SlideShare a Scribd company logo
See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/351362037
SWEET AND SOUR EXPERIENCE OF PLANT COMMISSIONING
Article  in  The Scientific World Journal · May 2021
DOI: 10.9186/GSJ.05052021
CITATIONS
0
1 author:
Some of the authors of this publication are also working on these related projects:
Comparison Stamicarbon Saipem View project
Silo (UREA) level measurement View project
Prem Baboo
Dangote Fertilizer Ltd
70 PUBLICATIONS   13 CITATIONS   
SEE PROFILE
All content following this page was uploaded by Prem Baboo on 06 May 2021.
The user has requested enhancement of the downloaded file.
1
GSJ: Volume 9, Issue 5, May 2021, Online: ISSN 2320-9186
www.globalscientificjournal.com
SWEET AND SOUR EXPERIENCE OF PLANT COMMISSIONING
By
Prem Baboo
DGM (Production & process)
Abstract.
The paper describes a successful of plant start-
up despite the pandemic difficulties and
introduces a set of first considerations about the
possible future application of available digital
technologies for remote and distributed control
system from central control room
commissioning of complex Dangote Fertilizer
Plants. The numbers of problem were faced
during commissioning stage ultimately the 17th
march 2021 was the historical date for achieved
plant production of line-1 plant .The major
problem was pandemic due to which scarcity of
staff availability. However numbers of problems
faced in Ammonia and urea plants. About 4
time’s unsuccessful attempt were done and
finally we got historical success. In this paper
we described the failure attempt and types of
problems faced in ammonia and urea plants and
each time problems were differ from previous.
Keywords’-Commissioning, carryover,
Granular, choking, strainers. Plant design.
Introduction
Dangote Fertilizer Project is the largest
Granulated Urea Fertilizer complex coming up
in the entire fertilizer industry history in the
World, with an investment of 2.5 Billion USD
capacity of 3 Mil TPA. Acquired 500 hectares of
land for the Fertilizer Complex. Natural gas is
the main raw material for the plant. SAIPEM,
Italy, is the Engineering, Procurement and
Construction (EPC) Contractor for the project.
Tata Consulting Engineers, India, is the Project
Management Consultants (PMC) for the project.
The Dangote Fertilizer complex consists of
Ammonia and Urea plants with associated
facilities and infrastructure, to produce 3
MMTPA Urea.
The complex envisages :
• 2 x 2,200 MTPD Ammonia Plants based
on Halder Topsoe technology
• 2 x 3850 MTPD Melt Urea Plants based
on Saipem technology
• 2 x 3850 MTPD Urea Granulation
Plants based on Uhde Technology
• A Captive Power plant comprising of 3
Steam Turbine Generators of 40 MW
capacity each. Total 120 MW
• 3 Auxiliary Boilers for 40 ata steam
generation of 200 te capacity each
Process Description
The Saipem ammonia stripping process is
characterized by a urea synthesis loop operating
at about 160 kg/cm2
(g) with ammonia to carbon
dioxide molar ratio at urea reactor inlet of 3.3 -
3.6.This allows a CO2 conversion into urea of 60
- 63% in the reactor itself, also thanks to the
perforated trays which prevent back-flow and
favour gas absorption by the liquid.There are
two kinds of chemical reactions at the same time
in the urea reactor:
2NH3 + CO2 =NH2-COO-NH4 + 136230
kJ/kmol of carbamate (at 1.03 kg/cm2
; 25°C);
NH2-COO-NH4= NH2-CO-NH2 + H2O,- 17575
kJ/kmol of urea (at 1.03 kg/cm2
; 25°C)
The First reaction is strongly exothermic and the
second one is weakly endothermic and occurs in
the liquid phase at low speed. Downstream the
urea synthesis the decomposition (and relevant
recovery) of unconverted chemical reagents is
carried out in three subsequent steps: High
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 140
GSJ© 2021
www.globalscientificjournal.com
2
Pressure Decomposition in H.P. stripper;
Medium Pressure Decomposition in M.P.
Decomposer and, finally, Low Pressure
Decomposition in L.P. Decomposer. The
decomposition reaction is the reverse reaction of
the first one above showed, viz.:
Fig-1(Ammonia Plant Flow diagram)
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 141
GSJ© 2021
www.globalscientificjournal.com
3
Fig-2(Urea Plant Flow diagram)
NH2-COO-NH4 = 2NH3 + CO2 (- Heat) ,
and, as can be inferred from the equation, it is
promoted by reducing pressure and adding heat.
Water treatment Plants
“The Dangote group” has acquired the requisite
industrial land in the Lekki Free Trade Zone, for
setting up the Fertilizer Complex. To meet the
water requirement of Fertilizer plant, there is a
Raw Water Treatment Plant. The Dangote
Fertilizer Project Site is located in Nigeria,
Lagos State, and Lekki Free Trade Zone. The
Lekki Lagoon is a large expanse of shallow fresh
water located in both Lagos and Ogun state of
Nigeria. This lagoon is considered to be a
reservoir of relatively fresh water but TDS
varies from low values in wet season to high
value in dry season. The DANGOTE GROUP
has ventured into the business of manufacturing
and marketing of fertilizers. The proposed
Fertilizer complex consists of Ammonia and
Urea plants with associated facilities and
infrastructures.
The water requirement at normal capacity for the
fertilizer project for various purposes is as
follows:
► DM water (Flow rate: 120 m3/Hr. max.).
► CT make-up (Flow rate: 2140 m3/Hr. max.)
► Service water, Fire water & Potable water
(Non-drinking) (100 m3/Hr.).
► Firefighting water.
The design total treated water flow requirement
for fertilizer plant is minimum 2500 m3/hr.
The unit includes the following functional
sections:
1. Demineralized Water Production and
Storage;
2. Condensate Polishing System.
3. The plant, located in Lekki free trade
zone, Okunraye, Ibeju at Lagos state.
State will be an excellent example of
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 142
GSJ© 2021
www.globalscientificjournal.com
4
how to utilize a substantial amount of
the country’s significant gas resources,
as a raw material in the Ammonia-Urea
fertilizer process. Ultimately, the
project, when completed will make the
country self-sufficient in fertilizer
production, thereby saving it the huge
foreign reserves presently spent on
importation of fertilizer. Dangote
Group is one of the most diversified
business conglomerates in Africa with a
hard - earned reputation for excellent
business practices and products’ quality.
• Dangote Fertiliser Project is the largest
Granulated Urea Fertiliser complex
coming up in the entire fertiliser
industry history in the World, with an
investment of 2.5 Billion USD capacity
of 3 Mil TPA.
• Acquired 500 hectares of land for the
Fertiliser Complex.
• Natural gas is the main raw material for
the plant.
• Saipem, Italy is the Engineering,
Procurement and Construction (EPC)
Contractor for the project.
• Tata Consulting Engineers, India, is the
Project Management Consultants (PMC)
for the project.
• Current consumption of Urea is 700,000
tonnes. Very Poor per hectare usage of
fertiliser leading to very poor crop yield.
• By 2020, Nigerian Population - around
207 Million which would lead to
increased food consumption.
• Estimates point out that around 5 million
tonnes of Fertilisers are required per
year in Nigeria in next 5-7 years
bifurcated into 3.5 Mil tonnes of Urea
and 1.5 Mil tonnes of NPK
• Current production levels are at 1.6 Mil
tonnes
Process Design
The Raw Water Treatment Plant will
comprise of the following:
1. Intake System from Lekki Lagoon
2. Biological Treatment System (SBR)
3. Dual Media Filters
4. Ultra filtration (UF) System
5. Reverse Osmosis system
6. Outfall piping & sub-sea diffuser piping
for Reject disposal.
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 143
GSJ© 2021
www.globalscientificjournal.com
5
Fig-3
Pre-Commissioning Activities
The system was checked for conformance with
the P&ID diagrams and necessary was tested.
The purpose of this steam blowing to ensure the
associated system is clean for unit start up. HS
header and associated lines steam blowing were
carried out with HS steam supplied from
Utilities HS header. The HS lines above 6” was
provided with a blow stack to minimize the
noise pollution during steam blowing, in
addition Turbine inlets with target plates as per
Turbine vendor guidelines. Before starting steam
blowing, clearance was taken from Utilities and
their coordination. All catch pot drains in the HS
header was kept opened to avoid hammering in
the HS header. Before blowing started,
protection of equipment/piping nearby the
circuit outlets was carefully arranged, in order
avoid any damage (equipment inlet flanges was
disconnected or properly blinded). Kept close all
the instrument impulse tapping root valves.
Except the blowing loop related isolation valves,
remaining all isolation valves in the system were
closed. Steam Blowing was carried out with
Utilities/Ammonia B/L 14”-11-HS2500-15A-I
HS header 6” bypass valve. Before Steam
blowing start, all steam lines was warmed up
with the help of available drains and vents to
avoid hammering of lines. After isolation of
steam blowing loop, Vents and the drain valves
was kept open during cooling down of the
header.
