Session 2: Overview of Barangay Development Planning (BDP)
and CapDev Agenda Formulation
BDP Step 6:
DETERMINING
PROGRAMS, PROJECTS,
ACTIVITIES, AND CAPDEV
AGENDA
FM-LGTDD-10D Rev. 00 01/03/2018
BDP Step 6:
Determining Programs, Projects, Activities,
and Capdev Agenda
PARTICIPATORY BDP
PROCESS
Organizing
the BPT &
BDC-TWG
STEP 1
Crafting the
M&E Plan
STEP 8 Participatory
Situational
Analysis
STEP 3
Determining
the PPAs &
CapDev
Agenda
STEP 6
Updating the
Barangay
Databases/
Profile
STEP 2
Formulating
or Revisiting
the Barangay
Vision
STEP 4
Goal &
Objective
Setting
STEP 5
Investment
Programming
STEP 7
Writing and
Packaging the
BDP
STEP 9
Adoption &
Approval of
the BDP
STEP 10
FM-LGTDD-10D Rev. 00 01/03/2018
PROBLEM
IDENTIFICATION
(Initial assessment
of problems and
institutional
environment)
CAUSE AND EFFECT
ANALYSIS
(SECTORAL)
(Finding root causes
of the problems and
their effects)
DETAILED
IMPLEMENTATION
PLAN WITH BUDGET
Summary of
Findings/ Issues
& Possible
Actions
PROBLEM
PRIORITIZATION
(What are the
central problems?)
INTERVENTIONS
PROGRAM, PROJECT,
ACTIVITIES
SETTING GOALS AND
OBJECTIVES
(SECTORAL)
Potential solutions to address
the issue, maximize
opportunities, and fulfill
aspirations
VISIONING
WHERE DO WE WANT TO
BE?
Community Dreams &
Aspirations – After knowing
their situation
FM-LGTDD-10D Rev. 00 01/03/2018
PROGRAMS, PROJECTS AND ACTIVITIES
▪ generally called “interventions” or “structuring solutions”
▪ to put into action the goals and objectives / BUBUHATON
▪ also include policy recommendations, legislative actions, regulatory
reform or institutional changes necessary to carry out the objectives;
▪ also consider access to resources of both the local, national and
private entities as well as opportunities, or cooperation with other
sectors or with adjoining barangays, if needed;
FM-LGTDD-10D Rev. 00 01/03/2018
PROGRAMS, PROJECTS AND ACTIVITIES
ACTIVITY: a single event and stand-alone action. It is composed
of a set of steps that, when followed, produces a specific output
or result.
PROJECT: a set of activities that put into action a chosen
program, these activities are usually grouped together under
different components. A project can have many outputs. It has a
definite start date and end date.
PROGRAM: composed of several related projects and activities.
Unlike projects that have a specified end date, programs often
continue indefinitely. The implementation of different projects
under a program is planned, scheduled, and managed in an
integrated way
FM-LGTDD-10D Rev. 00 01/03/2018
Workshop:
DETERMINING
PROGRAMS, PROJECTS,
AND ACTIVITIES
FM-LGTDD-10D Rev. 00 01/03/2018
Workshop:
Determining Programs, Projects, and Activities
MECHANICS:
• Look into the objective tree/s from the previous workshop. Some metacards or
objectives may be related and need to be clustered for a better organized
objective tree. These clustered objectives may result to coming up with a
project instead of just an activity
• Do a quick brainstorming session. For each objective, list all of the possible
actions that can be done to achieve it. Don’t filter or automatically reject an
idea at this stage—the more ideas, the better.
FM-LGTDD-10D Rev. 00 01/03/2018
ECONOMIC SECTOR
PROGRAM 1:
ESTABLISHMENT OF SAFE
AND IMPROVED COOKING
TECHNOLOGIES
ACTIVITY 1: Support
small business owners by
providing grants
ACTIVITY 2:
ACTIVITY 3:
PROGRAM 2:
CAPACITY BUILDING OF
SMALL BUSINESS OWNERS ON
ALTERNATIVE COOKING
TECHNOLOGIES
ACTIVITY 1: Support small
business owners to
ACTIVITY 2:
ACTIVITY 3:
PROGRAM 3:
NETWORK BUILDING WITH
PARTNERS
ACTIVITY 1: Conduct of
partners forum
ACTIVITY 2:
ACTIVITY 3:
Project 1
Project 2
EXAMPLE
FM-LGTDD-10D Rev. 00 01/03/2018
FM-LGTDD-10D Rev. 00 01/03/2018
FM-LGTDD-10D Rev. 00 01/03/2018
Workshop:
Determining Programs, Projects, and Activities
• Process the action ideas together as a group. Discuss each action idea, then
group together similar or related ideas. Check that the actions are aligned with
the goals and objectives.
• Decide together whether an action is a stand-alone activity, a multicomponent
project implemented within a specific time period, or a multi-project program
that will continue indefinitely
• Briefly describe each PPA. If possible and appropriate, include the PPA’s
approximate location, components, and initial estimates of cost requirement
• Identify the persons or households that will benefit from the proposed PPA
FM-LGTDD-10D Rev. 00 01/03/2018
Prioritization
of PPAs
FM-LGTDD-10D Rev. 00 01/03/2018
Prioritization of PPAs
Kung napakarami ng PPAs na
natukoy at kailangang mag-
prioritize, maaring gumamit muli
ng participatory ranking and
prioritization techniques/methods
FM-LGTDD-10D Rev. 00 01/03/2018
Participatory ranking and prioritization
techniques/methods
DOT VOTING DIRECT RANKING
Goal: To help uplift the living conditions of farmers and fishermen/fisher
folks by providing them with information and technical knowhow, and
proper facilities
PPA
Strate
gic
Value
Risk
Capaci
ty
Total
Construction of drying facilities 4 3 3 10
Training on Improving Production 4 4 3 11
Training on Processing and
Packaging of produce
5 5 2 12
Assistance on marketing and
distribution
5 4 3 12
Training on financial management 3 5 2 10
FM-LGTDD-10D Rev. 00 01/03/2018
Workshop:
Determining Programs, Projects, and Activities
Goal: To pursue well-maintained and adequate, resilient coastal defenses.
Objective:
To improve adaptive capacities of men and women in 11 Puroks along coastal areas against flooding by end of 2023
Program/Project/Activity
Brief description of the
project
Location and
beneficiaries
Budgetary Reqt.
(estimate)
FM-LGTDD-10D Rev. 00 01/03/2018
Barangay
Capacity
Development
(CapDev) Agenda
FM-LGTDD-10D Rev. 00 01/03/2018
Kakayanin ba?
Kamusta naman ang knowledge, skills
and motivation ng mga barangay actors?
Sino naman ang pwedeng lapitan at
makatuwang namin sa pangangailangan
ng dagdag na resources?
FM-LGTDD-10D Rev. 00 01/03/2018
Barangay Capacity Development
(CapDev) Agenda
Capacity Development
Process by which individual competencies and
institutional capacities are enhanced
through strategic and integrated interventions
to equip and empower LGUs/BLGUs to fulfill their
accountabilities and produce desired results
FM-LGTDD-10D Rev. 00 01/03/2018
CAPACITY
Kapasidad
Kakayahan ng LGU/BLGU na gampanan
ang mga tungkulin at panangutan nito, at
makamit ang hinahangad na resulta (kanilang
mga plano at serbisyo) o pagbabago (komportableng
pamumuhay ng bawat mamayan sa komunidad)
Ability of LGUs to perform functions to fulfill their
accountabilities and produce desired results
FM-LGTDD-10D Rev. 00 01/03/2018
CAPACITY PILLARS
STRUCTURE COMPETENCY
KNOWLEDGE
& LEARNING
MANAGEMENT
SYSTEMS
ENABLING
POLICIES
LEADERSHIP
FM-LGTDD-10D Rev. 00 01/03/2018
PERFORMANCE
Effectiveness ng barangay sa paggawa
ng kanyang misyon, mandato at
pagkamit ng hinahangad na resulta or
pagbabago
(serbisyong epektibo, totoo at angkop sa pangangailangan
ng komunidad)
Effectiveness of the LGU in doing its mission or
what its mandate says, and producing desired
results
FM-LGTDD-10D Rev. 00 01/03/2018
Capacity Performance
Ability of LGU to perform functions
to fulfill their accountabilities and
produce desired results
“means”
Effectiveness of the LGU in doing its
