This document provides details on public works capital improvement projects for the City of Evanston for 2014-2017. Section 1 lists projects for 2014 including street and infrastructure improvements as well as parks renovations. Section 2 highlights some featured 2014 projects including improvements for Davis Street, Sheridan Road, and the Civic Center parking lot. Section 3 outlines proposed infrastructure projects for 2015-2017 including streets, sidewalks, bike lanes, and streetscapes. The projects are organized by year and include estimated costs and funding sources.
In response to traffic congestion on St Clair Avenue West around Keele Street and Old Weston Road, City Council has directed staff to carry out an Environmental Assessment (EA) Study of the St. Clair Avenue / Rail Crossing between Keele Street and Old Weston Road. This project will investigate solutions to the traffic concerns in this area
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
Langley School Pump Station Community Meeting October 22, 2020Fairfax County
The community meeting was held to inform residents about the Langley School Pump Station project and to present the county's preliminary plans for the gravity sewer, pump station and force main.
This project included rehabilitation of four sanitary sewer metering vaults. These meter vaults included Dukes Car Wash, Lower Holmes Run, Tod Street, and Scotts Run. The Dukes Car Wash and Lower Holmes Run Meters are in the City of Alexandria, the Tod Street Meter is in Falls Church in the Providence District, and the Scotts Run Meter is in the Scotts Run Nature Preserve in the Dranesville District. Work included removal of existing control panels, conduits and metering equipment, rehabilitation of the interior of the vaults with a cementitious coating and epoxy liner system, installation of new control panels and conduit, and reinstallation of flow metering devices. This project was substantially complete on August 30, 2021.
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Fairfax County
A virtual meeting about the project will be held on August 19, 2020 at 6:00 p.m. Please see a how to sign in on slide 2. A 2019 study evaluated several alternatives for replacement. Those alternatives will be discussed with the community at the virtual meeting.
Presentation provided to the Marrowstone Island Community Presentation by the North Olympic Salmon Coalition to discuss the Kilisut Harbor Restoration Project.
MICA Kilisut Harbor Restoration Project Presentation- January 20th, 2014Sarah Doyle
Presentation provided to Marrowstone Community by the North Olympic Salmon Coalition. The presentation provides and overview of the upcoming Kilisut Harbor Restoration Project.
A Closed-Circuit Television (CCTV) Camera became stuck in the sanitary sewer line located in the Old Keene Mill Shopping Center. Wastewater Design and Construction Division mobilized to the site with the on-call contractor to begin the 15-foot excavation to replace 50 feet of broken gravity sewer. Because the work was within a shopping center parking lot, the project team worked the night shift to limit disturbance to the community. After four days of work, the camera was retrieved, and the pit was backfilled. This project was substantially complete on August 27, 2021.
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
Design Phase includes:
Finalize sewer alignment
Manhole locations and material selection
Construction phasing plan
Final restoration for former pump station site/access
Existing utility coordination
Easement acquisition (if applicable)
By-pass water & sewer locations
Temporary service outage plan – water/sewer/gas
Traffic control plans
Phasing
Detour and closure plan
In response to traffic congestion on St Clair Avenue West around Keele Street and Old Weston Road, City Council has directed staff to carry out an Environmental Assessment (EA) Study of the St. Clair Avenue / Rail Crossing between Keele Street and Old Weston Road. This project will investigate solutions to the traffic concerns in this area
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
Langley School Pump Station Community Meeting October 22, 2020Fairfax County
The community meeting was held to inform residents about the Langley School Pump Station project and to present the county's preliminary plans for the gravity sewer, pump station and force main.
This project included rehabilitation of four sanitary sewer metering vaults. These meter vaults included Dukes Car Wash, Lower Holmes Run, Tod Street, and Scotts Run. The Dukes Car Wash and Lower Holmes Run Meters are in the City of Alexandria, the Tod Street Meter is in Falls Church in the Providence District, and the Scotts Run Meter is in the Scotts Run Nature Preserve in the Dranesville District. Work included removal of existing control panels, conduits and metering equipment, rehabilitation of the interior of the vaults with a cementitious coating and epoxy liner system, installation of new control panels and conduit, and reinstallation of flow metering devices. This project was substantially complete on August 30, 2021.
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Fairfax County
A virtual meeting about the project will be held on August 19, 2020 at 6:00 p.m. Please see a how to sign in on slide 2. A 2019 study evaluated several alternatives for replacement. Those alternatives will be discussed with the community at the virtual meeting.
Presentation provided to the Marrowstone Island Community Presentation by the North Olympic Salmon Coalition to discuss the Kilisut Harbor Restoration Project.
MICA Kilisut Harbor Restoration Project Presentation- January 20th, 2014Sarah Doyle
Presentation provided to Marrowstone Community by the North Olympic Salmon Coalition. The presentation provides and overview of the upcoming Kilisut Harbor Restoration Project.
A Closed-Circuit Television (CCTV) Camera became stuck in the sanitary sewer line located in the Old Keene Mill Shopping Center. Wastewater Design and Construction Division mobilized to the site with the on-call contractor to begin the 15-foot excavation to replace 50 feet of broken gravity sewer. Because the work was within a shopping center parking lot, the project team worked the night shift to limit disturbance to the community. After four days of work, the camera was retrieved, and the pit was backfilled. This project was substantially complete on August 27, 2021.
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
Design Phase includes:
Finalize sewer alignment
Manhole locations and material selection
Construction phasing plan
Final restoration for former pump station site/access
Existing utility coordination
Easement acquisition (if applicable)
By-pass water & sewer locations
Temporary service outage plan – water/sewer/gas
Traffic control plans
Phasing
Detour and closure plan
The North Shore Drive Sidewalk Improvements project has been Substantially Completed. The overall project scope was to increase pedestrian safety along North Shore Drive . The new pedestrian walkway consists of 2,315 lineal feet of 5-foot wide concrete sidewalk and 224 lineal feet of 6-foot wide asphalt walking path. The project started approximately 500 feet West of Sycamore Valley drive and extended to approximately 400 feet East of Links Drive. Also, along with the improved pedestrian access, upgrades were made to the storm drain system, a new concrete pad was placed for the existing bus shelter and the Eastbound lane of North Shore Drive was milled and new asphalt and striping was installed.
Fulton Market Streetscape Meeting - CDOT discussed recommended improvements to Fulton Market between Halsted Street to Ogden Avenue. Gateway Arch Update and project timeline.
SBA & City of Evanston Economic Injury Webinar - 4/1/2020cityofevanston
Stephen Konkle from the Small Business Administration (SBA) presents options for City of Evanston businesses in the wake of the COVID-19 disaster. Includes information on the Economic Injury Disaster Loans (EIDL).
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Many ways to support street children.pptxSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
What is the point of small housing associations.pptxPaul Smith
Given the small scale of housing associations and their relative high cost per home what is the point of them and how do we justify their continued existance
This session provides a comprehensive overview of the latest updates to the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (commonly known as the Uniform Guidance) outlined in the 2 CFR 200.
With a focus on the 2024 revisions issued by the Office of Management and Budget (OMB), participants will gain insight into the key changes affecting federal grant recipients. The session will delve into critical regulatory updates, providing attendees with the knowledge and tools necessary to navigate and comply with the evolving landscape of federal grant management.
Learning Objectives:
- Understand the rationale behind the 2024 updates to the Uniform Guidance outlined in 2 CFR 200, and their implications for federal grant recipients.
- Identify the key changes and revisions introduced by the Office of Management and Budget (OMB) in the 2024 edition of 2 CFR 200.
- Gain proficiency in applying the updated regulations to ensure compliance with federal grant requirements and avoid potential audit findings.
- Develop strategies for effectively implementing the new guidelines within the grant management processes of their respective organizations, fostering efficiency and accountability in federal grant administration.
Understanding the Challenges of Street ChildrenSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
Russian anarchist and anti-war movement in the third year of full-scale warAntti Rautiainen
Anarchist group ANA Regensburg hosted my online-presentation on 16th of May 2024, in which I discussed tactics of anti-war activism in Russia, and reasons why the anti-war movement has not been able to make an impact to change the course of events yet. Cases of anarchists repressed for anti-war activities are presented, as well as strategies of support for political prisoners, and modest successes in supporting their struggles.