Plant Start up.
For the Pre commissioning activities was done
successfully and meaningfully carried out, it is
necessary to have an overlap with the
construction phase as many checks was
performed during final phases of erection of the
equipment. Such check was helping in taking
rectification/modification actions, necessary
within the least possible time as the job is still in
progress with the construction program.
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 144
GSJ© 2021
www.globalscientificjournal.com
6
Conformity checks and documents that support
requirements for Pre-commissioning and
Mechanical Completion Partial or System. These
procedures were provided guidelines and
directions for the implementation of
commissioning activities were carried out post
equipment installation and prior to achievement
of Mechanical Completion.
After number of problems faced ultimately a
milestone achievement in the history of Nigeria
birthed on the 17th of March 2021 by young
talented and hardworking set of Engineers and
experts of the Dangote Fertilizer Limited, Lagos
Nigeria. A great feat that will indeed boost the
agricultural sector of the country, Africa and the
world at large has come. This moment was so
delighted and greatly honored to be among the
team of engineers who realized this milestone of
the largest single train fertilizer plant in Africa
of 2200MT of ammonia and 3850MT of urea
granules production. we celebrate the dutiful
commitments of our colleagues and
superiors(Expats). We indeed put in so much
from the piping to mechanical hand over, pre-
commissioning & commissioning phase through
to the production of our first urea granules.
The Commissioning activities were started for
each Unit after Mechanically completion is
certified. The main activities were following:
1. Hot alignment checked
2. Remove temporary strainers
3. Verified the proper operability of
equipment
4. Run-in of pumps with water
5. Run-in of air coolers
6. Dry run operation of the granulator was
done boiling out and chemical cleaning
according to manufactures and
contractors procedure.
7. Commissioning of lube oil and seal oil
system circulate oil .
8. Run-in of centrifugal compressors
9. Dry out of furnace.
10. Functional check of control system.
11. Functional check of ESD system.
Project Outline
PROCESS PLANTS & UTILITIES
Sr. No. Unit Number Unit name
1 10,20 Urea Train -1 & 2
2 11,21 Ammonia Train -1 & 2
3 19,29 Urea Granulation Train -1 & 2
4 30 Ammonia Storage System
5 31 UFC Storage System
6 32 Urea Bulk Storage
7 33 Urea Handling System
8 34 Urea Bagging Unit
9 12 Water Treatment System
10 13 Steam & Power Generation System
11 14 Cooling Water System
12 15 Natural Gas System
13 16 Nitrogen Production & Storage
14 17 Instrument & Plant Air System
15 18 Potable Water System
16 22 Emergency & Power Diesel System
17 23 Effluent Treatment Plant
18 24 Fire Fighting System
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 145
GSJ© 2021
www.globalscientificjournal.com
7
19 25 Ammonia Plant Flaring System
Table-1
Natural Gas Consumption
Sr. No Natural Gas Nm3/h
Number of
Train/Equipments
Total for DFL
Complex, Nm3/h
1 Fuel Gas for Reformer 31845 2 63690
2 feed Gas 58799 2 117598
3 Start up Heater 1192 2 2384
4 Each Auxiliary Boiler 7419 3 22257
Total 205929
At start up Per Day 4942296
4.942296 X 106
Forty Nine Lacs Forty Two Thousand Two Hundred Ninety Six
4.9 Millians Forty Two Thousand Two Hundred Ninety Six
Table-2
PRODUCTION & CONSUMPTION
DANGOTE FERTILIZER LTD,.LAGOS,NIGERIA
Sr.
No.
Production/Consumption
Value
for one
unit
Number of
Train/equipmen
ts
Value Unit
1 Ammonia Per Day Production 2200 2 4400 MT/Day
2 Urea Per Day Production 3850 2 7700 MT/Day
3 Total Natural gas received for Complex 4942296 Nm3/Day
4 Power Production(3 Power Generator) 41 2 82 MWH
5 Raw water Received from Lekki Lgon 3300 3300 M3/hr
6 Cooling water Circulation 91083 91083 T/H
7
Boilers Steam Generation, P-46
kg/cm2
200 3 600
T/H
8
Waste Heat Boilers Steam
Generation(in Ammonia Plants) 3
Numbers
461.4 2 922.8 T/H
9 C.W. make up 2140 2140 M3/hr
10 Treated water Flow 2500 2500 M3/hr
11 Service water/Drinking /Fire water 100 100 M3/hr
12 Urea Formaldehyde Consumption 1.203 2 2.406 T/Hr
Table-3
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 146
GSJ© 2021
www.globalscientificjournal.com
8
Fig-4(Complex input/output)
Fig-5(All Compressor Steam balance)
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 147
GSJ© 2021
www.globalscientificjournal.com
9
Problem faced in first start up
The CO2 carryover from MP absorber to
ammonia receiver was took placed in first feed
in resulting the ammonia booster pump was
cavitated and left load the reflux to M.P absorber
valve was not operated at the time resulting the
temperature reached more than 800
C.The first
feed in done on dated 12/04/2021,the fed in rate
kept low because the temperature control in urea
reactor. The activities as following
Sr. No. Time activities
1 07.00 hrs Plant check up for control valves and stock checking
2 11.00 hrs The H.P. loop heating started through L.S.
3 14.00 hrs The H.P loop K.W. heating started at the rate of 500
/hr
4 16.00 hrs Ammoniation started at the rate of 30kg/cm2/hr
5 19.00 hrs Feed in done
6 21.00 hrs Overflow observed
7 22.00 Hrs CO2 Carryover to ammonia receiver. And feed cut
Table-4
3 unsuccessful attempts also done but each time
feed was cut due to numbers of problem some of
the PSV of MP loop passing observed. Finally
on 17th
April success achieved and urea granules
sent to silo but after 14 hrs operations feed was
cut due to MP loop PSV popped.
Following problem were faced in plant start
up
1. Reformer burner choking frequently
2. Trim heater problem faced in startup
3. Synthesis reaction rate very slow in start
up
4. Many time disturbed CO2 absorption
section.
5. Power failure in many times
6. Flare was extinguished many times
7. In urea plant CO2 carryover from MP
absorber to ammonia receiver.
8. Frequently choking of pumps suction
strainers
9. Waste water section was overloaded
10. Waste water section disturbed many
times
11. Choking of granulators inlet nozzles.
12. PSV of MP loop passing observed
resulting ammonia in environment and
disturbed of waste water section.
13. Choking of 2nd
bed cooler.
14. Choking of vibrating screens
15. Steam lines PSV popped.
16. Shortage of NG.
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 148
GSJ© 2021
www.globalscientificjournal.com
10
Overall view of the Plant
Fig-6(Plant Overview)
PLANT LAYOUT
Fig-7(Overview of the Project)
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 149
GSJ© 2021
www.globalscientificjournal.com
11
Fig-8(Urea granular)
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 150
GSJ© 2021
www.globalscientificjournal.com
12
Fig-9(Happiness when production achieved)
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 151
GSJ© 2021
www.globalscientificjournal.com
13
Fig-10(MP section)
Fig-11(waste water section)
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 152
GSJ© 2021
www.globalscientificjournal.com
14
Fig-12(ammonia booster pump strainer damaged)
Conclusion
After a lot of trouble, pandemic, staff etc finally
the plant got in operational. It was a huge
challenge, in the end the plant got in production
due to the efforts of M/S. Saipem and all the
dignity of all the people brought in production of
urea. It is beyond any doubt that Dangote
Fertilizer Project has been a successful project and
the key to the success is M/S. Saipem has made
available to M/S. Halder Topsoe an innovative
combination of know-how and technological
solutions and an effective strategy of project
execution, providing an efficient and reliable
plant. With its extended portfolio of proprietary
technologies and worldwide experience in
executing projects at all levels of responsibility,
Saipem has managed and executed the DFL
project providing a single and complete point of
competence from license through to Start-Up
condition of the Plant. The synergic combination
of Saipem know-how and process leadership in
Ammonia & Urea technology and Dangote
projects experience as global contractor, has
brought unparalleled advantages to the project and
finally to the end user. A successful
commissioning effort generates site-specific
knowledge that we used by the commissioning
team to assist in the startup. Some common
support functions include operator systems
training, process systems troubleshooting,
lockout-tag out practices and other safe work
procedures, and pre-startup safety review
participation.
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 153
GSJ© 2021
www.globalscientificjournal.com
15
References-
[1] Urea Plant equipments Inspection by Prem
Baboo published in International Journal of
Engineering Research and technology
(IJERT),Volume-9 issue 03, March 2020
[2] Trouble Shooting in Water Treatment Process
for Variable TDS by Prem Baboo, Published in
International Journal of Engineering Research and
Technology(IJERT, Volume 9, Issue 04, April
2020.
GSJ: Volume 9, Issue 5, May 2021
ISSN 2320-9186 154
GSJ© 2021
www.globalscientificjournal.com
View publication stats
View publication stats