mission or what its mandate says,
and producing desired results
“end”
Resources,
enabling
mechanisms
to run...
Processes
Systems
Programs
to produce/
deliver ...
Products
Services
that lead/
contribute to ...
Benefits
that meet the
needs of
constituents and
lead to…
Development
Improvement in
the lives of
constituents (e.g.,
MDG)
FM-LGTDD-10D Rev. 00 01/03/2018
ASSESSMENT NG KAPASIDAD
Capacity
Assessment
Proseso ng pagtukoy sa mga
kailangang pagpapabuti sa
kapasidad para maabot ang mga
goals and objectives
FM-LGTDD-10D Rev. 00 01/03/2018
Assess capacity
Capacity Assessment
• After the performance goals and objectives have been identified, the
next step is to determine the LGU’s/BLGU’s capacity to achieve those
goals and objectives.
• This defines the desired improvements in capacity and identifies
corresponding capacity development intervention to address the gaps.
• The analysis of current and desired states uses the framework of the
Capacity Pillars – (1) Structure, (2) Competency, (3) Management
System, (4) Enabling Policies, (5) Knowledge and Learning, and (6)
Leadership.
FM-LGTDD-10D Rev. 00 01/03/2018
SAMPLE GUIDE QUESTIONS: CAPACITY ASSESSMENT FOR BARANGAYS
Capacity Assessment
CAPACITY PILLARS GUIDE QUESTIONS
Leadership ● Does the barangay leadership actively engage other organizations and
stakeholders to work with as partners in development?
Structure ● How many people work in your barangay?
● What are the existing committees/ groups/ volunteers that you intend to tap to
work with barangays?
● Are all BBIs organized and are functional?
Competencies ● What is the technical experience and qualification of each staff member?
● What is the level of competency of barangay officials, and members of BBIs
relevant to barangay governance (katarungang pambarangay, planning, admin and
finance)?
● What is level of competency of barangay official in addressing health and nutrition
issues?
● What is the level of competencies of barangay officials in addressing poverty in the
barangay?
FM-LGTDD-10D Rev. 00 01/03/2018
SAMPLE GUIDE QUESTIONS: CAPACITY ASSESSMENT FOR BARANGAYS
Capacity Assessment
CAPACITY PILLARS GUIDE QUESTIONS
Management
Systems
(Planning, Budgeting/
Financing, Partnering,
Networking,
Stakeholdership
Building)
● Does barangays have existing work with the community? to implement the
projects identified?
● What external businesses, organization or government bodies does
barangay has strong linkage?
● Could you draw upon these relationships for certain types of projects?
Enabling Policies ● Are there any laws/ policies/ ordinance policies to support planned PPAs?
● Are ordinances and regulations updated to support the implementation of
the Barangay Development Plan?
● Is there a need for new policies and regulations related to the sectoral
areas?
● Are legislations supportive to promote livelihood activities of residents?
● Are there legislations to support poor communities?
FM-LGTDD-10D Rev. 00 01/03/2018
SAMPLE GUIDE QUESTIONS: CAPACITY ASSESSMENT FOR BARANGAYS
Capacity Assessment
CAPACITY PILLARS GUIDE QUESTIONS
Knowledge and
Learning
•Are there opportunities and events for residents and community members to
provide feedback on the quality of barangay governance, including delivery of
services?
•Does the barangay maintain updated information or data that can be used for
planning?
•Does the barangay conduct regular monitoring or evaluation of its activities,
projects and programs?
•Does the barangay actively compare or benchmark its performance with best
practices or well performing barangays? (local and international)
FM-LGTDD-10D Rev. 00 01/03/2018
Capacity Change Matrix
Capacity Assessment
Sector: _________________________
Capacity/Kapasidad
Kasalukuyang
Kalagayan/Estado
Inaasam na
Kalagayan/Estado
Intervention
Istruktura
____________________
Indibidwal na Kakayanan
______________________
Goal:
______________________________________________________________________________________
Objectives:
• ___________________________________________________________________________________
• ___________________________________________________________________________________
Programs/Projects/Activities:
• ___________________________________________________________________________________
• ___________________________________________________________________________________
FM-LGTDD-10D Rev. 00 01/03/2018
Sample Capacity Change Matrix
Capacity Assessment
Capacity/Kapasidad
Kasalukuyang Kalagayan/Estado Inaasam na Kalagayan/Estado Intervention
Istruktura: Hindi organisado ang
Barangay Physical Fitness and Sports
Development Council (BPFSDC)
Organisadong Brgy. Physical
Fitness and Sports Devt Council na
nagpapatupad ng regular na
programa para sa mga kabataan at
Senior Citizens
(1) Organize ang (BPFSDC);
(2) Gumawa ng ordinansa para
sa pagorganisa ng (BPFSDC);
(3) Gumawa ng plano;
(4) paglaanan ng pondo ang
mga plano;
Indibidwal na Kakayanan: Marami sa
mga bagong-talagang Lupon ay kulang
pa ang kaalaman sa Katarungang
Pambarangay
FM-LGTDD-10D Rev. 00 01/03/2018
Comprehensive guide for the
LGU/BLGU
in implementing capacity
development initiatives
CapDev Agenda
FM-LGTDD-10D Rev. 00 01/03/2018
Group Leader: Punong Barangay
(as Capdev Champion/ Executive Sponsor)
Members:
SB Member (Chairperson on Committee on Rules)
Barangay Administrator
Barangay Secretary
Barangay Treasurer
Lupong Tagapamayapa
SK Chairperson
Representatives of CSOs/NGOs (good governance advocates)
Representatives from other sectoral committees
INSTITUTIONAL SECTOR
Who are involved?
FM-LGTDD-10D Rev. 00 01/03/2018
▪ A three- year plan that serves as a roadmap of appropriate individual
and organizational enhancement interventions within specific
timeframes, identified milestones and deliverables, and available and
accessible resources to address priority capacity development
needs along defined LGU/BLGU performance outcomes
Barangay CapDev Agenda
• Expected Output: plan, program, system, process, trained staff
• Target of CapDev: who will be trained or be involved in the intervention
• Timeframe: which year, and what is the duration (e.g., 3months, etc.)
• Funding Requirements: estimated cost/ budget required
• Process Owner/ Office Responsible
• Source of Support/ Technical Assistance
FM-LGTDD-10D Rev. 00 01/03/2018
Barangay CapDev Agenda
FM-LGTDD-10D Rev. 00 01/03/2018
Workshop:
Barangay CapDev Agenda
FM-LGTDD-10D Rev. 00 01/03/2018
Workshop:
PRIORITIZATION OF PPAs
MECHANICS
▪ Brainstorm with members of the sectoral team. Identify what are the
capacities needed in order to achieve the set goals and objectives
(consider the capacity pillars, use guide questions)
▪ Indicate current state of that capacity as well as the desired state of
capacity
▪ Identify appropriate interventions to achieve the desired state of
capacity. Remember that capacity development interventions are
not limited to training and seminars.
FM-LGTDD-10D Rev. 00 01/03/2018
Workshop:
PRIORITIZATION OF PPAs
MECHANICS
▪ Indicate funding requirement
▪ Subject identified CapDev PPAs to prioritization to determine which
of the proposed interventions shall eb adopted, especially if there
are many, and the year of implementation
▪ Identify responsible office or person, people who will be involved
and support needed from other offices

