SlideShare a Scribd company logo
PROJECTS SUPERVISED:
A. Otumara Node for DOMGAS Projects – Construction/fabrication of Central
Processing Facility (3nos CPF Modules of 27,000 tons) which includes Piping,
structural, Equipment Installation works at Daewoo Nigeria Fab. Yard and
skidding/installation, hookup and commissioning at Otumara CPF site – 98%
completed.
B. Otumara Node for DOMGAS Projects; Pile Installation works for CPF-01, 02 &03
and Pipe Rack A/B, Exist Flowstation & Swamp area piling– 2014.
C. 3 Layer PE coating and Concrete coating of 12”, 6”, 4” and 2” line pipe for
Otumara Saghara-Escravos AG Solution Pipeline Project – 2012.
D. Site/Yard material audits at contractor’s yards – 2012.
E. Scoping/Project evaluation for Southern Swamp Associated Gas Solution projects
F. Drawing development/project scoping for Ogbotobo Flow lines/facility Rehabilitation
works – 2011.
J. Batan West Re-Entry Projects (2011):
1) Replacement of 4” (7 NOs) and 6” (1 NO) Vandalized Flow Lines at Batan Flow station.
 River-Crossings of 4 inch and 6 inch vandalized flow lines at Batan flow station.
 The ROW ditching and backfilling of the flow lines.
 Pressure testing, hook up, wellhead platform and riser fabrication.
2) Replacements of 7 swamp WellHead Platforms to Ajuju 6T & 1L/S & Batan 2S, 5T, 6S &
9T.
3) Scoping, Designing, Scheduling, Planning and supervising of the 2 inch station waterlines,
and 3 inch fire hydrant lines.
4) Designing and Selection of the Pressure Boosting System of the Hydrant Lines
5) Station Maintenance Works at Batan Flow Station.

More Related Content

What's hot

Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meeting
VDOT Northern Virginia
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
VDOT Northern Virginia
 
Project Listing-Career-2016 (V2)
Project Listing-Career-2016 (V2)Project Listing-Career-2016 (V2)
Project Listing-Career-2016 (V2)Cary Jones
 
Van Dyk H - WSP PB Master CV
Van Dyk H - WSP PB Master CVVan Dyk H - WSP PB Master CV
Van Dyk H - WSP PB Master CVHenk van Dyk
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
VDOT Northern Virginia
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
Crosstown TO
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
VDOT Northern Virginia
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Crosstown TO
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank Station
Crosstown TO
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
City Council April 3, 2012 Hickory Aquifer Project Update
City Council April 3, 2012 Hickory Aquifer Project UpdateCity Council April 3, 2012 Hickory Aquifer Project Update
City Council April 3, 2012 Hickory Aquifer Project UpdateCity of San Angelo Texas
 
Needs Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportNeeds Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportUGPTI
 
Project - Solomon Spur Rail
Project - Solomon Spur RailProject - Solomon Spur Rail
Project - Solomon Spur RailDamian Brandon
 
Crumb Rubber Life Cycle Cost Assessment (LCCA) Project
Crumb Rubber Life Cycle Cost Assessment (LCCA) ProjectCrumb Rubber Life Cycle Cost Assessment (LCCA) Project
Crumb Rubber Life Cycle Cost Assessment (LCCA) Project
Michael R. Barr
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
Crosstown TO
 
Four Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force PresentationFour Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force Presentation
Northern Virginia Regional Commission
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Crosstown TO
 
A Central District Water Plant
A Central District Water PlantA Central District Water Plant
A Central District Water Plant
McKenney's Inc
 

What's hot (20)

Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meeting
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 
Scott Smith-CV
Scott Smith-CVScott Smith-CV
Scott Smith-CV
 
Project Listing-Career-2016 (V2)
Project Listing-Career-2016 (V2)Project Listing-Career-2016 (V2)
Project Listing-Career-2016 (V2)
 