More Related Content

What's hot

Super conversion in urea reactors with super cup high efficiency trays
Super conversion in urea reactors with super cup high efficiency traysSuper conversion in urea reactors with super cup high efficiency trays
Super conversion in urea reactors with super cup high efficiency trays
Prem Baboo
 
High pressure vessel leakage in urea plants
High pressure vessel leakage in urea plantsHigh pressure vessel leakage in urea plants
High pressure vessel leakage in urea plants
Prem Baboo
 
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...Mumin HACIMUSALAR
 
Ureaplantenergysavingbyselectionoflinermaterialandinernals
UreaplantenergysavingbyselectionoflinermaterialandinernalsUreaplantenergysavingbyselectionoflinermaterialandinernals
Ureaplantenergysavingbyselectionoflinermaterialandinernals
Prem Baboo
 
Recent efforts in energy conservation in ammonia and urea plants
Recent efforts in energy conservation in ammonia and urea plantsRecent efforts in energy conservation in ammonia and urea plants
Recent efforts in energy conservation in ammonia and urea plantssweetapple763
 
Urea plant NFL Intern report
Urea plant NFL Intern reportUrea plant NFL Intern report
Urea plant NFL Intern report
Dharmendra Choudhary
 
Presentation1
Presentation1Presentation1
Presentation1
kanhaiya lal
 
Exploring market potential of ammonia absorption refrigeration plant in ferti...
Exploring market potential of ammonia absorption refrigeration plant in ferti...Exploring market potential of ammonia absorption refrigeration plant in ferti...
Exploring market potential of ammonia absorption refrigeration plant in ferti...
Supa Buoy
 
Mega Planta De Etileno - Steam Cracking
Mega Planta De Etileno  - Steam CrackingMega Planta De Etileno  - Steam Cracking
Mega Planta De Etileno - Steam Crackingeargume
 
Urea 2000plus
Urea 2000plusUrea 2000plus
Urea 2000plus
Prem Baboo
 
The project of oil refinery
The project of oil refineryThe project of oil refinery
The project of oil refinerysergio014
 
Experience of material in fertilizers industries
Experience of material in fertilizers industriesExperience of material in fertilizers industries
Experience of material in fertilizers industries
Prem Baboo
 
Installation of s 50 in ammonia plants
Installation of s 50 in ammonia plantsInstallation of s 50 in ammonia plants
Installation of s 50 in ammonia plants
Prem Baboo
 
Hydrogen recovery from purge gas(energy saving)
Hydrogen recovery from purge gas(energy saving)Hydrogen recovery from purge gas(energy saving)
Hydrogen recovery from purge gas(energy saving)
Prem Baboo
 
Fertilizers technology book
Fertilizers technology bookFertilizers technology book
Fertilizers technology book
Prem Baboo
 
Reactor & Impeller Design in Hydrogenation
Reactor & Impeller Design in Hydrogenation Reactor & Impeller Design in Hydrogenation
Reactor & Impeller Design in Hydrogenation
Gerard B. Hawkins
 
Air liquide lurgi 2016 overview of coal heavy oil ch4 to syngas h2 ammonia me...
Air liquide lurgi 2016 overview of coal heavy oil ch4 to syngas h2 ammonia me...Air liquide lurgi 2016 overview of coal heavy oil ch4 to syngas h2 ammonia me...
Air liquide lurgi 2016 overview of coal heavy oil ch4 to syngas h2 ammonia me...
Steve Wittrig
 
Gas To Liquids Technology By Valerie Sage
Gas To Liquids Technology By Valerie SageGas To Liquids Technology By Valerie Sage
Gas To Liquids Technology By Valerie SageEngineers Australia
 

What's hot (20)

Super conversion in urea reactors with super cup high efficiency trays
Super conversion in urea reactors with super cup high efficiency traysSuper conversion in urea reactors with super cup high efficiency trays
Super conversion in urea reactors with super cup high efficiency trays
 
High pressure vessel leakage in urea plants
High pressure vessel leakage in urea plantsHigh pressure vessel leakage in urea plants
High pressure vessel leakage in urea plants
 
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independ...
 