More Related Content

What's hot

326918375-Barangay-Development-Planning.ppt
326918375-Barangay-Development-Planning.ppt326918375-Barangay-Development-Planning.ppt
326918375-Barangay-Development-Planning.pptbenito procia
 
Local Government Planning ICBP Presentation
Local Government Planning ICBP PresentationLocal Government Planning ICBP Presentation
Local Government Planning ICBP PresentationHydee Zerrudo
 
Local development planning
Local development planningLocal development planning
Local development planningGil Sr.
 
2020 Annual Accomplishment Report
2020 Annual Accomplishment Report2020 Annual Accomplishment Report
2020 Annual Accomplishment Reportjo bitonio
 
Manual on community participation in government procurement.pptx
Manual on community participation in government procurement.pptxManual on community participation in government procurement.pptx
Manual on community participation in government procurement.pptxalvicroda2
 
dilg-memocircular-2022-026_SGLG.pdf
dilg-memocircular-2022-026_SGLG.pdfdilg-memocircular-2022-026_SGLG.pdf
dilg-memocircular-2022-026_SGLG.pdfFrancisCoronelJr
 
1. BNEO FrAMEWORK.pptx
1. BNEO FrAMEWORK.pptx1. BNEO FrAMEWORK.pptx
1. BNEO FrAMEWORK.pptxJohnpaulOcba
 
Local planning and budgeting linkage_version 2.0
Local planning and budgeting linkage_version 2.0Local planning and budgeting linkage_version 2.0
Local planning and budgeting linkage_version 2.0yee tandog
 
(institutional sector) rev
(institutional  sector) rev(institutional  sector) rev
(institutional sector) revPrimum Nocere
 
Rationalizing the Local Planning System and the Local Planning Structure.pptx
Rationalizing the Local Planning System and the Local Planning Structure.pptxRationalizing the Local Planning System and the Local Planning Structure.pptx
Rationalizing the Local Planning System and the Local Planning Structure.pptxHanin Laguindab
 
(environmental sector)
 (environmental sector) (environmental sector)
(environmental sector)Primum Nocere
 
Philippine Rural Development Problems Issues and Directions.pptx
Philippine Rural Development Problems Issues and Directions.pptxPhilippine Rural Development Problems Issues and Directions.pptx
Philippine Rural Development Problems Issues and Directions.pptxJo Balucanag - Bitonio
 
capdev (1).pptx
capdev (1).pptxcapdev (1).pptx
capdev (1).pptxRgPerola
 
Mandanas Ruling.pptx
Mandanas Ruling.pptxMandanas Ruling.pptx
Mandanas Ruling.pptxDrPerryBTizon
 

What's hot (20)

326918375-Barangay-Development-Planning.ppt
326918375-Barangay-Development-Planning.ppt326918375-Barangay-Development-Planning.ppt
326918375-Barangay-Development-Planning.ppt
 
Local Government Planning ICBP Presentation
Local Government Planning ICBP PresentationLocal Government Planning ICBP Presentation
Local Government Planning ICBP Presentation
 
Rationalized Planning System
Rationalized Planning SystemRationalized Planning System
Rationalized Planning System
 
Local development planning
Local development planningLocal development planning
Local development planning
 
Comprehensive Development Plan
Comprehensive Development PlanComprehensive Development Plan
Comprehensive Development Plan
 
2020 Annual Accomplishment Report
2020 Annual Accomplishment Report2020 Annual Accomplishment Report
2020 Annual Accomplishment Report
 
Manual on community participation in government procurement.pptx
Manual on community participation in government procurement.pptxManual on community participation in government procurement.pptx
Manual on community participation in government procurement.pptx
 
dilg-memocircular-2022-026_SGLG.pdf
dilg-memocircular-2022-026_SGLG.pdfdilg-memocircular-2022-026_SGLG.pdf
dilg-memocircular-2022-026_SGLG.pdf
 
1. BNEO FrAMEWORK.pptx
1. BNEO FrAMEWORK.pptx1. BNEO FrAMEWORK.pptx
1. BNEO FrAMEWORK.pptx
 
Local planning and budgeting linkage_version 2.0
Local planning and budgeting linkage_version 2.0Local planning and budgeting linkage_version 2.0
Local planning and budgeting linkage_version 2.0
 
(institutional sector) rev
(institutional  sector) rev(institutional  sector) rev
(institutional sector) rev
 
Rationalizing the Local Planning System and the Local Planning Structure.pptx
Rationalizing the Local Planning System and the Local Planning Structure.pptxRationalizing the Local Planning System and the Local Planning Structure.pptx
Rationalizing the Local Planning System and the Local Planning Structure.pptx
 
LCCAP Formulation
LCCAP FormulationLCCAP Formulation
LCCAP Formulation
 
Local Development Planning
Local Development PlanningLocal Development Planning
Local Development Planning
 
Local Development Planning
Local Development PlanningLocal Development Planning
Local Development Planning
 
(environmental sector)
 (environmental sector) (environmental sector)
(environmental sector)
 
Philippine Rural Development Problems Issues and Directions.pptx
Philippine Rural Development Problems Issues and Directions.pptxPhilippine Rural Development Problems Issues and Directions.pptx
Philippine Rural Development Problems Issues and Directions.pptx
 
capdev (1).pptx
capdev (1).pptxcapdev (1).pptx
capdev (1).pptx
 
Mandanas Ruling.pptx
Mandanas Ruling.pptxMandanas Ruling.pptx
Mandanas Ruling.pptx
 
SOCCSKSARGEN RDP 2017 2022 Midterm Update
SOCCSKSARGEN RDP 2017 2022 Midterm UpdateSOCCSKSARGEN RDP 2017 2022 Midterm Update
SOCCSKSARGEN RDP 2017 2022 Midterm Update
 

Similar to Step_6_Determining_the_PPAs___CapDev_Agenda.pptx

Drafting of 2023 GAD Plan and Policy Development.pptx
Drafting of 2023 GAD Plan and Policy Development.pptxDrafting of 2023 GAD Plan and Policy Development.pptx
Drafting of 2023 GAD Plan and Policy Development.pptxMarlon Viejo
 
Strategic Planning for Co_ops
Strategic Planning for Co_opsStrategic Planning for Co_ops
Strategic Planning for Co_opsjo bitonio
 
Training Workshop on Lean Project Management to Participants of Coir Cluster...
Training Workshop on Lean Project Management  to Participants of Coir Cluster...Training Workshop on Lean Project Management  to Participants of Coir Cluster...
Training Workshop on Lean Project Management to Participants of Coir Cluster...SN Panigrahi, PMP
 
Strategy Implementation of Financial and General Services Development (FGSD)
Strategy Implementation of Financial and General Services Development (FGSD)  Strategy Implementation of Financial and General Services Development (FGSD)
Strategy Implementation of Financial and General Services Development (FGSD) jo bitonio
 
(Pakistan) 20 tes-appk03 training of trainer - kaizen practitioners program
(Pakistan) 20 tes-appk03 training of trainer - kaizen practitioners program(Pakistan) 20 tes-appk03 training of trainer - kaizen practitioners program
(Pakistan) 20 tes-appk03 training of trainer - kaizen practitioners programabdulqayoom72
 
Project Logframe for planning and administration
Project Logframe for  planning and administrationProject Logframe for  planning and administration
Project Logframe for planning and administrationSudhir Kumar Soam
 
The Compass of Local Competitiveness v0.9
The Compass of Local Competitiveness v0.9The Compass of Local Competitiveness v0.9
The Compass of Local Competitiveness v0.9led4lgus
 
Day 1 1410 - 1455 - pearl 2 - vijay sane
Day 1   1410 - 1455 - pearl 2 - vijay saneDay 1   1410 - 1455 - pearl 2 - vijay sane
Day 1 1410 - 1455 - pearl 2 - vijay sanePMI2011
 
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02PMI_IREP_TP
 
My strategicplan.strategyhuddle.012010
My strategicplan.strategyhuddle.012010My strategicplan.strategyhuddle.012010
My strategicplan.strategyhuddle.012010M3Planning
 
Strategy Implementation for Institutional Services Department of PANELCO III
Strategy Implementation for Institutional Services Department of PANELCO IIIStrategy Implementation for Institutional Services Department of PANELCO III
Strategy Implementation for Institutional Services Department of PANELCO IIIJo Balucanag - Bitonio
 
CDSB Framework 101
CDSB Framework 101CDSB Framework 101
CDSB Framework 101CDSB
 
IRJET- An Overview on Project Management
IRJET- An Overview on Project ManagementIRJET- An Overview on Project Management
IRJET- An Overview on Project ManagementIRJET Journal
 
Unit 5-Digital Notes - MG 8091 EDP - VIII Sem Mech.pdf
Unit 5-Digital Notes - MG 8091 EDP - VIII Sem Mech.pdfUnit 5-Digital Notes - MG 8091 EDP - VIII Sem Mech.pdf
Unit 5-Digital Notes - MG 8091 EDP - VIII Sem Mech.pdfWorkCit
 
Project Development and Assistance Unit Accomplishment Report CY 2018
Project Development and Assistance Unit Accomplishment Report CY 2018Project Development and Assistance Unit Accomplishment Report CY 2018
Project Development and Assistance Unit Accomplishment Report CY 2018jo bitonio
 
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMajor Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMd. Masudur Rahman, PMP
 

Similar to Step_6_Determining_the_PPAs___CapDev_Agenda.pptx (20)

Drafting of 2023 GAD Plan and Policy Development.pptx
Drafting of 2023 GAD Plan and Policy Development.pptxDrafting of 2023 GAD Plan and Policy Development.pptx
Drafting of 2023 GAD Plan and Policy Development.pptx
 
Strategic Planning for Co_ops
Strategic Planning for Co_opsStrategic Planning for Co_ops
Strategic Planning for Co_ops
 
Training Workshop on Lean Project Management to Participants of Coir Cluster...
Training Workshop on Lean Project Management  to Participants of Coir Cluster...Training Workshop on Lean Project Management  to Participants of Coir Cluster...
Training Workshop on Lean Project Management to Participants of Coir Cluster...
 
Strategy Implementation of Financial and General Services Development (FGSD)
Strategy Implementation of Financial and General Services Development (FGSD)  Strategy Implementation of Financial and General Services Development (FGSD)
Strategy Implementation of Financial and General Services Development (FGSD)
 
(Pakistan) 20 tes-appk03 training of trainer - kaizen practitioners program
(Pakistan) 20 tes-appk03 training of trainer - kaizen practitioners program(Pakistan) 20 tes-appk03 training of trainer - kaizen practitioners program
(Pakistan) 20 tes-appk03 training of trainer - kaizen practitioners program
 
MG2015
MG2015MG2015
MG2015
 
Practical experiences of portfolio management
Practical experiences of portfolio managementPractical experiences of portfolio management
Practical experiences of portfolio management
 
Project Logframe for planning and administration
Project Logframe for  planning and administrationProject Logframe for  planning and administration
Project Logframe for planning and administration
 
The Compass of Local Competitiveness v0.9
The Compass of Local Competitiveness v0.9The Compass of Local Competitiveness v0.9
The Compass of Local Competitiveness v0.9
 
Day 1 1410 - 1455 - pearl 2 - vijay sane
Day 1   1410 - 1455 - pearl 2 - vijay saneDay 1   1410 - 1455 - pearl 2 - vijay sane
Day 1 1410 - 1455 - pearl 2 - vijay sane
 
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
 
My strategicplan.strategyhuddle.012010
My strategicplan.strategyhuddle.012010My strategicplan.strategyhuddle.012010
My strategicplan.strategyhuddle.012010
 
Strategy Implementation for Institutional Services Department of PANELCO III
Strategy Implementation for Institutional Services Department of PANELCO IIIStrategy Implementation for Institutional Services Department of PANELCO III
Strategy Implementation for Institutional Services Department of PANELCO III
 
CDSB Framework 101
CDSB Framework 101CDSB Framework 101
CDSB Framework 101
 
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
 
Ranking portfolio initiatives, Bernard Marshall, june 2012
Ranking portfolio initiatives, Bernard Marshall, june 2012Ranking portfolio initiatives, Bernard Marshall, june 2012
Ranking portfolio initiatives, Bernard Marshall, june 2012
 
IRJET- An Overview on Project Management
IRJET- An Overview on Project ManagementIRJET- An Overview on Project Management
IRJET- An Overview on Project Management
 
Unit 5-Digital Notes - MG 8091 EDP - VIII Sem Mech.pdf
Unit 5-Digital Notes - MG 8091 EDP - VIII Sem Mech.pdfUnit 5-Digital Notes - MG 8091 EDP - VIII Sem Mech.pdf
Unit 5-Digital Notes - MG 8091 EDP - VIII Sem Mech.pdf
 
Project Development and Assistance Unit Accomplishment Report CY 2018
Project Development and Assistance Unit Accomplishment Report CY 2018Project Development and Assistance Unit Accomplishment Report CY 2018
Project Development and Assistance Unit Accomplishment Report CY 2018
 
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMajor Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptx
 

More from JesselQuitorio4

FLCT Chapter 1 developmentalandsocialfactorsandindividualdifferences.pptx
FLCT Chapter 1 developmentalandsocialfactorsandindividualdifferences.pptxFLCT Chapter 1 developmentalandsocialfactorsandindividualdifferences.pptx
FLCT Chapter 1 developmentalandsocialfactorsandindividualdifferences.pptxJesselQuitorio4
 
The Little Prince from the subject Great Books.pptx
The Little Prince from the subject Great Books.pptxThe Little Prince from the subject Great Books.pptx
The Little Prince from the subject Great Books.pptxJesselQuitorio4
 
GREET-BOOKS-REPORT REPORT REPORT REPORT.pptx
GREET-BOOKS-REPORT REPORT REPORT REPORT.pptxGREET-BOOKS-REPORT REPORT REPORT REPORT.pptx
GREET-BOOKS-REPORT REPORT REPORT REPORT.pptxJesselQuitorio4
 
resume writing for first job seekers.pptx
resume writing for first job seekers.pptxresume writing for first job seekers.pptx
resume writing for first job seekers.pptxJesselQuitorio4
 
Lesson 2 Readings in the Philippine History.pptx
Lesson 2 Readings in the Philippine History.pptxLesson 2 Readings in the Philippine History.pptx
Lesson 2 Readings in the Philippine History.pptxJesselQuitorio4
 
online-notebook-XL.pptx Field Study for Teaching Assisstantship
online-notebook-XL.pptx Field Study for Teaching Assisstantshiponline-notebook-XL.pptx Field Study for Teaching Assisstantship
online-notebook-XL.pptx Field Study for Teaching AssisstantshipJesselQuitorio4
 
MTB-ME3_Modyul 1_Pagsulat ng Pahayag at Opinyon.pdf
MTB-ME3_Modyul 1_Pagsulat ng Pahayag at Opinyon.pdfMTB-ME3_Modyul 1_Pagsulat ng Pahayag at Opinyon.pdf
MTB-ME3_Modyul 1_Pagsulat ng Pahayag at Opinyon.pdfJesselQuitorio4
 