Van Dyk H - WSP PB Master CV
Van Dyk H - WSP PB Master CVVan Dyk H - WSP PB Master CV
Van Dyk H - WSP PB Master CV
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank Station
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 
Electromech
Electromech Electromech
Electromech
 
City Council April 3, 2012 Hickory Aquifer Project Update
City Council April 3, 2012 Hickory Aquifer Project UpdateCity Council April 3, 2012 Hickory Aquifer Project Update
City Council April 3, 2012 Hickory Aquifer Project Update
 
Needs Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportNeeds Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status Report
 
Project - Solomon Spur Rail
Project - Solomon Spur RailProject - Solomon Spur Rail
Project - Solomon Spur Rail
 
Crumb Rubber Life Cycle Cost Assessment (LCCA) Project
Crumb Rubber Life Cycle Cost Assessment (LCCA) ProjectCrumb Rubber Life Cycle Cost Assessment (LCCA) Project
Crumb Rubber Life Cycle Cost Assessment (LCCA) Project
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Four Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force PresentationFour Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force Presentation
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
A Central District Water Plant
A Central District Water PlantA Central District Water Plant
A Central District Water Plant
 

Viewers also liked

JUGChennai and Adopt-a-JSR program
JUGChennai and Adopt-a-JSR programJUGChennai and Adopt-a-JSR program
JUGChennai and Adopt-a-JSR program
Rajmahendra Hegde
 
Tabla de posiciones cat. juvenil sala 4
Tabla de posiciones cat. juvenil sala 4Tabla de posiciones cat. juvenil sala 4
Tabla de posiciones cat. juvenil sala 4
TORNEOS INDER GUARNE
 
About Lamborghini:-Untold Bussiness Facts
About Lamborghini:-Untold Bussiness FactsAbout Lamborghini:-Untold Bussiness Facts
About Lamborghini:-Untold Bussiness Facts
Jerin George
 
estrategia_para_la_incorporacion_de_genero_en_sector_ambiental
estrategia_para_la_incorporacion_de_genero_en_sector_ambientalestrategia_para_la_incorporacion_de_genero_en_sector_ambiental
estrategia_para_la_incorporacion_de_genero_en_sector_ambientalGloria Aviles
 
Tabla de posiciones cat. veredal 4
Tabla de posiciones cat. veredal 4Tabla de posiciones cat. veredal 4
Tabla de posiciones cat. veredal 4
TORNEOS INDER GUARNE
 
Dial up your flow
Dial up your flowDial up your flow
Dial up your flow
Wes Eklund
 
Coursera whartonmarketing 2015
Coursera whartonmarketing 2015Coursera whartonmarketing 2015
Coursera whartonmarketing 2015Soon Khei
 
LS Roller Coaster reloaded
LS Roller Coaster reloadedLS Roller Coaster reloaded
LS Roller Coaster reloaded
Carlos Morales Socorro
 
Measuring the agile process improvement
Measuring the agile process improvementMeasuring the agile process improvement
Measuring the agile process improvement
Konstantin Savenkov
 
Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis Deepu Rajan
 

Viewers also liked (12)

JUGChennai and Adopt-a-JSR program
JUGChennai and Adopt-a-JSR programJUGChennai and Adopt-a-JSR program
JUGChennai and Adopt-a-JSR program
 
Test
TestTest
Test
 
Tabla de posiciones cat. juvenil sala 4
Tabla de posiciones cat. juvenil sala 4Tabla de posiciones cat. juvenil sala 4
Tabla de posiciones cat. juvenil sala 4
 
WoD UniGE Programme 5.1
WoD UniGE Programme 5.1WoD UniGE Programme 5.1
WoD UniGE Programme 5.1
 