Thumbnail picture is by MediaZona, you may read their report on anti-war arson attacks in Russia here: https://en.zona.media/article/2022/10/13/burn-map
Links:
Autonomous Action
http://Avtonom.org
Anarchist Black Cross Moscow
http://Avtonom.org/abc
Solidarity Zone
https://t.me/solidarity_zone
Memorial
https://memopzk.org/, https://t.me/pzk_memorial
OVD-Info
https://en.ovdinfo.org/antiwar-ovd-info-guide
RosUznik
https://rosuznik.org/
Uznik Online
http://uznikonline.tilda.ws/
Russian Reader
https://therussianreader.com/
ABC Irkutsk
https://abc38.noblogs.org/
Send mail to prisoners from abroad:
http://Prisonmail.online
YouTube: https://youtu.be/c5nSOdU48O8
Spotify: https://podcasters.spotify.com/pod/show/libertarianlifecoach/episodes/Russian-anarchist-and-anti-war-movement-in-the-third-year-of-full-scale-war-e2k8ai4
2. INTRODUCTION
Section 1: 2014 CIP Project List and Schedule
Section 2: 2014 Project Highlights
Section 3: 2015-2017 CIP Infrastructure Projects
Section 4: Parks Improvement Plan
Comments and Questions
2
3. 3
SECTION 1: 2014 PROJECTS
Project Name Start Date Completion Date
Arrington Lakefront Lagoon Renovations - Construction Spring 2014 Fall 2014
Baker Park Renovations TBD TBD
Capital Studies (Facilities, Infrastructure Asset Appraisal) - Evaluation TBD TBD
Church Street Boat Ramp Renovations - Design Summer 2014 Fall 2014
Clark Street Beach Bird Habitat Restoration - Design Fall 2014 Spring 2015
Currey Park Renovations - Design Fall 2014 Spring 2015
Dempster Street Boat Rack Installations - Construction Summer 2014 Fall 2014
Fountain Square Reconstruction Study - Study TBD TBD
Grey Park Renovations – Design Fall 2014 Spring 2015
Ladd Arboretum Bike Path Renovations - Design Summer 2014 Spring 2015
Parks and Facilities Contingency Account N/A N/A
Penny Park Renovations TBD TBD
4. 4
SECTION 1: 2014 PROJECTS
Project Name Start Date Completion Date
Animal Shelter Renovations – Construction TBD TBD
Capital Studies (Facilities, Infrastructure, Asset Appraisal) – Evaluation TBD TBD
Chandler Center Minor Improvements – Construction Fall 2014 Fall 2014
Civic Center Boiler Building Renovations – Construction Summer 2014 Summer 2014
Civic Center Security Improvements – Construction TBD TBD
Collector’s Office Renovations – Construction TBD TBD
Crown Center Minor Improvements – Construction Summer 2014 Fall 2014
Crown Center Partnership Study – Study TBD TBD
Ecology Center Renovations – Construction Fall 2014 Fall 2014
Facilities Capital Improvement Contingency N/A N/A
Fire Station #2 Renovations – Construction Fall 2014 Winter 2014
Fleetwood-Jourdain Minor Improvements – Construction Summer 2014 Summer 2014
Levy Center Renovations – Study Spring 2014 Spring 2014
Noyes Center Roofing and Masonry Repairs – Construction Summer 2013 Spring 2014
Parking Garage Capital Maintenance – Church – Evaluation Spring 2014 Summer 2014
Parking Garage Capital Maintenance – Maple – Evaluation Spring 2014 Summer 2014
Parking Garage Capital Maintenance – Sherman - Evaluation Summer 2014 Fall 2014
Police Fire Headquarters Renovations TBD TBD
Service Center Renovations – Study Spring 2014 Spring 2014
5. 5
SECTION 1: 2014 PROJECTS
2014 Street Improvement Plan
Water Main Replacement and Street Resurfacing Project
Project Proposed Start Date Estimated Completion Date
Lake Street (Forest Ave. to Sheridan Rd.) May 12, 2014 July 31, 2014
Bennett Avenue (Elgin Rd. to Simpson St.) May 12, 2014 July 31, 2014
Prairie Avenue (Grant St. to Lincoln St.) May 12, 2014 July 31, 2014
Woodland Road (Ewing Ave to Bennett Ave.) May 12, 2014 July 31, 2014
Ridge Terrace (Ridge Ave. to Sherman Ave.) May 12, 2014 July 31, 2014
Greenwood Street (Sherman Ave. to Hinman Ave.) July 7, 2014 September 30, 2014
Keeney Street (Hinman Ave. to Forest Ave.) July 7, 2014 September 30, 2014
Keeney Street (Forest Ave. to Sheridan Rd.) July 7, 2014 September 30, 2014
Davis Street (Wesley Ave. to Asbury Ave.) July 7, 2014 September 30, 2014
Howard Street (Custer Ave. to Chicago Ave./Dominick's) July 7, 2014 September 30, 2014
Street Resurfacing CIP
Clark Street (Ridge Ave. to Oak Ave.) June 16, 2014 August 22, 2014
Oak Avenue (Church St. to Clark St.) June 16, 2014 August 22, 2014
Oakton Street (Dodge Ave. to Asbury Ave.) June 16, 2014 August 22, 2014
Ingleside Pl (Sheridan Rd. to East End) June 16, 2014 August 22, 2014
6. 6
SECTION 1: 2014 PROJECTS
ADDITIONAL STREETS RESURFACING
Washington Street (Dodge Ave. to Dewey Ave.) August 2014 September 2014
Madison Street (Chicago Ave. to Custer Ave) August 2014 September 2014
Hartrey Avenue (Greenwood St. to Lake St.) August 2014 September 2014
Thayer Street (Princeton Ave. to Crawford
Ave.)
August 2014 September 2014
Darrow Avenue (Greenleaf St. to Crain St.) August 2014 September 2014
Grove Street (West End to Asbury Ave.) August 2014 September 2014
Project Proposed Start Date Estimated Completion Date
Pitner Sidewalk July 2014 August 2014
Civic Center Parking Lot Reconstruction
Project
August 2014 October 2014
Dodge Ave. Protected Bike Lane September 2014 October 2014
Bridge Street Bridge Reconstruction August 2013 July 2014
2013 Davis Street Protected Bike Lane and
Pavement Markings
June 15, 2014 August 15, 2014
Central Street Improvements Study
(Hartrey to Eastwood)
May 1, 2014 April 2015
Sheridan Road/Chicago Avenue
Improvements Design
May 15, 2014 December 2014
Salt Dome May 2014 August 2014
7. 7
SECTION 1: 2014 PROJECTS
Project Proposed Start Date Estimated Completion Date
Bike Plan Update August 2013 June 2014
ETHS/Church St. Bike Path May 2014
Neighborhood Traffic Calming & Pedestrian/Bike
Accommodations
April 2014 November 2014
Emerson/Ridge/ Green Bay Intersection December 2013 January 2015
Safe Routes to School Improvements July 2014 August 2014
50/50 Sidewalk Replacement Program March 2014 October 2014
CMAQ Chicago Avenue Signal Improvement
Reimbursement
Completed
Dempster Signal Phase I Engineering August 2013 May 2014
Dempster Signal Phase II & III and Construction
Engineering
June 2014 September 2015
ETHS/Dodge Avenue Pedestrian Light
Improvement
April 2014 October 2014
Pedestrian Safety, Pavement Marking, Streetlight
Improvements
May 2014 October 2014
SNAP Lighting May 2014 December 2014
8. 8
SECTION 2: DAVIS STREET
Davis Streetscape Furniture
• 4 benches
• 30 Bike Rack
• 24 Trash Cans
• Color? Black or Bronze
• Cost $52,000
• Installed in July 2014
Davis Street Pavement Markings
• Permanent lane markings
• Permanent bike lane
• Sign installation
• Installed in July 2014
9. 9
Limits: Chicago Ave to Isabella
Roadway / Bike Improvements
Option One
• 3 lane cross section road with on street bike lanes
Option Two
• 4 lane roadway with expand multi-use path on east side of the road
Sustainable Parkway
Consultant Selection April 2014
Design in 2014, Construction in Summer 2015
SECTION 2: SHERIDAN ROAD
10. 10
Limits: Sheridan to Grove
Roadway / Bike Improvement
• Resurface roadway
• Install a two-way cycle track on west
side of road
Design in 2014, Construction in Spring
2015
SECTION 2: CHICAGO AVENUE
11. 11
SECTION 2: CIVIC CENTER PARKING
Sustainable Lot
Construction Fall
2014, 80% funded by
MWRD
12. 12
SECTION 3: 2015 INFRASTRUCTURE
2015 Infrastructure Proposed Projects
Project Name Funding Sources
CIP WM MFT TIF FEDERAL TOTAL
Streets and Water Main Improvements
Dodge (Oakton to Mulford) $350,000.00 $494,000.00 $844,000.00
Sheridan (Isabella to Chicago)* $950,000.00 $1,600,000.00 $2,550,000.00
Isabella Bridge Design $120,000.00 $120,000.00
Chicago (Sheridan to Grove) $500,000.00 $254,600.00 $1,000,000.00 $1,754,600.00
Main (Hinman to Sheridan) $225,000.00 $608,000.00 $833,000.00
Dempster (McCormick to Ridge) $615,500.00 $615,500.00
Pitner (Dempster to Nathaniel) $195,000.00 $617,500.00 $812,500.00
Hinman (Main to South Blvd) $400,000.00 $400,000.00
Ashland (Isabella to Central)* $600,000.00 $608,000.00 $1,208,000.00
Lake (Chicago to Sherman) $115,000.00 $115,000.00
Streetscape and Sidewalk Improvements
Central Streetscape (Greenbay to Prairie (north side)) $500,000.00 $500,000.00
50/50 Sidewalk Program $250,000.00 $250,000.00
Central Streetscape (Lincolnwood to Ewing( north side)) $350,000.00 $350,000.00
Chicago (Church to Grove) $100,000.00 $500,000.00 $600,000.00
Pedestrian Safety $200,000.00 $200,000.00
Biking Improvements
Sheridan/Chicago Bike Lane (Grove to Isabella)* $396,603.00 $1,468,900.00 $1,865,503.00
Ladd Arboretum Multi-use Path $145,000.00 $580,000.00 $725,000.00
Hinman Bike Lane (Main to South Blvd) $50,000.00 $50,000.00
Total $4,046,603.00 $3,197,600.00 $1,400,000.00 $1,500,000.00 $3,648,900.00 $13,793,103.00
* Note: These items are located adjacent to Northwestern
and the City plans to requests funding participation from the
university.
13. 13
SECTION 3: 2016 INFRASTRUCTURE
2016 Proposal for Streets, Water Main, and Streetscape Improvement
Project Name Funding Sources
CIP WM MFT TIF Federal TOTALS
Streets and Water Main Improvements
Poplar (South end to Colfax) $21,933.00 $21,933.00
Howard (Dodge to Ashland) $127,353.00 $653,600.00 $780,953.00
Howard (City Limits to Dodge) $180,000.00 $200,000.00 $380,000.00
Otto Lane (West-End to Highland) $63,726.00 $63,726.00
Maple (Emerson to University) $100,599.00 $100,599.00
Hartrey (Cleveland to Oakton) $241,705.00 $241,705.00
Hartrey (Washington to Cleveland) $109,500.00 $109,500.00
Asbury (Green Bay to Emerson) $117,248.00 $171,000.00 $288,248.00
Green Bay (Channel-Emerson) $94,240.00 $494,000.00 $588,240.00
Green Bay (Simpson-Asbury) $94,240.00 $361,000.00 $455,240.00
Green Bay/Ridge/Emerson Intersection $410,000.00 $410,000.00
Dewey (Davis to Lake) $91,593.00 $589,000.00 $680,593.00
Lee (Dodge to Dewey) $108,047.00 $334,000.00 $442,047.00
Hastings (Harrison to Colfax) $83,334.00 $273,600.00 $356,934.00
Bennett (Lincoln to Colfax) $43,000.00 $180,500.00 $223,500.00
Davis (Fowler to Pitner) $58,227.00 $58,227.00
Brown (Washington to Cleveland) $93,006.00 $93,006.00
Lincoln (Lincolnwood toGreenbay) $391,000.00 $299,060.00 $690,060.00
Sherman Ave.(Church-Grove) $600,000.00 $600,000.00
Chicago (South Blvd to Howard) $600,000.00 $600,000.00
Isabella Bridge Construction $600,000.00 $600,000.00
Streetscape and Sidewalk Improvements