Lesson 1 Mother Tongue-Based Multilingual Education.pptx
Lesson 1 Mother Tongue-Based Multilingual Education.pptxLesson 1 Mother Tongue-Based Multilingual Education.pptx
Lesson 1 Mother Tongue-Based Multilingual Education.pptxJesselQuitorio4
 
Chapter 4 Teaching English in the e.pptx
Chapter 4 Teaching English in the e.pptxChapter 4 Teaching English in the e.pptx
Chapter 4 Teaching English in the e.pptxJesselQuitorio4
 

More from JesselQuitorio4 (9)

FLCT Chapter 1 developmentalandsocialfactorsandindividualdifferences.pptx
FLCT Chapter 1 developmentalandsocialfactorsandindividualdifferences.pptxFLCT Chapter 1 developmentalandsocialfactorsandindividualdifferences.pptx
FLCT Chapter 1 developmentalandsocialfactorsandindividualdifferences.pptx
 
The Little Prince from the subject Great Books.pptx
The Little Prince from the subject Great Books.pptxThe Little Prince from the subject Great Books.pptx
The Little Prince from the subject Great Books.pptx
 
GREET-BOOKS-REPORT REPORT REPORT REPORT.pptx
GREET-BOOKS-REPORT REPORT REPORT REPORT.pptxGREET-BOOKS-REPORT REPORT REPORT REPORT.pptx
GREET-BOOKS-REPORT REPORT REPORT REPORT.pptx
 
resume writing for first job seekers.pptx
resume writing for first job seekers.pptxresume writing for first job seekers.pptx
resume writing for first job seekers.pptx
 
Lesson 2 Readings in the Philippine History.pptx
Lesson 2 Readings in the Philippine History.pptxLesson 2 Readings in the Philippine History.pptx
Lesson 2 Readings in the Philippine History.pptx
 
online-notebook-XL.pptx Field Study for Teaching Assisstantship
online-notebook-XL.pptx Field Study for Teaching Assisstantshiponline-notebook-XL.pptx Field Study for Teaching Assisstantship
online-notebook-XL.pptx Field Study for Teaching Assisstantship
 
MTB-ME3_Modyul 1_Pagsulat ng Pahayag at Opinyon.pdf
MTB-ME3_Modyul 1_Pagsulat ng Pahayag at Opinyon.pdfMTB-ME3_Modyul 1_Pagsulat ng Pahayag at Opinyon.pdf
MTB-ME3_Modyul 1_Pagsulat ng Pahayag at Opinyon.pdf
 
Lesson 1 Mother Tongue-Based Multilingual Education.pptx
Lesson 1 Mother Tongue-Based Multilingual Education.pptxLesson 1 Mother Tongue-Based Multilingual Education.pptx
Lesson 1 Mother Tongue-Based Multilingual Education.pptx
 
Chapter 4 Teaching English in the e.pptx
Chapter 4 Teaching English in the e.pptxChapter 4 Teaching English in the e.pptx
Chapter 4 Teaching English in the e.pptx
 

Recently uploaded

Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Roomishabajaj13
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Call Girls in Nagpur High Profile
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxSwastiRanjanNayak
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...Suhani Kapoor
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escortsaditipandeya
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
Fair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CTFair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CTaccounts329278
 

Recently uploaded (20)

Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
How to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the ThreatHow to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the Threat
 
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
 
Fair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CTFair Trash Reduction - West Hartford, CT
Fair Trash Reduction - West Hartford, CT
 