Ureaplantenergysavingbyselectionoflinermaterialandinernals
UreaplantenergysavingbyselectionoflinermaterialandinernalsUreaplantenergysavingbyselectionoflinermaterialandinernals
Ureaplantenergysavingbyselectionoflinermaterialandinernals
 
Recent efforts in energy conservation in ammonia and urea plants
Recent efforts in energy conservation in ammonia and urea plantsRecent efforts in energy conservation in ammonia and urea plants
Recent efforts in energy conservation in ammonia and urea plants
 
Urea plant NFL Intern report
Urea plant NFL Intern reportUrea plant NFL Intern report
Urea plant NFL Intern report
 
Presentation1
Presentation1Presentation1
Presentation1
 
Exploring market potential of ammonia absorption refrigeration plant in ferti...
Exploring market potential of ammonia absorption refrigeration plant in ferti...Exploring market potential of ammonia absorption refrigeration plant in ferti...
Exploring market potential of ammonia absorption refrigeration plant in ferti...
 
Mega Planta De Etileno - Steam Cracking
Mega Planta De Etileno  - Steam CrackingMega Planta De Etileno  - Steam Cracking
Mega Planta De Etileno - Steam Cracking
 
Urea 2000plus
Urea 2000plusUrea 2000plus
Urea 2000plus
 
The project of oil refinery
The project of oil refineryThe project of oil refinery
The project of oil refinery
 
Experience of material in fertilizers industries
Experience of material in fertilizers industriesExperience of material in fertilizers industries
Experience of material in fertilizers industries
 
Installation of s 50 in ammonia plants
Installation of s 50 in ammonia plantsInstallation of s 50 in ammonia plants
Installation of s 50 in ammonia plants
 
Hydrogen recovery from purge gas(energy saving)
Hydrogen recovery from purge gas(energy saving)Hydrogen recovery from purge gas(energy saving)
Hydrogen recovery from purge gas(energy saving)
 
Fertilizers technology book
Fertilizers technology bookFertilizers technology book
Fertilizers technology book
 
Reactor & Impeller Design in Hydrogenation
Reactor & Impeller Design in Hydrogenation Reactor & Impeller Design in Hydrogenation
Reactor & Impeller Design in Hydrogenation
 
Air liquide lurgi 2016 overview of coal heavy oil ch4 to syngas h2 ammonia me...
Air liquide lurgi 2016 overview of coal heavy oil ch4 to syngas h2 ammonia me...Air liquide lurgi 2016 overview of coal heavy oil ch4 to syngas h2 ammonia me...
Air liquide lurgi 2016 overview of coal heavy oil ch4 to syngas h2 ammonia me...
 
aniruddh training report
aniruddh training reportaniruddh training report
aniruddh training report
 
GTL
GTLGTL
GTL
 
Gas To Liquids Technology By Valerie Sage
Gas To Liquids Technology By Valerie SageGas To Liquids Technology By Valerie Sage
Gas To Liquids Technology By Valerie Sage
 

Similar to Sweet and sour experience of commissioning 1

Fertilizer
FertilizerFertilizer
Fertilizer
Santosh Mariyappan
 
biogas
biogasbiogas
IFFCO AONLA BARIELLY summer Training file.pdf
IFFCO AONLA BARIELLY summer   Training file.pdfIFFCO AONLA BARIELLY summer   Training file.pdf
IFFCO AONLA BARIELLY summer Training file.pdf
FIT Mahatma Jyotiba Phule Rohilkhand University Bareilly
 
Secutor Capital Management Corporation Update on Commerce Resources Corp. (Fe...
Secutor Capital Management Corporation Update on Commerce Resources Corp. (Fe...Secutor Capital Management Corporation Update on Commerce Resources Corp. (Fe...
Secutor Capital Management Corporation Update on Commerce Resources Corp. (Fe...
Rare Earths / Rare Metals
 
Oil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative NotesOil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative Notes
williampatricklaw
 
Environmental-Protection-in-Fertilizer-Plants.pdf
Environmental-Protection-in-Fertilizer-Plants.pdfEnvironmental-Protection-in-Fertilizer-Plants.pdf
Environmental-Protection-in-Fertilizer-Plants.pdf
PremBaboo4
 
IRJET-Influence of Advanced Settling Zone on COD Removal Efficiency of UASB R...
IRJET-Influence of Advanced Settling Zone on COD Removal Efficiency of UASB R...IRJET-Influence of Advanced Settling Zone on COD Removal Efficiency of UASB R...
IRJET-Influence of Advanced Settling Zone on COD Removal Efficiency of UASB R...
IRJET Journal
 
Case Study of Compressed Bio Gas Plant Installed at Hingoniya Gaushala, Jaipu...
Case Study of Compressed Bio Gas Plant Installed at Hingoniya Gaushala, Jaipu...Case Study of Compressed Bio Gas Plant Installed at Hingoniya Gaushala, Jaipu...
Case Study of Compressed Bio Gas Plant Installed at Hingoniya Gaushala, Jaipu...
IRJET Journal
 
IRJET- Treatment of Sugar Industry Wastewater by Upflow Anaerobic Sludge ...
IRJET-  	  Treatment of Sugar Industry Wastewater by Upflow Anaerobic Sludge ...IRJET-  	  Treatment of Sugar Industry Wastewater by Upflow Anaerobic Sludge ...
IRJET- Treatment of Sugar Industry Wastewater by Upflow Anaerobic Sludge ...
IRJET Journal
 
International Gas Union Bert Klamer Tokyo Japan 2003 (2)
International Gas Union Bert Klamer Tokyo Japan 2003 (2)International Gas Union Bert Klamer Tokyo Japan 2003 (2)
International Gas Union Bert Klamer Tokyo Japan 2003 (2)Bert Klamer
 
CDM project 9142 myagri bio-organic plant at ketengah palm oil mill kemaman
CDM project 9142   myagri bio-organic plant at ketengah palm oil mill kemamanCDM project 9142   myagri bio-organic plant at ketengah palm oil mill kemaman
CDM project 9142 myagri bio-organic plant at ketengah palm oil mill kemaman
Ethaya Rajan
 
NOx SOx CO2 and Urea Dust Control inFertilizers Plants.pdf
NOx SOx CO2 and Urea Dust Control inFertilizers  Plants.pdfNOx SOx CO2 and Urea Dust Control inFertilizers  Plants.pdf
NOx SOx CO2 and Urea Dust Control inFertilizers Plants.pdf
PremBaboo4
 
Transforming Invading Plants into Fuel Pellets in Senegal
Transforming Invading Plants into Fuel Pellets in Senegal  Transforming Invading Plants into Fuel Pellets in Senegal
Transforming Invading Plants into Fuel Pellets in Senegal
QZ1
 
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
William Toomey
 
tianjin by hagay shemer[1]
tianjin by hagay shemer[1]tianjin by hagay shemer[1]
tianjin by hagay shemer[1]hagay shemer
 
SMART SEWAGE TREATMENT PLANTS FOR SMART CITIES IN INDIA, NY USA - Mr. Asim C ...
SMART SEWAGE TREATMENT PLANTS FOR SMART CITIES IN INDIA, NY USA - Mr. Asim C ...SMART SEWAGE TREATMENT PLANTS FOR SMART CITIES IN INDIA, NY USA - Mr. Asim C ...
SMART SEWAGE TREATMENT PLANTS FOR SMART CITIES IN INDIA, NY USA - Mr. Asim C ...
IPPAI
 
Qatargas debottlenecking project
Qatargas debottlenecking projectQatargas debottlenecking project
Qatargas debottlenecking project
John Kingsley
 
