BUILDING FOR 22ND CENTURY LONDON
IAM CONFERENCE
JUNE 2017
3
HISTORY OF LONDON’S SEWERS
Sewerage History of London
8 million people 62 million cubic meters Strained ecosystem
6
TUNNEL DESIGN, CONSTRUCTION AND HANDOVER
London Tideway Improvements
Riverside
Long Reach
Mogden
Crossness
Sewage Works Upgrades
Lee Tunnel
Thames Tideway Tunnel
Beckton
Tunnelling through London
Engineering challenges
• Variable ground conditions
• 120 year design life
• Dissipate energy and minimise
air entrapment
• Provide mechanical ventilation
and odour treatment
Interfaces with existing infrastructure
Bridges: 75
Victoria Embankment
Critical periods of transition and certification
Design / Construction phase
System Acceptance
Period (up to 3 years)
System
Commissioning
Commencement
System
AcceptanceHandover
Construction
Start
Licence
Award
August
2015
OCI Period TWUL maintains
MEICA elements
Pre-System (Worksite)
Commissioning Period
Planning
Ready
?
System
Commissioning
Period
TWUL Operates
Integrated CSO System
TWUL Operators begin CSO
System Training
SCCD
Criteria
Certify System
is Ready for
Commissioning
Handover
Criteria
Certify System
is Ready for
Handover
SA
Criteria
Certify System
is Ready for
Acceptance
Operational Phase Responsibilities
15
DELIVERING THE PROJECT
Tideway at a glance
Revenue collection/
operator of Sewer
Network/TWUL Works
Debt Equity
Ofwat Thames Water
100% ownership
Project Licence
Government Support
Package
TIDEWAY
DEFRA
Bazalgette Tunnel Limited: trading as Tideway
The new Infrastructure Provider is the first Wastewater only
company in the UK. It is made up of the following shareholders:
The investor group includes a significant proportion of UK pension
funds through which over 1.7 million UK pensioners will have an
indirect investment in Tideway.
West - BMB JV Central - FLO JV East - CVB JV
Who is delivering what?
London Clay London Clay/Lambeth Group/Thanet Chalk
Project wide System Integrator (SCADA)
Tideway Delivery Team, NEC Project Manager, Supervisor, System
Commissioning
20
The Role of the System Integrator
LTT SCADA purpose
LTT
SCADA
Main
Work
Sites
Pumping
Stations
CSOs
Tunnel
Ventilation
Thames
Water
Control
Sites
Secure
environment
and Tideway PS / CSO
Abbey Mills, Beckton STW,
Tideway PS and Tunnel
Greenwich – Crossness STW
Greenwich –
Deptford – Earl PS
Victoria -
Blackfriars
Albert –
Heathwall PS
Cremorne-Chelsea-
Western PS
West CSOs &
Hammersmith PS
Frogmore
Tunnel &
PS
Integrating with the existing subsystems
Interface with Thames Water SCADA
Acton Storm Tanks
Hammersmith PS
Lots Road PS
Falconbrook PS
Heathwall PS
Greenwich PSEarl PS
Abbey Mills PS
Beckton STW
Main works at TWUL sites without TWUL interface
Main works with TWUL interface
Interface with Thames Water SCADA
MWC Sites
TWUL Sites
CSO Monitoring Sites
CSO Surveys
30
OPERATING THE SYSTEM
Normal Operation
Flow from the NLL is lifted by pumps at Station F to enable gravity flow
to join the NOS and flow to Beckton for treatment.
At the moment, if the restriction of flow to the NOS requires alternative
discharge from Abbey Mills, then the river penstocks will open and the
flow diverts to the Channelsea river.
Once the Lee tunnel is operating, those river penstocks will permanently
close and the TTT penstocks will divert flow via the Lee tunnel.
When the TTT is operating and joined to the Lee tunnel to form the LTT
discharge to the Channelsea River will be possible during storm conditions
(or at high levels, -3mAOD)
Abbey Mills
Ideally flow travels down the nos, enters Beckton inlet works, gets
treated and the effluent is discharged to river
The nos flow might be combined with flow from Abbey Mills, and
Meanwhile to protect the nos there might also be flow diverting to TTT
If Beckton starts to reach capacity (there is an F5 at the inlet wks) flow
can be diverted to the storm tanks and if necessary discharged to River
(untreated).
If LTT levels at Beckton reach a certain point,, it can discharge to River
via the Tideway CSO (weir).
If Beckton has the capacity, the Tideway PS lifts the TTT flow to the nos
for treatment.
When the TTT is built, there will be discharge point lower than the
Tideway CSO (weir), so this will no longer be used to discharge in storm
conditions.
Instead the Tideway PS flow will be controlled by penstocks so that it
Beckton
Cyber Security
Trend Micro published paper in 2013 highlighting the extent to which cyber criminals
are now actively targeting Industrial Control Systems, specifically water plants.
Honey pots were created and within 18 hours attacks started. Over 28 days 39 attacks
from 14 countries were recorded of which 17 would have been catastrophic.
Secure LTT
Infrastructure
Virtual
isation Network
Segmentatio
n
Patch
Management
Recoverable
Backups
Authenticati
on
USB Control
Application
Control
Log
Monitoring
Intrusion
Detection
and
Prevention
Server and
device
hardening
Performance
Monitoring
Vulnerability
Scanning
Anti-
Malware
43
TIDEWAY LEGACY
We do things safely or not at all
Gender
Ability
Action
Cultures LGBT+
“The Great Think” is Tideway’s innovation programme
Can we find our very own 21st Century
Sir Joseph Bazalgette’s?