Step_6_Determining_the_PPAs___CapDev_Agenda.pptx

  • 1. FM-LGTDD-10D Rev. 00 01/03/2018 Session 2: Overview of Barangay Development Planning (BDP) and CapDev Agenda Formulation BDP Step 6: DETERMINING PROGRAMS, PROJECTS, ACTIVITIES, AND CAPDEV AGENDA
  • 2. FM-LGTDD-10D Rev. 00 01/03/2018 BDP Step 6: Determining Programs, Projects, Activities, and Capdev Agenda PARTICIPATORY BDP PROCESS Organizing the BPT & BDC-TWG STEP 1 Crafting the M&E Plan STEP 8 Participatory Situational Analysis STEP 3 Determining the PPAs & CapDev Agenda STEP 6 Updating the Barangay Databases/ Profile STEP 2 Formulating or Revisiting the Barangay Vision STEP 4 Goal & Objective Setting STEP 5 Investment Programming STEP 7 Writing and Packaging the BDP STEP 9 Adoption & Approval of the BDP STEP 10
  • 3. FM-LGTDD-10D Rev. 00 01/03/2018 PROBLEM IDENTIFICATION (Initial assessment of problems and institutional environment) CAUSE AND EFFECT ANALYSIS (SECTORAL) (Finding root causes of the problems and their effects) DETAILED IMPLEMENTATION PLAN WITH BUDGET Summary of Findings/ Issues & Possible Actions PROBLEM PRIORITIZATION (What are the central problems?) INTERVENTIONS PROGRAM, PROJECT, ACTIVITIES SETTING GOALS AND OBJECTIVES (SECTORAL) Potential solutions to address the issue, maximize opportunities, and fulfill aspirations VISIONING WHERE DO WE WANT TO BE? Community Dreams & Aspirations – After knowing their situation
  • 4. FM-LGTDD-10D Rev. 00 01/03/2018 PROGRAMS, PROJECTS AND ACTIVITIES ▪ generally called “interventions” or “structuring solutions” ▪ to put into action the goals and objectives / BUBUHATON ▪ also include policy recommendations, legislative actions, regulatory reform or institutional changes necessary to carry out the objectives; ▪ also consider access to resources of both the local, national and private entities as well as opportunities, or cooperation with other sectors or with adjoining barangays, if needed;
  • 5. FM-LGTDD-10D Rev. 00 01/03/2018 PROGRAMS, PROJECTS AND ACTIVITIES ACTIVITY: a single event and stand-alone action. It is composed of a set of steps that, when followed, produces a specific output or result. PROJECT: a set of activities that put into action a chosen program, these activities are usually grouped together under different components. A project can have many outputs. It has a definite start date and end date. PROGRAM: composed of several related projects and activities. Unlike projects that have a specified end date, programs often continue indefinitely. The implementation of different projects under a program is planned, scheduled, and managed in an integrated way
  • 6. FM-LGTDD-10D Rev. 00 01/03/2018 Workshop: DETERMINING PROGRAMS, PROJECTS, AND ACTIVITIES
  • 7. FM-LGTDD-10D Rev. 00 01/03/2018 Workshop: Determining Programs, Projects, and Activities MECHANICS: • Look into the objective tree/s from the previous workshop. Some metacards or objectives may be related and need to be clustered for a better organized objective tree. These clustered objectives may result to coming up with a project instead of just an activity • Do a quick brainstorming session. For each objective, list all of the possible actions that can be done to achieve it. Don’t filter or automatically reject an idea at this stage—the more ideas, the better.
  • 8. FM-LGTDD-10D Rev. 00 01/03/2018 ECONOMIC SECTOR PROGRAM 1: ESTABLISHMENT OF SAFE AND IMPROVED COOKING TECHNOLOGIES ACTIVITY 1: Support small business owners by providing grants ACTIVITY 2: ACTIVITY 3: PROGRAM 2: CAPACITY BUILDING OF SMALL BUSINESS OWNERS ON ALTERNATIVE COOKING TECHNOLOGIES ACTIVITY 1: Support small business owners to ACTIVITY 2: ACTIVITY 3: PROGRAM 3: NETWORK BUILDING WITH PARTNERS ACTIVITY 1: Conduct of partners forum ACTIVITY 2: ACTIVITY 3: Project 1 Project 2 EXAMPLE
  • 9. FM-LGTDD-10D Rev. 00 01/03/2018
  • 10. FM-LGTDD-10D Rev. 00 01/03/2018
  • 11. FM-LGTDD-10D Rev. 00 01/03/2018 Workshop: Determining Programs, Projects, and Activities • Process the action ideas together as a group. Discuss each action idea, then group together similar or related ideas. Check that the actions are aligned with the goals and objectives. • Decide together whether an action is a stand-alone activity, a multicomponent project implemented within a specific time period, or a multi-project program that will continue indefinitely • Briefly describe each PPA. If possible and appropriate, include the PPA’s approximate location, components, and initial estimates of cost requirement • Identify the persons or households that will benefit from the proposed PPA
  • 12. FM-LGTDD-10D Rev. 00 01/03/2018 Prioritization of PPAs
  • 13. FM-LGTDD-10D Rev. 00 01/03/2018 Prioritization of PPAs Kung napakarami ng PPAs na natukoy at kailangang mag- prioritize, maaring gumamit muli ng participatory ranking and prioritization techniques/methods
  • 14. FM-LGTDD-10D Rev. 00 01/03/2018 Participatory ranking and prioritization techniques/methods DOT VOTING DIRECT RANKING Goal: To help uplift the living conditions of farmers and fishermen/fisher folks by providing them with information and technical knowhow, and proper facilities PPA Strate gic Value Risk Capaci ty Total Construction of drying facilities 4 3 3 10 Training on Improving Production 4 4 3 11 Training on Processing and Packaging of produce 5 5 2 12 Assistance on marketing and distribution 5 4 3 12 Training on financial management 3 5 2 10
  • 15. FM-LGTDD-10D Rev. 00 01/03/2018 Workshop: Determining Programs, Projects, and Activities Goal: To pursue well-maintained and adequate, resilient coastal defenses. Objective: To improve adaptive capacities of men and women in 11 Puroks along coastal areas against flooding by end of 2023 Program/Project/Activity Brief description of the project Location and beneficiaries Budgetary Reqt. (estimate)
  • 16. FM-LGTDD-10D Rev. 00 01/03/2018 Barangay Capacity Development (CapDev) Agenda
  • 17. FM-LGTDD-10D Rev. 00 01/03/2018 Kakayanin ba? Kamusta naman ang knowledge, skills and motivation ng mga barangay actors? Sino naman ang pwedeng lapitan at makatuwang namin sa pangangailangan ng dagdag na resources?
  • 18. FM-LGTDD-10D Rev. 00 01/03/2018 Barangay Capacity Development (CapDev) Agenda Capacity Development Process by which individual competencies and institutional capacities are enhanced through strategic and integrated interventions to equip and empower LGUs/BLGUs to fulfill their accountabilities and produce desired results
  • 19. FM-LGTDD-10D Rev. 00 01/03/2018 CAPACITY Kapasidad Kakayahan ng LGU/BLGU na gampanan ang mga tungkulin at panangutan nito, at makamit ang hinahangad na resulta (kanilang mga plano at serbisyo) o pagbabago (komportableng pamumuhay ng bawat mamayan sa komunidad) Ability of LGUs to perform functions to fulfill their accountabilities and produce desired results
  • 20. FM-LGTDD-10D Rev. 00 01/03/2018 CAPACITY PILLARS STRUCTURE COMPETENCY KNOWLEDGE & LEARNING MANAGEMENT SYSTEMS ENABLING POLICIES LEADERSHIP
  • 21. FM-LGTDD-10D Rev. 00 01/03/2018 PERFORMANCE Effectiveness ng barangay sa paggawa ng kanyang misyon, mandato at pagkamit ng hinahangad na resulta or pagbabago (serbisyong epektibo, totoo at angkop sa pangangailangan ng komunidad) Effectiveness of the LGU in doing its mission or what its mandate says, and producing desired results