Algae.Tec Advanced Biofuels: Investor Presentation
Algae.Tec Advanced Biofuels: Investor PresentationAlgae.Tec Advanced Biofuels: Investor Presentation
Algae.Tec Advanced Biofuels: Investor Presentation
Susan Fitzpatrick-Napier
 
The role of material in fertilizers industries with energy saving
The role of material in fertilizers industries with energy savingThe role of material in fertilizers industries with energy saving
The role of material in fertilizers industries with energy saving
PremBaboo4
 

Similar to Sweet and sour experience of commissioning 1 (20)

Fertilizer
FertilizerFertilizer
Fertilizer
 
biogas
biogasbiogas
biogas
 
IFFCO AONLA BARIELLY summer Training file.pdf
IFFCO AONLA BARIELLY summer   Training file.pdfIFFCO AONLA BARIELLY summer   Training file.pdf
IFFCO AONLA BARIELLY summer Training file.pdf
 
Secutor Capital Management Corporation Update on Commerce Resources Corp. (Fe...
Secutor Capital Management Corporation Update on Commerce Resources Corp. (Fe...Secutor Capital Management Corporation Update on Commerce Resources Corp. (Fe...
Secutor Capital Management Corporation Update on Commerce Resources Corp. (Fe...
 
Oil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative NotesOil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative Notes
 
Environmental-Protection-in-Fertilizer-Plants.pdf
Environmental-Protection-in-Fertilizer-Plants.pdfEnvironmental-Protection-in-Fertilizer-Plants.pdf
Environmental-Protection-in-Fertilizer-Plants.pdf
 
IRJET-Influence of Advanced Settling Zone on COD Removal Efficiency of UASB R...
IRJET-Influence of Advanced Settling Zone on COD Removal Efficiency of UASB R...IRJET-Influence of Advanced Settling Zone on COD Removal Efficiency of UASB R...
IRJET-Influence of Advanced Settling Zone on COD Removal Efficiency of UASB R...
 
Case Study of Compressed Bio Gas Plant Installed at Hingoniya Gaushala, Jaipu...
Case Study of Compressed Bio Gas Plant Installed at Hingoniya Gaushala, Jaipu...Case Study of Compressed Bio Gas Plant Installed at Hingoniya Gaushala, Jaipu...
Case Study of Compressed Bio Gas Plant Installed at Hingoniya Gaushala, Jaipu...
 
IRJET- Treatment of Sugar Industry Wastewater by Upflow Anaerobic Sludge ...
IRJET-  	  Treatment of Sugar Industry Wastewater by Upflow Anaerobic Sludge ...IRJET-  	  Treatment of Sugar Industry Wastewater by Upflow Anaerobic Sludge ...
IRJET- Treatment of Sugar Industry Wastewater by Upflow Anaerobic Sludge ...
 
International Gas Union Bert Klamer Tokyo Japan 2003 (2)
International Gas Union Bert Klamer Tokyo Japan 2003 (2)International Gas Union Bert Klamer Tokyo Japan 2003 (2)
International Gas Union Bert Klamer Tokyo Japan 2003 (2)
 
CDM project 9142 myagri bio-organic plant at ketengah palm oil mill kemaman
CDM project 9142   myagri bio-organic plant at ketengah palm oil mill kemamanCDM project 9142   myagri bio-organic plant at ketengah palm oil mill kemaman
CDM project 9142 myagri bio-organic plant at ketengah palm oil mill kemaman
 
NOx SOx CO2 and Urea Dust Control inFertilizers Plants.pdf
NOx SOx CO2 and Urea Dust Control inFertilizers  Plants.pdfNOx SOx CO2 and Urea Dust Control inFertilizers  Plants.pdf
NOx SOx CO2 and Urea Dust Control inFertilizers Plants.pdf
 
Transforming Invading Plants into Fuel Pellets in Senegal
Transforming Invading Plants into Fuel Pellets in Senegal  Transforming Invading Plants into Fuel Pellets in Senegal
Transforming Invading Plants into Fuel Pellets in Senegal
 
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
Valudor DAF, dissolved air flotation, and SHURE technology combine with proce...
 
tianjin by hagay shemer[1]
tianjin by hagay shemer[1]tianjin by hagay shemer[1]
tianjin by hagay shemer[1]
 
CCUS_Fracking
CCUS_FrackingCCUS_Fracking
CCUS_Fracking
 
SMART SEWAGE TREATMENT PLANTS FOR SMART CITIES IN INDIA, NY USA - Mr. Asim C ...
SMART SEWAGE TREATMENT PLANTS FOR SMART CITIES IN INDIA, NY USA - Mr. Asim C ...SMART SEWAGE TREATMENT PLANTS FOR SMART CITIES IN INDIA, NY USA - Mr. Asim C ...
SMART SEWAGE TREATMENT PLANTS FOR SMART CITIES IN INDIA, NY USA - Mr. Asim C ...
 
Qatargas debottlenecking project
Qatargas debottlenecking projectQatargas debottlenecking project
Qatargas debottlenecking project
 
Algae.Tec Advanced Biofuels: Investor Presentation
Algae.Tec Advanced Biofuels: Investor PresentationAlgae.Tec Advanced Biofuels: Investor Presentation
Algae.Tec Advanced Biofuels: Investor Presentation
 
The role of material in fertilizers industries with energy saving
The role of material in fertilizers industries with energy savingThe role of material in fertilizers industries with energy saving
The role of material in fertilizers industries with energy saving
 

More from Prem Baboo

The explosion hazard in urea process (1)
The explosion hazard in urea process (1)The explosion hazard in urea process (1)
The explosion hazard in urea process (1)
Prem Baboo
 
Urea process flow diagram
Urea process flow diagramUrea process flow diagram
Urea process flow diagram
Prem Baboo
 
Materialtechnologyforfertilizersindustries
MaterialtechnologyforfertilizersindustriesMaterialtechnologyforfertilizersindustries
Materialtechnologyforfertilizersindustries
Prem Baboo
 
Neemcoatedureaaphilosophyforenvironment
NeemcoatedureaaphilosophyforenvironmentNeemcoatedureaaphilosophyforenvironment
Neemcoatedureaaphilosophyforenvironment
Prem Baboo
 
Nano ureathephilosophyoffuture
Nano ureathephilosophyoffutureNano ureathephilosophyoffuture
Nano ureathephilosophyoffuture
Prem Baboo
 
Ammonia plant material balance
Ammonia plant material balanceAmmonia plant material balance
Ammonia plant material balance
Prem Baboo
 
How to improve safety and reliability of the high pressure section of urea pl...
How to improve safety and reliability of the high pressure section of urea pl...How to improve safety and reliability of the high pressure section of urea pl...
How to improve safety and reliability of the high pressure section of urea pl...
Prem Baboo
 
High pressure vessel_leakage_in_urea_plants (1)
High pressure vessel_leakage_in_urea_plants (1)High pressure vessel_leakage_in_urea_plants (1)
High pressure vessel_leakage_in_urea_plants (1)
Prem Baboo
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
Prem Baboo
 
P & i diagram and tagging philosphy for
P & i diagram and tagging philosphy forP & i diagram and tagging philosphy for
P & i diagram and tagging philosphy for
Prem Baboo
 
5000 tpd urea mega plants design
5000 tpd urea  mega plants design5000 tpd urea  mega plants design
5000 tpd urea mega plants design
Prem Baboo
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practices
Prem Baboo
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practices
Prem Baboo
 
5000 tpd urea plant
5000 tpd urea plant5000 tpd urea plant
5000 tpd urea plant
Prem Baboo
 
Urea granulation
Urea granulationUrea granulation
Urea granulation
Prem Baboo
 
Energy saving and waste control in mtc process
Energy saving and waste control in mtc processEnergy saving and waste control in mtc process
Energy saving and waste control in mtc process
Prem Baboo
 
2018 11 baboo the analysis and prevention of safety hazards in nfl complex
2018 11 baboo the analysis and prevention of safety hazards in nfl complex2018 11 baboo the analysis and prevention of safety hazards in nfl complex
2018 11 baboo the analysis and prevention of safety hazards in nfl complex
Prem Baboo
 
2018 baboo the lessons learned from the first 100 safety hazards in urea pla...
2018 baboo the lessons learned from the  first 100 safety hazards in urea pla...2018 baboo the lessons learned from the  first 100 safety hazards in urea pla...
2018 baboo the lessons learned from the first 100 safety hazards in urea pla...
Prem Baboo
 
Ureap lant energy improved with operation philosophyand reactor internals
Ureap lant energy improved with operation philosophyand reactor internalsUreap lant energy improved with operation philosophyand reactor internals
Ureap lant energy improved with operation philosophyand reactor internals
Prem Baboo
 
2018 06 baboo caking of urea in summer season
2018 06 baboo caking of urea in summer season2018 06 baboo caking of urea in summer season
2018 06 baboo caking of urea in summer season
Prem Baboo
 

More from Prem Baboo (20)

The explosion hazard in urea process (1)
The explosion hazard in urea process (1)The explosion hazard in urea process (1)
The explosion hazard in urea process (1)
 
Urea process flow diagram
Urea process flow diagramUrea process flow diagram
Urea process flow diagram
 
Materialtechnologyforfertilizersindustries
MaterialtechnologyforfertilizersindustriesMaterialtechnologyforfertilizersindustries
Materialtechnologyforfertilizersindustries
 
Neemcoatedureaaphilosophyforenvironment
NeemcoatedureaaphilosophyforenvironmentNeemcoatedureaaphilosophyforenvironment
Neemcoatedureaaphilosophyforenvironment
 
Nano ureathephilosophyoffuture
Nano ureathephilosophyoffutureNano ureathephilosophyoffuture
Nano ureathephilosophyoffuture
 
Ammonia plant material balance
Ammonia plant material balanceAmmonia plant material balance
Ammonia plant material balance
 
How to improve safety and reliability of the high pressure section of urea pl...
How to improve safety and reliability of the high pressure section of urea pl...How to improve safety and reliability of the high pressure section of urea pl...
How to improve safety and reliability of the high pressure section of urea pl...
 
High pressure vessel_leakage_in_urea_plants (1)
High pressure vessel_leakage_in_urea_plants (1)High pressure vessel_leakage_in_urea_plants (1)
High pressure vessel_leakage_in_urea_plants (1)
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
P & i diagram and tagging philosphy for
P & i diagram and tagging philosphy forP & i diagram and tagging philosphy for
P & i diagram and tagging philosphy for
 
5000 tpd urea mega plants design
5000 tpd urea  mega plants design5000 tpd urea  mega plants design
5000 tpd urea mega plants design
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practices
 
Inst maint practices
Inst maint practicesInst maint practices
Inst maint practices
 
5000 tpd urea plant
5000 tpd urea plant5000 tpd urea plant
5000 tpd urea plant
 
Urea granulation
Urea granulationUrea granulation
Urea granulation
 
Energy saving and waste control in mtc process
Energy saving and waste control in mtc processEnergy saving and waste control in mtc process
Energy saving and waste control in mtc process
 
2018 11 baboo the analysis and prevention of safety hazards in nfl complex
2018 11 baboo the analysis and prevention of safety hazards in nfl complex2018 11 baboo the analysis and prevention of safety hazards in nfl complex
2018 11 baboo the analysis and prevention of safety hazards in nfl complex
 
2018 baboo the lessons learned from the first 100 safety hazards in urea pla...
2018 baboo the lessons learned from the  first 100 safety hazards in urea pla...2018 baboo the lessons learned from the  first 100 safety hazards in urea pla...
2018 baboo the lessons learned from the first 100 safety hazards in urea pla...
 
Ureap lant energy improved with operation philosophyand reactor internals
Ureap lant energy improved with operation philosophyand reactor internalsUreap lant energy improved with operation philosophyand reactor internals
Ureap lant energy improved with operation philosophyand reactor internals
 
2018 06 baboo caking of urea in summer season
2018 06 baboo caking of urea in summer season2018 06 baboo caking of urea in summer season
2018 06 baboo caking of urea in summer season
 

Recently uploaded

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 

Recently uploaded (20)