‘Tideway will deliver a sustainable legacy of innovation by capturing
and sharing our solutions via I3P (Infrastructure Industry Innovation
Platform) to support UK’s Construction 2025 strategic vision’
Innovation in 2017 and beyond?
The Great Think is hosted on ‘i3P’
www.thegreatthink.london
Our innovation legacy commitment:
Stream D_Sian Thomas Rachel Blundell

Stream D_Sian Thomas Rachel Blundell

  • 1.
    BUILDING FOR 22NDCENTURY LONDON IAM CONFERENCE JUNE 2017
  • 3.
  • 4.
  • 5.
    8 million people62 million cubic meters Strained ecosystem
  • 6.
  • 7.
    London Tideway Improvements Riverside LongReach Mogden Crossness Sewage Works Upgrades Lee Tunnel Thames Tideway Tunnel Beckton
  • 8.
  • 9.
    Engineering challenges • Variableground conditions • 120 year design life • Dissipate energy and minimise air entrapment • Provide mechanical ventilation and odour treatment
  • 10.
    Interfaces with existinginfrastructure Bridges: 75
  • 11.
  • 13.
    Critical periods oftransition and certification Design / Construction phase System Acceptance Period (up to 3 years) System Commissioning Commencement System AcceptanceHandover Construction Start Licence Award August 2015 OCI Period TWUL maintains MEICA elements Pre-System (Worksite) Commissioning Period Planning Ready ? System Commissioning Period TWUL Operates Integrated CSO System TWUL Operators begin CSO System Training SCCD Criteria Certify System is Ready for Commissioning Handover Criteria Certify System is Ready for Handover SA Criteria Certify System is Ready for Acceptance
  • 14.
  • 15.
  • 16.
    Tideway at aglance Revenue collection/ operator of Sewer Network/TWUL Works Debt Equity Ofwat Thames Water 100% ownership Project Licence Government Support Package TIDEWAY DEFRA
  • 17.
    Bazalgette Tunnel Limited:trading as Tideway The new Infrastructure Provider is the first Wastewater only company in the UK. It is made up of the following shareholders: The investor group includes a significant proportion of UK pension funds through which over 1.7 million UK pensioners will have an indirect investment in Tideway.
  • 18.
    West - BMBJV Central - FLO JV East - CVB JV Who is delivering what? London Clay London Clay/Lambeth Group/Thanet Chalk Project wide System Integrator (SCADA) Tideway Delivery Team, NEC Project Manager, Supervisor, System Commissioning
  • 20.
    20 The Role ofthe System Integrator
  • 22.
  • 23.
    and Tideway PS/ CSO Abbey Mills, Beckton STW, Tideway PS and Tunnel Greenwich – Crossness STW Greenwich – Deptford – Earl PS Victoria - Blackfriars Albert – Heathwall PS Cremorne-Chelsea- Western PS West CSOs & Hammersmith PS Frogmore Tunnel & PS Integrating with the existing subsystems
  • 24.
    Interface with ThamesWater SCADA Acton Storm Tanks Hammersmith PS Lots Road PS Falconbrook PS Heathwall PS Greenwich PSEarl PS Abbey Mills PS Beckton STW Main works at TWUL sites without TWUL interface Main works with TWUL interface
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30.
  • 39.
    Normal Operation Flow fromthe NLL is lifted by pumps at Station F to enable gravity flow to join the NOS and flow to Beckton for treatment. At the moment, if the restriction of flow to the NOS requires alternative discharge from Abbey Mills, then the river penstocks will open and the flow diverts to the Channelsea river. Once the Lee tunnel is operating, those river penstocks will permanently close and the TTT penstocks will divert flow via the Lee tunnel. When the TTT is operating and joined to the Lee tunnel to form the LTT discharge to the Channelsea River will be possible during storm conditions (or at high levels, -3mAOD) Abbey Mills
  • 40.
    Ideally flow travelsdown the nos, enters Beckton inlet works, gets treated and the effluent is discharged to river The nos flow might be combined with flow from Abbey Mills, and Meanwhile to protect the nos there might also be flow diverting to TTT If Beckton starts to reach capacity (there is an F5 at the inlet wks) flow can be diverted to the storm tanks and if necessary discharged to River (untreated). If LTT levels at Beckton reach a certain point,, it can discharge to River via the Tideway CSO (weir). If Beckton has the capacity, the Tideway PS lifts the TTT flow to the nos for treatment. When the TTT is built, there will be discharge point lower than the Tideway CSO (weir), so this will no longer be used to discharge in storm conditions. Instead the Tideway PS flow will be controlled by penstocks so that it Beckton
  • 41.
    Cyber Security Trend Micropublished paper in 2013 highlighting the extent to which cyber criminals are now actively targeting Industrial Control Systems, specifically water plants. Honey pots were created and within 18 hours attacks started. Over 28 days 39 attacks from 14 countries were recorded of which 17 would have been catastrophic.
  • 42.
    Secure LTT Infrastructure Virtual isation Network Segmentatio n Patch Management Recoverable Backups Authenticati on USBControl Application Control Log Monitoring Intrusion Detection and Prevention Server and device hardening Performance Monitoring Vulnerability Scanning Anti- Malware
  • 43.
  • 44.
    We do thingssafely or not at all
  • 46.
  • 50.
    “The Great Think”is Tideway’s innovation programme Can we find our very own 21st Century Sir Joseph Bazalgette’s? ‘Tideway will deliver a sustainable legacy of innovation by capturing and sharing our solutions via I3P (Infrastructure Industry Innovation Platform) to support UK’s Construction 2025 strategic vision’ Innovation in 2017 and beyond? The Great Think is hosted on ‘i3P’ www.thegreatthink.london Our innovation legacy commitment: