SlideShare a Scribd company logo
This document and any and all attachments hereto: (i) are intended for discussion purposes only; (ii) do not 
obligate the parties to negotiate or enter into any possible transaction; (iii) do not obligate either party to 
proceed with or continue any such negotiations or transaction. 
9/29/2014 
Proposal Submitted to the 
Maine Public Utilities Commission
Table of Contents 
PUBLIC 2 
Page 
Executive Summary 3 
Spectra Energy’s Proposal 7 
Appendix 
Spectra Energy Overview 17 
Business Segment Overview 19 
The Way Spectra Energy Works 20 
Regulatory and Permitting 21 
Environmental Stewardship 25 
Stakeholder Outreach 28
Executive Summary 
At the outset of Phase One of Docket No. 2014‐00071, the Maine Public Utilities Commission (Commission or 
PUC) invited the submission of proposals for the State of Maine to consider regarding Energy Cost Reduction 
Contracts (ECRC). Spectra Energy Partners, LP (Spectra Energy) has a long‐standing presence in New England as 
major transporters of natural gas through Algonquin Gas Transmission, LLC (Algonquin) and Maritimes & 
Northeast Pipeline, L.L.C. (Maritimes), and welcomes the opportunity to work with the PUC to develop the 
infrastructure required now, and in the future, to help alleviate regional energy price spikes during the coldest 
days of winter. We believe our proposal maximizes the opportunity to decrease capacity costs and enhance 
electrical and natural gas reliability throughout the region. 
While we remain supportive of a full, transparent Request for Proposal (RFP) in Phase Two of the instant 
proceeding, we are mindful of the Commission’s need to have all information available to it as it deliberates 
even within Phase One and as such are providing these proposals for Atlantic Bridge and Access Northeast as the 
Commission considers next steps. Our proposals closely reflect the project descriptions we introduced in Phase 
One. In the case of Atlantic Bridge in particular, the deadline for filing with FERC to ensure a November 2017 in‐service 
date is rapidly approaching. This fact, coupled with recent delays in the current ECRC case, necessitated 
that we submit our proposal at this time. In short, if the Commission decides to proceed with an ECRC, our hope 
is to expedite the process by which the Commission would be able to move forward. 
This proposal is intended to provide the Commission with flexible alternatives for exercising its ECRC authority, 
depending in part on the results of Phase One of this proceeding. If the Commission determines that Maine 
should move forward with an ECRC at this time, our proposal enables the Commission to enter into an ECRC of 
up to 200MMcf/d or $75 million/year equivalent as part of the Atlantic Bridge project, maximizing the benefits 
available to the state from an incremental expansion of the existing Algonquin pipeline as early as 2017. 
Our proposal also allows the Commission to enter into an ECRC for a later in‐service date through participation 
in the Access Northeast project. Like Atlantic Bridge, the Access Northeast project offers the benefits of 
deliverability to gas‐fired generators in the region, and it also offers the benefits of collaboration with Northeast 
Utilities, one of the region’s largest utilities. The Access Northeast project demonstrates the importance of 
providing services that directly meet the needs of gas‐fired generators. This innovative offering, combined with 
the resources of the partners, enhance the certainty that this project will move forward. 
Drawing upon Spectra Energy’s successful history of developing, constructing and operating natural gas 
pipelines, the proposed projects contained within this proposal address the Commission’s objective to reduce 
energy prices and enhance electrical and natural gas reliability in the State. 
Bidders Information 
Spectra Energy owns and operates the 1127‐mile, Federal Energy Regulatory Commission (FERC) regulated 
Algonquin Pipeline and the 346‐mile, FERC‐regulated Maritimes Pipeline. Algonquin interconnects with the 
Spectra Energy‐owned Texas Eastern Transmission system, the Tennessee Gas Pipeline system, the Millennium 
Pipeline, and the Iroquois Pipeline system, all of which link the Marcellus Shale and Appalachian Basin natural 
gas supplies to the Northeast markets. Through Algonquin’s connection to Maritimes, markets in 
PUBLIC 3
Massachusetts, New Hampshire and Maine will also have the opportunity to connect to these diverse and 
emerging natural gas supplies. To discuss any questions or to seek additional information regarding this 
proposal, please contact: 
Greg Crisp 
General Manger, Business Development 713‐627‐4611 phone 
Spectra Energy Transmission 713‐627‐4724 fax 
5400 Westheimer Court gncrisp@spectraenergy.com 
Houston, TX 77056 
PUBLIC 4
Key Features 
Value Added Benefits of Service from Algonquin and Maritimes: 
 Provides an opportunity to bring more low‐cost, domestically sourced natural gas to delivery points in Maine 
that serve gas‐fired electric generators, industrial customers, and other energy consumers in Maine or the 
region through scalable expansions of the existing Algonquin and Maritimes pipeline systems and offering 
receipt and delivery points on those systems, including direct delivery points to 60% of the gas‐fired 
generation fleet in the region 
o This is important because the best way for Maine to moderate electric prices in the region is to 
ensure that gas can be directly delivered to the greatest number of gas‐fired generators in the 
region on peak days, and our proposal is consistent with this approach. 
 Offers flexible terms with multiple protections for Maine’s potential investment in pipeline capacity 
o Flexible commitments that can be altered, rescinded, or changed as market conditions evolve 
o Maximum ability to assign capacity to other entities 
o Fully negotiable costs that are not incurred until projects are in‐service 
o Explicit contractual provisions to protect Maine’s ratepayers should a regional solution emerge prior 
to the FERC filing of the projects 
 Includes mechanisms to promote maximum return on investment by leveraging private commitments and 
shifting an ECRC investment to the project or projects likely to yield the best results 
 Provides optimal timeliness to market. Our solution allows natural gas capacity to reach gas‐fired 
generators in the region sooner than uncertain greenfield proposals, which is important given that every 
year of delay costs Maine consumers. 
 Provides direct deliveries of domestically sourced natural gas to Maine in the fastest timeframe 
 Provides innovative use of existing resources in the region by leveraging storage to meet peak day needs 
 Atlantic Bridge and Access Northeast maximize the use of existing rights‐of‐way and do not substantially rely 
on greenfield construction, which can be susceptible to substantial delays due to public opposition and 
mitigation of environmental impacts. Thus, Maine can have greater confidence that our projects will come 
online within the projects’ time estimates. 
 Offers better coordination between electric sector and natural gas sector through collaboration between 
Northeast Utilities and Spectra Energy 
 Does not hinge on achieving a certain level of subscription from third parties outside of Maine’s control 
PUBLIC 5
 Includes extending the upstream Algonquin piping as needed, the replacement of existing pipe with larger 
diameter pipe, pipeline looping, miscellaneous meter station upgrades, the addition of new compression as 
needed, and the potential for bidirectional flow on the Maritimes pipeline 
 Provides assurances that come with FERC‐jurisdictional oversight regarding the sensitivities of landowners, 
environmental resources, cultural resources, and other stakeholders who might be impacted during 
construction, as well as continued oversight of the transportation service on Algonquin and Maritimes 
throughout the contract term 
 Provides additional diversity of supply as traditional supply sources decline 
 Provides reliable firm transportation service directly to end users 
 Provides access to premium natural gas commodity markets resulting in unmatched optionality 
 Projects are scalable to meet the specific capacity requirements of the market and the State of Maine 
 Directly impacts reliability leading to more balanced supply and demand 
 Spectra Energy has a proven track record for constructing and operating pipelines in New England and 
throughout North America 
Together, Atlantic Bridge and Access Northeast will help remove bottlenecks in New England’s pipeline 
infrastructure and reduce electric and natural gas price volatility in New England. 
PUBLIC 6
Proposal 
Atlantic Bridge 
Spectra Energy is proposing to expand the existing Algonquin and Maritimes pipelines to meet the needs of 
consumers, serving growing markets in New England and Maine. On the Algonquin system, the expansion will 
consist of the replacement of smaller diameter pipe with larger diameter pipe, pipeline looping at some points 
along the existing system, miscellaneous meter station upgrades, the addition of a new compressor station in 
Weymouth, Massachusetts, and additional compression at existing stations to facilitate the flow of gas north 
into Maritimes. On the Maritimes system, modifications could include bidirectional flow modifications 
depending on the ultimate requested flow into the Maritimes system. 
The capacity being built through the Algonquin Incremental Market expansion (AIM) (in‐service in 2016) and 
Atlantic Bridge projects could provide 600 MMcf/d of new capacity into ISO‐NE territory, resulting in a 60% 
increase through current constraint points on Algonquin by 2017. Both projects will enchance electric and 
natural gas reliability throughout New England and will bring postitive economic benefits directly to Maine 
energy consumers. 
PUBLIC 7
Market response to Atlantic Bridge has been strong, and the project will go forward with or without an ECRC 
from the Commission. The project will be supported by private entities, including private entities in the State of 
Maine requesting specific Maine deliveries. Algonquin and Maritimes are in the final stages of negotiations for 
Atlantic Bridge, and the project is anticipated to be buildable at 200‐300 MMcf/d for a 2017 in‐service date. 
Today, the final capacity for Atlantic Bridge is not known for certain. This final capacity is dependent upon 
specific receipt and delivery points which will ultimately determine the facilites required and dictate the amount 
of capacity that may be constructed for a 2017 in‐service date. 
Algonquin and Maritimes intend to pre‐file Atlantic Bridge with FERC in early November 2014. At that time, 
Algonquin and Maritimes can provide a more definitive description of how much capacity is available, if any, and 
how much of the capacity will be directly deliverable to Maine. Prior to the filing or after the filing, Maine can 
enter into an ECRC to ensure that Atlantic Bridge goes forward at the maximum buildable capacity and 
maximum deliverability to Maine for 2017, and ensure that no time is wasted in securing benefits for Maine as 
soon as possible. 
 Capacity can be for up to 200 MMcf/d or $75 million/year, depending on the amount of unsubscribed 
capacity, if any, available at the time Maine is able to enter into a definitive agreement 
 In‐service date of November 1, 2017 
 Maine can designate any of the following receipt points: 
o “Head of G system” – Algonquin market area receipt 
o Brookfield interconnect with Iroquois – equivalent to TGP’s Northeast Energy Direct receipt at 
Wright, NY 
o Ramapo interconnect with Millennium – direct access to Marcellus producers 
o Interconnects upstream of Ramapo with recently expanded interstate pipelines such as Texas 
Eastern, Columbia, Transco, and Tennessee Gas Pipeline 
 Maine can designate any of the following delivery points: 
o Any Algonquin delivery point Maine determines is in the best interest of Maine consumers, including 
the Algonquin interconnect with Maritimes at Beverly, MA 
o Any Maritimes delivery point in the State of Maine 
o The Commission may also express any interest in new interconnects to connect Maine customers 
 Rate to be negotiated in a confidential meeting 
 All capacity commitments to the maximum degree allowed under current regulations can be assigned to 
another party or parties. 
PUBLIC 8
 No costs will be incurred until the project is in service 
 To the extent that private entities or other shippers subscribe to the maximum build for the project in 2017 
outside of an ECRC, Maine will be able to reduce or terminate its participation in Atlantic Bridge 
 Regardless of any conditions above, Maine will have a unilateral right, subject to negotiable conditions 
precedent, to terminate its participation in the project prior to July 1, 2015, at no risk to Maine 
 Additionally, if Algonquin and Maritimes move forward with a regional solution, we will discuss termination 
of Maine’s participation in Atlantic Bridge and Access Northest, the Algonquin and Maritimes regional 
solution 
Access Northeast 
On June 27, 2014, Spectra Energy provided a plan to the New England States Committee on Electricity (NESCOE) 
to expand existing natural gas pipeline capacity and meet critical demand for reliable electric power generation. 
This was in response to the New England governors’ initiative on new energy infrastructure in anticipation of a 
Request for Proposal (“RFP”). Unfortunately, the NESCOE RFP effort has been delayed; however, Spectra Energy 
and Northeast Utilities are moving forward with the Access Northeast project to help maintain the momentum 
of the process and to provide a regional solution. We continue to believe the NESCOE process is good for New 
England and Maine, and we applaud the leadership and commitment demonstrated by the States to achieve 
positive results for New England energy customers. 
Consistent with information provided by Algonquin and Maritimes in the ECRC proceeding, the Commission will 
recognize Access Northeast as the project regularly referred to as the “Reliability Project.” And we have made 
progress in further developing the project. We have a leading New England utility as a project partner, and 
together we are actively pursuing contractual commitments from shippers. Access Northeast is an alternative to 
a large greenfield proposal and is better focused on addressing electric reliability for New England. Access 
Northeast will provide innovative alternatives and solutions long sought by electric generators to improve 
reliability and bring down energy costs in the region, but without the environmental impacts of a greenfield 
project. 
The expansion project will enhance the Algonquin and Maritimes pipeline systems, using existing routes to 
minimize impacts on communities, landowners, and the environment. The project will be scalable to meet 
growing needs by expanding access to clean, abundant, and affordable natural gas, and it will be capable of 
reliably delivering in excess of one billion cubic feet of natural gas per day to serve the region's most efficient 
power plants and meet increasing demand from heating customers. Access Northeast will combine targeted 
pipeline capacity additions with the smart use of regional storage facilities to more effectively match the 
economic and environmental needs of the region. 
PUBLIC 9
Spectra Energy and Northeast Utilities’ collaborative proposal includes: 
 Scalable expansion of existing pipeline infrastructure, which is directly attached to approximately 60% of 
ISO‐NE’s natural gas generation capacity 
 Collaboration with existing regional storage providers to offer firm services to gas‐fired power plants in the 
region with guaranteed natural gas supplies on peak days, and to enable rapid response to sudden changes 
in power output that supports renewable generation development 
 An environmentally responsible approach that will minimize impact by using existing asset footprints 
 Additional Algonquin and Maritimes delivery points for local distribution companies (LDC) to access diverse, 
low‐cost natural gas resources where necessary 
Access Northeast is a direct response to numerous requests from regional stakeholders and governmental 
agencies in New England for an environmentally responsible, scalable, efficient and effective pipeline project to 
meet the needs of energy consumers in New England over the next decade to keep energy prices at competitive 
levels with a low risk of volatility. Spectra Energy’s and Northeast Utilities’ collaborative solution and 
partnership with regional stakeholders achieves all of these objectives by providing access to low‐cost supply 
diversity while minimizing community and environmental impacts through the enhancement of existing 
infrastructure. Access Northeast is scalable for further expansion, and is projected to be in service as early as 
November 2018. 
Maine can participate in Access Northeast in one of the following ways, either in addition to Atlantic Bridge, or 
separately: 
 Through support and continued pursuit of the NESCOE process 
 By leveraging its ECRC authorization with other New England States who currently have the ability to direct 
their regulated utilities to subscribe to capacity 
 By subscribing to the scalable Access Northeast project on a stand‐alone basis 
PUBLIC 10
Benefits of Atlantic Bridge and Access Northeast 
Best Fulfills the Requirements of the Energy Cost Reduction Act and Represents True 
Transformative Capacity: 
To enter into an ECRC per the Energy Cost Reduction Act, the Commission must have determined in an 
adjudicatory proceeding that the ECRC is commercially reasonable and in the public interest, and that the 
contract is reasonably likely to accomplish the following objectives: 
 To materially enhance natural gas transmission pipeline capacity into the State or into the ISO‐NE region; 
 that the additional capacity it provides will be economically beneficial to Maine's electric consumers, natural 
gas consumers, or both; 
 that the overall costs of the contract are outweighed by its benefits to Maine's electric consumers, natural 
gas consumers, or both; and 
 To enhance electrical and natural gas reliability in the State. 
Atlantic Bridge and Access Northeast exactly meet the foregoing criteria. 
Commercially reasonable terms. The contractual terms of both projects are commercially reasonable because 
they reflect FERC‐approved language and accomplish the following goals: (1) maximize deliverability to gas‐fired 
generators; (2) meet the goal of speed to market; and (3) provide the Commission with contractual “off‐ramps” 
in the event later events suggest that an ECRC is no longer prudent in any way. 
Public interest. A key element is whether the Commission determines in Phase One of the ECRC proceeding 
that moving forward with an ECRC is prudent. If the Commission decides in the affirmative, the Atlantic Bridge 
and Access Northeast projects will maximize the public interest because these projects: (1) are most likely to 
reach market sooner than other proposals; (2) are most likely to proceed to completion given the incremental 
nature of the projects; and (3) offer the greatest benefits of reliability and lower costs because they target gas 
capacity toward the greatest number of gas‐fired generators in the region. 
Material enchancement of capacity to Maine or the region. Because both projects involve bringing gas 
capacity into New England, they meet the “material enchancement of capacity” test. Both projects also offer 
the additional benefit of delivery directly into Maine. 
Economic benefits to Maine consumers. Both projects are targeted at bringing natural gas capacity where it is 
most needed: gas‐fired generators in the region. Ensuring that gas is deliverable to these generators maximizes 
the likelihood that the greatest number of gas‐fired generators will have firm capacity during the coldest days of 
winter, which ensures lower electric price volatility and lower overall electric prices. The additional capacity also 
addresses the needs of natural gas consumers in the State by permitting access to lower cost supply from 
existing pipeline interconnects. 
PUBLIC 11
Benefits outweigh the costs. The Commission has embarked on a separate process to determine whether the 
benefits of entering into an ECRC outweigh the costs. If the Commission finds in the affirmative based on the 
information available at this time, both projects offered by Spectra Energy maximize the benefits to Maine by 
targeting Maine’s investment where it is most needed: ensuring that the greatest number of gas‐fired 
generators are able to have firm capacity during the coldest days of winter. Both projects also offer contractual 
“off ramps” for the Commission in the event later events suggest that moving forward with an ECRC is no longer 
in Maine’s best interest. 
Enhance reliability. The current problem of electric price spikes in New England is fundamentally an issue of 
gas‐fired generators in the region not having sufficient access to gas capacity during the coldest days of winter. 
This is a reliability problem, and both projects Spectra proposes are aimed at resolving the reliability problem by 
targeting gas capacity directly at these gas‐fired generators. Moreover, by resolving the reliability challenge 
these generators face, the ability of these generators to operate during the coldest days of winter is enhanced, 
which improves the overall reliablity of the region’s electric system. 
Flexible Conditions Precedent and Variation of Volumes and/or Contractual Off‐ramps 
for PUC Contracts Gives Multiple Protections for Maine’s Potential Investment: 
Maine’s energy consumers and the Commission face an extraordinary dilemma. High price spikes in regional 
natural gas and electricity pricing during the winter have recently undermined Maine’s economic vitality, but 
there is the possiblity these spikes could be mitigated with sufficient, timely investment in natural gas pipeline 
facilities. The regional nature of energy pricing means all consumers in the region could benefit from an 
investment in gas capacity, but regional cooperation to solve the issue has slowed. Nevertheless, the benefits of 
Maine taking action on its own could be meaningful. At the same time, those benefits could be overwhelmed by 
actions of other entities in the market. Or, those benefits could be drastically reduced if the regional process 
restarts after Maine decides to invest on its own. Absent favorable action by other regional players or FERC, an 
ECRC could saddle Maine ratepayers with extra costs even though the Commission appropriately exercised its 
authority when signing an agreement. 
The Commission, therefore, needs assurance that it is investing in the right project at the right price at the right 
time. But there is no crystal ball. One cannot know for certain when signing a precedent agreement if the 
capacity being purchased will provide the energy cost reductions anticipated given the variety of factors at work. 
Nevertheless, standard terms, conditions and obligations of parties to a precedent agreement need not be a 
constraint. In fact, Spectra Energy is offering the Commission agreements on Atlantic Bridge and Access 
Northeast that can be evaluated and rescinded prior to project filings with FERC. This unique feature gives the 
Commission the luxury of reevaluating the cost/benefit ratio of its investment closer to project execution and, 
therefore, provides more certainty about the likelihood of benefits. In addition, as conditions in the market are 
evaluated in the future, the Commission could determine there are more impactful projects, rescind its 
agreement, and redeploy its investment. More specifically, the contractual “off‐ramp” included within these 
proposals enables the Commission to later determine whether future private or regional investments in pipeline 
capacity alter the calculus of benefits of an ECRC. If, under these circumstances, the Commission determines 
within the terms of the “off ramp” that moving forward with an ECRC is no longer warranted on the same terms, 
the Commission would have room to back out of the contract or make a more limited, strategic investment in 
PUBLIC 12
capacity at a specific location aimed at addressing a particular bottleneck that impacts the ability of one or more 
gas‐fired generators to have access to gas during the coldest days of winter. 
Atlantic Bridge: 
The PUC or its designee can execute a precedent agreement for up to 200 MMcf/d or $75 million/yr equivalent 
capacity that includes periodic updates on how much capacity is committed to other Maine entities. For each 
increment of additional Maine‐based capacity, the Commission can elect to scale back its investment as the 
project is filled out to maximum capacity for a 2017 in‐service date. This allows the PUC optionality to re‐deploy 
its investment as it sees fit. No firm transportation service agreement is executed until after receipt of the FERC 
certificate for the project, and no payments under that service agreement are required until the project is 
placed into service. 
Access Northeast: 
An Access Northeast precedent agreement is fully assignable with termination rights for certain circumstances. 
We are confident that Access Northeast could proceed based on market support irrespective of a Maine ECRC. 
Therefore, we can provide maximum flexibility for a partial or complete contractual off‐ramp for Maine in the 
event a regional effort proceeds that Maine believes will make an ECRC unneccessary or uneconomic. In our 
proposal, protection of Maine’s ratepayers would not be subject to a supplemental regulatory process or 
capacity release rules, provided the firm service agreement has been executed at the time the PUC would want 
to exercise this out. 
Assessing the future impact of an ECRC is is extremely difficult. Depending on the circumstances, the benefits of 
an ECRC may not actually outweigh the costs. If the Commisssion decides at this stage to proceed with an ECRC 
but later becomes concerned that any of the benefits may not be realized (e.g. market reforms impact basis 
differential and reliability, private market actors secure sufficient commitment for other pipeline capacity), the 
Commission can terminate its precedent agreement within a mutually agreeable timeframe. 
Promotes Maximum Return on Investment by Leveraging Private Commitments: 
For Atlantic Bridge, private interest in the project is sufficient at this time for Algonquin and Maritimes to say 
with confidence that the project will move forward. For Access Northeast, Northeast Utilities’ interest in the 
project as one of the region’s largest utilities also signals the importance of this project to the needs of electric 
consumers. By targeting capacity towards the gas‐fired generators who typically set the market price for electric 
commodity in the region, Access Northeast offers the greatest opportunity to maximize the benefits of 
additional gas capacity on regional electric prices. 
Timeliness to Market: 
The sooner pipeline capacity is added, the sooner Maine will see lower energy costs. Assuming the Commission 
moves forward to Phase Two, the Commission should select the project with the best chance of providing quick 
and tangible benefits to Maine energy consumers. This proposal provides those benefits, and does so with the 
speed‐to‐market the State expects. Atlantic Bridge is proposed to be in service by the winter of 2017‐2018. The 
project is largely a replacement and modification of existing pipelines that requires work on facilities covering 
PUBLIC 13
relatively few miles, is located on existing rights of way, and is being conducted by a pipeline developer with a 
history of meeting in‐service dates for projects in congested areas, including Boston, New York, and 
Philadelphia. Access Northeast is planned for similar construction techniques with a proposed in‐service date in 
November 2018. Pre‐filing with FERC for Atlantic Bridge is expected in the fourth quarter of 2014. 
Scalable Expansion of Atlantic Bridge/Access Northeast: 
The Atlantic Bridge and Access Northeast projects are flexible and easily scalable because the expansions occur 
primarily within the existing pipeline footprints. These projects can be sized to meet the specific capacity 
requirements of the Maine market, allowing for customized receipt and delivery points (including multiple 
receipt and delivery points) to meet individual customers’ needs. Adding right‐sized expansion projects along 
the system also provides incremental pipeline capacity as it is needed, when it is needed, to satisfy increased 
customer demand. 
Atlantic Bridge and Access Northeast are projects that involve the incremental expansion of existing gas 
infrastructure that is scalable to meet the needs of specific shippers in specific locations. In contrast to a 
greenfield project that requires a substantial level of commitment by shippers to move forward, the ability of 
the incremental projects to proceed is less dependent on the actions of others. So, as Maine decides whether to 
invest in projects that are more likely to happen, it should give serious consideration to incremental projects like 
Atlantic Bridge and Access Northeast whose size can be adjusted to meet the needs of the shippers, including 
that of the State of Maine. 
Domestically Sourced Natural Gas Deliveries to Maine: 
The Atlantic Bridge project offers the opportunity to allow gas to directly flow into Maine from abundant and 
lower‐priced domestic sources south of Maine such as the Marcellus region in Pennsylvania. This project offers 
Maine an opportunity—for the first time—to procure gas supply directly into the State. 
Maine currently receives limited natural gas supplies from domestic sources. Yet, today in North America, 
Appalachian Basin natural gas, not Canadian gas, drives prices for the commodity. To bring that lower‐cost, 
market‐making natural gas to delivery points in Maine requires significant changes to the regional pipeline 
system. To realize fully the advantages of Appalachian shale gas in Maine requires bringing more robust gas‐on‐gas 
competition to the State. 
Atlantic Bridge provides that link from this low‐cost resource to Maine’s energy consumers. At capacity, Atlantic 
Bridge could transport between 200‐300 MMcf/d to Maine delivery points by expanding Algonquin and 
changing Maritimes to a bidirectional facility that can move gas from Algonquin receipts to Maine deliveries. 
Directly Impacts Customers in Maine: 
Maine would benefit from the addition of new pipeline capacity into the region because it would allow Maine to 
directly access new, lower priced, abundant natural gas supplies. Maine is in a unique situation where 
customers in the State are not only plagued by high electricity costs due to infrastructure capacity constraints in 
New England from the south, but they are also held captive to higher‐cost, often insufficient, natural gas 
supplies from the north. 
PUBLIC 14
Electric prices in the ISO‐NE region have spiked over the past two years when temperature drops prevented gas‐fired 
generators from having sufficient gas capacity to run, or required such generators to purchase high‐priced 
gas on the spot market. To address this problem, it is not enough that gas be physically present in the region; 
rather, it is essential that the gas molecules actually be able to reach these gas‐fired generators on the coldest 
days of winter. The Algonquin and Maritimes systems directly serve approximately 60% of the gas‐fired 
generation in the ISO‐NE region, and access to many of these generators is accomplished via telescoping laterals 
that can be constrained when gas demand is high. The benefit of the Atlantic Bridge and Access Northeast 
projects is that they not only ensure that gas capacity is available in the region, but they also ensure that the 
natural gas can physically reach the gas‐fired generators who need the gas during the coldest days of winter. 
Moreover, because the regional electric price hinges on the price of the last unit called upon to serve, the more 
gas‐fired generators with firm access to gas, the lower the likelihood that more expensive units will end up 
setting the regional price of electricity. In short, if Maine wants to maximize the value of an ECRC, it should 
focus on projects like Atlantic Bridge and Access Northeast that maximize the delivery of gas to the greatest 
number of gas‐fired generators. 
An additional benefit for Maine’s manufacturers could also be achieved by the Commission by procuring Atlantic 
Bridge capacity. During peak price days in recent winters, some of Maine’s manufacturers had to slow or stop 
production activities due to high energy costs. These work stoppages impacted the bottom lines of the affected 
companies and their employees. Yet, some of these manufacturers have significant electric generation 
capability on site and may be able to meet some or all of their electricity needs. But, they are likely not able to 
cost‐efficiently produce electricity for their own needs on these peak days because of pipeline capacity 
constraints. Given the limitations, the Commission could consider procuring gas capacity through Atlantic Bridge 
and releasing it to the market periodically as a hedge. Then, on the coldest days, Maine could release the 
capacity at below market prices to willing manufactures with generation capability. This action could, in some 
circumstances, be of more value to Maine’s manufacturers than the impact of the capacity on the clearing price 
of electricity in the region. 
Innovative Use of Existing Resources (Storage) in the Region: 
Access Northeast will support renewable energy development by enabling rapid response to sudden changes in 
power output with regional storage facilities and quick‐start natural gas‐fueled power generation. Access 
Northeast will provide new Electric Reliability Service (ERS) for firm transportation of natural gas and natural gas 
supply supported by regional storage facilities for any party (Customer). This proposed service provides greater 
fuel certainty for generators and performance flexibility through reserved No Notice Transportation with an 
hourly supply option. Illustrative tariffs can be found at spectraenergy.com/NewEngland. While certain 
measures could meet New England’s basic needs, Access Northeast will combine well‐tuned pipeline capacity 
additions with the smart use of regional storage facilities to more effectively match the economic and 
environmental needs of the region. 
Innovative and Novel Approach: 
Rate Schedule ERS is a reserved No‐notice transportation service that incorporates non‐rateable delivery rights 
for primary firm deliveries. The firm capacity is reserved for Shippers full MDTQ on a 24/7 basis. The No‐notice 
flexibility is supported through regional storage facilities and allows a shipper to commence delivery up to two 
hours without commensurate supply in advance of flow. This combination of firm reserved pipeline capacity 
PUBLIC 15
and non‐rateable deliveries allows for generators and other parties that contract for the service to ensure that 
pipeline capacity will be available when they call on it, and the non‐rateable service provides the flexibility that 
more aligns with gas‐fired generator burn profiles. 
The MSOA (Multi‐shipper Option Agreement) allows multiple parties to contract under one administrator to act 
on their behalf. The electric distribution companies (EDC) would be the Principals under an MSOA, and they 
would have an Administrator that would manage the collective capacity ensuring that the gas‐fired plants have 
priority access to the generation related pipeline capacity/services to reliably serve their plants. The 
Administrator would also optimize any unutilized or underutilized capacity. 
Transportation Service Will Be FERC‐Jurisdictional: 
All facilities and services will fall under the regulatory oversight of the FERC. A FERC‐regulated facility provides 
transparency and oversight to ensure that: (1) due diligence is followed on all aspects of the construction of 
facilities, especially those involving environmental and cultural resources; (2) all issues related to regulatory, 
environmental, permitting, landowners and other stakeholders are addressed; (3) all facilities are appropriate 
for the service; and (4) continued oversight is maintained throughout the term of the contract. In short, FERC 
review, approval and oversight helps to minimize risk for all involved parties, particularly with respect to 
involvement with the project by local and regional environmental, landowner, and public official stakeholders. 
Provides Direct Access to New Supply Regions: 
Historically, the Northeast region has relied on three main supply areas: Gulf Coast U.S., Canada and LNG. 
During the last decade, the supply sources expanded to include Rockies/Midcontinent gas and eastern Canada 
production. The biggest change has occurred in just the last six years with the rapid development of the 
Marcellus Shale gas basin in Appalachia. Production from the Marcellus has transformed the supply dynamic 
into the Northeast. 
Marcellus production has grown from 2 Bcf/d in 2008 to over 16 Bcf/d in 2014. As the new local production has 
emerged, there has been a decline in the Northeast region’s imports from other U.S. supply basins, Canada, and 
LNG. This extraordinary upswing in Northeast production is resulting in new delivery points and new pipeline 
infrastructure to bring this shale gas to market, and with it lower prices for consumers. 
Canadian and LNG supplies have long played a significant role in gas supply to the Northeast U.S. Canada 
remains pivotal to the region, but with new Marcellus supplies so near, the level of imports has begun to 
decline, falling by 50% from 2009 to 2012. 
Natural gas production in the Marcellus and Utica regions is currently at approximately 16 Bcf/d and production 
is continuing to grow. Algonquin is connected to this supply through approximately 3 Bcf/d of existing pipeline 
interconnections on pipelines with capacity in excess of 10 Bcf/d providing multiple receipt point options 
including, but not limited to upstream pipelines: Texas Eastern, Transco, Columbia, Tennessee Gas Pipeline, 
Millennium and Iroquois. With Atlantic Bridge and/or Access Northeast, these multiple receipt point options 
provide a direct connection to a new, lower‐cost, stable source of natural gas supply for customers in New 
England and, more specifically, customers in Maine who have traditionally been tied to declining, often sporadic 
and expensive natural gas delivered from the north. 
PUBLIC 16
Provides Firm Pipeline Transportation 24/7/365: 
The regional need for access to new natural gas supplies and new firm pipeline transportation is evident. The 
Atlantic Bridge and/or Access Northeast projects provide economic solutions to the infrastructure gap between 
Marcellus supply and the Maine markets, offering year‐round firm transportation capacity. This reliable and 
consistent service means customers will enjoy the benefits of accessing lower cost natural gas supplies with the 
confidence that it will be delivered by Algonquin and Maritimes on a firm basis. 
Provides Access to Premium Markets: 
Algonquin’s footprint traverses what is considered the most premium markets in North America. Serving local 
distribution companies, industrial, and power generation customers, Algonquin currently delivers 2.6 Bcf/d of 
natural gas to delivery points across New Jersey, New York, Connecticut and Massachusetts. As part of this 
customer base, Algonquin has approximately 1.4 Bcf/d of gas‐fired generation customers directly connected to 
the system. Together with approximately 375,000 Dth/d of peak power generation demand on Maritimes, this 
represents approximately 60% of New England’s power generation demand directly connected to the two 
Spectra Energy pipelines. In short, this makes Algonquin and Maritimes a critical fuel delivery system for New 
England power producers. 
PUBLIC 17
Historically, power generators operating in the New England market have relied predominantly on unutilized 
capacity to deliver the natural gas required to power their plants. This capacity, largely held by LDCs, has over 
the last number of winters become increasingly unavailable due to increased demand. This has resulted in 
extreme electricity price volatility in the region. Spectra Energy is aligned with the Commission in the belief that 
additional natural gas pipeline infrastructure, both in the short term and the long term, is essential to 
strengthening electric reliability, which in turn will result in a reduction of prices and a reduction of daily price 
volatility. 
PUBLIC 18
This presents a unique opportunity for customers in Maine who participate in the Atlantic Bridge and/or Access 
Northeast projects. Given the New England market dynamics, and Algonquin’s vast footprint in the market, 
customers in Maine could take advantage of exceptional pipeline transportation optionality with access to these 
premium markets on a secondary basis when not fully utilizing their firm pipeline transportation. 
Minimizes Environmental and Stakeholder Impact: 
Customizing expansion capacity and building that new capacity within Algonquin and Maritimes’ existing 
pipeline footprint minimizes the environmental and stakeholder impact. By utilizing existing corridors where the 
pipeline is already operating, the need for additional land acquisition is minimized, and disturbance to land 
owners and the communities that they live in is also minimized. Expanding an existing pipeline within an 
established footprint also helps to reduce project execution risk. While risk is inherent in any project, the 
probability of economic, regulatory, construction, or timing risk is dramatically reduced as compared to new 
greenfield pipeline development projects. Reducing this risk will help to ensure timely project execution success 
for Algonquin and Maritimes. 
Spectra Energy Has a Proven Track Record: 
Spectra Energy is one of North America’s premier pipeline and midstream companies, developing critically 
important pipeline and related energy infrastructure projects for nearly a century. Spectra Energy’s expertise, 
vast experience, existing and extensive pipeline footprint, connection to diverse supply sources and premium 
markets, and strong customer and stakeholder relationships all contribute to Spectra Energy’s proven track 
record of successful pipeline construction and operation in New England and throughout North America. 
PUBLIC 19
At Spectra Energy, Safety Is at the Forefront: 
Spectra Energy is dedicated to safety in ALL aspects of its business and is extremely focused on 
uncompromisingly safe construction and operation of its facilities. Spectra Energy follows a “compliance plus” 
mindset that goes beyond regulatory requirements. Moreover, Spectra Energy reaches out beyond its internal 
focus and works closely with its contractors, regulators, and customers to ensure a safe work environment at all 
levels and dimensions of its business. Further details on some of Spectra Energy’s specific safety initiatives and 
programs can be found on pages 23‐24 of this proposal. 
PUBLIC 20
Project Execution Experience 
Spectra Energy grows its business by adding infrastructure capacity and services. Since separating from Duke 
Energy in 2007, Spectra Energy has placed into service 63 fee‐based expansion projects totaling more than $7.5 
billion. Over the next three years, the company has plans to invest approximately $6 billion in additional growth 
projects. 
Key to Spectra Energy’s success has been a culture of excellence in project execution. Spectra Energy 
understands that executing projects requires attention to many details. In addition to this focus on the technical 
excellence of design and construction of new facilities, Spectra Energy is committed to a comprehensive 
stakeholder outreach effort that encompasses extensive consultation with landowners, politicians and agencies 
to identify environmental permitting considerations for the project. 
These projects are delivered by using a disciplined management approach to project execution. The approach 
consists of phases and dates that describe the project life‐cycle and critical decision points. The methodology is 
aligned with Project Management Institute’s best practices for establishing the right priorities and ensuring that 
decisions are based on well‐developed information. 
A macro overview of the capital expansion project lifecycle management system is provided below, with key 
processes/activities and quality goals highlighted beneath each phase. 
PHASE 2 
Scope/Cost 
Refinement 
PHASE 1 
Initial 
Project Scoping 
» Concept 
development 
» Feasibility 
» Economic feasibility 
» Initial risk 
assessment 
» PFA/seed capital 
reqs 
» Project team 
activated 
» Pre‐budget 
» Risk assessment 
» Project plan 
developed 
PHASE 3 
Baseline 
Regulatory Filings 
» Project team 
expanded 
» Budget 
» P2 design drawings 
» RFI/RFQ 
construction 
» Project plan 
baseline 
» Review risks 
PHASE 4 
Regulatory 
Approvals 
Design & Permit 
» Project execution 
team 
» Design drawings 
IFB/IFC 
» Monitor change 
controls 
» Construction bid 
documents 
» Project execution 
plan 
» Regulatory response 
» Project monitoring 
PHASE 5 
Construction & 
Commissioning 
» Begin 
construction 
» Materials 
coordination 
» Inspections 
» Project 
monitoring & 
controls 
» Risk review 
PHASE 6 
Project Closure 
» Restoration 
reporting 
» Landowner releases 
» Reg/Envpermits 
» As‐builts and 
turnover 
» Financial closure 
» Lessons learned 
» Contractor closure 
QUALITY GOALS 
» Put a sound strategy 
in place ‐ prepare 
for commercial deal 
and project success 
» Conduct sound 
planning ‐ refine 
strategic planning 
requirements and 
facility/scope/cost 
estimates; prepare for 
regulatory approvals 
and next phase. 
» Conduct sound 
planning ‐ refine all 
estimates and prepare 
for regulatory 
approvals, execution of 
strategies/plans and 
construction phases. 
» Perform Effective 
Execution ‐ approvals, 
budget and materials 
management 
throughout 
construction and 
commissioning phases 
» Perform Effective 
Execution ‐ approvals, 
accurate cost forecasting, 
construction and 
materials management 
throughout construction 
and commissioning 
phases 
» Project Closure & 
Continuous Learnings 
– completion of all 
closure components 
and documentation, 
including Lessons 
Learned for future 
reference 
PUBLIC 21
Recent Projects in Execution or Recently In Service 
The following diagram provides a geographical perspective of the scope and scale of projects Spectra Energy has 
currently in execution. 
Of particular interest would be the AIM project. The AIM project is currently in the permitting phase of 
development, with the project’s FERC application being filed in February 2014. Algonquin secured contractual 
commitments for the project from local distribution companies for new pipeline capacity of 342,000 Dth/d. The 
planned in‐service of the AIM project is November 2016. 
PUBLIC 22
Safe, Responsible and Reliable Operations 
Safety is the top priority for Spectra Energy. The vision is that all Spectra Energy employees and contractors will 
demonstrate personal commitment to continuous safety improvement, resulting in a zero‐injury and zero‐work‐related 
illness culture. 
We have a strong safety record. Over the past five years, the incident rate for Spectra Energy’s onshore 
pipelines in the US is half of that in the industry as a whole. While we already have a strong safety record, our 
goal is zero incidents. No incident is acceptable. Spectra Energy works closely with federal and state regulators 
to ensure safe, reliable natural gas for Americans, and we inspect more pipeline annually than required by state 
and federal regulations. We also are committed to being a good neighbor in the communities that host our 
facilities. 
Spectra Energy is committed to managing its operations in a way that protects the safety, security, and health of 
its employees, its customers, and the public. Experienced and highly trained employees operate and maintain 
the company’s pipelines and facilities using thoroughly tested internal procedures and standards, while adhering 
to strict regulations. Spectra Energy strives to be an industry leader in pipeline integrity and service reliability. 
Each business provides contractor safety management programs. The SAFE3 Contractor Safety Management 
Program focuses on hiring “safety capable” contractors, identifying and mitigating risks, oversight, and post‐job 
evaluations. Since SAFE3’s development and implementation three years ago, Spectra Energy has achieved a 
significant reduction in U.S. contractor injuries. 
Spectra Energy actively manages the integrity of its assets in order to protect its employees and the public, and 
to ensure the reliable delivery of natural gas to its customers. The company’s leadership and commitment to 
pipeline integrity has earned it industry‐wide respect and credibility. 
Spectra Energy’s well‐established Integrity Management Program includes systematic management and 
maintenance practices, such as sophisticated inspection devices and aerial pipeline patrols, designed to mitigate 
PUBLIC 23
threats to its facilities. 
Customers rely on Spectra Energy to provide uninterrupted transportation of natural gas, so its facilities and 
equipment must be properly maintained and monitored. The company tracks measures of reliability specific to 
its businesses. 
PUBLIC 24
Appendix 
PUBLIC 25
Spectra Energy Overview 
Spectra Energy Corp (NYSE: SE), a Fortune 500 company, is one of North America’s leading pipeline and 
midstream companies. Based in Houston, Texas, the company’s operations in the United States and Canada 
includes more than 22,000 miles of natural gas, natural gas liquids, and crude oil pipelines; approximately 305 
billion cubic feet (Bcf) of natural gas storage; 4.8 million barrels of crude oil storage; as well as natural gas 
gathering, processing, and local distribution operations. 
Spectra Energy is the general partner of Spectra Energy Partners (NYSE: SEP), one of the largest pipeline master 
limited partnerships in the United States and owner of the natural gas, liquids, and crude oil assets in Spectra 
Energy’s U.S. portfolio. Spectra Energy also has a 50 percent ownership in DCP Midstream, the largest producer 
of natural gas liquids and the largest natural gas gatherer and processor in the United States. 
Spectra Energy’s natural gas assets strategically connect conventional and unconventional natural gas supplies 
with four of the five fastest‐growing markets in North America. Its natural gas storage facilities are strategically 
positioned to serve local distribution companies, power and gas utilities, marketers and traders, and producers. 
PUBLIC 26
At Spectra Energy, we pride ourselves on creating a world‐class work environment and offering the most 
advance, sustainable energy solutions. Below are some of our most recent awards. Spectra Energy has served 
North America customers and communities for more than a century. The company’s longstanding values are 
recognized through its inclusion in the Dow Jones Sustainability World and North America Indexes and the CDP 
Global 500 and S&P 500 Climate Disclosure and Performance Leadership Indexes. 
For the seventh consecutive year Spectra Energy Corp was named to the 2014 CDP S&P 500 Climate Disclosure 
Leadership Index (CDLI) and Climate Performance Leadership Index (CPLI). For the second consecutive year 
Spectra Energy was the only energy company to be named to the CPLI and the only energy company to make 
both indices. 
Spectra Energy has also been named to the Dow Jones Sustainability World Index (DJSI World) for the fifth 
consecutive year, to the Dow Jones Sustainability North America Index (DJSI NA) for the seventh consecutive 
year, and as an Industry Leader among its peers. 
Fortune Magazine's FORTUNE 500 
 Annual ranking of America's largest corporations: 2008‐2014 
Corporate Responsibility Magazine’s 100 Best Corporate Citizens List 
 Named to the 100 Best Corporate Citizens List: 2011‐2014 
 Recognized as the best corporate citizen among utilities: 2012‐2013 
Ethisphere Institute's World's Most Ethical Companies List 
Most recently, Spectra Energy was named for the third year in a row to Ethisphere Institute’s World’s Most 
Ethical Companies List for 2014. Recognized for leadership in promoting ethical business standards, exceeding 
legal minimums for compliance and introducing innovative ideas: 2012‐2014. 
For more information, please go to www.spectraenergy.com. 
PUBLIC 27
Business Segment Overview 
Spectra Energy is focused on delivering premium services through four very distinct business segments: 
 U.S. Transmission – Spectra Energy has one of the largest pipeline and storage systems in North America 
 Distribution – Spectra Energy is the second largest local distribution company in Canada serving 1.4 million 
customers in 400 communities and has the largest storage facilities in Canada 
 Western Canada Transmission & Processing – Spectra Energy is one of the largest producers of natural gas 
liquids in Canada 
 Field Services – Spectra Energy has a 50 percent interest in DCP Midstream – the largest natural gas 
processor in the U.S. 
PUBLIC 28
The Way Spectra Energy Works 
Spectra Energy’s purpose is to create sustainable value for its investors, customers, employees and communities by 
providing natural gas gathering and processing, transmission, storage and distribution services. It builds value by: 
 Advancing the role of natural gas in meeting North America’s energy needs 
 Delivering excellence in safety, reliability, customer responsiveness and profitability 
 Capitalizing on the size and attributes of its existing assets 
 Executing its expansion projects on time and on budget 
 Pursuing strategic growth opportunities 
Spectra Energy’s Charter, Code of Business Ethics and commitment to economic, environmental and social 
responsibility define the way the company works. 
Spectra Energy’s values which guide the company’s actions and shape its decisions are: 
 Stewardship – Demonstrating a commitment to environmental responsibility and vibrant communities 
 Integrity – Ethically and honestly doing what it says it will do 
 Respect for the Individual – Embracing diversity and inclusion, enhanced by openness, sharing, trust, 
leadership, teamwork and involvement 
 Safety – Sharing a relentless commitment to a zero‐work‐related injury and illness culture 
 High Performance – Accountability, achieving superior business results and stretching its capabilities 
 Win‐Win Relationships – Having relationships which focus on the creation of value for all parties 
 Initiative – Having the courage, creativity and discipline to lead change and shape the future 
The company distinguishes itself through its commitments to strong corporate governance and business ethics; 
safe, reliable operations; environmental stewardship; and community support and engagement. 
Corporate Governance and Business Ethics 
Spectra Energy conducts its business with integrity, transparency and accountability. Its corporate governance 
systems are designed to be transparent and to ensure it complies with the letter and intent of all laws, regulations 
and rules that apply to its business and the industry, and that the company operates both ethically and profitably. 
The Spectra Energy Charter establishes the vision, purpose, values and measures of success. The values guide 
employees in the conduct of the business. The Code of Business Ethics (Code) establishes standards designed to 
help employees conduct business ethically and honestly. All company representatives are expected to abide by 
the Code. 
The company’s policies guide its employees in managing day‐to‐day compliance with the Code and set corporate 
standards and guidance for conducting business. In 2009, Spectra Energy strengthened its ethics expectations 
by revising the Code to address contractors, service providers and suppliers. Contractors now undergo the 
company’s ethics training, and supply contracts and master services agreements now require vendors to abide 
by the Code and ethics practices. 
PUBLIC 29
Regulatory and Permitting 
FERC Natural Gas Pipeline and Storage Process 
For purposes of illustration, Spectra Energy is describing the approach to obtaining a FERC Certificate for natural 
gas pipelines and storage facilities. Spectra Energy has been actively involved with FERC in the review and 
approval process for natural gas pipeline and storage facilities for many years. Since the inception of Spectra 
Energy in 2007, the company has worked with its customers and its regulators to successfully place into service 
over 63 projects. Spectra Energy maintains an excellent working relationship with FERC. 
FERC plays a key role in the development and expansion of U.S. natural gas transmission projects. Under 
direction from the U.S. Congress, FERC regulates the transmission and storage of natural gas in interstate 
commerce. FERC is charged with determining whether proposed projects are needed and in the public interest, 
and ultimately whether to issue a Certificate authorizing the construction and operation of facilities comprising 
the projects. Their project development efforts continue by monitoring compliance through construction, 
operational commissioning, and post‐construction restoration work. 
FERC’s natural gas certificate processes include consulting with stakeholders, such as landowners, community 
leaders, public officials and relevant federal, state and local agencies, identifying environmental and land‐use 
issues through a process that FERC refers to as its “scoping” process, and preparing environmental documents 
such as Environmental Assessments or Environmental Impact Statements. Sponsors of large greenfield projects 
often request and receive a preliminary determination on non‐environmental issues prior to receipt of a final 
FERC order to provide an early indication of FERC’s findings regarding the economic aspects of the project. 
Certificates are issued by final FERC order. 
Pipeline companies seeking project authorization must file an Application for a Certificate (Certificate 
Application) with FERC. The Certificate Application describes the purpose and commercial need for the project, 
the transportation rate to be charged to customers, and any specific terms and conditions of service that will 
apply to the project, proposed timing and scope of the facilities to be constructed, and a demonstration that the 
project applicant will be in compliance with all applicable regulatory requirements with respect to the project. 
Applicants must evaluate project alternatives, identify a preferred alternative, and complete a thorough 
environmental analysis, including consultation with appropriate regulatory agencies, data reviews and field 
surveys. Information obtained through this review is compiled into a document known as the “Environmental 
Report,” which the Applicant prepares as part of the Certificate Application. The Environmental Report also 
details all other federal, state and local permits required for the project, as well as agencies consulted in 
preparation of the Environmental Report. 
To determine whether a proposed project is in the public convenience and necessity, FERC, in addition to its 
review of the economic aspects of the project, conducts a comprehensive environmental review of the projects, 
in accordance with the National Environmental Policy Act (NEPA). In the NEPA process, FERC works closely with 
Federal, state, and local agencies such as the U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service, state 
departments of environmental protection, and other state and local agencies. Other stakeholders, including 
project neighbors, landowners, and surrounding communities, are also invited to participate in the FERC process 
by attending meetings and providing comments or concerns at particular times in FERC’s review process. 
PUBLIC 30
FERC will review the project, evaluating the need, proposed facility locations, and overall impact of project 
construction and operation, and will summarize its findings in either an Environmental Assessment or an 
Environmental Impact Statement, depending on characteristics of the project. Upon completion of an 
Environmental Assessment or Environmental Impact Statement for a project and completion of its review of the 
economic aspects of the project, FERC will issue an order in which it determines, based on the entirety of its 
review, whether the project is in the public convenience and necessity. If FERC so determines, it will issue a 
Certificate authorizing the construction and operation of the project facilities. 
FERC Pre‐Filing Process 
FERC has established a collaborative pre‐application process that gives landowners, government agencies and 
other interested stakeholders the opportunity to review project information and identify issues or concerns 
before a Certificate Application is filed with FERC or other permit applications are made. This phase of project 
development is referred to as the Pre‐Filing Process. 
Throughout the process, the Applicant and FERC will actively seek input from interested stakeholders through 
public outreach efforts that include written communications and public meetings. Stakeholders are encouraged 
to participate and share any questions or concerns so they can be addressed prior to submittal of the Certificate 
Application. Additionally, FERC reviews drafts of the Applicant’s Environmental Report during this stage of the 
project. The Certificate Application, once filed, will identify a more detailed route and/or set of facilities and 
locations based on input that the Applicant has received from FERC and interested stakeholders during the Pre‐ 
Filing Process. 
At the beginning of the Pre‐Filing Process, FERC issues a Notice of Intent, or NOI, to prepare an Environmental 
Assessment or Environmental Impact Statement (environmental document) for the proposed project. With the 
NOI, FERC initiates a scoping period in which it seeks to discover and address concerns the public may have with 
the environmental and land‐use aspects of the project. The primary goal of the scoping process is to focus 
FERC’s analysis in the Environmental Assessment or Environmental Impact Statement on the important 
environmental and land‐use issues. Comments received during the scoping period will be incorporated into 
FERC’s environmental document. 
Project Application 
Once the Pre‐Filing Process is complete, the Applicant files a Certificate Application for the project along with an 
anticipated schedule. Additionally, permit applications are submitted to other federal, state, and local agencies. 
The permit proceedings conducted by these agencies often provide additional opportunity for public 
involvement. 
Once the Certificate Application has been filed, FERC will issue a Certificate Docket number (CP__‐). As with the 
Pre‐Filing Process, all public documents associated with the Certificate Application and filed with or issued by 
FERC are accessible via the e‐Library on FERC’s Web site (www.ferc.gov). Additionally, copies of the Certificate 
Application and the Environmental Report will be made available at public locations within each county 
impacted by the project so that all stakeholders will have the opportunity to review and comment on the 
Certificate Application. Notices of the Certificate Application filing and the locations to view the documents are 
PUBLIC 31
sent to all identified stakeholders. The project sponsors’ outreach effort to interested stakeholders continues 
through this stage of the project. 
Within 10 business days of filing the Certificate Application, FERC will issue a Notice of Application, which will be 
posted in the Federal Register, notifying the public of the filing of the Certificate Application and the process for 
filing interventions or comments in the docket, and within 90 days of such notice, will issue a notice of schedule 
for environmental review of the Certificate Application, indicating when it expects to issue the final 
environmental document for the project and the deadline for final decisions from other relevant federal 
permitting agencies. During its review period, FERC will identify any additional or clarifying information that 
may be needed from the Applicant and will complete its environmental document in accordance with NEPA and 
its evaluation of the economic aspects of the project. 
Following issuance of the environmental document by FERC, stakeholders will have an opportunity to provide 
additional comments regarding the project. FERC will review any comments received and respond to them in 
either a final environmental document or, provided FERC agrees that the project is of public convenience and 
necessity, the agency may address comments directly in its Certificate. 
Project Authorization 
Once FERC issues a Certificate, the Applicant must: 
 Accept the Certificate within 30 days; 
 File an affirmative statement indicating commitment to provide environmental training to all individuals 
working on the project; and 
 File an Implementation Plan(s) within 60 days of the Certificate Order indicating how the project will comply 
with the conditions outlined in the Certificate Order. 
Project construction cannot begin until FERC authorizes a Notice to Proceed. The FERC staff will conduct 
periodic site visits throughout construction to ensure ongoing compliance, including a visit as construction nears 
completion to review restoration efforts and identify any additional needed measures. Applicants are also 
required to receive FERC approval prior to placing the project facilities into service. Additional monitoring of the 
right‐of‐way will continue after the project facilities are placed into service to ensure restoration efforts are 
successful. 
Spectra Energy’s Approach to the FERC Process 
Spectra Energy understands the importance of communicating with FERC Staff as well as representatives of 
other regulatory agencies, landowners, special interest groups, and other stakeholders during the development, 
permitting, and construction of new projects. To that end, Spectra Energy has received numerous recognitions 
and commendations on the success of their projects and Spectra Energy’s collaborative approach to working 
with all parties during the various stages of a project. 
Spectra Energy will communicate early and often with FERC Staff and other stakeholders to identify and address 
potential problems and issues in the most efficient and effective manner. This collaborative approach will be 
reflected in all phases of the project, from the identification of the optimum route for the pipeline to defining 
mitigation measures to address and minimize potential environmental impact, and to closely managing and 
PUBLIC 32
monitoring pipeline construction activities to ensure compliance with permit conditions and commitments made 
to landowners and other stakeholders. 
Spectra Energy is committed to embracing the FERC process and working with the FERC staff to successfully 
permit, construct, and operate the Project. 
PUBLIC 33
Environmental Stewardship 
Description 
Environmental stewardship refers to responsibility for environmental quality shared by those whose actions 
affect the environment during development of a natural gas pipeline project. Due diligence in identifying, 
mitigating and managing environmental impacts is important in order to ensure on‐time and on‐budget 
projects. This process also informs engagement strategies with regulatory agencies, landowners, communities 
and other key stakeholder groups. 
Spectra Energy’s Approach 
Spectra Energy’s approach to managing environmental risks and impacts in construction will be consistent with 
its corporate approach across all its operations, as follows: 
• Identify and understand environmental impacts; 
• Design projects to avoid or minimize environmental impacts; 
• Manage and mitigate unavoidable impacts; 
• Encourage responsible use of natural gas in its retail market areas; 
• Engage and respond to stakeholders; 
• Meet or exceed compliance requirements with applicable laws and regulations; and 
• Implement best management practices to minimize operational and environmental risks. 
Spectra Energy has committed to be a responsible environmental steward while striving to help meet North 
America’s increasing demand for natural gas. This environmental commitment is central to decisions on how 
Spectra Energy builds and manages its operations, helps customers address environmental impacts, and 
advocates for responsible public policies. 
Agency Outreach – Approach 
Spectra Energy will create a Public and Agency Participation Plan to contact key federal and state agencies with 
jurisdiction over the general project area to define the resources, factors, and processes that could influence the 
successful permitting of a project of this magnitude. Items that would typically be addressed include the 
following: 
 Identify the agency’s jurisdictional authority; 
 Identify resources and issues that may be pertinent when the characteristics of the project are (better) 
defined; 
 Identify general approaches that the agency (and, more specifically, the agency staff) would recommend 
once formal consultation begins; 
 Identify local experts and special interest groups in the project area that may be parties; 
 Establish a general timeline for the agency’s consultation and permitting process; and 
PUBLIC 34
 Identify typical mitigation considerations that may ultimately be advocated by agencies and special interest 
groups. 
Based on the information that is collected, Spectra Energy will prepare a preliminary cost estimate and schedule 
for environmental studies and permitting. This will allow the company to evaluate potential schedule and cost 
implications of the project. The results of this review will be documented in a Critical Issues Report. 
Public – Approach 
After conducting environmental due diligence and establishing a plan for initial agency dialogue, Spectra Energy 
will determine a public outreach and community engagement strategy in close cooperation with the Maine 
Public Utilities Commission. In previous projects Spectra Energy has conducted “open houses” in order to 
provide the company’s description of the project to interested stakeholders and solicit information from 
participants about the project and any potential concerns. For more information about Spectra Energy’s 
approach to public outreach refer to the section on Stakeholder engagement. 
Environmental Studies – Approach 
During the Development Period, Spectra Energy will initiate detailed agency consultation with a detailed project 
description to define the agency required field studies, including the protocols for those field studies. Typical 
field studies may include the following. 
Special Status Species Surveys 
Special status species are those species of animals and plants for which state or federal agencies afford 
protection by law, regulation, or policy. Included in this category are federally listed and federally proposed 
species that are protected under the Endangered Species Act, or are considered as candidates for such listing by 
the U.S. Fish and Wildlife Service or National Marine Fisheries Service and those species that are state‐listed as 
threatened or endangered species or species of special concern. 
Spectra Energy will consult with U.S. Fish and Wildlife Service and state commissions to review rare and 
endangered species. Based on this information, Spectra Energy will conduct surveys of the project area for 
occurrences of or habitat for any such species identified as potentially present in the study area. If it is 
necessary for Spectra Energy to contract agency‐recognized or agency‐required specialists to conduct or 
participate in such surveys, Spectra Energy will incorporate those specialists into the Spectra Energy team as 
early as possible. 
Cultural Resource Surveys 
Section 106 of the National Historic Preservation Act (NHPA) requires that the lead federal agency under the 
NEPA (which will certainly be the FERC for this project) take into account the effects of its undertakings on 
properties listed on, or eligible for listing on, the National Register of Historic Places and provide the Advisory 
Council on Historic Preservation (ACHP) an opportunity to comment on the undertaking. 
To meet this requirement and assist with the formal federal and state consultation related to cultural resources, 
Spectra Energy will consult with the Division of Historical Resources and define what surveys will be required 
and what survey protocols (e.g., survey corridor widths and shovel test intervals) will have to be followed. Once 
PUBLIC 35
these parameters are defined, Spectra Energy will conduct field surveys in the survey area defined by the State 
Historic Preservation Office. 
Ambient Noise and Air Quality Measurements 
Depending on project requirements for compression equipment, Spectra Energy may conduct measurements of 
the ambient noise and air quality environments in the vicinity of any required/proposed compression units. Any 
such measurements will be compliant with required standards and guidance from staff representatives of the 
jurisdictional regulatory agencies. 
PUBLIC 36
Stakeholder Outreach 
For Spectra Energy, stakeholders are those who are, or could be, affected by the company’s operations. These 
include, but are not limited to, customers, landowners, communities, government officials, regulators, non‐governmental 
organizations, suppliers, analysts, media and shareholders. 
Spectra Energy is committed to identifying the stakeholders and potential issues related to the Project, 
determining appropriate and effective methods of communication, identifying responsible parties, documenting 
the public consultation process and adhering to communication protocols. 
Spectra Energy believes earlier and more collaborative involvement will lead to project designs that minimize 
impacts to landowners, communities and the environment while enabling the company to develop more 
comprehensive applications submitted to submit to the FERC, state agencies, and local jurisdictions. 
Stakeholder Outreach Principles and Approach 
Spectra Energy works closely with stakeholders in areas affected by its projects to foster long‐term relationships 
built on trust and respect. Spectra Energy’s core values guide its stakeholder outreach programs and activities 
as well as the work of its employees and contractors. 
In conducting business, Spectra Energy’s values guide its approach: 
• Stewardship ‐ Demonstrating a commitment to environmental responsibility and vibrant communities. 
• Respect for the Individual ‐ Embracing diversity and inclusion, enhanced by openness, sharing, trust, 
leadership, teamwork and involvement. 
• Integrity ‐ Ethically and honestly doing what we say we will do. 
• Win‐Win Relationships ‐ Having relationships that focus on the creation of value for all parties. 
• Initiative ‐ Having the courage, creativity and discipline to lead change and shape the future. 
While these values guide the company’s company‐wide stakeholder outreach approach, Spectra Energy tailors 
its activities for each project, ensuring that the dialogue with stakeholders is open, transparent and meaningful. 
Spectra Energy’s Stakeholder Engagement Principles, developed to guide its interactions, are: 
• To be respectful of and considerate to all stakeholders. 
• To engage with those affected by our business. 
• To consider stakeholder‐identified issues in its decision‐making process. 
• To provide timely and accurate communication using accessible information and language. 
• To be transparent in its processes and communications. 
Spectra Energy’s stakeholder outreach activities are endorsed by its executive management team. 
Spectra Energy has a company‐wide and customized programs for each activity and project, and communication 
plans that provide employees the “who, what, where and when” protocols when conducting business. 
PUBLIC 37
To ensure effective dialogue with its stakeholders, Spectra Energy relies on one‐on‐one discussions, face‐to‐face 
meetings, open houses, websites, legal notices, media outreach and individual letters sent via mail. 
Communications and materials are conducted in multiple languages, as needed. 
The key criteria inherent in implementing a successful stakeholder consultation plan are the ability and 
knowledge to explain a project’s benefits and its potential impacts; to respond to questions, concerns and 
issues; and, whenever possible, to mitigate potential impacts. In order to sustain a successful program, 
Spectra Energy seeks, involves, informs and responds to stakeholders by implementing the planning process 
early, with open and collaborative activities. The company executes its plans by engaging in and sustaining 
understandable, accurate and timely dialogue with its stakeholders. This process helps build and maintain win‐win 
relationships. 
Spectra Energy works closely with stakeholders in areas affected by its projects and strives to create mutually 
beneficial relationships with communities built on trust and respect. Spectra Energy also has a long history of 
working successfully with indigenous peoples across many of its operating areas. 
PUBLIC 38

More Related Content

What's hot

Ct alt. fuel corridors clean cities meeting 10 30-19
Ct alt. fuel corridors clean cities meeting 10 30-19Ct alt. fuel corridors clean cities meeting 10 30-19
Ct alt. fuel corridors clean cities meeting 10 30-19
Emily Zimmerman
 
Franklin Line Meeting - Dec 17, 2019
Franklin Line Meeting - Dec 17, 2019Franklin Line Meeting - Dec 17, 2019
Franklin Line Meeting - Dec 17, 2019
Franklin Matters
 
Hydrogen Progress, Priorities and Opportunities
Hydrogen Progress, Priorities and OpportunitiesHydrogen Progress, Priorities and Opportunities
Hydrogen Progress, Priorities and Opportunities
California Fuel Cell Partnership
 
Valone_TampaPortAuthority_GatewayRail_05132013
Valone_TampaPortAuthority_GatewayRail_05132013Valone_TampaPortAuthority_GatewayRail_05132013
Valone_TampaPortAuthority_GatewayRail_05132013Rebecca Valone,PMP
 
Va rail update
Va rail updateVa rail update
Va rail update
Jeff South
 
Mpx corp presentation eng
Mpx corp presentation engMpx corp presentation eng
Mpx corp presentation engMPX_RI
 
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Marcellus Drilling News
 
Ppt regulatory overview of shale gas in bc final
Ppt regulatory overview of shale gas in bc finalPpt regulatory overview of shale gas in bc final
Ppt regulatory overview of shale gas in bc final
bcogcommission
 
St lucias energy transition
St lucias energy transitionSt lucias energy transition
St lucias energy transition
Japan Caribbean Climate Change Partnership
 
CENAGAS, the operator of SISTRANGAS seeks to expand
CENAGAS, the operator of SISTRANGAS seeks to expandCENAGAS, the operator of SISTRANGAS seeks to expand
CENAGAS, the operator of SISTRANGAS seeks to expand
María Serna
 
Disinfection System
Disinfection SystemDisinfection System
Caltrain hsrmo uletter
Caltrain hsrmo uletterCaltrain hsrmo uletter
Caltrain hsrmo uletterAdina Levin
 
Integration of High Levels of Renewables on the Vermont Electric System
Integration of High Levels of Renewables on the Vermont Electric SystemIntegration of High Levels of Renewables on the Vermont Electric System
Integration of High Levels of Renewables on the Vermont Electric System
Power System Operation
 
Bluestone Gathering System Pipeline Data Sheet
Bluestone Gathering System Pipeline Data SheetBluestone Gathering System Pipeline Data Sheet
Bluestone Gathering System Pipeline Data Sheet
Marcellus Drilling News
 
Babst Calland Bulletin on Proposed PHMSA Change in Pipeline Regulations for N...
Babst Calland Bulletin on Proposed PHMSA Change in Pipeline Regulations for N...Babst Calland Bulletin on Proposed PHMSA Change in Pipeline Regulations for N...
Babst Calland Bulletin on Proposed PHMSA Change in Pipeline Regulations for N...
Marcellus Drilling News
 
CCSE Conference Plenary Presentation
CCSE Conference Plenary PresentationCCSE Conference Plenary Presentation
CCSE Conference Plenary Presentation
Center for Sustainable Energy
 

What's hot (18)

Ct alt. fuel corridors clean cities meeting 10 30-19
Ct alt. fuel corridors clean cities meeting 10 30-19Ct alt. fuel corridors clean cities meeting 10 30-19
Ct alt. fuel corridors clean cities meeting 10 30-19
 
Franklin Line Meeting - Dec 17, 2019
Franklin Line Meeting - Dec 17, 2019Franklin Line Meeting - Dec 17, 2019
Franklin Line Meeting - Dec 17, 2019
 
Hydrogen Progress, Priorities and Opportunities
Hydrogen Progress, Priorities and OpportunitiesHydrogen Progress, Priorities and Opportunities
Hydrogen Progress, Priorities and Opportunities
 
Valone_TampaPortAuthority_GatewayRail_05132013
Valone_TampaPortAuthority_GatewayRail_05132013Valone_TampaPortAuthority_GatewayRail_05132013
Valone_TampaPortAuthority_GatewayRail_05132013
 
Va rail update
Va rail updateVa rail update
Va rail update
 
Spectra present14
Spectra present14Spectra present14
Spectra present14
 
Mpx corp presentation eng
Mpx corp presentation engMpx corp presentation eng
Mpx corp presentation eng
 
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
 
Ppt regulatory overview of shale gas in bc final
Ppt regulatory overview of shale gas in bc finalPpt regulatory overview of shale gas in bc final
Ppt regulatory overview of shale gas in bc final
 
St lucias energy transition
St lucias energy transitionSt lucias energy transition
St lucias energy transition
 
CENAGAS, the operator of SISTRANGAS seeks to expand
CENAGAS, the operator of SISTRANGAS seeks to expandCENAGAS, the operator of SISTRANGAS seeks to expand
CENAGAS, the operator of SISTRANGAS seeks to expand
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
2013 01 24
2013 01 242013 01 24
2013 01 24
 
Caltrain hsrmo uletter
Caltrain hsrmo uletterCaltrain hsrmo uletter
Caltrain hsrmo uletter
 
Integration of High Levels of Renewables on the Vermont Electric System
Integration of High Levels of Renewables on the Vermont Electric SystemIntegration of High Levels of Renewables on the Vermont Electric System
Integration of High Levels of Renewables on the Vermont Electric System
 
Bluestone Gathering System Pipeline Data Sheet
Bluestone Gathering System Pipeline Data SheetBluestone Gathering System Pipeline Data Sheet
Bluestone Gathering System Pipeline Data Sheet
 
Babst Calland Bulletin on Proposed PHMSA Change in Pipeline Regulations for N...
Babst Calland Bulletin on Proposed PHMSA Change in Pipeline Regulations for N...Babst Calland Bulletin on Proposed PHMSA Change in Pipeline Regulations for N...
Babst Calland Bulletin on Proposed PHMSA Change in Pipeline Regulations for N...
 
CCSE Conference Plenary Presentation
CCSE Conference Plenary PresentationCCSE Conference Plenary Presentation
CCSE Conference Plenary Presentation
 

Viewers also liked

Marcellus Shale Gas Development and Pennsylvania School Districts: What Are t...
Marcellus Shale Gas Development and Pennsylvania School Districts: What Are t...Marcellus Shale Gas Development and Pennsylvania School Districts: What Are t...
Marcellus Shale Gas Development and Pennsylvania School Districts: What Are t...
Marcellus Drilling News
 
JLCNY Declaration of Landowner Rights
JLCNY Declaration of Landowner RightsJLCNY Declaration of Landowner Rights
JLCNY Declaration of Landowner Rights
Marcellus Drilling News
 
Research Study: Economic Potential for Shale Formations in Ohio
Research Study: Economic Potential for Shale Formations in OhioResearch Study: Economic Potential for Shale Formations in Ohio
Research Study: Economic Potential for Shale Formations in Ohio
Marcellus Drilling News
 
Marist College Poll on Hydrofracking in New York State
Marist College Poll on Hydrofracking in New York StateMarist College Poll on Hydrofracking in New York State
Marist College Poll on Hydrofracking in New York State
Marcellus Drilling News
 
Investing in America: Building an Economy that Lasts
Investing in America: Building an Economy that LastsInvesting in America: Building an Economy that Lasts
Investing in America: Building an Economy that Lasts
Marcellus Drilling News
 
CBO: The Economic and Budgetary Effects of Producing Oil and Natural Gas from...
CBO: The Economic and Budgetary Effects of Producing Oil and Natural Gas from...CBO: The Economic and Budgetary Effects of Producing Oil and Natural Gas from...
CBO: The Economic and Budgetary Effects of Producing Oil and Natural Gas from...
Marcellus Drilling News
 
Sanctimonious Letter from Delaware Riverkeeper & Others to PA DEP
Sanctimonious Letter from Delaware Riverkeeper & Others to PA DEPSanctimonious Letter from Delaware Riverkeeper & Others to PA DEP
Sanctimonious Letter from Delaware Riverkeeper & Others to PA DEP
Marcellus Drilling News
 
PennFuture Lawsuit Against Ultra Resources Alleging Air Pollution
PennFuture Lawsuit Against Ultra Resources Alleging Air PollutionPennFuture Lawsuit Against Ultra Resources Alleging Air Pollution
PennFuture Lawsuit Against Ultra Resources Alleging Air Pollution
Marcellus Drilling News
 
Penn State Cooperative Extension Marcellus Education Fact Sheet
Penn State Cooperative Extension Marcellus Education Fact SheetPenn State Cooperative Extension Marcellus Education Fact Sheet
Penn State Cooperative Extension Marcellus Education Fact Sheet
Marcellus Drilling News
 
Beck Energy and Exxon Mobil Bill of Sale #2 - Monroe County, OH
Beck Energy and Exxon Mobil Bill of Sale #2 - Monroe County, OHBeck Energy and Exxon Mobil Bill of Sale #2 - Monroe County, OH
Beck Energy and Exxon Mobil Bill of Sale #2 - Monroe County, OH
Marcellus Drilling News
 
Middlefield, NY Court Decision on Shale Gas Drilling Ban
Middlefield, NY Court Decision on Shale Gas Drilling BanMiddlefield, NY Court Decision on Shale Gas Drilling Ban
Middlefield, NY Court Decision on Shale Gas Drilling Ban
Marcellus Drilling News
 
Beck Energy and Exxon Mobil Bill of Sale - Monroe County, OH
Beck Energy and Exxon Mobil Bill of Sale - Monroe County, OHBeck Energy and Exxon Mobil Bill of Sale - Monroe County, OH
Beck Energy and Exxon Mobil Bill of Sale - Monroe County, OH
Marcellus Drilling News
 
Health Care Providers Letter to Gov. Andrew Cuomo Against Fracking
Health Care Providers Letter to Gov. Andrew Cuomo Against FrackingHealth Care Providers Letter to Gov. Andrew Cuomo Against Fracking
Health Care Providers Letter to Gov. Andrew Cuomo Against Fracking
Marcellus Drilling News
 
The Economic Impact of the Value Chain of a Marcellus Shale Well
The Economic Impact of the Value Chain of a Marcellus Shale WellThe Economic Impact of the Value Chain of a Marcellus Shale Well
The Economic Impact of the Value Chain of a Marcellus Shale Well
Marcellus Drilling News
 
Draft Discussion Paper: Transportation Impacts of Potential Marcellus Shale G...
Draft Discussion Paper: Transportation Impacts of Potential Marcellus Shale G...Draft Discussion Paper: Transportation Impacts of Potential Marcellus Shale G...
Draft Discussion Paper: Transportation Impacts of Potential Marcellus Shale G...
Marcellus Drilling News
 
Budgeting and Implementation Plan
Budgeting and Implementation PlanBudgeting and Implementation Plan
Budgeting and Implementation Plan
Jo Balucanag - Bitonio
 
Water Treatment Plant Design project
Water Treatment Plant Design projectWater Treatment Plant Design project
Water Treatment Plant Design project
chris30277
 

Viewers also liked (18)

Marcellus Shale Gas Development and Pennsylvania School Districts: What Are t...
Marcellus Shale Gas Development and Pennsylvania School Districts: What Are t...Marcellus Shale Gas Development and Pennsylvania School Districts: What Are t...
Marcellus Shale Gas Development and Pennsylvania School Districts: What Are t...
 
JLCNY Declaration of Landowner Rights
JLCNY Declaration of Landowner RightsJLCNY Declaration of Landowner Rights
JLCNY Declaration of Landowner Rights
 
Research Study: Economic Potential for Shale Formations in Ohio
Research Study: Economic Potential for Shale Formations in OhioResearch Study: Economic Potential for Shale Formations in Ohio
Research Study: Economic Potential for Shale Formations in Ohio
 
Marist College Poll on Hydrofracking in New York State
Marist College Poll on Hydrofracking in New York StateMarist College Poll on Hydrofracking in New York State
Marist College Poll on Hydrofracking in New York State
 
Investing in America: Building an Economy that Lasts
Investing in America: Building an Economy that LastsInvesting in America: Building an Economy that Lasts
Investing in America: Building an Economy that Lasts
 
CBO: The Economic and Budgetary Effects of Producing Oil and Natural Gas from...
CBO: The Economic and Budgetary Effects of Producing Oil and Natural Gas from...CBO: The Economic and Budgetary Effects of Producing Oil and Natural Gas from...
CBO: The Economic and Budgetary Effects of Producing Oil and Natural Gas from...
 