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 

Sweet and sour experience of commissioning 1

  • 1. See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/351362037 SWEET AND SOUR EXPERIENCE OF PLANT COMMISSIONING Article  in  The Scientific World Journal · May 2021 DOI: 10.9186/GSJ.05052021 CITATIONS 0 1 author: Some of the authors of this publication are also working on these related projects: Comparison Stamicarbon Saipem View project Silo (UREA) level measurement View project Prem Baboo Dangote Fertilizer Ltd 70 PUBLICATIONS   13 CITATIONS    SEE PROFILE All content following this page was uploaded by Prem Baboo on 06 May 2021. The user has requested enhancement of the downloaded file.
  • 2. 1 GSJ: Volume 9, Issue 5, May 2021, Online: ISSN 2320-9186 www.globalscientificjournal.com SWEET AND SOUR EXPERIENCE OF PLANT COMMISSIONING By Prem Baboo DGM (Production & process) Abstract. The paper describes a successful of plant start- up despite the pandemic difficulties and introduces a set of first considerations about the possible future application of available digital technologies for remote and distributed control system from central control room commissioning of complex Dangote Fertilizer Plants. The numbers of problem were faced during commissioning stage ultimately the 17th march 2021 was the historical date for achieved plant production of line-1 plant .The major problem was pandemic due to which scarcity of staff availability. However numbers of problems faced in Ammonia and urea plants. About 4 time’s unsuccessful attempt were done and finally we got historical success. In this paper we described the failure attempt and types of problems faced in ammonia and urea plants and each time problems were differ from previous. Keywords’-Commissioning, carryover, Granular, choking, strainers. Plant design. Introduction Dangote Fertilizer Project is the largest Granulated Urea Fertilizer complex coming up in the entire fertilizer industry history in the World, with an investment of 2.5 Billion USD capacity of 3 Mil TPA. Acquired 500 hectares of land for the Fertilizer Complex. Natural gas is the main raw material for the plant. SAIPEM, Italy, is the Engineering, Procurement and Construction (EPC) Contractor for the project. Tata Consulting Engineers, India, is the Project Management Consultants (PMC) for the project. The Dangote Fertilizer complex consists of Ammonia and Urea plants with associated facilities and infrastructure, to produce 3 MMTPA Urea. The complex envisages : • 2 x 2,200 MTPD Ammonia Plants based on Halder Topsoe technology • 2 x 3850 MTPD Melt Urea Plants based on Saipem technology • 2 x 3850 MTPD Urea Granulation Plants based on Uhde Technology • A Captive Power plant comprising of 3 Steam Turbine Generators of 40 MW capacity each. Total 120 MW • 3 Auxiliary Boilers for 40 ata steam generation of 200 te capacity each Process Description The Saipem ammonia stripping process is characterized by a urea synthesis loop operating at about 160 kg/cm2 (g) with ammonia to carbon dioxide molar ratio at urea reactor inlet of 3.3 - 3.6.This allows a CO2 conversion into urea of 60 - 63% in the reactor itself, also thanks to the perforated trays which prevent back-flow and favour gas absorption by the liquid.There are two kinds of chemical reactions at the same time in the urea reactor: 2NH3 + CO2 =NH2-COO-NH4 + 136230 kJ/kmol of carbamate (at 1.03 kg/cm2 ; 25°C); NH2-COO-NH4= NH2-CO-NH2 + H2O,- 17575 kJ/kmol of urea (at 1.03 kg/cm2 ; 25°C) The First reaction is strongly exothermic and the second one is weakly endothermic and occurs in the liquid phase at low speed. Downstream the urea synthesis the decomposition (and relevant recovery) of unconverted chemical reagents is carried out in three subsequent steps: High GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 140 GSJ© 2021 www.globalscientificjournal.com
  • 3. 2 Pressure Decomposition in H.P. stripper; Medium Pressure Decomposition in M.P. Decomposer and, finally, Low Pressure Decomposition in L.P. Decomposer. The decomposition reaction is the reverse reaction of the first one above showed, viz.: Fig-1(Ammonia Plant Flow diagram) GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 141 GSJ© 2021 www.globalscientificjournal.com
  • 4. 3 Fig-2(Urea Plant Flow diagram) NH2-COO-NH4 = 2NH3 + CO2 (- Heat) , and, as can be inferred from the equation, it is promoted by reducing pressure and adding heat. Water treatment Plants “The Dangote group” has acquired the requisite industrial land in the Lekki Free Trade Zone, for setting up the Fertilizer Complex. To meet the water requirement of Fertilizer plant, there is a Raw Water Treatment Plant. The Dangote Fertilizer Project Site is located in Nigeria, Lagos State, and Lekki Free Trade Zone. The Lekki Lagoon is a large expanse of shallow fresh water located in both Lagos and Ogun state of Nigeria. This lagoon is considered to be a reservoir of relatively fresh water but TDS varies from low values in wet season to high value in dry season. The DANGOTE GROUP has ventured into the business of manufacturing and marketing of fertilizers. The proposed Fertilizer complex consists of Ammonia and Urea plants with associated facilities and infrastructures. The water requirement at normal capacity for the fertilizer project for various purposes is as follows: ► DM water (Flow rate: 120 m3/Hr. max.). ► CT make-up (Flow rate: 2140 m3/Hr. max.) ► Service water, Fire water & Potable water (Non-drinking) (100 m3/Hr.). ► Firefighting water. The design total treated water flow requirement for fertilizer plant is minimum 2500 m3/hr. The unit includes the following functional sections: 1. Demineralized Water Production and Storage; 2. Condensate Polishing System. 3. The plant, located in Lekki free trade zone, Okunraye, Ibeju at Lagos state. State will be an excellent example of GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 142 GSJ© 2021 www.globalscientificjournal.com
  • 5. 4 how to utilize a substantial amount of the country’s significant gas resources, as a raw material in the Ammonia-Urea fertilizer process. Ultimately, the project, when completed will make the country self-sufficient in fertilizer production, thereby saving it the huge foreign reserves presently spent on importation of fertilizer. Dangote Group is one of the most diversified business conglomerates in Africa with a hard - earned reputation for excellent business practices and products’ quality. • Dangote Fertiliser Project is the largest Granulated Urea Fertiliser complex coming up in the entire fertiliser industry history in the World, with an investment of 2.5 Billion USD capacity of 3 Mil TPA. • Acquired 500 hectares of land for the Fertiliser Complex. • Natural gas is the main raw material for the plant. • Saipem, Italy is the Engineering, Procurement and Construction (EPC) Contractor for the project. • Tata Consulting Engineers, India, is the Project Management Consultants (PMC) for the project. • Current consumption of Urea is 700,000 tonnes. Very Poor per hectare usage of fertiliser leading to very poor crop yield. • By 2020, Nigerian Population - around 207 Million which would lead to increased food consumption. • Estimates point out that around 5 million tonnes of Fertilisers are required per year in Nigeria in next 5-7 years bifurcated into 3.5 Mil tonnes of Urea and 1.5 Mil tonnes of NPK • Current production levels are at 1.6 Mil tonnes Process Design The Raw Water Treatment Plant will comprise of the following: 1. Intake System from Lekki Lagoon 2. Biological Treatment System (SBR) 3. Dual Media Filters 4. Ultra filtration (UF) System 5. Reverse Osmosis system 6. Outfall piping & sub-sea diffuser piping for Reject disposal. GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 143 GSJ© 2021 www.globalscientificjournal.com
  • 6. 5 Fig-3 Pre-Commissioning Activities The system was checked for conformance with the P&ID diagrams and necessary was tested. The purpose of this steam blowing to ensure the associated system is clean for unit start up. HS header and associated lines steam blowing were carried out with HS steam supplied from Utilities HS header. The HS lines above 6” was provided with a blow stack to minimize the noise pollution during steam blowing, in addition Turbine inlets with target plates as per Turbine vendor guidelines. Before starting steam blowing, clearance was taken from Utilities and their coordination. All catch pot drains in the HS header was kept opened to avoid hammering in the HS header. Before blowing started, protection of equipment/piping nearby the circuit outlets was carefully arranged, in order avoid any damage (equipment inlet flanges was disconnected or properly blinded). Kept close all the instrument impulse tapping root valves. Except the blowing loop related isolation valves, remaining all isolation valves in the system were closed. Steam Blowing was carried out with Utilities/Ammonia B/L 14”-11-HS2500-15A-I HS header 6” bypass valve. Before Steam blowing start, all steam lines was warmed up with the help of available drains and vents to avoid hammering of lines. After isolation of steam blowing loop, Vents and the drain valves was kept open during cooling down of the header. Plant Start up. For the Pre commissioning activities was done successfully and meaningfully carried out, it is necessary to have an overlap with the construction phase as many checks was performed during final phases of erection of the equipment. Such check was helping in taking rectification/modification actions, necessary within the least possible time as the job is still in progress with the construction program. GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 144 GSJ© 2021 www.globalscientificjournal.com