50/50 Sidewalk $250,000.00 $250,000.00
Pedestrian Safety $200,000.00 $200,000.00
Howard Streetscape (Hartrey-Kedzie) $250,000.00 $500,000.00
Maple Ave. Streetscape (University Place-Clark) $400,000.00 $400,000.00
Central Streetscape (Greenbay-Prairie) $400,000.00 $400,000.00
Sherman Ave Fountain and Streetscape $2,300,000.00 $2,300,000.00
Biking Improvements
Lincoln Bike Lane (Lincolnwood-Greenbay)* $600,000.00 $600,000.00
Chicago Bike Lane (South Blvd to Howard) $75,000.00 $75,000.00
Total $3,524,994.00 $3,355,760.00 $1,428,757.00 $3,350,000.00 $600,000.00 $12,259,511.00
*Note: Bike lane improvement will be part of an ITEP grant
14. 14
SECTION 3: 2017 INFRASTRUCTURE
2017 Proposal for Streets, Water Main, and Streetscape Improvement
Project Name Funding Sources
CIP WM MFT TIF FEDERAL TOTALS
Streets and Water Main Improvements
Main Street (Maple to Hinman) $247,926.00 $315,400.00 $891,540.00 $1,454,866.00
Chicago (Hamilton to Madison) $580,266.00 $741,000.00 $505,400.00 $1,826,666.00
Lawndale (Grant to Simpson) $203,833.00 $494,000.00 $1,066,899.00
Grant (Cowper to Lawndale) $134,667.00 $437,000.00 $571,667.00
Seward (Hartrey to Dodge) $152,507.00 $482,600.00 $635,107.00
Colfax (Bryant to Ridge) $78,120.00 $313,500.00 $391,620.00
Chicago (Grove to Hamilton) $0.00
Crain (Florence to Asbury) $165,200 $165,200.00
Dewey (Kirk to Oakton) $102,000 $102,000.00
South Blvd. (Barton to Asbury) $74,600 $74,600.00
Sherman Avenue (Crain to Dempster) $107,000 $107,000.00
Grey Avenue (Noyes to Grant) $51,500 $51,500.00
Florence Avenue (Washington to Main) $68,400 $68,400.00
Oak Street (Davis to Church) $142,600 $142,600.00
Oakton Street (Asbury to Custer) $619,000 $619,000.00
Streetscape and Sidewalk Improvements
50/50 Sidewalk Program $250,000.00 $250,000.00
Pedestrian Safety $200,000.00 $200,000.00
Chicago Avenue Streetscape $500,000.00 $100,000.00 $600,000.00
Main Street Streetscape $250,000.00 $500,000.00 $750,000.00
Biking Improvements
Chicago Avenue Bike Lane $75,000.00 $75,000.00
Total $2,672,319.00 $2,783,500.00 $1,330,300.00 $1,996,940.00 $0.00 $8,783,059.00
15. METHODOLOGY FOR STREET
RESURFACING
• Utility Priority
• Surface Condition
• Grant/TIF Priority
15
SURFACE
CONDITION Total SQ YD Cost
Less than 40 35722.42 $1,821,844
40 - 50 51374.89 $2,620,119
50 - 59 91053.18 $4,643,712
60 - 65 89531.91 $4,566,127
Total $13,651,802
SURFACE
CONDITION Total SQ YD Cost
Less than 40 31141.00 $1,276,781
40 - 50 96344.40 $3,950,120
50 - 59 225700.80 $9,253,733
60 - 65 208599.10 $8,552,563
Total $23,033,197
Primary Routes
Residential Routes
Implementation of
2015 to 2017 Plan will
result in completing all
primary and
residential routes rated
below 50
16. 16Open Space in Evanston
SECTION 4: PARKS
2001Parks Strategic Plan
• Evaluated / classified
park system
• Developed detailed list
of capital needs
17. 17
Methodology for Park Improvements
Individual Park Components
• Condition of Individual Park Components
• Accessibility
• Funding opportunities
Park Redesign
• Condition of Overall Site
• Accessibility
• Community concerns about existing amenities and/or their
location
• Funding opportunities
Once a methodology is developed staff will develop a 2015 to 2017 plan
and request a dedicated CIP funding level each year to ensure we
maintain a high quality park system
Facilities will be discussed at a future Council meeting
SECTION 4: PARKS