Sanctimonious Letter from Delaware Riverkeeper & Others to PA DEP
Sanctimonious Letter from Delaware Riverkeeper & Others to PA DEPSanctimonious Letter from Delaware Riverkeeper & Others to PA DEP
Sanctimonious Letter from Delaware Riverkeeper & Others to PA DEP
 
PennFuture Lawsuit Against Ultra Resources Alleging Air Pollution
PennFuture Lawsuit Against Ultra Resources Alleging Air PollutionPennFuture Lawsuit Against Ultra Resources Alleging Air Pollution
PennFuture Lawsuit Against Ultra Resources Alleging Air Pollution
 
Penn State Cooperative Extension Marcellus Education Fact Sheet
Penn State Cooperative Extension Marcellus Education Fact SheetPenn State Cooperative Extension Marcellus Education Fact Sheet
Penn State Cooperative Extension Marcellus Education Fact Sheet
 
Beck Energy and Exxon Mobil Bill of Sale #2 - Monroe County, OH
Beck Energy and Exxon Mobil Bill of Sale #2 - Monroe County, OHBeck Energy and Exxon Mobil Bill of Sale #2 - Monroe County, OH
Beck Energy and Exxon Mobil Bill of Sale #2 - Monroe County, OH
 
Middlefield, NY Court Decision on Shale Gas Drilling Ban
Middlefield, NY Court Decision on Shale Gas Drilling BanMiddlefield, NY Court Decision on Shale Gas Drilling Ban
Middlefield, NY Court Decision on Shale Gas Drilling Ban
 
Beck Energy and Exxon Mobil Bill of Sale - Monroe County, OH
Beck Energy and Exxon Mobil Bill of Sale - Monroe County, OHBeck Energy and Exxon Mobil Bill of Sale - Monroe County, OH
Beck Energy and Exxon Mobil Bill of Sale - Monroe County, OH
 
Health Care Providers Letter to Gov. Andrew Cuomo Against Fracking
Health Care Providers Letter to Gov. Andrew Cuomo Against FrackingHealth Care Providers Letter to Gov. Andrew Cuomo Against Fracking
Health Care Providers Letter to Gov. Andrew Cuomo Against Fracking
 
20120118102309.2012 01-16 cmea presentation jatiluhur
20120118102309.2012 01-16 cmea presentation jatiluhur20120118102309.2012 01-16 cmea presentation jatiluhur
20120118102309.2012 01-16 cmea presentation jatiluhur
 
The Economic Impact of the Value Chain of a Marcellus Shale Well
The Economic Impact of the Value Chain of a Marcellus Shale WellThe Economic Impact of the Value Chain of a Marcellus Shale Well
The Economic Impact of the Value Chain of a Marcellus Shale Well
 
Draft Discussion Paper: Transportation Impacts of Potential Marcellus Shale G...
Draft Discussion Paper: Transportation Impacts of Potential Marcellus Shale G...Draft Discussion Paper: Transportation Impacts of Potential Marcellus Shale G...
Draft Discussion Paper: Transportation Impacts of Potential Marcellus Shale G...
 
Budgeting and Implementation Plan
Budgeting and Implementation PlanBudgeting and Implementation Plan
Budgeting and Implementation Plan
 
Water Treatment Plant Design project
Water Treatment Plant Design projectWater Treatment Plant Design project
Water Treatment Plant Design project
 

Similar to Spectra Energy Pipeline Proposal for Maine Public Utilities Commission

Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...
Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...
Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...
Marcellus Drilling News
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Resurgent India
 
Ohio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to Gulf
Ohio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to GulfOhio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to Gulf
Ohio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to Gulf
Marcellus Drilling News
 
FERC Ruling on Ohio-Louisiana Access Project
FERC Ruling on Ohio-Louisiana Access ProjectFERC Ruling on Ohio-Louisiana Access Project
FERC Ruling on Ohio-Louisiana Access Project
Marcellus Drilling News
 
64 Mufford Project Status - Dec 15, 2008
64 Mufford Project Status - Dec 15, 200864 Mufford Project Status - Dec 15, 2008
64 Mufford Project Status - Dec 15, 2008
jgabateman
 
HAWAII - LNG - Governor David Ige Early and Consistent
HAWAII - LNG - Governor David Ige Early and Consistent     HAWAII - LNG - Governor David Ige Early and Consistent
HAWAII - LNG - Governor David Ige Early and Consistent
Clifton M. Hasegawa & Associates, LLC
 
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion ProjectFERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
Marcellus Drilling News
 
Pre SOQ Workshop
Pre SOQ WorkshopPre SOQ Workshop
Pre SOQ Workshopmsialaska
 
FERC Approval for ESNG's White Oak Mainline Expansion Project
FERC Approval for ESNG's White Oak Mainline Expansion ProjectFERC Approval for ESNG's White Oak Mainline Expansion Project
FERC Approval for ESNG's White Oak Mainline Expansion Project
Marcellus Drilling News
 
FERC Docket No. CP15-89-000 - Approving Garden State Expansion Project
FERC Docket No. CP15-89-000 - Approving Garden State Expansion ProjectFERC Docket No. CP15-89-000 - Approving Garden State Expansion Project
FERC Docket No. CP15-89-000 - Approving Garden State Expansion Project
Marcellus Drilling News
 
GE Report: The Age of Gas & The Power of Networks
GE Report: The Age of Gas & The Power of NetworksGE Report: The Age of Gas & The Power of Networks
GE Report: The Age of Gas & The Power of Networks
Marcellus Drilling News
 
Project SEANERGY Foundation Brief
Project SEANERGY Foundation BriefProject SEANERGY Foundation Brief
Project SEANERGY Foundation Brief
Project Seanergy Foundation
 
scalinguptofacemidstreamchallengesoctober2016_final (1)
scalinguptofacemidstreamchallengesoctober2016_final (1)scalinguptofacemidstreamchallengesoctober2016_final (1)
scalinguptofacemidstreamchallengesoctober2016_final (1)Eric Kuhle
 
Show and Tell - Zero Emission Transport.pdf
Show and Tell - Zero Emission Transport.pdfShow and Tell - Zero Emission Transport.pdf
Show and Tell - Zero Emission Transport.pdf
SIFOfgem
 
20090923 Lsb Multiple Topics
20090923 Lsb Multiple Topics20090923 Lsb Multiple Topics
20090923 Lsb Multiple Topics
aectnet
 
THE CHALLENGES AND OPPORTUNITIES FOR LOCAL AREA ENERGY SYSTEMS IN THE UK ENER...
THE CHALLENGES AND OPPORTUNITIES FOR LOCAL AREA ENERGY SYSTEMS IN THE UK ENER...THE CHALLENGES AND OPPORTUNITIES FOR LOCAL AREA ENERGY SYSTEMS IN THE UK ENER...
THE CHALLENGES AND OPPORTUNITIES FOR LOCAL AREA ENERGY SYSTEMS IN THE UK ENER...
Peter Jones
 
ILFI presentation on energy sector by ILFI National Council on Energy
ILFI presentation on energy sector by ILFI National Council on EnergyILFI presentation on energy sector by ILFI National Council on Energy
ILFI presentation on energy sector by ILFI National Council on EnergyILFIindia
 
14
1414
FERC Approval for ESNG's System Reliability Project
FERC Approval for ESNG's System Reliability ProjectFERC Approval for ESNG's System Reliability Project
FERC Approval for ESNG's System Reliability Project
Marcellus Drilling News
 

Similar to Spectra Energy Pipeline Proposal for Maine Public Utilities Commission (20)

Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...
Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...
Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
 
Ohio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to Gulf
Ohio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to GulfOhio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to Gulf
Ohio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to Gulf
 
FERC Ruling on Ohio-Louisiana Access Project
FERC Ruling on Ohio-Louisiana Access ProjectFERC Ruling on Ohio-Louisiana Access Project
FERC Ruling on Ohio-Louisiana Access Project
 
64 Mufford Project Status - Dec 15, 2008
64 Mufford Project Status - Dec 15, 200864 Mufford Project Status - Dec 15, 2008
64 Mufford Project Status - Dec 15, 2008
 
HAWAII - LNG - Governor David Ige Early and Consistent
HAWAII - LNG - Governor David Ige Early and Consistent     HAWAII - LNG - Governor David Ige Early and Consistent
HAWAII - LNG - Governor David Ige Early and Consistent
 
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion ProjectFERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
 
Pre SOQ Workshop
Pre SOQ WorkshopPre SOQ Workshop
Pre SOQ Workshop
 
FERC Approval for ESNG's White Oak Mainline Expansion Project
FERC Approval for ESNG's White Oak Mainline Expansion ProjectFERC Approval for ESNG's White Oak Mainline Expansion Project
FERC Approval for ESNG's White Oak Mainline Expansion Project
 
FERC Docket No. CP15-89-000 - Approving Garden State Expansion Project
FERC Docket No. CP15-89-000 - Approving Garden State Expansion ProjectFERC Docket No. CP15-89-000 - Approving Garden State Expansion Project
FERC Docket No. CP15-89-000 - Approving Garden State Expansion Project
 
GE Report: The Age of Gas & The Power of Networks
GE Report: The Age of Gas & The Power of NetworksGE Report: The Age of Gas & The Power of Networks
GE Report: The Age of Gas & The Power of Networks
 
Project SEANERGY Foundation Brief
Project SEANERGY Foundation BriefProject SEANERGY Foundation Brief
Project SEANERGY Foundation Brief
 
scalinguptofacemidstreamchallengesoctober2016_final (1)
scalinguptofacemidstreamchallengesoctober2016_final (1)scalinguptofacemidstreamchallengesoctober2016_final (1)
scalinguptofacemidstreamchallengesoctober2016_final (1)
 
Draft EIS - Kemper County IGCC Project
Draft EIS - Kemper County IGCC ProjectDraft EIS - Kemper County IGCC Project
Draft EIS - Kemper County IGCC Project
 
Show and Tell - Zero Emission Transport.pdf
Show and Tell - Zero Emission Transport.pdfShow and Tell - Zero Emission Transport.pdf
Show and Tell - Zero Emission Transport.pdf
 
20090923 Lsb Multiple Topics
20090923 Lsb Multiple Topics20090923 Lsb Multiple Topics
20090923 Lsb Multiple Topics
 
THE CHALLENGES AND OPPORTUNITIES FOR LOCAL AREA ENERGY SYSTEMS IN THE UK ENER...
THE CHALLENGES AND OPPORTUNITIES FOR LOCAL AREA ENERGY SYSTEMS IN THE UK ENER...THE CHALLENGES AND OPPORTUNITIES FOR LOCAL AREA ENERGY SYSTEMS IN THE UK ENER...
THE CHALLENGES AND OPPORTUNITIES FOR LOCAL AREA ENERGY SYSTEMS IN THE UK ENER...
 
ILFI presentation on energy sector by ILFI National Council on Energy
ILFI presentation on energy sector by ILFI National Council on EnergyILFI presentation on energy sector by ILFI National Council on Energy
ILFI presentation on energy sector by ILFI National Council on Energy
 
14
1414
14
 
FERC Approval for ESNG's System Reliability Project
FERC Approval for ESNG's System Reliability ProjectFERC Approval for ESNG's System Reliability Project
FERC Approval for ESNG's System Reliability Project
 

More from Marcellus Drilling News

Five facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strongFive facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strong
Marcellus Drilling News
 
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Marcellus Drilling News
 
Access Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 UpdateAccess Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 Update
Marcellus Drilling News
 
Rover Pipeline Letter to FERC Requesting Final Certificate
Rover Pipeline Letter to FERC Requesting Final CertificateRover Pipeline Letter to FERC Requesting Final Certificate
Rover Pipeline Letter to FERC Requesting Final Certificate
Marcellus Drilling News
 
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA CountriesDOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
Marcellus Drilling News
 
LSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. ManufacturingLSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. Manufacturing
Marcellus Drilling News
 
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Marcellus Drilling News
 
Report: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental ExternalitiesReport: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental Externalities
Marcellus Drilling News
 
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
Marcellus Drilling News
 
U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015
Marcellus Drilling News
 
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids PlantsVelocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
Marcellus Drilling News
 
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
Marcellus Drilling News
 
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
Marcellus Drilling News
 
PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas Operations
Marcellus Drilling News
 
US EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy OutlookUS EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy Outlook
Marcellus Drilling News
 
Northeast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical GuideNortheast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical Guide
Marcellus Drilling News
 
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee AuditPA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
Marcellus Drilling News
 
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Marcellus Drilling News
 
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final ReportClyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
Marcellus Drilling News
 
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion ProjectFERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
Marcellus Drilling News
 

More from Marcellus Drilling News (20)

Five facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strongFive facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strong
 
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
 
Access Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 UpdateAccess Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 Update
 
Rover Pipeline Letter to FERC Requesting Final Certificate
Rover Pipeline Letter to FERC Requesting Final CertificateRover Pipeline Letter to FERC Requesting Final Certificate
Rover Pipeline Letter to FERC Requesting Final Certificate
 
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA CountriesDOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
 
LSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. ManufacturingLSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. Manufacturing
 
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
 
Report: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental ExternalitiesReport: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental Externalities
 
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
 
U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015
 
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids PlantsVelocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
 
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
 
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
 
PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas Operations
 
US EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy OutlookUS EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy Outlook
 
Northeast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical GuideNortheast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical Guide
 
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee AuditPA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
 
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
 
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final ReportClyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
 
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion ProjectFERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
FERC Order Denying Stay of Kinder Morgan's Broad Run Expansion Project
 

Recently uploaded

03062024_First India Newspaper Jaipur.pdf
03062024_First India Newspaper Jaipur.pdf03062024_First India Newspaper Jaipur.pdf
03062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
2024 is the point of certainty. Forecast of UIF experts
2024 is the point of certainty. Forecast of UIF experts2024 is the point of certainty. Forecast of UIF experts
2024 is the point of certainty. Forecast of UIF experts
olaola5673
 
Sharjeel-Imam-Judgement-CRLA-215-2024_29-05-2024.pdf
Sharjeel-Imam-Judgement-CRLA-215-2024_29-05-2024.pdfSharjeel-Imam-Judgement-CRLA-215-2024_29-05-2024.pdf
Sharjeel-Imam-Judgement-CRLA-215-2024_29-05-2024.pdf
bhavenpr
 
Codes n Conventionss copy (1).paaaaaaptx
Codes n Conventionss copy (1).paaaaaaptxCodes n Conventionss copy (1).paaaaaaptx
Codes n Conventionss copy (1).paaaaaaptx
ZackSpencer3
 
Do Linguistics Still Matter in the Age of Large Language Models.pptx
Do Linguistics Still Matter in the Age of Large Language Models.pptxDo Linguistics Still Matter in the Age of Large Language Models.pptx
Do Linguistics Still Matter in the Age of Large Language Models.pptx
Slator- Language Industry Intelligence
 
AI and Covert Influence Operations: Latest Trends
AI and Covert Influence Operations: Latest TrendsAI and Covert Influence Operations: Latest Trends
AI and Covert Influence Operations: Latest Trends
CI kumparan
 
31052024_First India Newspaper Jaipur.pdf
31052024_First India Newspaper Jaipur.pdf31052024_First India Newspaper Jaipur.pdf
31052024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
01062024_First India Newspaper Jaipur.pdf
01062024_First India Newspaper Jaipur.pdf01062024_First India Newspaper Jaipur.pdf
01062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
Hogan Comes Home: an MIA WWII crewman is returned
Hogan Comes Home: an MIA WWII crewman is returnedHogan Comes Home: an MIA WWII crewman is returned
Hogan Comes Home: an MIA WWII crewman is returned
rbakerj2
 
Resolutions-Key-Interventions-28-May-2024.pdf
Resolutions-Key-Interventions-28-May-2024.pdfResolutions-Key-Interventions-28-May-2024.pdf
Resolutions-Key-Interventions-28-May-2024.pdf
bhavenpr
 
Preview of Court Document for Iseyin community
Preview of Court Document for Iseyin communityPreview of Court Document for Iseyin community
Preview of Court Document for Iseyin community
contact193699
 
role of women and girls in various terror groups
role of women and girls in various terror groupsrole of women and girls in various terror groups
role of women and girls in various terror groups
sadiakorobi2
 
Draft-1-Resolutions-Key-Interventions-.pdf
Draft-1-Resolutions-Key-Interventions-.pdfDraft-1-Resolutions-Key-Interventions-.pdf
Draft-1-Resolutions-Key-Interventions-.pdf
bhavenpr
 

Recently uploaded (13)

03062024_First India Newspaper Jaipur.pdf
03062024_First India Newspaper Jaipur.pdf03062024_First India Newspaper Jaipur.pdf
03062024_First India Newspaper Jaipur.pdf
 
2024 is the point of certainty. Forecast of UIF experts
2024 is the point of certainty. Forecast of UIF experts2024 is the point of certainty. Forecast of UIF experts
2024 is the point of certainty. Forecast of UIF experts
 
Sharjeel-Imam-Judgement-CRLA-215-2024_29-05-2024.pdf
Sharjeel-Imam-Judgement-CRLA-215-2024_29-05-2024.pdfSharjeel-Imam-Judgement-CRLA-215-2024_29-05-2024.pdf
Sharjeel-Imam-Judgement-CRLA-215-2024_29-05-2024.pdf
 
Codes n Conventionss copy (1).paaaaaaptx
Codes n Conventionss copy (1).paaaaaaptxCodes n Conventionss copy (1).paaaaaaptx
Codes n Conventionss copy (1).paaaaaaptx
 
Do Linguistics Still Matter in the Age of Large Language Models.pptx
Do Linguistics Still Matter in the Age of Large Language Models.pptxDo Linguistics Still Matter in the Age of Large Language Models.pptx
Do Linguistics Still Matter in the Age of Large Language Models.pptx
 
AI and Covert Influence Operations: Latest Trends
AI and Covert Influence Operations: Latest TrendsAI and Covert Influence Operations: Latest Trends
AI and Covert Influence Operations: Latest Trends
 
31052024_First India Newspaper Jaipur.pdf
31052024_First India Newspaper Jaipur.pdf31052024_First India Newspaper Jaipur.pdf
31052024_First India Newspaper Jaipur.pdf
 
01062024_First India Newspaper Jaipur.pdf
01062024_First India Newspaper Jaipur.pdf01062024_First India Newspaper Jaipur.pdf
01062024_First India Newspaper Jaipur.pdf
 
Hogan Comes Home: an MIA WWII crewman is returned
Hogan Comes Home: an MIA WWII crewman is returnedHogan Comes Home: an MIA WWII crewman is returned
Hogan Comes Home: an MIA WWII crewman is returned
 
Resolutions-Key-Interventions-28-May-2024.pdf
Resolutions-Key-Interventions-28-May-2024.pdfResolutions-Key-Interventions-28-May-2024.pdf
Resolutions-Key-Interventions-28-May-2024.pdf
 
Preview of Court Document for Iseyin community
Preview of Court Document for Iseyin communityPreview of Court Document for Iseyin community
Preview of Court Document for Iseyin community
 
role of women and girls in various terror groups
role of women and girls in various terror groupsrole of women and girls in various terror groups
role of women and girls in various terror groups
 
Draft-1-Resolutions-Key-Interventions-.pdf
Draft-1-Resolutions-Key-Interventions-.pdfDraft-1-Resolutions-Key-Interventions-.pdf
Draft-1-Resolutions-Key-Interventions-.pdf
 