  • 22. FM-LGTDD-10D Rev. 00 01/03/2018 Capacity Performance Ability of LGU to perform functions to fulfill their accountabilities and produce desired results “means” Effectiveness of the LGU in doing its mission or what its mandate says, and producing desired results “end” Resources, enabling mechanisms to run... Processes Systems Programs to produce/ deliver ... Products Services that lead/ contribute to ... Benefits that meet the needs of constituents and lead to… Development Improvement in the lives of constituents (e.g., MDG)
  • 23. FM-LGTDD-10D Rev. 00 01/03/2018 ASSESSMENT NG KAPASIDAD Capacity Assessment Proseso ng pagtukoy sa mga kailangang pagpapabuti sa kapasidad para maabot ang mga goals and objectives
  • 24. FM-LGTDD-10D Rev. 00 01/03/2018 Assess capacity Capacity Assessment • After the performance goals and objectives have been identified, the next step is to determine the LGU’s/BLGU’s capacity to achieve those goals and objectives. • This defines the desired improvements in capacity and identifies corresponding capacity development intervention to address the gaps. • The analysis of current and desired states uses the framework of the Capacity Pillars – (1) Structure, (2) Competency, (3) Management System, (4) Enabling Policies, (5) Knowledge and Learning, and (6) Leadership.
  • 25. FM-LGTDD-10D Rev. 00 01/03/2018 SAMPLE GUIDE QUESTIONS: CAPACITY ASSESSMENT FOR BARANGAYS Capacity Assessment CAPACITY PILLARS GUIDE QUESTIONS Leadership ● Does the barangay leadership actively engage other organizations and stakeholders to work with as partners in development? Structure ● How many people work in your barangay? ● What are the existing committees/ groups/ volunteers that you intend to tap to work with barangays? ● Are all BBIs organized and are functional? Competencies ● What is the technical experience and qualification of each staff member? ● What is the level of competency of barangay officials, and members of BBIs relevant to barangay governance (katarungang pambarangay, planning, admin and finance)? ● What is level of competency of barangay official in addressing health and nutrition issues? ● What is the level of competencies of barangay officials in addressing poverty in the barangay?
  • 26. FM-LGTDD-10D Rev. 00 01/03/2018 SAMPLE GUIDE QUESTIONS: CAPACITY ASSESSMENT FOR BARANGAYS Capacity Assessment CAPACITY PILLARS GUIDE QUESTIONS Management Systems (Planning, Budgeting/ Financing, Partnering, Networking, Stakeholdership Building) ● Does barangays have existing work with the community? to implement the projects identified? ● What external businesses, organization or government bodies does barangay has strong linkage? ● Could you draw upon these relationships for certain types of projects? Enabling Policies ● Are there any laws/ policies/ ordinance policies to support planned PPAs? ● Are ordinances and regulations updated to support the implementation of the Barangay Development Plan? ● Is there a need for new policies and regulations related to the sectoral areas? ● Are legislations supportive to promote livelihood activities of residents? ● Are there legislations to support poor communities?
  • 27. FM-LGTDD-10D Rev. 00 01/03/2018 SAMPLE GUIDE QUESTIONS: CAPACITY ASSESSMENT FOR BARANGAYS Capacity Assessment CAPACITY PILLARS GUIDE QUESTIONS Knowledge and Learning •Are there opportunities and events for residents and community members to provide feedback on the quality of barangay governance, including delivery of services? •Does the barangay maintain updated information or data that can be used for planning? •Does the barangay conduct regular monitoring or evaluation of its activities, projects and programs? •Does the barangay actively compare or benchmark its performance with best practices or well performing barangays? (local and international)
  • 28. FM-LGTDD-10D Rev. 00 01/03/2018 Capacity Change Matrix Capacity Assessment Sector: _________________________ Capacity/Kapasidad Kasalukuyang Kalagayan/Estado Inaasam na Kalagayan/Estado Intervention Istruktura ____________________ Indibidwal na Kakayanan ______________________ Goal: ______________________________________________________________________________________ Objectives: • ___________________________________________________________________________________ • ___________________________________________________________________________________ Programs/Projects/Activities: • ___________________________________________________________________________________ • ___________________________________________________________________________________
  • 29. FM-LGTDD-10D Rev. 00 01/03/2018 Sample Capacity Change Matrix Capacity Assessment Capacity/Kapasidad Kasalukuyang Kalagayan/Estado Inaasam na Kalagayan/Estado Intervention Istruktura: Hindi organisado ang Barangay Physical Fitness and Sports Development Council (BPFSDC) Organisadong Brgy. Physical Fitness and Sports Devt Council na nagpapatupad ng regular na programa para sa mga kabataan at Senior Citizens (1) Organize ang (BPFSDC); (2) Gumawa ng ordinansa para sa pagorganisa ng (BPFSDC); (3) Gumawa ng plano; (4) paglaanan ng pondo ang mga plano; Indibidwal na Kakayanan: Marami sa mga bagong-talagang Lupon ay kulang pa ang kaalaman sa Katarungang Pambarangay
  • 30. FM-LGTDD-10D Rev. 00 01/03/2018 Comprehensive guide for the LGU/BLGU in implementing capacity development initiatives CapDev Agenda
  • 31. FM-LGTDD-10D Rev. 00 01/03/2018 Group Leader: Punong Barangay (as Capdev Champion/ Executive Sponsor) Members: SB Member (Chairperson on Committee on Rules) Barangay Administrator Barangay Secretary Barangay Treasurer Lupong Tagapamayapa SK Chairperson Representatives of CSOs/NGOs (good governance advocates) Representatives from other sectoral committees INSTITUTIONAL SECTOR Who are involved?
  • 32. FM-LGTDD-10D Rev. 00 01/03/2018 ▪ A three- year plan that serves as a roadmap of appropriate individual and organizational enhancement interventions within specific timeframes, identified milestones and deliverables, and available and accessible resources to address priority capacity development needs along defined LGU/BLGU performance outcomes Barangay CapDev Agenda • Expected Output: plan, program, system, process, trained staff • Target of CapDev: who will be trained or be involved in the intervention • Timeframe: which year, and what is the duration (e.g., 3months, etc.) • Funding Requirements: estimated cost/ budget required • Process Owner/ Office Responsible • Source of Support/ Technical Assistance
  • 33. FM-LGTDD-10D Rev. 00 01/03/2018 Barangay CapDev Agenda
  • 34. FM-LGTDD-10D Rev. 00 01/03/2018 Workshop: Barangay CapDev Agenda
  • 35. FM-LGTDD-10D Rev. 00 01/03/2018 Workshop: PRIORITIZATION OF PPAs MECHANICS ▪ Brainstorm with members of the sectoral team. Identify what are the capacities needed in order to achieve the set goals and objectives (consider the capacity pillars, use guide questions) ▪ Indicate current state of that capacity as well as the desired state of capacity ▪ Identify appropriate interventions to achieve the desired state of capacity. Remember that capacity development interventions are not limited to training and seminars.
  • 36. FM-LGTDD-10D Rev. 00 01/03/2018 Workshop: PRIORITIZATION OF PPAs MECHANICS ▪ Indicate funding requirement ▪ Subject identified CapDev PPAs to prioritization to determine which of the proposed interventions shall eb adopted, especially if there are many, and the year of implementation ▪ Identify responsible office or person, people who will be involved and support needed from other offices