PROJECTS SUPERVISED:
A. Otumara Node for DOMGAS Projects – Construction/fabrication of Central
Processing Facility (3nos CPF Modules of 27,000 tons) which includes Piping,
structural, Equipment Installation works at Daewoo Nigeria Fab. Yard and
skidding/installation, hookup and commissioning at Otumara CPF site – 98%
completed.
B. Otumara Node for DOMGAS Projects; Pile Installation works for CPF-01, 02 &03
and Pipe Rack A/B, Exist Flowstation & Swamp area piling– 2014.
C. 3 Layer PE coating and Concrete coating of 12”, 6”, 4” and 2” line pipe for
Otumara Saghara-Escravos AG Solution Pipeline Project – 2012.
D. Site/Yard material audits at contractor’s yards – 2012.
E. Scoping/Project evaluation for Southern Swamp Associated Gas Solution projects
F. Drawing development/project scoping for Ogbotobo Flow lines/facility Rehabilitation
works – 2011.
J. Batan West Re-Entry Projects (2011):
1) Replacement of 4” (7 NOs) and 6” (1 NO) Vandalized Flow Lines at Batan Flow station.
 River-Crossings of 4 inch and 6 inch vandalized flow lines at Batan flow station.
 The ROW ditching and backfilling of the flow lines.
 Pressure testing, hook up, wellhead platform and riser fabrication.
2) Replacements of 7 swamp WellHead Platforms to Ajuju 6T & 1L/S & Batan 2S, 5T, 6S &
9T.
3) Scoping, Designing, Scheduling, Planning and supervising of the 2 inch station waterlines,
and 3 inch fire hydrant lines.
4) Designing and Selection of the Pressure Boosting System of the Hydrant Lines
5) Station Maintenance Works at Batan Flow Station.

SOME OF THE PROJECTS HANDLED

  • 1.
    PROJECTS SUPERVISED: A. OtumaraNode for DOMGAS Projects – Construction/fabrication of Central Processing Facility (3nos CPF Modules of 27,000 tons) which includes Piping, structural, Equipment Installation works at Daewoo Nigeria Fab. Yard and skidding/installation, hookup and commissioning at Otumara CPF site – 98% completed. B. Otumara Node for DOMGAS Projects; Pile Installation works for CPF-01, 02 &03 and Pipe Rack A/B, Exist Flowstation & Swamp area piling– 2014. C. 3 Layer PE coating and Concrete coating of 12”, 6”, 4” and 2” line pipe for Otumara Saghara-Escravos AG Solution Pipeline Project – 2012. D. Site/Yard material audits at contractor’s yards – 2012. E. Scoping/Project evaluation for Southern Swamp Associated Gas Solution projects F. Drawing development/project scoping for Ogbotobo Flow lines/facility Rehabilitation works – 2011. J. Batan West Re-Entry Projects (2011): 1) Replacement of 4” (7 NOs) and 6” (1 NO) Vandalized Flow Lines at Batan Flow station.  River-Crossings of 4 inch and 6 inch vandalized flow lines at Batan flow station.  The ROW ditching and backfilling of the flow lines.  Pressure testing, hook up, wellhead platform and riser fabrication. 2) Replacements of 7 swamp WellHead Platforms to Ajuju 6T & 1L/S & Batan 2S, 5T, 6S & 9T. 3) Scoping, Designing, Scheduling, Planning and supervising of the 2 inch station waterlines, and 3 inch fire hydrant lines. 4) Designing and Selection of the Pressure Boosting System of the Hydrant Lines 5) Station Maintenance Works at Batan Flow Station.