Spectra Energy Pipeline Proposal for Maine Public Utilities Commission

  • 1. This document and any and all attachments hereto: (i) are intended for discussion purposes only; (ii) do not obligate the parties to negotiate or enter into any possible transaction; (iii) do not obligate either party to proceed with or continue any such negotiations or transaction. 9/29/2014 Proposal Submitted to the Maine Public Utilities Commission
  • 2. Table of Contents PUBLIC 2 Page Executive Summary 3 Spectra Energy’s Proposal 7 Appendix Spectra Energy Overview 17 Business Segment Overview 19 The Way Spectra Energy Works 20 Regulatory and Permitting 21 Environmental Stewardship 25 Stakeholder Outreach 28
  • 3. Executive Summary At the outset of Phase One of Docket No. 2014‐00071, the Maine Public Utilities Commission (Commission or PUC) invited the submission of proposals for the State of Maine to consider regarding Energy Cost Reduction Contracts (ECRC). Spectra Energy Partners, LP (Spectra Energy) has a long‐standing presence in New England as major transporters of natural gas through Algonquin Gas Transmission, LLC (Algonquin) and Maritimes & Northeast Pipeline, L.L.C. (Maritimes), and welcomes the opportunity to work with the PUC to develop the infrastructure required now, and in the future, to help alleviate regional energy price spikes during the coldest days of winter. We believe our proposal maximizes the opportunity to decrease capacity costs and enhance electrical and natural gas reliability throughout the region. While we remain supportive of a full, transparent Request for Proposal (RFP) in Phase Two of the instant proceeding, we are mindful of the Commission’s need to have all information available to it as it deliberates even within Phase One and as such are providing these proposals for Atlantic Bridge and Access Northeast as the Commission considers next steps. Our proposals closely reflect the project descriptions we introduced in Phase One. In the case of Atlantic Bridge in particular, the deadline for filing with FERC to ensure a November 2017 in‐service date is rapidly approaching. This fact, coupled with recent delays in the current ECRC case, necessitated that we submit our proposal at this time. In short, if the Commission decides to proceed with an ECRC, our hope is to expedite the process by which the Commission would be able to move forward. This proposal is intended to provide the Commission with flexible alternatives for exercising its ECRC authority, depending in part on the results of Phase One of this proceeding. If the Commission determines that Maine should move forward with an ECRC at this time, our proposal enables the Commission to enter into an ECRC of up to 200MMcf/d or $75 million/year equivalent as part of the Atlantic Bridge project, maximizing the benefits available to the state from an incremental expansion of the existing Algonquin pipeline as early as 2017. Our proposal also allows the Commission to enter into an ECRC for a later in‐service date through participation in the Access Northeast project. Like Atlantic Bridge, the Access Northeast project offers the benefits of deliverability to gas‐fired generators in the region, and it also offers the benefits of collaboration with Northeast Utilities, one of the region’s largest utilities. The Access Northeast project demonstrates the importance of providing services that directly meet the needs of gas‐fired generators. This innovative offering, combined with the resources of the partners, enhance the certainty that this project will move forward. Drawing upon Spectra Energy’s successful history of developing, constructing and operating natural gas pipelines, the proposed projects contained within this proposal address the Commission’s objective to reduce energy prices and enhance electrical and natural gas reliability in the State. Bidders Information Spectra Energy owns and operates the 1127‐mile, Federal Energy Regulatory Commission (FERC) regulated Algonquin Pipeline and the 346‐mile, FERC‐regulated Maritimes Pipeline. Algonquin interconnects with the Spectra Energy‐owned Texas Eastern Transmission system, the Tennessee Gas Pipeline system, the Millennium Pipeline, and the Iroquois Pipeline system, all of which link the Marcellus Shale and Appalachian Basin natural gas supplies to the Northeast markets. Through Algonquin’s connection to Maritimes, markets in PUBLIC 3
  • 4. Massachusetts, New Hampshire and Maine will also have the opportunity to connect to these diverse and emerging natural gas supplies. To discuss any questions or to seek additional information regarding this proposal, please contact: Greg Crisp General Manger, Business Development 713‐627‐4611 phone Spectra Energy Transmission 713‐627‐4724 fax 5400 Westheimer Court gncrisp@spectraenergy.com Houston, TX 77056 PUBLIC 4
  • 5. Key Features Value Added Benefits of Service from Algonquin and Maritimes:  Provides an opportunity to bring more low‐cost, domestically sourced natural gas to delivery points in Maine that serve gas‐fired electric generators, industrial customers, and other energy consumers in Maine or the region through scalable expansions of the existing Algonquin and Maritimes pipeline systems and offering receipt and delivery points on those systems, including direct delivery points to 60% of the gas‐fired generation fleet in the region o This is important because the best way for Maine to moderate electric prices in the region is to ensure that gas can be directly delivered to the greatest number of gas‐fired generators in the region on peak days, and our proposal is consistent with this approach.  Offers flexible terms with multiple protections for Maine’s potential investment in pipeline capacity o Flexible commitments that can be altered, rescinded, or changed as market conditions evolve o Maximum ability to assign capacity to other entities o Fully negotiable costs that are not incurred until projects are in‐service o Explicit contractual provisions to protect Maine’s ratepayers should a regional solution emerge prior to the FERC filing of the projects  Includes mechanisms to promote maximum return on investment by leveraging private commitments and shifting an ECRC investment to the project or projects likely to yield the best results  Provides optimal timeliness to market. Our solution allows natural gas capacity to reach gas‐fired generators in the region sooner than uncertain greenfield proposals, which is important given that every year of delay costs Maine consumers.  Provides direct deliveries of domestically sourced natural gas to Maine in the fastest timeframe  Provides innovative use of existing resources in the region by leveraging storage to meet peak day needs  Atlantic Bridge and Access Northeast maximize the use of existing rights‐of‐way and do not substantially rely on greenfield construction, which can be susceptible to substantial delays due to public opposition and mitigation of environmental impacts. Thus, Maine can have greater confidence that our projects will come online within the projects’ time estimates.  Offers better coordination between electric sector and natural gas sector through collaboration between Northeast Utilities and Spectra Energy  Does not hinge on achieving a certain level of subscription from third parties outside of Maine’s control PUBLIC 5
  • 6.  Includes extending the upstream Algonquin piping as needed, the replacement of existing pipe with larger diameter pipe, pipeline looping, miscellaneous meter station upgrades, the addition of new compression as needed, and the potential for bidirectional flow on the Maritimes pipeline  Provides assurances that come with FERC‐jurisdictional oversight regarding the sensitivities of landowners, environmental resources, cultural resources, and other stakeholders who might be impacted during construction, as well as continued oversight of the transportation service on Algonquin and Maritimes throughout the contract term  Provides additional diversity of supply as traditional supply sources decline  Provides reliable firm transportation service directly to end users  Provides access to premium natural gas commodity markets resulting in unmatched optionality  Projects are scalable to meet the specific capacity requirements of the market and the State of Maine  Directly impacts reliability leading to more balanced supply and demand  Spectra Energy has a proven track record for constructing and operating pipelines in New England and throughout North America Together, Atlantic Bridge and Access Northeast will help remove bottlenecks in New England’s pipeline infrastructure and reduce electric and natural gas price volatility in New England. PUBLIC 6
  • 7. Proposal Atlantic Bridge Spectra Energy is proposing to expand the existing Algonquin and Maritimes pipelines to meet the needs of consumers, serving growing markets in New England and Maine. On the Algonquin system, the expansion will consist of the replacement of smaller diameter pipe with larger diameter pipe, pipeline looping at some points along the existing system, miscellaneous meter station upgrades, the addition of a new compressor station in Weymouth, Massachusetts, and additional compression at existing stations to facilitate the flow of gas north into Maritimes. On the Maritimes system, modifications could include bidirectional flow modifications depending on the ultimate requested flow into the Maritimes system. The capacity being built through the Algonquin Incremental Market expansion (AIM) (in‐service in 2016) and Atlantic Bridge projects could provide 600 MMcf/d of new capacity into ISO‐NE territory, resulting in a 60% increase through current constraint points on Algonquin by 2017. Both projects will enchance electric and natural gas reliability throughout New England and will bring postitive economic benefits directly to Maine energy consumers. PUBLIC 7
  • 8. Market response to Atlantic Bridge has been strong, and the project will go forward with or without an ECRC from the Commission. The project will be supported by private entities, including private entities in the State of Maine requesting specific Maine deliveries. Algonquin and Maritimes are in the final stages of negotiations for Atlantic Bridge, and the project is anticipated to be buildable at 200‐300 MMcf/d for a 2017 in‐service date. Today, the final capacity for Atlantic Bridge is not known for certain. This final capacity is dependent upon specific receipt and delivery points which will ultimately determine the facilites required and dictate the amount of capacity that may be constructed for a 2017 in‐service date. Algonquin and Maritimes intend to pre‐file Atlantic Bridge with FERC in early November 2014. At that time, Algonquin and Maritimes can provide a more definitive description of how much capacity is available, if any, and how much of the capacity will be directly deliverable to Maine. Prior to the filing or after the filing, Maine can enter into an ECRC to ensure that Atlantic Bridge goes forward at the maximum buildable capacity and maximum deliverability to Maine for 2017, and ensure that no time is wasted in securing benefits for Maine as soon as possible.  Capacity can be for up to 200 MMcf/d or $75 million/year, depending on the amount of unsubscribed capacity, if any, available at the time Maine is able to enter into a definitive agreement  In‐service date of November 1, 2017  Maine can designate any of the following receipt points: o “Head of G system” – Algonquin market area receipt o Brookfield interconnect with Iroquois – equivalent to TGP’s Northeast Energy Direct receipt at Wright, NY o Ramapo interconnect with Millennium – direct access to Marcellus producers o Interconnects upstream of Ramapo with recently expanded interstate pipelines such as Texas Eastern, Columbia, Transco, and Tennessee Gas Pipeline  Maine can designate any of the following delivery points: o Any Algonquin delivery point Maine determines is in the best interest of Maine consumers, including the Algonquin interconnect with Maritimes at Beverly, MA o Any Maritimes delivery point in the State of Maine o The Commission may also express any interest in new interconnects to connect Maine customers  Rate to be negotiated in a confidential meeting  All capacity commitments to the maximum degree allowed under current regulations can be assigned to another party or parties. PUBLIC 8
  • 9.  No costs will be incurred until the project is in service  To the extent that private entities or other shippers subscribe to the maximum build for the project in 2017 outside of an ECRC, Maine will be able to reduce or terminate its participation in Atlantic Bridge  Regardless of any conditions above, Maine will have a unilateral right, subject to negotiable conditions precedent, to terminate its participation in the project prior to July 1, 2015, at no risk to Maine  Additionally, if Algonquin and Maritimes move forward with a regional solution, we will discuss termination of Maine’s participation in Atlantic Bridge and Access Northest, the Algonquin and Maritimes regional solution Access Northeast On June 27, 2014, Spectra Energy provided a plan to the New England States Committee on Electricity (NESCOE) to expand existing natural gas pipeline capacity and meet critical demand for reliable electric power generation. This was in response to the New England governors’ initiative on new energy infrastructure in anticipation of a Request for Proposal (“RFP”). Unfortunately, the NESCOE RFP effort has been delayed; however, Spectra Energy and Northeast Utilities are moving forward with the Access Northeast project to help maintain the momentum of the process and to provide a regional solution. We continue to believe the NESCOE process is good for New England and Maine, and we applaud the leadership and commitment demonstrated by the States to achieve positive results for New England energy customers. Consistent with information provided by Algonquin and Maritimes in the ECRC proceeding, the Commission will recognize Access Northeast as the project regularly referred to as the “Reliability Project.” And we have made progress in further developing the project. We have a leading New England utility as a project partner, and together we are actively pursuing contractual commitments from shippers. Access Northeast is an alternative to a large greenfield proposal and is better focused on addressing electric reliability for New England. Access Northeast will provide innovative alternatives and solutions long sought by electric generators to improve reliability and bring down energy costs in the region, but without the environmental impacts of a greenfield project. The expansion project will enhance the Algonquin and Maritimes pipeline systems, using existing routes to minimize impacts on communities, landowners, and the environment. The project will be scalable to meet growing needs by expanding access to clean, abundant, and affordable natural gas, and it will be capable of reliably delivering in excess of one billion cubic feet of natural gas per day to serve the region's most efficient power plants and meet increasing demand from heating customers. Access Northeast will combine targeted pipeline capacity additions with the smart use of regional storage facilities to more effectively match the economic and environmental needs of the region. PUBLIC 9
  • 10. Spectra Energy and Northeast Utilities’ collaborative proposal includes:  Scalable expansion of existing pipeline infrastructure, which is directly attached to approximately 60% of ISO‐NE’s natural gas generation capacity  Collaboration with existing regional storage providers to offer firm services to gas‐fired power plants in the region with guaranteed natural gas supplies on peak days, and to enable rapid response to sudden changes in power output that supports renewable generation development  An environmentally responsible approach that will minimize impact by using existing asset footprints  Additional Algonquin and Maritimes delivery points for local distribution companies (LDC) to access diverse, low‐cost natural gas resources where necessary Access Northeast is a direct response to numerous requests from regional stakeholders and governmental agencies in New England for an environmentally responsible, scalable, efficient and effective pipeline project to meet the needs of energy consumers in New England over the next decade to keep energy prices at competitive levels with a low risk of volatility. Spectra Energy’s and Northeast Utilities’ collaborative solution and partnership with regional stakeholders achieves all of these objectives by providing access to low‐cost supply diversity while minimizing community and environmental impacts through the enhancement of existing infrastructure. Access Northeast is scalable for further expansion, and is projected to be in service as early as November 2018. Maine can participate in Access Northeast in one of the following ways, either in addition to Atlantic Bridge, or separately:  Through support and continued pursuit of the NESCOE process  By leveraging its ECRC authorization with other New England States who currently have the ability to direct their regulated utilities to subscribe to capacity  By subscribing to the scalable Access Northeast project on a stand‐alone basis PUBLIC 10
  • 11. Benefits of Atlantic Bridge and Access Northeast Best Fulfills the Requirements of the Energy Cost Reduction Act and Represents True Transformative Capacity: To enter into an ECRC per the Energy Cost Reduction Act, the Commission must have determined in an adjudicatory proceeding that the ECRC is commercially reasonable and in the public interest, and that the contract is reasonably likely to accomplish the following objectives:  To materially enhance natural gas transmission pipeline capacity into the State or into the ISO‐NE region;  that the additional capacity it provides will be economically beneficial to Maine's electric consumers, natural gas consumers, or both;  that the overall costs of the contract are outweighed by its benefits to Maine's electric consumers, natural gas consumers, or both; and  To enhance electrical and natural gas reliability in the State. Atlantic Bridge and Access Northeast exactly meet the foregoing criteria. Commercially reasonable terms. The contractual terms of both projects are commercially reasonable because they reflect FERC‐approved language and accomplish the following goals: (1) maximize deliverability to gas‐fired generators; (2) meet the goal of speed to market; and (3) provide the Commission with contractual “off‐ramps” in the event later events suggest that an ECRC is no longer prudent in any way. Public interest. A key element is whether the Commission determines in Phase One of the ECRC proceeding that moving forward with an ECRC is prudent. If the Commission decides in the affirmative, the Atlantic Bridge and Access Northeast projects will maximize the public interest because these projects: (1) are most likely to reach market sooner than other proposals; (2) are most likely to proceed to completion given the incremental nature of the projects; and (3) offer the greatest benefits of reliability and lower costs because they target gas capacity toward the greatest number of gas‐fired generators in the region. Material enchancement of capacity to Maine or the region. Because both projects involve bringing gas capacity into New England, they meet the “material enchancement of capacity” test. Both projects also offer the additional benefit of delivery directly into Maine. Economic benefits to Maine consumers. Both projects are targeted at bringing natural gas capacity where it is most needed: gas‐fired generators in the region. Ensuring that gas is deliverable to these generators maximizes the likelihood that the greatest number of gas‐fired generators will have firm capacity during the coldest days of winter, which ensures lower electric price volatility and lower overall electric prices. The additional capacity also addresses the needs of natural gas consumers in the State by permitting access to lower cost supply from existing pipeline interconnects. PUBLIC 11
  • 12. Benefits outweigh the costs. The Commission has embarked on a separate process to determine whether the benefits of entering into an ECRC outweigh the costs. If the Commission finds in the affirmative based on the information available at this time, both projects offered by Spectra Energy maximize the benefits to Maine by targeting Maine’s investment where it is most needed: ensuring that the greatest number of gas‐fired generators are able to have firm capacity during the coldest days of winter. Both projects also offer contractual “off ramps” for the Commission in the event later events suggest that moving forward with an ECRC is no longer in Maine’s best interest. Enhance reliability. The current problem of electric price spikes in New England is fundamentally an issue of gas‐fired generators in the region not having sufficient access to gas capacity during the coldest days of winter. This is a reliability problem, and both projects Spectra proposes are aimed at resolving the reliability problem by targeting gas capacity directly at these gas‐fired generators. Moreover, by resolving the reliability challenge these generators face, the ability of these generators to operate during the coldest days of winter is enhanced, which improves the overall reliablity of the region’s electric system. Flexible Conditions Precedent and Variation of Volumes and/or Contractual Off‐ramps for PUC Contracts Gives Multiple Protections for Maine’s Potential Investment: Maine’s energy consumers and the Commission face an extraordinary dilemma. High price spikes in regional natural gas and electricity pricing during the winter have recently undermined Maine’s economic vitality, but there is the possiblity these spikes could be mitigated with sufficient, timely investment in natural gas pipeline facilities. The regional nature of energy pricing means all consumers in the region could benefit from an investment in gas capacity, but regional cooperation to solve the issue has slowed. Nevertheless, the benefits of Maine taking action on its own could be meaningful. At the same time, those benefits could be overwhelmed by actions of other entities in the market. Or, those benefits could be drastically reduced if the regional process restarts after Maine decides to invest on its own. Absent favorable action by other regional players or FERC, an ECRC could saddle Maine ratepayers with extra costs even though the Commission appropriately exercised its authority when signing an agreement. The Commission, therefore, needs assurance that it is investing in the right project at the right price at the right time. But there is no crystal ball. One cannot know for certain when signing a precedent agreement if the capacity being purchased will provide the energy cost reductions anticipated given the variety of factors at work. Nevertheless, standard terms, conditions and obligations of parties to a precedent agreement need not be a constraint. In fact, Spectra Energy is offering the Commission agreements on Atlantic Bridge and Access Northeast that can be evaluated and rescinded prior to project filings with FERC. This unique feature gives the Commission the luxury of reevaluating the cost/benefit ratio of its investment closer to project execution and, therefore, provides more certainty about the likelihood of benefits. In addition, as conditions in the market are evaluated in the future, the Commission could determine there are more impactful projects, rescind its agreement, and redeploy its investment. More specifically, the contractual “off‐ramp” included within these proposals enables the Commission to later determine whether future private or regional investments in pipeline capacity alter the calculus of benefits of an ECRC. If, under these circumstances, the Commission determines within the terms of the “off ramp” that moving forward with an ECRC is no longer warranted on the same terms, the Commission would have room to back out of the contract or make a more limited, strategic investment in PUBLIC 12
