bond Construction Program
 
2016 04 Jennifer Chuang Resume Portfolio
2016 04 Jennifer Chuang Resume Portfolio2016 04 Jennifer Chuang Resume Portfolio
2016 04 Jennifer Chuang Resume Portfolio
 
Science Demonstrator Session: Social and Earth Sciences
Science Demonstrator Session: Social and Earth SciencesScience Demonstrator Session: Social and Earth Sciences
Science Demonstrator Session: Social and Earth Sciences
 
2015-design-paper
2015-design-paper2015-design-paper
2015-design-paper
 
SteveHerron-Portfolio_160208
SteveHerron-Portfolio_160208SteveHerron-Portfolio_160208
SteveHerron-Portfolio_160208
 
LohYewCheng-Portfolio-20160405
LohYewCheng-Portfolio-20160405LohYewCheng-Portfolio-20160405
LohYewCheng-Portfolio-20160405
 
Tubine foundation design
Tubine foundation designTubine foundation design
Tubine foundation design
 
IRJET- Design and Optimization of Carbonized Liquids in a Filling Bottle ...
IRJET-  	  Design and Optimization of Carbonized Liquids in a Filling Bottle ...IRJET-  	  Design and Optimization of Carbonized Liquids in a Filling Bottle ...
IRJET- Design and Optimization of Carbonized Liquids in a Filling Bottle ...
 
AECOM Design Overview
AECOM Design OverviewAECOM Design Overview
AECOM Design Overview
 
Nikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural PortfolioNikola Dakic - Architectural Portfolio
Nikola Dakic - Architectural Portfolio
 
Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16
 
Eurohull LTD presentation
Eurohull LTD presentationEurohull LTD presentation
Eurohull LTD presentation
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