About Lamborghini:-Untold Bussiness Facts
About Lamborghini:-Untold Bussiness FactsAbout Lamborghini:-Untold Bussiness Facts
About Lamborghini:-Untold Bussiness Facts
 
estrategia_para_la_incorporacion_de_genero_en_sector_ambiental
estrategia_para_la_incorporacion_de_genero_en_sector_ambientalestrategia_para_la_incorporacion_de_genero_en_sector_ambiental
estrategia_para_la_incorporacion_de_genero_en_sector_ambiental
 
Tabla de posiciones cat. veredal 4
Tabla de posiciones cat. veredal 4Tabla de posiciones cat. veredal 4
Tabla de posiciones cat. veredal 4
 
Dial up your flow
Dial up your flowDial up your flow
Dial up your flow
 
Coursera whartonmarketing 2015
Coursera whartonmarketing 2015Coursera whartonmarketing 2015
Coursera whartonmarketing 2015
 
LS Roller Coaster reloaded
LS Roller Coaster reloadedLS Roller Coaster reloaded
LS Roller Coaster reloaded
 
Measuring the agile process improvement
Measuring the agile process improvementMeasuring the agile process improvement
Measuring the agile process improvement
 
Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis
 

Similar to SOME OF THE PROJECTS HANDLED

JA CV 050915 (1) (1)
JA CV 050915 (1) (1)JA CV 050915 (1) (1)
JA CV 050915 (1) (1)John Adams
 
CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016Rolando Garcia
 
Prime consulting group brochure
Prime consulting group brochurePrime consulting group brochure
Prime consulting group brochure
MANOJ PATNE
 
Amended CV of Eng. Ibrahim A.A. march 2015
Amended CV of Eng. Ibrahim A.A.   march 2015Amended CV of Eng. Ibrahim A.A.   march 2015
Amended CV of Eng. Ibrahim A.A. march 2015Ibrahim Consultant
 
company Profile_June 2016
company Profile_June 2016company Profile_June 2016
company Profile_June 2016Tony Martini
 
Piping & Pipeline Designer
Piping & Pipeline DesignerPiping & Pipeline Designer
Piping & Pipeline Designerbharath kumar
 
Prime Consulting Group Profile
Prime Consulting Group ProfilePrime Consulting Group Profile
Prime Consulting Group Profile
MANOJ PATNE
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
Fairfax County
 
Technical_Career_Accomplishments-R._Freeborn
Technical_Career_Accomplishments-R._FreebornTechnical_Career_Accomplishments-R._Freeborn
Technical_Career_Accomplishments-R._FreebornBob Freeborn
 
EN Mr.Rittiporn Pinrod resume(update 13-03-15)
EN Mr.Rittiporn Pinrod resume(update 13-03-15)EN Mr.Rittiporn Pinrod resume(update 13-03-15)
EN Mr.Rittiporn Pinrod resume(update 13-03-15)Rittiporn Pinrod
 
EN Mr.Rittiporn Pinrod resume(update 13-03-15)
EN Mr.Rittiporn Pinrod resume(update 13-03-15)EN Mr.Rittiporn Pinrod resume(update 13-03-15)
EN Mr.Rittiporn Pinrod resume(update 13-03-15)Rittiporn Pinrod
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowMark Oberschmidt
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
Fairfax County
 
Resume - Wan Sazali, PDMS Piping Designer
Resume - Wan Sazali, PDMS Piping DesignerResume - Wan Sazali, PDMS Piping Designer
Resume - Wan Sazali, PDMS Piping DesignerWan Sazali
 
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016Khoirul A'mal Mohd Hanafiah
 

Similar to SOME OF THE PROJECTS HANDLED (20)

CV of F Verschueren - 11-04-2016
CV of F Verschueren - 11-04-2016CV of F Verschueren - 11-04-2016
CV of F Verschueren - 11-04-2016
 
JA CV 050915 (1) (1)
JA CV 050915 (1) (1)JA CV 050915 (1) (1)
JA CV 050915 (1) (1)
 
ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2
 
CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016
 
CV - AGK LinkedIn
CV - AGK LinkedInCV - AGK LinkedIn
CV - AGK LinkedIn
 
Prime consulting group brochure
Prime consulting group brochurePrime consulting group brochure
Prime consulting group brochure
 
Amended CV of Eng. Ibrahim A.A. march 2015
Amended CV of Eng. Ibrahim A.A.   march 2015Amended CV of Eng. Ibrahim A.A.   march 2015
Amended CV of Eng. Ibrahim A.A. march 2015
 
CVAQ5
CVAQ5CVAQ5
CVAQ5
 
company Profile_June 2016
company Profile_June 2016company Profile_June 2016
company Profile_June 2016
 
Piping & Pipeline Designer
Piping & Pipeline DesignerPiping & Pipeline Designer
Piping & Pipeline Designer
 
Prime Consulting Group Profile
Prime Consulting Group ProfilePrime Consulting Group Profile
Prime Consulting Group Profile
 
Nazmy Markos
Nazmy MarkosNazmy Markos
Nazmy Markos
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Technical_Career_Accomplishments-R._Freeborn
Technical_Career_Accomplishments-R._FreebornTechnical_Career_Accomplishments-R._Freeborn
Technical_Career_Accomplishments-R._Freeborn
 
EN Mr.Rittiporn Pinrod resume(update 13-03-15)
EN Mr.Rittiporn Pinrod resume(update 13-03-15)EN Mr.Rittiporn Pinrod resume(update 13-03-15)
EN Mr.Rittiporn Pinrod resume(update 13-03-15)
 
EN Mr.Rittiporn Pinrod resume(update 13-03-15)
EN Mr.Rittiporn Pinrod resume(update 13-03-15)EN Mr.Rittiporn Pinrod resume(update 13-03-15)
EN Mr.Rittiporn Pinrod resume(update 13-03-15)
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
 
Resume - Wan Sazali, PDMS Piping Designer
Resume - Wan Sazali, PDMS Piping DesignerResume - Wan Sazali, PDMS Piping Designer
Resume - Wan Sazali, PDMS Piping Designer
 
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
 

SOME OF THE PROJECTS HANDLED

  • 1. PROJECTS SUPERVISED: A. Otumara Node for DOMGAS Projects – Construction/fabrication of Central Processing Facility (3nos CPF Modules of 27,000 tons) which includes Piping, structural, Equipment Installation works at Daewoo Nigeria Fab. Yard and skidding/installation, hookup and commissioning at Otumara CPF site – 98% completed. B. Otumara Node for DOMGAS Projects; Pile Installation works for CPF-01, 02 &03 and Pipe Rack A/B, Exist Flowstation & Swamp area piling– 2014. C. 3 Layer PE coating and Concrete coating of 12”, 6”, 4” and 2” line pipe for Otumara Saghara-Escravos AG Solution Pipeline Project – 2012. D. Site/Yard material audits at contractor’s yards – 2012. E. Scoping/Project evaluation for Southern Swamp Associated Gas Solution projects F. Drawing development/project scoping for Ogbotobo Flow lines/facility Rehabilitation works – 2011. J. Batan West Re-Entry Projects (2011): 1) Replacement of 4” (7 NOs) and 6” (1 NO) Vandalized Flow Lines at Batan Flow station.  River-Crossings of 4 inch and 6 inch vandalized flow lines at Batan flow station.  The ROW ditching and backfilling of the flow lines.  Pressure testing, hook up, wellhead platform and riser fabrication. 2) Replacements of 7 swamp WellHead Platforms to Ajuju 6T & 1L/S & Batan 2S, 5T, 6S & 9T. 3) Scoping, Designing, Scheduling, Planning and supervising of the 2 inch station waterlines, and 3 inch fire hydrant lines. 4) Designing and Selection of the Pressure Boosting System of the Hydrant Lines 5) Station Maintenance Works at Batan Flow Station.