  • 13. capacity at a specific location aimed at addressing a particular bottleneck that impacts the ability of one or more gas‐fired generators to have access to gas during the coldest days of winter. Atlantic Bridge: The PUC or its designee can execute a precedent agreement for up to 200 MMcf/d or $75 million/yr equivalent capacity that includes periodic updates on how much capacity is committed to other Maine entities. For each increment of additional Maine‐based capacity, the Commission can elect to scale back its investment as the project is filled out to maximum capacity for a 2017 in‐service date. This allows the PUC optionality to re‐deploy its investment as it sees fit. No firm transportation service agreement is executed until after receipt of the FERC certificate for the project, and no payments under that service agreement are required until the project is placed into service. Access Northeast: An Access Northeast precedent agreement is fully assignable with termination rights for certain circumstances. We are confident that Access Northeast could proceed based on market support irrespective of a Maine ECRC. Therefore, we can provide maximum flexibility for a partial or complete contractual off‐ramp for Maine in the event a regional effort proceeds that Maine believes will make an ECRC unneccessary or uneconomic. In our proposal, protection of Maine’s ratepayers would not be subject to a supplemental regulatory process or capacity release rules, provided the firm service agreement has been executed at the time the PUC would want to exercise this out. Assessing the future impact of an ECRC is is extremely difficult. Depending on the circumstances, the benefits of an ECRC may not actually outweigh the costs. If the Commisssion decides at this stage to proceed with an ECRC but later becomes concerned that any of the benefits may not be realized (e.g. market reforms impact basis differential and reliability, private market actors secure sufficient commitment for other pipeline capacity), the Commission can terminate its precedent agreement within a mutually agreeable timeframe. Promotes Maximum Return on Investment by Leveraging Private Commitments: For Atlantic Bridge, private interest in the project is sufficient at this time for Algonquin and Maritimes to say with confidence that the project will move forward. For Access Northeast, Northeast Utilities’ interest in the project as one of the region’s largest utilities also signals the importance of this project to the needs of electric consumers. By targeting capacity towards the gas‐fired generators who typically set the market price for electric commodity in the region, Access Northeast offers the greatest opportunity to maximize the benefits of additional gas capacity on regional electric prices. Timeliness to Market: The sooner pipeline capacity is added, the sooner Maine will see lower energy costs. Assuming the Commission moves forward to Phase Two, the Commission should select the project with the best chance of providing quick and tangible benefits to Maine energy consumers. This proposal provides those benefits, and does so with the speed‐to‐market the State expects. Atlantic Bridge is proposed to be in service by the winter of 2017‐2018. The project is largely a replacement and modification of existing pipelines that requires work on facilities covering PUBLIC 13
  • 14. relatively few miles, is located on existing rights of way, and is being conducted by a pipeline developer with a history of meeting in‐service dates for projects in congested areas, including Boston, New York, and Philadelphia. Access Northeast is planned for similar construction techniques with a proposed in‐service date in November 2018. Pre‐filing with FERC for Atlantic Bridge is expected in the fourth quarter of 2014. Scalable Expansion of Atlantic Bridge/Access Northeast: The Atlantic Bridge and Access Northeast projects are flexible and easily scalable because the expansions occur primarily within the existing pipeline footprints. These projects can be sized to meet the specific capacity requirements of the Maine market, allowing for customized receipt and delivery points (including multiple receipt and delivery points) to meet individual customers’ needs. Adding right‐sized expansion projects along the system also provides incremental pipeline capacity as it is needed, when it is needed, to satisfy increased customer demand. Atlantic Bridge and Access Northeast are projects that involve the incremental expansion of existing gas infrastructure that is scalable to meet the needs of specific shippers in specific locations. In contrast to a greenfield project that requires a substantial level of commitment by shippers to move forward, the ability of the incremental projects to proceed is less dependent on the actions of others. So, as Maine decides whether to invest in projects that are more likely to happen, it should give serious consideration to incremental projects like Atlantic Bridge and Access Northeast whose size can be adjusted to meet the needs of the shippers, including that of the State of Maine. Domestically Sourced Natural Gas Deliveries to Maine: The Atlantic Bridge project offers the opportunity to allow gas to directly flow into Maine from abundant and lower‐priced domestic sources south of Maine such as the Marcellus region in Pennsylvania. This project offers Maine an opportunity—for the first time—to procure gas supply directly into the State. Maine currently receives limited natural gas supplies from domestic sources. Yet, today in North America, Appalachian Basin natural gas, not Canadian gas, drives prices for the commodity. To bring that lower‐cost, market‐making natural gas to delivery points in Maine requires significant changes to the regional pipeline system. To realize fully the advantages of Appalachian shale gas in Maine requires bringing more robust gas‐on‐gas competition to the State. Atlantic Bridge provides that link from this low‐cost resource to Maine’s energy consumers. At capacity, Atlantic Bridge could transport between 200‐300 MMcf/d to Maine delivery points by expanding Algonquin and changing Maritimes to a bidirectional facility that can move gas from Algonquin receipts to Maine deliveries. Directly Impacts Customers in Maine: Maine would benefit from the addition of new pipeline capacity into the region because it would allow Maine to directly access new, lower priced, abundant natural gas supplies. Maine is in a unique situation where customers in the State are not only plagued by high electricity costs due to infrastructure capacity constraints in New England from the south, but they are also held captive to higher‐cost, often insufficient, natural gas supplies from the north. PUBLIC 14
  • 15. Electric prices in the ISO‐NE region have spiked over the past two years when temperature drops prevented gas‐fired generators from having sufficient gas capacity to run, or required such generators to purchase high‐priced gas on the spot market. To address this problem, it is not enough that gas be physically present in the region; rather, it is essential that the gas molecules actually be able to reach these gas‐fired generators on the coldest days of winter. The Algonquin and Maritimes systems directly serve approximately 60% of the gas‐fired generation in the ISO‐NE region, and access to many of these generators is accomplished via telescoping laterals that can be constrained when gas demand is high. The benefit of the Atlantic Bridge and Access Northeast projects is that they not only ensure that gas capacity is available in the region, but they also ensure that the natural gas can physically reach the gas‐fired generators who need the gas during the coldest days of winter. Moreover, because the regional electric price hinges on the price of the last unit called upon to serve, the more gas‐fired generators with firm access to gas, the lower the likelihood that more expensive units will end up setting the regional price of electricity. In short, if Maine wants to maximize the value of an ECRC, it should focus on projects like Atlantic Bridge and Access Northeast that maximize the delivery of gas to the greatest number of gas‐fired generators. An additional benefit for Maine’s manufacturers could also be achieved by the Commission by procuring Atlantic Bridge capacity. During peak price days in recent winters, some of Maine’s manufacturers had to slow or stop production activities due to high energy costs. These work stoppages impacted the bottom lines of the affected companies and their employees. Yet, some of these manufacturers have significant electric generation capability on site and may be able to meet some or all of their electricity needs. But, they are likely not able to cost‐efficiently produce electricity for their own needs on these peak days because of pipeline capacity constraints. Given the limitations, the Commission could consider procuring gas capacity through Atlantic Bridge and releasing it to the market periodically as a hedge. Then, on the coldest days, Maine could release the capacity at below market prices to willing manufactures with generation capability. This action could, in some circumstances, be of more value to Maine’s manufacturers than the impact of the capacity on the clearing price of electricity in the region. Innovative Use of Existing Resources (Storage) in the Region: Access Northeast will support renewable energy development by enabling rapid response to sudden changes in power output with regional storage facilities and quick‐start natural gas‐fueled power generation. Access Northeast will provide new Electric Reliability Service (ERS) for firm transportation of natural gas and natural gas supply supported by regional storage facilities for any party (Customer). This proposed service provides greater fuel certainty for generators and performance flexibility through reserved No Notice Transportation with an hourly supply option. Illustrative tariffs can be found at spectraenergy.com/NewEngland. While certain measures could meet New England’s basic needs, Access Northeast will combine well‐tuned pipeline capacity additions with the smart use of regional storage facilities to more effectively match the economic and environmental needs of the region. Innovative and Novel Approach: Rate Schedule ERS is a reserved No‐notice transportation service that incorporates non‐rateable delivery rights for primary firm deliveries. The firm capacity is reserved for Shippers full MDTQ on a 24/7 basis. The No‐notice flexibility is supported through regional storage facilities and allows a shipper to commence delivery up to two hours without commensurate supply in advance of flow. This combination of firm reserved pipeline capacity PUBLIC 15
  • 16. and non‐rateable deliveries allows for generators and other parties that contract for the service to ensure that pipeline capacity will be available when they call on it, and the non‐rateable service provides the flexibility that more aligns with gas‐fired generator burn profiles. The MSOA (Multi‐shipper Option Agreement) allows multiple parties to contract under one administrator to act on their behalf. The electric distribution companies (EDC) would be the Principals under an MSOA, and they would have an Administrator that would manage the collective capacity ensuring that the gas‐fired plants have priority access to the generation related pipeline capacity/services to reliably serve their plants. The Administrator would also optimize any unutilized or underutilized capacity. Transportation Service Will Be FERC‐Jurisdictional: All facilities and services will fall under the regulatory oversight of the FERC. A FERC‐regulated facility provides transparency and oversight to ensure that: (1) due diligence is followed on all aspects of the construction of facilities, especially those involving environmental and cultural resources; (2) all issues related to regulatory, environmental, permitting, landowners and other stakeholders are addressed; (3) all facilities are appropriate for the service; and (4) continued oversight is maintained throughout the term of the contract. In short, FERC review, approval and oversight helps to minimize risk for all involved parties, particularly with respect to involvement with the project by local and regional environmental, landowner, and public official stakeholders. Provides Direct Access to New Supply Regions: Historically, the Northeast region has relied on three main supply areas: Gulf Coast U.S., Canada and LNG. During the last decade, the supply sources expanded to include Rockies/Midcontinent gas and eastern Canada production. The biggest change has occurred in just the last six years with the rapid development of the Marcellus Shale gas basin in Appalachia. Production from the Marcellus has transformed the supply dynamic into the Northeast. Marcellus production has grown from 2 Bcf/d in 2008 to over 16 Bcf/d in 2014. As the new local production has emerged, there has been a decline in the Northeast region’s imports from other U.S. supply basins, Canada, and LNG. This extraordinary upswing in Northeast production is resulting in new delivery points and new pipeline infrastructure to bring this shale gas to market, and with it lower prices for consumers. Canadian and LNG supplies have long played a significant role in gas supply to the Northeast U.S. Canada remains pivotal to the region, but with new Marcellus supplies so near, the level of imports has begun to decline, falling by 50% from 2009 to 2012. Natural gas production in the Marcellus and Utica regions is currently at approximately 16 Bcf/d and production is continuing to grow. Algonquin is connected to this supply through approximately 3 Bcf/d of existing pipeline interconnections on pipelines with capacity in excess of 10 Bcf/d providing multiple receipt point options including, but not limited to upstream pipelines: Texas Eastern, Transco, Columbia, Tennessee Gas Pipeline, Millennium and Iroquois. With Atlantic Bridge and/or Access Northeast, these multiple receipt point options provide a direct connection to a new, lower‐cost, stable source of natural gas supply for customers in New England and, more specifically, customers in Maine who have traditionally been tied to declining, often sporadic and expensive natural gas delivered from the north. PUBLIC 16
  • 17. Provides Firm Pipeline Transportation 24/7/365: The regional need for access to new natural gas supplies and new firm pipeline transportation is evident. The Atlantic Bridge and/or Access Northeast projects provide economic solutions to the infrastructure gap between Marcellus supply and the Maine markets, offering year‐round firm transportation capacity. This reliable and consistent service means customers will enjoy the benefits of accessing lower cost natural gas supplies with the confidence that it will be delivered by Algonquin and Maritimes on a firm basis. Provides Access to Premium Markets: Algonquin’s footprint traverses what is considered the most premium markets in North America. Serving local distribution companies, industrial, and power generation customers, Algonquin currently delivers 2.6 Bcf/d of natural gas to delivery points across New Jersey, New York, Connecticut and Massachusetts. As part of this customer base, Algonquin has approximately 1.4 Bcf/d of gas‐fired generation customers directly connected to the system. Together with approximately 375,000 Dth/d of peak power generation demand on Maritimes, this represents approximately 60% of New England’s power generation demand directly connected to the two Spectra Energy pipelines. In short, this makes Algonquin and Maritimes a critical fuel delivery system for New England power producers. PUBLIC 17
  • 18. Historically, power generators operating in the New England market have relied predominantly on unutilized capacity to deliver the natural gas required to power their plants. This capacity, largely held by LDCs, has over the last number of winters become increasingly unavailable due to increased demand. This has resulted in extreme electricity price volatility in the region. Spectra Energy is aligned with the Commission in the belief that additional natural gas pipeline infrastructure, both in the short term and the long term, is essential to strengthening electric reliability, which in turn will result in a reduction of prices and a reduction of daily price volatility. PUBLIC 18
  • 19. This presents a unique opportunity for customers in Maine who participate in the Atlantic Bridge and/or Access Northeast projects. Given the New England market dynamics, and Algonquin’s vast footprint in the market, customers in Maine could take advantage of exceptional pipeline transportation optionality with access to these premium markets on a secondary basis when not fully utilizing their firm pipeline transportation. Minimizes Environmental and Stakeholder Impact: Customizing expansion capacity and building that new capacity within Algonquin and Maritimes’ existing pipeline footprint minimizes the environmental and stakeholder impact. By utilizing existing corridors where the pipeline is already operating, the need for additional land acquisition is minimized, and disturbance to land owners and the communities that they live in is also minimized. Expanding an existing pipeline within an established footprint also helps to reduce project execution risk. While risk is inherent in any project, the probability of economic, regulatory, construction, or timing risk is dramatically reduced as compared to new greenfield pipeline development projects. Reducing this risk will help to ensure timely project execution success for Algonquin and Maritimes. Spectra Energy Has a Proven Track Record: Spectra Energy is one of North America’s premier pipeline and midstream companies, developing critically important pipeline and related energy infrastructure projects for nearly a century. Spectra Energy’s expertise, vast experience, existing and extensive pipeline footprint, connection to diverse supply sources and premium markets, and strong customer and stakeholder relationships all contribute to Spectra Energy’s proven track record of successful pipeline construction and operation in New England and throughout North America. PUBLIC 19
  • 20. At Spectra Energy, Safety Is at the Forefront: Spectra Energy is dedicated to safety in ALL aspects of its business and is extremely focused on uncompromisingly safe construction and operation of its facilities. Spectra Energy follows a “compliance plus” mindset that goes beyond regulatory requirements. Moreover, Spectra Energy reaches out beyond its internal focus and works closely with its contractors, regulators, and customers to ensure a safe work environment at all levels and dimensions of its business. Further details on some of Spectra Energy’s specific safety initiatives and programs can be found on pages 23‐24 of this proposal. PUBLIC 20
  • 21. Project Execution Experience Spectra Energy grows its business by adding infrastructure capacity and services. Since separating from Duke Energy in 2007, Spectra Energy has placed into service 63 fee‐based expansion projects totaling more than $7.5 billion. Over the next three years, the company has plans to invest approximately $6 billion in additional growth projects. Key to Spectra Energy’s success has been a culture of excellence in project execution. Spectra Energy understands that executing projects requires attention to many details. In addition to this focus on the technical excellence of design and construction of new facilities, Spectra Energy is committed to a comprehensive stakeholder outreach effort that encompasses extensive consultation with landowners, politicians and agencies to identify environmental permitting considerations for the project. These projects are delivered by using a disciplined management approach to project execution. The approach consists of phases and dates that describe the project life‐cycle and critical decision points. The methodology is aligned with Project Management Institute’s best practices for establishing the right priorities and ensuring that decisions are based on well‐developed information. A macro overview of the capital expansion project lifecycle management system is provided below, with key processes/activities and quality goals highlighted beneath each phase. PHASE 2 Scope/Cost Refinement PHASE 1 Initial Project Scoping » Concept development » Feasibility » Economic feasibility » Initial risk assessment » PFA/seed capital reqs » Project team activated » Pre‐budget » Risk assessment » Project plan developed PHASE 3 Baseline Regulatory Filings » Project team expanded » Budget » P2 design drawings » RFI/RFQ construction » Project plan baseline » Review risks PHASE 4 Regulatory Approvals Design & Permit » Project execution team » Design drawings IFB/IFC » Monitor change controls » Construction bid documents » Project execution plan » Regulatory response » Project monitoring PHASE 5 Construction & Commissioning » Begin construction » Materials coordination » Inspections » Project monitoring & controls » Risk review PHASE 6 Project Closure » Restoration reporting » Landowner releases » Reg/Envpermits » As‐builts and turnover » Financial closure » Lessons learned » Contractor closure QUALITY GOALS » Put a sound strategy in place ‐ prepare for commercial deal and project success » Conduct sound planning ‐ refine strategic planning requirements and facility/scope/cost estimates; prepare for regulatory approvals and next phase. » Conduct sound planning ‐ refine all estimates and prepare for regulatory approvals, execution of strategies/plans and construction phases. » Perform Effective Execution ‐ approvals, budget and materials management throughout construction and commissioning phases » Perform Effective Execution ‐ approvals, accurate cost forecasting, construction and materials management throughout construction and commissioning phases » Project Closure & Continuous Learnings – completion of all closure components and documentation, including Lessons Learned for future reference PUBLIC 21
  • 22. Recent Projects in Execution or Recently In Service The following diagram provides a geographical perspective of the scope and scale of projects Spectra Energy has currently in execution. Of particular interest would be the AIM project. The AIM project is currently in the permitting phase of development, with the project’s FERC application being filed in February 2014. Algonquin secured contractual commitments for the project from local distribution companies for new pipeline capacity of 342,000 Dth/d. The planned in‐service of the AIM project is November 2016. PUBLIC 22
  • 23. Safe, Responsible and Reliable Operations Safety is the top priority for Spectra Energy. The vision is that all Spectra Energy employees and contractors will demonstrate personal commitment to continuous safety improvement, resulting in a zero‐injury and zero‐work‐related illness culture. We have a strong safety record. Over the past five years, the incident rate for Spectra Energy’s onshore pipelines in the US is half of that in the industry as a whole. While we already have a strong safety record, our goal is zero incidents. No incident is acceptable. Spectra Energy works closely with federal and state regulators to ensure safe, reliable natural gas for Americans, and we inspect more pipeline annually than required by state and federal regulations. We also are committed to being a good neighbor in the communities that host our facilities. Spectra Energy is committed to managing its operations in a way that protects the safety, security, and health of its employees, its customers, and the public. Experienced and highly trained employees operate and maintain the company’s pipelines and facilities using thoroughly tested internal procedures and standards, while adhering to strict regulations. Spectra Energy strives to be an industry leader in pipeline integrity and service reliability. Each business provides contractor safety management programs. The SAFE3 Contractor Safety Management Program focuses on hiring “safety capable” contractors, identifying and mitigating risks, oversight, and post‐job evaluations. Since SAFE3’s development and implementation three years ago, Spectra Energy has achieved a significant reduction in U.S. contractor injuries. Spectra Energy actively manages the integrity of its assets in order to protect its employees and the public, and to ensure the reliable delivery of natural gas to its customers. The company’s leadership and commitment to pipeline integrity has earned it industry‐wide respect and credibility. Spectra Energy’s well‐established Integrity Management Program includes systematic management and maintenance practices, such as sophisticated inspection devices and aerial pipeline patrols, designed to mitigate PUBLIC 23
  • 24. threats to its facilities. Customers rely on Spectra Energy to provide uninterrupted transportation of natural gas, so its facilities and equipment must be properly maintained and monitored. The company tracks measures of reliability specific to its businesses. PUBLIC 24
  • 26. Spectra Energy Overview Spectra Energy Corp (NYSE: SE), a Fortune 500 company, is one of North America’s leading pipeline and midstream companies. Based in Houston, Texas, the company’s operations in the United States and Canada includes more than 22,000 miles of natural gas, natural gas liquids, and crude oil pipelines; approximately 305 billion cubic feet (Bcf) of natural gas storage; 4.8 million barrels of crude oil storage; as well as natural gas gathering, processing, and local distribution operations. Spectra Energy is the general partner of Spectra Energy Partners (NYSE: SEP), one of the largest pipeline master limited partnerships in the United States and owner of the natural gas, liquids, and crude oil assets in Spectra Energy’s U.S. portfolio. Spectra Energy also has a 50 percent ownership in DCP Midstream, the largest producer of natural gas liquids and the largest natural gas gatherer and processor in the United States. Spectra Energy’s natural gas assets strategically connect conventional and unconventional natural gas supplies with four of the five fastest‐growing markets in North America. Its natural gas storage facilities are strategically positioned to serve local distribution companies, power and gas utilities, marketers and traders, and producers. PUBLIC 26
  • 27. At Spectra Energy, we pride ourselves on creating a world‐class work environment and offering the most advance, sustainable energy solutions. Below are some of our most recent awards. Spectra Energy has served North America customers and communities for more than a century. The company’s longstanding values are recognized through its inclusion in the Dow Jones Sustainability World and North America Indexes and the CDP Global 500 and S&P 500 Climate Disclosure and Performance Leadership Indexes. For the seventh consecutive year Spectra Energy Corp was named to the 2014 CDP S&P 500 Climate Disclosure Leadership Index (CDLI) and Climate Performance Leadership Index (CPLI). For the second consecutive year Spectra Energy was the only energy company to be named to the CPLI and the only energy company to make both indices. Spectra Energy has also been named to the Dow Jones Sustainability World Index (DJSI World) for the fifth consecutive year, to the Dow Jones Sustainability North America Index (DJSI NA) for the seventh consecutive year, and as an Industry Leader among its peers. Fortune Magazine's FORTUNE 500  Annual ranking of America's largest corporations: 2008‐2014 Corporate Responsibility Magazine’s 100 Best Corporate Citizens List  Named to the 100 Best Corporate Citizens List: 2011‐2014  Recognized as the best corporate citizen among utilities: 2012‐2013 Ethisphere Institute's World's Most Ethical Companies List Most recently, Spectra Energy was named for the third year in a row to Ethisphere Institute’s World’s Most Ethical Companies List for 2014. Recognized for leadership in promoting ethical business standards, exceeding legal minimums for compliance and introducing innovative ideas: 2012‐2014. For more information, please go to www.spectraenergy.com. PUBLIC 27
  • 28. Business Segment Overview Spectra Energy is focused on delivering premium services through four very distinct business segments:  U.S. Transmission – Spectra Energy has one of the largest pipeline and storage systems in North America  Distribution – Spectra Energy is the second largest local distribution company in Canada serving 1.4 million customers in 400 communities and has the largest storage facilities in Canada  Western Canada Transmission & Processing – Spectra Energy is one of the largest producers of natural gas liquids in Canada  Field Services – Spectra Energy has a 50 percent interest in DCP Midstream – the largest natural gas processor in the U.S. PUBLIC 28
  • 29. The Way Spectra Energy Works Spectra Energy’s purpose is to create sustainable value for its investors, customers, employees and communities by providing natural gas gathering and processing, transmission, storage and distribution services. It builds value by:  Advancing the role of natural gas in meeting North America’s energy needs  Delivering excellence in safety, reliability, customer responsiveness and profitability  Capitalizing on the size and attributes of its existing assets  Executing its expansion projects on time and on budget  Pursuing strategic growth opportunities Spectra Energy’s Charter, Code of Business Ethics and commitment to economic, environmental and social responsibility define the way the company works. Spectra Energy’s values which guide the company’s actions and shape its decisions are:  Stewardship – Demonstrating a commitment to environmental responsibility and vibrant communities  Integrity – Ethically and honestly doing what it says it will do  Respect for the Individual – Embracing diversity and inclusion, enhanced by openness, sharing, trust, leadership, teamwork and involvement  Safety – Sharing a relentless commitment to a zero‐work‐related injury and illness culture  High Performance – Accountability, achieving superior business results and stretching its capabilities  Win‐Win Relationships – Having relationships which focus on the creation of value for all parties  Initiative – Having the courage, creativity and discipline to lead change and shape the future The company distinguishes itself through its commitments to strong corporate governance and business ethics; safe, reliable operations; environmental stewardship; and community support and engagement. Corporate Governance and Business Ethics Spectra Energy conducts its business with integrity, transparency and accountability. Its corporate governance systems are designed to be transparent and to ensure it complies with the letter and intent of all laws, regulations and rules that apply to its business and the industry, and that the company operates both ethically and profitably. The Spectra Energy Charter establishes the vision, purpose, values and measures of success. The values guide employees in the conduct of the business. The Code of Business Ethics (Code) establishes standards designed to help employees conduct business ethically and honestly. All company representatives are expected to abide by the Code. The company’s policies guide its employees in managing day‐to‐day compliance with the Code and set corporate standards and guidance for conducting business. In 2009, Spectra Energy strengthened its ethics expectations by revising the Code to address contractors, service providers and suppliers. Contractors now undergo the company’s ethics training, and supply contracts and master services agreements now require vendors to abide by the Code and ethics practices. PUBLIC 29
  • 30. Regulatory and Permitting FERC Natural Gas Pipeline and Storage Process For purposes of illustration, Spectra Energy is describing the approach to obtaining a FERC Certificate for natural gas pipelines and storage facilities. Spectra Energy has been actively involved with FERC in the review and approval process for natural gas pipeline and storage facilities for many years. Since the inception of Spectra Energy in 2007, the company has worked with its customers and its regulators to successfully place into service over 63 projects. Spectra Energy maintains an excellent working relationship with FERC. FERC plays a key role in the development and expansion of U.S. natural gas transmission projects. Under direction from the U.S. Congress, FERC regulates the transmission and storage of natural gas in interstate commerce. FERC is charged with determining whether proposed projects are needed and in the public interest, and ultimately whether to issue a Certificate authorizing the construction and operation of facilities comprising the projects. Their project development efforts continue by monitoring compliance through construction, operational commissioning, and post‐construction restoration work. FERC’s natural gas certificate processes include consulting with stakeholders, such as landowners, community leaders, public officials and relevant federal, state and local agencies, identifying environmental and land‐use issues through a process that FERC refers to as its “scoping” process, and preparing environmental documents such as Environmental Assessments or Environmental Impact Statements. Sponsors of large greenfield projects often request and receive a preliminary determination on non‐environmental issues prior to receipt of a final FERC order to provide an early indication of FERC’s findings regarding the economic aspects of the project. Certificates are issued by final FERC order. Pipeline companies seeking project authorization must file an Application for a Certificate (Certificate Application) with FERC. The Certificate Application describes the purpose and commercial need for the project, the transportation rate to be charged to customers, and any specific terms and conditions of service that will apply to the project, proposed timing and scope of the facilities to be constructed, and a demonstration that the project applicant will be in compliance with all applicable regulatory requirements with respect to the project. Applicants must evaluate project alternatives, identify a preferred alternative, and complete a thorough environmental analysis, including consultation with appropriate regulatory agencies, data reviews and field surveys. Information obtained through this review is compiled into a document known as the “Environmental Report,” which the Applicant prepares as part of the Certificate Application. The Environmental Report also details all other federal, state and local permits required for the project, as well as agencies consulted in preparation of the Environmental Report. To determine whether a proposed project is in the public convenience and necessity, FERC, in addition to its review of the economic aspects of the project, conducts a comprehensive environmental review of the projects, in accordance with the National Environmental Policy Act (NEPA). In the NEPA process, FERC works closely with Federal, state, and local agencies such as the U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service, state departments of environmental protection, and other state and local agencies. Other stakeholders, including project neighbors, landowners, and surrounding communities, are also invited to participate in the FERC process by attending meetings and providing comments or concerns at particular times in FERC’s review process. PUBLIC 30
  • 31. FERC will review the project, evaluating the need, proposed facility locations, and overall impact of project construction and operation, and will summarize its findings in either an Environmental Assessment or an Environmental Impact Statement, depending on characteristics of the project. Upon completion of an Environmental Assessment or Environmental Impact Statement for a project and completion of its review of the economic aspects of the project, FERC will issue an order in which it determines, based on the entirety of its review, whether the project is in the public convenience and necessity. If FERC so determines, it will issue a Certificate authorizing the construction and operation of the project facilities. FERC Pre‐Filing Process FERC has established a collaborative pre‐application process that gives landowners, government agencies and other interested stakeholders the opportunity to review project information and identify issues or concerns before a Certificate Application is filed with FERC or other permit applications are made. This phase of project development is referred to as the Pre‐Filing Process. Throughout the process, the Applicant and FERC will actively seek input from interested stakeholders through public outreach efforts that include written communications and public meetings. Stakeholders are encouraged to participate and share any questions or concerns so they can be addressed prior to submittal of the Certificate Application. Additionally, FERC reviews drafts of the Applicant’s Environmental Report during this stage of the project. The Certificate Application, once filed, will identify a more detailed route and/or set of facilities and locations based on input that the Applicant has received from FERC and interested stakeholders during the Pre‐ Filing Process. At the beginning of the Pre‐Filing Process, FERC issues a Notice of Intent, or NOI, to prepare an Environmental Assessment or Environmental Impact Statement (environmental document) for the proposed project. With the NOI, FERC initiates a scoping period in which it seeks to discover and address concerns the public may have with the environmental and land‐use aspects of the project. The primary goal of the scoping process is to focus FERC’s analysis in the Environmental Assessment or Environmental Impact Statement on the important environmental and land‐use issues. Comments received during the scoping period will be incorporated into FERC’s environmental document. Project Application Once the Pre‐Filing Process is complete, the Applicant files a Certificate Application for the project along with an anticipated schedule. Additionally, permit applications are submitted to other federal, state, and local agencies. The permit proceedings conducted by these agencies often provide additional opportunity for public involvement. Once the Certificate Application has been filed, FERC will issue a Certificate Docket number (CP__‐). As with the Pre‐Filing Process, all public documents associated with the Certificate Application and filed with or issued by FERC are accessible via the e‐Library on FERC’s Web site (www.ferc.gov). Additionally, copies of the Certificate Application and the Environmental Report will be made available at public locations within each county impacted by the project so that all stakeholders will have the opportunity to review and comment on the Certificate Application. Notices of the Certificate Application filing and the locations to view the documents are PUBLIC 31
  • 32. sent to all identified stakeholders. The project sponsors’ outreach effort to interested stakeholders continues through this stage of the project. Within 10 business days of filing the Certificate Application, FERC will issue a Notice of Application, which will be posted in the Federal Register, notifying the public of the filing of the Certificate Application and the process for filing interventions or comments in the docket, and within 90 days of such notice, will issue a notice of schedule for environmental review of the Certificate Application, indicating when it expects to issue the final environmental document for the project and the deadline for final decisions from other relevant federal permitting agencies. During its review period, FERC will identify any additional or clarifying information that may be needed from the Applicant and will complete its environmental document in accordance with NEPA and its evaluation of the economic aspects of the project. Following issuance of the environmental document by FERC, stakeholders will have an opportunity to provide additional comments regarding the project. FERC will review any comments received and respond to them in either a final environmental document or, provided FERC agrees that the project is of public convenience and necessity, the agency may address comments directly in its Certificate. Project Authorization Once FERC issues a Certificate, the Applicant must:  Accept the Certificate within 30 days;  File an affirmative statement indicating commitment to provide environmental training to all individuals working on the project; and  File an Implementation Plan(s) within 60 days of the Certificate Order indicating how the project will comply with the conditions outlined in the Certificate Order. Project construction cannot begin until FERC authorizes a Notice to Proceed. The FERC staff will conduct periodic site visits throughout construction to ensure ongoing compliance, including a visit as construction nears completion to review restoration efforts and identify any additional needed measures. Applicants are also required to receive FERC approval prior to placing the project facilities into service. Additional monitoring of the right‐of‐way will continue after the project facilities are placed into service to ensure restoration efforts are successful. Spectra Energy’s Approach to the FERC Process Spectra Energy understands the importance of communicating with FERC Staff as well as representatives of other regulatory agencies, landowners, special interest groups, and other stakeholders during the development, permitting, and construction of new projects. To that end, Spectra Energy has received numerous recognitions and commendations on the success of their projects and Spectra Energy’s collaborative approach to working with all parties during the various stages of a project. Spectra Energy will communicate early and often with FERC Staff and other stakeholders to identify and address potential problems and issues in the most efficient and effective manner. This collaborative approach will be reflected in all phases of the project, from the identification of the optimum route for the pipeline to defining mitigation measures to address and minimize potential environmental impact, and to closely managing and PUBLIC 32
  • 33. monitoring pipeline construction activities to ensure compliance with permit conditions and commitments made to landowners and other stakeholders. Spectra Energy is committed to embracing the FERC process and working with the FERC staff to successfully permit, construct, and operate the Project. PUBLIC 33
  • 34. Environmental Stewardship Description Environmental stewardship refers to responsibility for environmental quality shared by those whose actions affect the environment during development of a natural gas pipeline project. Due diligence in identifying, mitigating and managing environmental impacts is important in order to ensure on‐time and on‐budget projects. This process also informs engagement strategies with regulatory agencies, landowners, communities and other key stakeholder groups. Spectra Energy’s Approach Spectra Energy’s approach to managing environmental risks and impacts in construction will be consistent with its corporate approach across all its operations, as follows: • Identify and understand environmental impacts; • Design projects to avoid or minimize environmental impacts; • Manage and mitigate unavoidable impacts; • Encourage responsible use of natural gas in its retail market areas; • Engage and respond to stakeholders; • Meet or exceed compliance requirements with applicable laws and regulations; and • Implement best management practices to minimize operational and environmental risks. Spectra Energy has committed to be a responsible environmental steward while striving to help meet North America’s increasing demand for natural gas. This environmental commitment is central to decisions on how Spectra Energy builds and manages its operations, helps customers address environmental impacts, and advocates for responsible public policies. Agency Outreach – Approach Spectra Energy will create a Public and Agency Participation Plan to contact key federal and state agencies with jurisdiction over the general project area to define the resources, factors, and processes that could influence the successful permitting of a project of this magnitude. Items that would typically be addressed include the following:  Identify the agency’s jurisdictional authority;  Identify resources and issues that may be pertinent when the characteristics of the project are (better) defined;  Identify general approaches that the agency (and, more specifically, the agency staff) would recommend once formal consultation begins;  Identify local experts and special interest groups in the project area that may be parties;  Establish a general timeline for the agency’s consultation and permitting process; and PUBLIC 34
  • 35.  Identify typical mitigation considerations that may ultimately be advocated by agencies and special interest groups. Based on the information that is collected, Spectra Energy will prepare a preliminary cost estimate and schedule for environmental studies and permitting. This will allow the company to evaluate potential schedule and cost implications of the project. The results of this review will be documented in a Critical Issues Report. Public – Approach After conducting environmental due diligence and establishing a plan for initial agency dialogue, Spectra Energy will determine a public outreach and community engagement strategy in close cooperation with the Maine Public Utilities Commission. In previous projects Spectra Energy has conducted “open houses” in order to provide the company’s description of the project to interested stakeholders and solicit information from participants about the project and any potential concerns. For more information about Spectra Energy’s approach to public outreach refer to the section on Stakeholder engagement. Environmental Studies – Approach During the Development Period, Spectra Energy will initiate detailed agency consultation with a detailed project description to define the agency required field studies, including the protocols for those field studies. Typical field studies may include the following. Special Status Species Surveys Special status species are those species of animals and plants for which state or federal agencies afford protection by law, regulation, or policy. Included in this category are federally listed and federally proposed species that are protected under the Endangered Species Act, or are considered as candidates for such listing by the U.S. Fish and Wildlife Service or National Marine Fisheries Service and those species that are state‐listed as threatened or endangered species or species of special concern. Spectra Energy will consult with U.S. Fish and Wildlife Service and state commissions to review rare and endangered species. Based on this information, Spectra Energy will conduct surveys of the project area for occurrences of or habitat for any such species identified as potentially present in the study area. If it is necessary for Spectra Energy to contract agency‐recognized or agency‐required specialists to conduct or participate in such surveys, Spectra Energy will incorporate those specialists into the Spectra Energy team as early as possible. Cultural Resource Surveys Section 106 of the National Historic Preservation Act (NHPA) requires that the lead federal agency under the NEPA (which will certainly be the FERC for this project) take into account the effects of its undertakings on properties listed on, or eligible for listing on, the National Register of Historic Places and provide the Advisory Council on Historic Preservation (ACHP) an opportunity to comment on the undertaking. To meet this requirement and assist with the formal federal and state consultation related to cultural resources, Spectra Energy will consult with the Division of Historical Resources and define what surveys will be required and what survey protocols (e.g., survey corridor widths and shovel test intervals) will have to be followed. Once PUBLIC 35
  • 36. these parameters are defined, Spectra Energy will conduct field surveys in the survey area defined by the State Historic Preservation Office. Ambient Noise and Air Quality Measurements Depending on project requirements for compression equipment, Spectra Energy may conduct measurements of the ambient noise and air quality environments in the vicinity of any required/proposed compression units. Any such measurements will be compliant with required standards and guidance from staff representatives of the jurisdictional regulatory agencies. PUBLIC 36
  • 37. Stakeholder Outreach For Spectra Energy, stakeholders are those who are, or could be, affected by the company’s operations. These include, but are not limited to, customers, landowners, communities, government officials, regulators, non‐governmental organizations, suppliers, analysts, media and shareholders. Spectra Energy is committed to identifying the stakeholders and potential issues related to the Project, determining appropriate and effective methods of communication, identifying responsible parties, documenting the public consultation process and adhering to communication protocols. Spectra Energy believes earlier and more collaborative involvement will lead to project designs that minimize impacts to landowners, communities and the environment while enabling the company to develop more comprehensive applications submitted to submit to the FERC, state agencies, and local jurisdictions. Stakeholder Outreach Principles and Approach Spectra Energy works closely with stakeholders in areas affected by its projects to foster long‐term relationships built on trust and respect. Spectra Energy’s core values guide its stakeholder outreach programs and activities as well as the work of its employees and contractors. In conducting business, Spectra Energy’s values guide its approach: • Stewardship ‐ Demonstrating a commitment to environmental responsibility and vibrant communities. • Respect for the Individual ‐ Embracing diversity and inclusion, enhanced by openness, sharing, trust, leadership, teamwork and involvement. • Integrity ‐ Ethically and honestly doing what we say we will do. • Win‐Win Relationships ‐ Having relationships that focus on the creation of value for all parties. • Initiative ‐ Having the courage, creativity and discipline to lead change and shape the future. While these values guide the company’s company‐wide stakeholder outreach approach, Spectra Energy tailors its activities for each project, ensuring that the dialogue with stakeholders is open, transparent and meaningful. Spectra Energy’s Stakeholder Engagement Principles, developed to guide its interactions, are: • To be respectful of and considerate to all stakeholders. • To engage with those affected by our business. • To consider stakeholder‐identified issues in its decision‐making process. • To provide timely and accurate communication using accessible information and language. • To be transparent in its processes and communications. Spectra Energy’s stakeholder outreach activities are endorsed by its executive management team. Spectra Energy has a company‐wide and customized programs for each activity and project, and communication plans that provide employees the “who, what, where and when” protocols when conducting business. PUBLIC 37
  • 38. To ensure effective dialogue with its stakeholders, Spectra Energy relies on one‐on‐one discussions, face‐to‐face meetings, open houses, websites, legal notices, media outreach and individual letters sent via mail. Communications and materials are conducted in multiple languages, as needed. The key criteria inherent in implementing a successful stakeholder consultation plan are the ability and knowledge to explain a project’s benefits and its potential impacts; to respond to questions, concerns and issues; and, whenever possible, to mitigate potential impacts. In order to sustain a successful program, Spectra Energy seeks, involves, informs and responds to stakeholders by implementing the planning process early, with open and collaborative activities. The company executes its plans by engaging in and sustaining understandable, accurate and timely dialogue with its stakeholders. This process helps build and maintain win‐win relationships. Spectra Energy works closely with stakeholders in areas affected by its projects and strives to create mutually beneficial relationships with communities built on trust and respect. Spectra Energy also has a long history of working successfully with indigenous peoples across many of its operating areas. PUBLIC 38