The Water Cube, Beijing.pdf

  • 1. 1 Introduction The ambition of the Beijing Olympics was to be “the green games, the hi-tech games, and the peoples’ games”. In the short time since its opening, the Water Cube has become an icon of a ‘new Beijing’. The venue amazed visitors and inspired athletes at the 2008 Olympic Games, hosting the swimming, diving and water polo events. Twenty-five world records were set in what is now the fastest pool in world, Great Britain’s Rebecca Adlington became a double Olympic Champion, and Michael Phelps set a new Olympic landmark with eight gold medals. The design was delivered from competition stage through to a fully approved scheme in just 12 weeks, with the fast-track programme continuing through to the official opening of the Water Cube in January this year. Arup received a glowing tribute from the client, Thomas Yi, Vice General Manager of China Construction Design Institute (CCDI); “With regard to Arup’s performance on the project we felt that the design consortium did an amazing job. We were deeply impressed by the professionalism of the Arup team, who delivered the multi-disciplinary engineering services required for this key venue for the 2008 Beijing Olympics. The project was completed on time and within budget.” Overseas Project of the Year 2008 Arup for The Water Cube, Beijing. Category Winner Sponsor The project WINNER’S CASE STUDY APM Project Management Awards
  • 2. 2 APM’s judges agreed that the Water Cube made a worthy winner; “Arup has managed to deliver, on time and to budget, a truly inspirational and enduring project for the Chinese people within a complex technical and cultural management environment, by establishing a clear vision and roadmap that all stakeholders aligned to. Clarity of communication was essential and Arup mitigated this key risk via interface management techniques aligned to the technical and commercial interdependencies, in an innovative manner.” The scale of the project was neatly summed up by Joanna Kennedy, Arup, who when accepting the award on behalf of Arup’s Australasian practice, described it as a “major collaboration” involving 20 different disciplines over four different countries. Background The Water Cube was the result of an international design competition with 10 short-listed participants, judged by a panel of architects, engineers and pre-eminent Chinese academics. The Arup + PTW + CCDI design was selected as the clear winner of the competition both by the international jury and the people of China themselves, although the outcome could have been quite different but for some tough decision-making by the Water Cube team. The Aquatics Centre was required to be the best Olympic swimming venue and then a popular and well-used leisure and training facility after the games. It was to cost no more than US$100M before the Olympics and US$10M for its conversion to legacy mode. The Olympic requirements included a 50metre competition pool, a 33metre diving pool and a 50metre warm up pool. The main pool hall was to have 17,000 seats for the games and then be reduced to 7,000 seats with other facilities added in order to make the Aquatics Centre a viable long-term legacy. The construction was to start before the end of 2003 and to be completed at least six months before the Olympics to allow a sufficient period for trial competitive events. In 2003, as the fast track development program got underway, the team from Arup, PTW Architects, and China Construction Design International (CCDI) agreed that the Aquatics Centre design should portray the way in which humanity relates to water, and devoted half of the available design competition period developing a design with a wave shaped roof depicting the power of the surf. Following the unveiling of the spectacular glowing Bird’s Nest design for the National Stadium by the team at Herzog & de Meuron and Arup just four weeks before the competition deadline the Aquatics Centre team realised their design could not win and made the difficult decision to scrap the wave design and swiftly agreed the component parts of the Water Cube concept. The National Stadium is on the neighbouring site to the Aquatics Centre, the two sites separated by a protected historic axis to Beijing’s Forbidden City, factors that led the team to develop a complimentary design to the Bird’s Nest. They concluded that a cube concept would appeal to the typical Chinese way of understanding beauty – a subtle, thought-provoking design representing the beauty and serenity of calm, untroubled water. The two opposing shapes sit together in harmony; the Water Cube is blue against the Stadium’s red, water versus fire, square versus round, male versus female, earth versus heaven. WINNER’S CASE STUDY APM Project Management Awards
  • 3. 3 While the structural solution based on the formation of soap bubbles is unique, other technical ambitions contributed to its iconic form. The Water Cube is an insulated greenhouse, which maximises the use of solar energy for both heating and lighting. The use of ETFE (ethylene tetrafluoroethylene – a kind of plastic) in lieu of glass creates a superior acoustic environment, reduces the weight of material supported by the structure, improves seismic performance, and is self cleaning and recyclable. The roof collects and re-uses all rainwater that falls on the building. Despite the building’s apparent complexity because the structure is based on a repetitive geometry, the sub-components repeat across the building. There are only four different nodal geometries, three typical member lengths, and 22 different ETFE pillow shapes, greatly reducing the time and costs of production and installation. The design sets a new precedent for engineering approvals for the Chinese Olympic venues. Without performance-based fire engineering (a first for China) the Water Cube as we know it would not exist. The building is the result of integrating the technical requirements of all the relevant engineering disciplines, not the result of a single dominant one. Due to its complexity (the structure consists of 22,000 steel members and 12,000 nodes), the entire project had to be conceived and modelled during the last three weeks of the design competition in three dimensions. Numerous new techniques and pieces of software were developed specifically for the Water Cube project. This new software was used to generate the geometry, create a physical prototype, optimise the structural performance, analyse acoustics, smoke spread, and pedestrian egress, and to provide construction documentation in a fully automated four dimensional sequence. The challenges In winning, the Arup team had created a significant challenge for itself. The competition concept had enormous wow-factor, and was based on solid engineering principles, but many of the concepts were so cutting edge that multiple streams of research and development were still needed to prove the design both internally and to design partners, and to sell technical aspects to the Chinese approval authorities. Despite the complexities involved, the Water Cube always had one absolute given – a fixed end date. It was up to Arup’s project management team to deal with major timing issues along the way, most notably delivering the physical venue design well in advance of knowing who would operate the Water Cube before and after the games, and how they may want to reconfigure the building. There were no easy answers to these issues, however the key to success was a combination of involving Arup’s specialist designers and project managers with expertise in Olympic sites. These specialists provided a real understanding of how Olympic events will be operated, how the many operational streams must be linked, how to balance the needs of stakeholders, and how the venue sits within the wider Olympic organisational framework. The design and construction of the Water Cube, while pushing back the boundaries of innovation, is essentially business as usual for Arup. Arup is renowned for taking on large and complex designs and bringing them to fruition. However, the actual project management of an Olympic venue for Arup is anything but business as usual. Communication The binding thread in the success of the Water Cube project was the quality and depth of communication both internally and externally. As well as day-to-day team communication and information management processes, Arup’s communication strategy established the vision and key messages, and how these would be integrated into daily project life. The strategy produced by Arup’s project managers went beyond planning the formal internal and external methods of communication – it encompassed the need for the continuous incorporation of lessons learnt in dealing with stakeholders in a different location, and with a different culture and language. In doing so it provided a vehicle for relationship management and stakeholder engagement. At the implementation plan workshop, Arup’s project management team focused initially on the need to articulate and communicate a very clear project vision for the Water Cube design. This was intended to have multiple benefits. Most simply, the vision would provide improved clarity and autonomy to the design team members. This would help achieve a quality outcome in a very short period of time, by allowing parallel streams of activity to converge quickly and accurately. It was also hoped that having a robust vision would greatly help achieve alignment and buy-in from other project stakeholders. International aspects - the management of difference More challenging for Arup’s project management team than the technical aspects of the Water Cube, and ultimately far more rewarding, was learning and understanding the business culture and context in China. It was not only ‘foreign’ to Arup at the start of the project, but also highly difficult to read, so they held some specific internal sessions with Chinese team members to agree WINNER’S CASE STUDY APM Project Management Awards
  • 4. 4 their approach to the early ‘management of difference’. This partly focused on maintaining leverage over commercial arrangements, but mainly looked at how to minimise and manage the risks of the specific differences in norms, practices and expectations through the project lifecycle. The complex and dynamic nature of the Chinese market, particularly in the context of the Olympics, meant that the risks associated with delivering the Water Cube could not be underestimated. Beijing’s lack of regulatory transparency and regional differences, as well as a relationship-based business culture were among the factors Arup identified that made China a challenging project environment. Arup’s project management team looked at a diverse range of risks, trying to understand and plan their approach to the project in the unfamiliar context of China’s legal, social, cultural, economical and technological environment. Other than the commercial risk of delayed payment, the key risks identified were social – how China’s business culture might affect the relationships and dynamics within the international Water Cube team, and with the external stakeholders involved in approving the design concept. Social risks such as cultural misunderstandings could have completely derailed or significantly delayed the Water Cube project. Relationship building is fundamental in Chinese business, so understanding Guanxi – a form of social networking – and how to authentically cultivate and manage it was vital to the Arup project management team. Other important factors in the approach included: Emphasising Arup’s international reputation and the depth and diversity of its activities and locations. Ensuring that all interactions with Chinese stakeholders involved giving them the highest possible quality of service, both in terms of the material issued and the Arup staff directly involved with them. It was important to involve well-respected senior engineers from Arup’s Beijing and Hong Kong offices at key stages of the approvals process. Their influence and local knowledge of the Chinese legislation, coupled with Arup’s involvement in other high profile Olympic projects in Beijing, were leveraged to convince some conservative authorities to accept a range of innovative approaches to the engineering design that didn’t follow the prescriptive rules of the Chinese building codes. This was the number one risk in the early stages of the project, and the formal approval of the engineering design in early 2004 set a major precedent and direction for other Olympic projects. Arup’s specialist project managers were very specific during contract negotiations to clearly define the scope of services and the interfaces with Chinese design partners, and were robust in contract negotiations that removed some of the post-Olympic payment milestones that were unrelated to Arup’s scope. The result was a financial success despite the considerable risks of working on such a fast track project, with international partners and stakeholders, on a project involving such groundbreaking design techniques and materials. By deliberately resolving any potential conflicts early, Arup were able to sign a contract and facilitate a smooth and seamless handover to their Chinese partners with clearly understood and accepted interfaces. WINNER’S CASE STUDY APM Project Management Awards
  • 5. 5 Interface management Some of the challenges faced included the integration and the coordination of the many interfaces for the project involving multiple stakeholders with conflicting demands. Coordinating the requirements for athletes, officials, VIPs, written press, broadcasters, workforce, sponsors, spectators, and of course the operator, is complex and requires delicate balance. Arup’s project management team had the challenge of coordinating 20 specialist Arup engineering disciplines, ensuring they were properly integrated, and that the complex interfaces of the Water Cube were properly understood and documented. Developing on previous Arup project management work at London’s Heathrow Terminal 5, the project management team introduced an interface management strategy which divided component parts of the Water Cube into volumes defined by physical and time boundaries which were described in a project volume register and each volume assigned an owner. An interface occurred when anything touched or crossed a boundary. Initially all high (key) and low level interfaces were identified and captured on a register, and regular interface management and coordination meetings held involving all parties. The principle began working very well internally, and was quickly expanded to include external interfaces where Arup required information from another team or third party – e.g. the interior designers, or utility supplies from off site. These external interfaces were classified as: Physical – a point or plane common to two or more parties at which a physical interdependency exists, e.g. the location of an underground service or duct route. Functional – a relationship between two parties at which performance independency exists, eg power requirements or data connectivity. Organisational and contractual – a relationship between two parties in which a delineation in scope or contractual responsibility exists, e.g. the development of details by Arup’s Chinese design partners CCDI based on Arup’s scheme designs, or interfaces between civil engineering and architectural landscaping documentation. Operational – a relationship between two parties at which delineation in operational responsibility exists, e.g. maintenance for equipment under warranty with the ongoing maintenance and replacement by the operator, and the short term responsibilities for Olympic overlay compared to pre-Olympics mode and then legacy mode. The management of interfaces became one of the most important functions of the project management team during the Water Cube design and in the longer term, Arup believes the results will also generate significant savings in construction cost compared to current practice. Safety in design Measured by international standards, construction site safety records in China are poor. At the implementation plan workshop, Arup’s project management team made a strong commitment to explore the risk-prone activities likely to occur in the construction of the Water Cube, and to potentially improve safety by following a ‘Safety in Design’ approach. This included producing documentation that would improve safety awareness, suggesting planned and logical methods for construction and maintenance. Using the UK Construction Design and Management (CDM) Regulations, and draft NSW legislation, this approach was intended to ensure that unusual hazards and risks (such as post-Olympic alterations to the internal fit-out, and working-at-height hazards involved in maintenance of light fittings or adjusting broadcasting equipment) were eliminated or controlled at the design stage wherever possible. The final hazard risk register was included with tender documentation along with recommendations that it be incorporated into the safety management plans for the various package contractors on site. The people factor To remove potential pinch points from specific key staff becoming overloaded, and to allow technical staff more freedom, Arup’s project managers established semi-independent teams with their own leadership, to progress in parallel streams. The four teams included design, product research, stakeholder engagement and commercial issues such as scope, contract and fees. For example, Arup established clean interfaces that would allow the finalisation of the structural geometry and research into the ETFE facade performance to proceed without holding up the general space planning of the building. Leadership for key stakeholder meetings was separate from commercial negotiations, so that one did not compromise the other. Following the success of the Water Cube implementation model, it has now become standard practice on all of Arup’s major projects. Having specialist project managers providing leadership, while still providing freedom to technical staff, significantly improved the design process and embedding project management into the business was more easily accepted as the specialist project managers on the Water Cube also had technical engineering backgrounds. In this way the specialist project managers were able to contribute at all levels, rather than ever being perceived as a ‘non-technical’ overhead. Developing the tools to deliver The Water Cube was a catalyst for the development of a range of bespoke project management planning and monitoring tools. Such tools were needed to deliver such WINNER’S CASE STUDY APM Project Management Awards
  • 6. 6 a large multidisciplinary project, delivered across different offices, and with a program that demanded reporting, monitoring and action to happen in real time. A range of project management tools established for the Water Cube have since been developed further through internal funding and are now being rolled out on all major Arup projects in the Australasia Region. These include simple protocols for shared servers and email filing between multiple offices, technical management of project interfaces, safety in design and construction sequencing, through to more complex programming applications that interface with Arup’s global cost monitoring system to provide detailed forecasting and performance reporting capabilities such as resource management and earned value management. In fact, following on from the momentum and success of the Water Cube, there is now a dedicated systems development & integration team based within Arup’s Brisbane project management team that services both internal major projects and also successfully provides these services direct to external clients, through licensing agreements and tailored systems development. Conclusions Stretching with their involvement in the design competition in 2003, through to the emerging dynamics of working between Chinese and Australian teams, the Water Cube has been an incredible learning and development experience for Arup. The Water Cube has acted as catalyst in advancing and codifying Arup’s approach to a number of key areas of project management knowledge. In particular, these included: Establishing and leading winning teams, Managing relationships with stakeholders across cultures, Project management processes required on major multidisciplinary projects, Technological improvements in modelling capability. These have since been used to great effect on many other Arup projects internationally. Watching the Olympic events in the Water Cube has been a rewarding and humbling experience for the Arup team. There is a genuine sense of authorship with the team members, and there have been many presentations and discussions about why the project was so special. Of all the key messages though, the one that has emerged above all others is the total, equitable and transparent partnership between Arup, PTW Architects, and CCDI. The Water Cube is a unique project brought about by a set of circumstances that perhaps may never repeat themselves. Olympic venues are always special, but the nature of Beijing’s aspirations to emerge on the global stage meant that the Water Cube became a representation to four billion viewers of a new Beijing. The fact that Beijing invited international designers to be part of the Olympics at all was unusual, and set the tone for a genuine collaboration on the Water Cube where western and eastern perspectives worked together with mutual respect and openness. The project management of the Water Cube has created a lasting legacy for Beijing, and a lasting legacy for Arup’s project management team. WINNER’S CASE STUDY APM Project Management Awards
  • 7. 7 The APM Project Management Awards have been celebrating project management excellence since 1993 and the broad range of categories is designed to make entry possible for projects and companies of all sizes and complexity. The awards reflect the invaluable contribution project managers make in all sectors of society and the event provides an opportunity for industry professionals to meet with colleagues and entertain guests as well as celebrate at one of the year’s most exciting events. Highly regarded in the project management industry, the awards reflect the dedication and talent that helps to shape the project management community and the world around us. The finalists, winners and sponsors of the awards attract national publicity for their achievement and involvement. Winning an award provides invaluable recognition and kudos to the careers of winners. WINNER’S CASE STUDY APM Project Management Awards For more details on the awards and how to enter or attend, visit www.apm.org.uk/awards.asp or email awards@apm.org.uk Joana Kennedy OBE, Director of Ove Arup & Partners Ltd collecting the 2008 Overseas Project of the Year Award for the Watercube, Beijing
  • 8. Ibis House, Regent Park Summerleys Road Princes Risborough Buckinghamshire, HP27 9LE Email info@apm.org.uk Web www.apm.org.uk Telephone 0845 458 1944 International +44 (0)1844 271640 Facsimile +44 (0)1844 274509 Association for Project Management