  • 7. 6 Conformity checks and documents that support requirements for Pre-commissioning and Mechanical Completion Partial or System. These procedures were provided guidelines and directions for the implementation of commissioning activities were carried out post equipment installation and prior to achievement of Mechanical Completion. After number of problems faced ultimately a milestone achievement in the history of Nigeria birthed on the 17th of March 2021 by young talented and hardworking set of Engineers and experts of the Dangote Fertilizer Limited, Lagos Nigeria. A great feat that will indeed boost the agricultural sector of the country, Africa and the world at large has come. This moment was so delighted and greatly honored to be among the team of engineers who realized this milestone of the largest single train fertilizer plant in Africa of 2200MT of ammonia and 3850MT of urea granules production. we celebrate the dutiful commitments of our colleagues and superiors(Expats). We indeed put in so much from the piping to mechanical hand over, pre- commissioning & commissioning phase through to the production of our first urea granules. The Commissioning activities were started for each Unit after Mechanically completion is certified. The main activities were following: 1. Hot alignment checked 2. Remove temporary strainers 3. Verified the proper operability of equipment 4. Run-in of pumps with water 5. Run-in of air coolers 6. Dry run operation of the granulator was done boiling out and chemical cleaning according to manufactures and contractors procedure. 7. Commissioning of lube oil and seal oil system circulate oil . 8. Run-in of centrifugal compressors 9. Dry out of furnace. 10. Functional check of control system. 11. Functional check of ESD system. Project Outline PROCESS PLANTS & UTILITIES Sr. No. Unit Number Unit name 1 10,20 Urea Train -1 & 2 2 11,21 Ammonia Train -1 & 2 3 19,29 Urea Granulation Train -1 & 2 4 30 Ammonia Storage System 5 31 UFC Storage System 6 32 Urea Bulk Storage 7 33 Urea Handling System 8 34 Urea Bagging Unit 9 12 Water Treatment System 10 13 Steam & Power Generation System 11 14 Cooling Water System 12 15 Natural Gas System 13 16 Nitrogen Production & Storage 14 17 Instrument & Plant Air System 15 18 Potable Water System 16 22 Emergency & Power Diesel System 17 23 Effluent Treatment Plant 18 24 Fire Fighting System GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 145 GSJ© 2021 www.globalscientificjournal.com
  • 8. 7 19 25 Ammonia Plant Flaring System Table-1 Natural Gas Consumption Sr. No Natural Gas Nm3/h Number of Train/Equipments Total for DFL Complex, Nm3/h 1 Fuel Gas for Reformer 31845 2 63690 2 feed Gas 58799 2 117598 3 Start up Heater 1192 2 2384 4 Each Auxiliary Boiler 7419 3 22257 Total 205929 At start up Per Day 4942296 4.942296 X 106 Forty Nine Lacs Forty Two Thousand Two Hundred Ninety Six 4.9 Millians Forty Two Thousand Two Hundred Ninety Six Table-2 PRODUCTION & CONSUMPTION DANGOTE FERTILIZER LTD,.LAGOS,NIGERIA Sr. No. Production/Consumption Value for one unit Number of Train/equipmen ts Value Unit 1 Ammonia Per Day Production 2200 2 4400 MT/Day 2 Urea Per Day Production 3850 2 7700 MT/Day 3 Total Natural gas received for Complex 4942296 Nm3/Day 4 Power Production(3 Power Generator) 41 2 82 MWH 5 Raw water Received from Lekki Lgon 3300 3300 M3/hr 6 Cooling water Circulation 91083 91083 T/H 7 Boilers Steam Generation, P-46 kg/cm2 200 3 600 T/H 8 Waste Heat Boilers Steam Generation(in Ammonia Plants) 3 Numbers 461.4 2 922.8 T/H 9 C.W. make up 2140 2140 M3/hr 10 Treated water Flow 2500 2500 M3/hr 11 Service water/Drinking /Fire water 100 100 M3/hr 12 Urea Formaldehyde Consumption 1.203 2 2.406 T/Hr Table-3 GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 146 GSJ© 2021 www.globalscientificjournal.com
  • 9. 8 Fig-4(Complex input/output) Fig-5(All Compressor Steam balance) GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 147 GSJ© 2021 www.globalscientificjournal.com
  • 10. 9 Problem faced in first start up The CO2 carryover from MP absorber to ammonia receiver was took placed in first feed in resulting the ammonia booster pump was cavitated and left load the reflux to M.P absorber valve was not operated at the time resulting the temperature reached more than 800 C.The first feed in done on dated 12/04/2021,the fed in rate kept low because the temperature control in urea reactor. The activities as following Sr. No. Time activities 1 07.00 hrs Plant check up for control valves and stock checking 2 11.00 hrs The H.P. loop heating started through L.S. 3 14.00 hrs The H.P loop K.W. heating started at the rate of 500 /hr 4 16.00 hrs Ammoniation started at the rate of 30kg/cm2/hr 5 19.00 hrs Feed in done 6 21.00 hrs Overflow observed 7 22.00 Hrs CO2 Carryover to ammonia receiver. And feed cut Table-4 3 unsuccessful attempts also done but each time feed was cut due to numbers of problem some of the PSV of MP loop passing observed. Finally on 17th April success achieved and urea granules sent to silo but after 14 hrs operations feed was cut due to MP loop PSV popped. Following problem were faced in plant start up 1. Reformer burner choking frequently 2. Trim heater problem faced in startup 3. Synthesis reaction rate very slow in start up 4. Many time disturbed CO2 absorption section. 5. Power failure in many times 6. Flare was extinguished many times 7. In urea plant CO2 carryover from MP absorber to ammonia receiver. 8. Frequently choking of pumps suction strainers 9. Waste water section was overloaded 10. Waste water section disturbed many times 11. Choking of granulators inlet nozzles. 12. PSV of MP loop passing observed resulting ammonia in environment and disturbed of waste water section. 13. Choking of 2nd bed cooler. 14. Choking of vibrating screens 15. Steam lines PSV popped. 16. Shortage of NG. GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 148 GSJ© 2021 www.globalscientificjournal.com
  • 11. 10 Overall view of the Plant Fig-6(Plant Overview) PLANT LAYOUT Fig-7(Overview of the Project) GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 149 GSJ© 2021 www.globalscientificjournal.com
  • 12. 11 Fig-8(Urea granular) GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 150 GSJ© 2021 www.globalscientificjournal.com
  • 13. 12 Fig-9(Happiness when production achieved) GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 151 GSJ© 2021 www.globalscientificjournal.com
  • 14. 13 Fig-10(MP section) Fig-11(waste water section) GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 152 GSJ© 2021 www.globalscientificjournal.com
  • 15. 14 Fig-12(ammonia booster pump strainer damaged) Conclusion After a lot of trouble, pandemic, staff etc finally the plant got in operational. It was a huge challenge, in the end the plant got in production due to the efforts of M/S. Saipem and all the dignity of all the people brought in production of urea. It is beyond any doubt that Dangote Fertilizer Project has been a successful project and the key to the success is M/S. Saipem has made available to M/S. Halder Topsoe an innovative combination of know-how and technological solutions and an effective strategy of project execution, providing an efficient and reliable plant. With its extended portfolio of proprietary technologies and worldwide experience in executing projects at all levels of responsibility, Saipem has managed and executed the DFL project providing a single and complete point of competence from license through to Start-Up condition of the Plant. The synergic combination of Saipem know-how and process leadership in Ammonia & Urea technology and Dangote projects experience as global contractor, has brought unparalleled advantages to the project and finally to the end user. A successful commissioning effort generates site-specific knowledge that we used by the commissioning team to assist in the startup. Some common support functions include operator systems training, process systems troubleshooting, lockout-tag out practices and other safe work procedures, and pre-startup safety review participation. GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 153 GSJ© 2021 www.globalscientificjournal.com
  • 16. 15 References- [1] Urea Plant equipments Inspection by Prem Baboo published in International Journal of Engineering Research and technology (IJERT),Volume-9 issue 03, March 2020 [2] Trouble Shooting in Water Treatment Process for Variable TDS by Prem Baboo, Published in International Journal of Engineering Research and Technology(IJERT, Volume 9, Issue 04, April 2020. GSJ: Volume 9, Issue 5, May 2021 ISSN 2320-9186 154 GSJ© 2021 www.globalscientificjournal.com View publication stats View publication stats