SlideShare a Scribd company logo
Final Design:
Small PV System for Cabin in Boone, NC
James Koehler
Scanlin
1) Intro
For this project, a small battery-based, grid-tied PV system was designed for a small cabin in the Ap-
palachian Mountains of Boone, NC. It will include a 24V battery-based system with a MPPT controller,
60 cell modules and a connection to the grid.
2) Loads
These loads will all be AC-powered with the exception of heating, which is assumed to be powered by an
alternative energy source (grid or other).
3) Modules
For this system, Canadian Solar polycrystalline 260W, 24V, 60-cell solar modules were used. The
cost of a module is $0.90 per Watt, or $233.
4) Array Sizing
Using the Excel spread sheet, it was found that 2 series strings with 2 modules per string (4
total) would be required to power the loads when using a MPPT controller with a maximum input voltage
of 150 volts.


5) Array Schematic
6) Array Wire Sizing Calculations
Maximum amperage in each series string will be Isc x 1.56 = 8.99 x 1.56 = 14.02 A. Therefore a
90 C, wet-rated, and sunlight resistant USE-2 or PV wire must be selected that has a temperature derated
ampacity greater than 14.02 A. # 14 USE-2 copper wire in free air has a rated ampacity of 35 amps at 86
degrees and should be enough to carry the 14.02 amps. However, since the conductors will be located in
the hot junction boxes the conductors will need to be temperature derated to a temperature of 141 – 158 F.
This requires a 58% derating or 35 x .58 = 20.3 A. Even with this derating, # 14 USE-2 conductors in
free air would be enough to carry the maximum amperage and as a result # 14 USE-2 will be used.
7) Rack
A DPW Power Rail P4 racking system will be used to mount these modules to the roof of the cabin. The
modules each have a width of 3.225 feet; since we have 4 total modules, the racking system will have to
have a minimum length of 13 feet (156”). So, there would need to be two 13-foot racks mounted to the
roof, which would cost roughly $96 ($48 each).
Important Module Specs
*8.99 Isc
*37 Voc
*0.58 temperature derating
for record cold temp of
141-158 F
#14 USE-2 Cop-
per wire: 90C, wet
rated, sunlight
resistant
8) Combiner Box and Overcurrent Protection Devices
Since there are 2 module series string, there will be 2 overcurrent protections in the combiner box of this
system. The fuses or circuit breakers must be greater than the short circuit current of the module multi-
plied by 1.56, and the fuse or circuit breaker size must be less than the series fuse rating of the module.
The Isc of the module is 8.99 amps and the series fuse rating is 15 amps.
Also, we can use circuit breakers only if the open circuit voltage Voc multiplied by the number
of module in the series string and by 1.25 (for record cold temperatures), is less than 150 Volts.
As the result is smaller than 150 V, we can use circuit breakers in the combiner box. Therefore we need 2
– 15 amp circuit breakers with a DC rating of 150 volts, which would cost roughly $22.70.
These 2 circuit breakers will be put in the MidNite Solar MNPV3 combiner box, which costs $99. The
MidNite lightning arrestor shown in schematic on the next page costs $250. Below are the characteristics
of this combiner box:
9) Array Schematic and Combiner Box
Name Amps
DC Voltage
Rating
Cost
MidNite Solar
MNEPV
15 150 $11.35
Max 150
VDC
breakers
Max out-
put cir-
cuits
Max out-
put wire
size
MNPV
combiner
dimensions
Cost
3 1 #1/0 11x5x4 $99
10) Wire Sizing between Combiner Box and BOS Components
The conductors coming out of the combiner box and traveling to the house will have to carry the Isc X
1.56 x 2 strings or 8.99 A x 1.56 x 2 = 28.04 Amps. Since these conductors are in a potentially hot envi-
ronment inside the combiner box, they will have to be temperature derated and will need to have a tem-
perature derated capacity of 28.04 amps. # 8 – 90 C conductors in conduit have an ampacity of 55 amps at
86 F, but since they will be installed inside a potentially hot combiner box we will derate the ampacity by
multiplying by .58. 55 x .58 = 31.9, which is greater than the 28.04 A required. They will be installed in
conduit which will run between the combiner box and the house. We assume that there is 100’ distance
between the combiner box and the BOS components. To avoid a voltage drop greater than 2%, we are
going to size the wire by calculating the Voltage Drop Index. We should use the Imp coming out of the
combiner box and do not have to multiply by 1.56. Since this is not a code violation or safety issue we
just want to model typical performance.
Using the VDI Chart, the copper wire size #4 will carry the Imp with no more than a 2 % voltage drop
and therefore # 4 will be used.
11) DC Junction Box and Charge Controller
The DC junction Box will be an E-panel from MidNite Solar and will include a Positive bus bar
to transition from the larger #4 to small gauge wires that will be easier to work with and a 30 amp breaker
on the incoming side of the charge controller. This breaker needs to be larger than the Isc x 1.56 amps
coming out of the combiner box, but less than the ampacity of the wire used, which will be #12 which can
carry the 30 amps that are coming into the DC junction box. We will have to have 2 of these: 1 before the
charge controller and one after going to the batteries.
The charge controller used will be MidNite Solar’s The KID, which costs $315. The specifications are
listed below:
The two breakers used will also cost a combined total of $22.70. Specifications are listed below:
Name Amps
DC Voltage
Rating
Cost
MidNite Solar
MNEPV
30 150 $11.35
These breakers will be installed in a MidNite Solar Mini-DC Disconnect Power Center MNDC250, which
costs $184.92. The specifications are listed below:
12) Array, Combiner and DC Junction Schematic
Combiner Box
DC Junction Box
13) Inverter Sizing
The total of AC power in the cabin is 2,912 W. Therefore, the continuous watts of the inverter must be
greater than or equal to 2,912 W. So, the Sunny Boy SMA SB5000TL-US-22 3,200 W inverter was cho-
sen, which costs around $2,000. Specifications are listed below:
14) Breaker Sizing for Inverter Wiring
The minimum breaker size for inverter wiring is the maximum DC wattage divided by the cut-out voltage
with the maximum DC wattage, which is equal to the maximum continuous AC output wattage divided by
the inverter efficiency. Moreover, it has to be less than the ampacity of the wire use (#4/0) 90 C conductor
which is 260 amps.
There is only the DC rated circuit breaker MNEDC 250, which costs $86.18. Specs listed below:
Amps Poles Voltage Rating (DC) Cost
250 1 125 $86.18
15) Battery Sizing
For this design, 4 “L-16” 350 Ah batteries would have to be used. This would create a com-
bined cost of $152.50.
Specifications are listed below:
16) Final Schematic
Total costs listed below:
17) Cost Estimate and Conclusion
Total cost of system: $4,160.90 (not including taxes and wire costs)
Cost of power: $4,160.90/1,040W = $4 per Watt
Batteries $152.50
Rack $96
260 A Breaker $86.18
Sunny Boy 3,200 W Inverter $2,000
DC Junction Box $184.82
4 20-30A Breakers $45.4
Charge Controller $315
Lighting Arrestor $250
4 260W Modules $932
Combiner Box $99

More Related Content

What's hot

How to reach electricity to our homes
How to reach electricity to our homesHow to reach electricity to our homes
How to reach electricity to our homes
Abdulwali Mohamed Salad
 
Electrical services
Electrical servicesElectrical services
Electrical services
Piyush Purshottam Lalwani
 
How to check the quality of miniature circuit breaker (mcb)
How to check the quality of miniature circuit breaker (mcb)How to check the quality of miniature circuit breaker (mcb)
How to check the quality of miniature circuit breaker (mcb)
Guangzhou Shilin Electrical Co., Ltd.
 
Electrical household wiring.
Electrical household wiring.Electrical household wiring.
Electrical household wiring.
mvenkat2016
 
WIRING SYSTEM
WIRING SYSTEMWIRING SYSTEM
WIRING SYSTEM
Md Emran Saidi
 
132 gss ppt
132 gss ppt132 gss ppt
132 gss ppt
hunk143
 
Perfiles
PerfilesPerfiles
Electrical testing
Electrical testingElectrical testing
Electrical testing
Aarjun Singh Panesar
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices ppt
ZuhairQadri
 
electricity supply ppt
electricity supply pptelectricity supply ppt
electricity supply ppt
sameerchat
 
400 kV GSS RRVPNL , Surpura jodhpur
400 kV GSS RRVPNL , Surpura jodhpur400 kV GSS RRVPNL , Surpura jodhpur
400 kV GSS RRVPNL , Surpura jodhpur
MANISH BISHNOI
 
eIQ Datasheet - 350-WATT DC-TO-DC Converter Module
eIQ Datasheet - 350-WATT DC-TO-DC Converter ModuleeIQ Datasheet - 350-WATT DC-TO-DC Converter Module
eIQ Datasheet - 350-WATT DC-TO-DC Converter Module
xmeteorite
 
Earthing
EarthingEarthing
Earthing
AKANSHA GURELE
 
Production and distribution of electricity
Production and distribution of electricityProduction and distribution of electricity
Production and distribution of electricity
Vesa Linja-aho
 
Electromechanical energy conversion principles
Electromechanical energy conversion principlesElectromechanical energy conversion principles
Electromechanical energy conversion principles
Vijay Raskar
 
Bssss
BssssBssss
Household wiring
Household wiringHousehold wiring
Household wiring
Rohan Nagpal
 
Failure of fuse & mcb
Failure of fuse & mcbFailure of fuse & mcb
Failure of fuse & mcb
Abhay Pratap Singh
 

What's hot (18)

How to reach electricity to our homes
How to reach electricity to our homesHow to reach electricity to our homes
How to reach electricity to our homes
 
Electrical services
Electrical servicesElectrical services
Electrical services
 
How to check the quality of miniature circuit breaker (mcb)
How to check the quality of miniature circuit breaker (mcb)How to check the quality of miniature circuit breaker (mcb)
How to check the quality of miniature circuit breaker (mcb)
 
Electrical household wiring.
Electrical household wiring.Electrical household wiring.
Electrical household wiring.
 
WIRING SYSTEM
WIRING SYSTEMWIRING SYSTEM
WIRING SYSTEM
 
132 gss ppt
132 gss ppt132 gss ppt
132 gss ppt
 
Perfiles
PerfilesPerfiles
Perfiles
 
Electrical testing
Electrical testingElectrical testing
Electrical testing
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices ppt
 
electricity supply ppt
electricity supply pptelectricity supply ppt
electricity supply ppt
 
400 kV GSS RRVPNL , Surpura jodhpur
400 kV GSS RRVPNL , Surpura jodhpur400 kV GSS RRVPNL , Surpura jodhpur
400 kV GSS RRVPNL , Surpura jodhpur
 
eIQ Datasheet - 350-WATT DC-TO-DC Converter Module
eIQ Datasheet - 350-WATT DC-TO-DC Converter ModuleeIQ Datasheet - 350-WATT DC-TO-DC Converter Module
eIQ Datasheet - 350-WATT DC-TO-DC Converter Module
 
Earthing
EarthingEarthing
Earthing
 
Production and distribution of electricity
Production and distribution of electricityProduction and distribution of electricity
Production and distribution of electricity
 
Electromechanical energy conversion principles
Electromechanical energy conversion principlesElectromechanical energy conversion principles
Electromechanical energy conversion principles
 
Bssss
BssssBssss
Bssss
 
Household wiring
Household wiringHousehold wiring
Household wiring
 
Failure of fuse & mcb
Failure of fuse & mcbFailure of fuse & mcb
Failure of fuse & mcb
 

Similar to Small_Cabin_PV_Design

presentations for the project of solar energy
presentations for the project of solar energypresentations for the project of solar energy
presentations for the project of solar energy
H2SO43
 
The Economics of Parallel System Design in Commercial-Scale Solar Plants
The Economics of Parallel System Design in Commercial-Scale Solar PlantsThe Economics of Parallel System Design in Commercial-Scale Solar Plants
The Economics of Parallel System Design in Commercial-Scale Solar Plants
xmeteorite
 
Solar ppt
Solar pptSolar ppt
17 mse011 solar inverter
17 mse011 solar inverter17 mse011 solar inverter
17 mse011 solar inverter
paneliya sagar
 
ISRO Funded IEEE Paper
ISRO Funded IEEE PaperISRO Funded IEEE Paper
ISRO Funded IEEE Paper
PRAJAKTA SHENDAGE
 
IRJET- Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET-  	  Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...IRJET-  	  Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET- Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET Journal
 
1232d
1232d1232d
Solar junction boxes jmv lps ltd
Solar junction boxes   jmv lps ltdSolar junction boxes   jmv lps ltd
Solar junction boxes jmv lps ltd
Mahesh Chandra Manav
 
Solar junction boxes jmv lps ltd
Solar junction boxes   jmv lps ltdSolar junction boxes   jmv lps ltd
Solar junction boxes jmv lps ltd
Mahesh Chandra Manav
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DC
Mahesh Chandra Manav
 
High voltage module
High voltage moduleHigh voltage module
High voltage module
GARANG MABIOR
 
Solar Panel Installations
Solar Panel InstallationsSolar Panel Installations
Solar Panel Installations
Chad Weiss
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1
Murugappa Group
 
Project body(powersupply+timer+filter7thsem)
Project body(powersupply+timer+filter7thsem)Project body(powersupply+timer+filter7thsem)
Project body(powersupply+timer+filter7thsem)
kaushikbandopadhyay
 
Afd Parts Operation
Afd Parts OperationAfd Parts Operation
Afd Parts Operation
guesteffa35
 
Afd Parts Operation
Afd Parts OperationAfd Parts Operation
Afd Parts Operation
Najam Siddiqui
 
Single phase power systems
Single phase power systemsSingle phase power systems
Single phase power systems
Bibek Chouhan
 
Single phase power systems
Single phase power systemsSingle phase power systems
Single phase power systems
Bibek Chouhan
 
Single phase power systems
Single phase power systemsSingle phase power systems
Single phase power systems
Bibek Chouhan
 
Inverter selection
Inverter selectionInverter selection
Inverter selection
Jay Ranvir
 

Similar to Small_Cabin_PV_Design (20)

presentations for the project of solar energy
presentations for the project of solar energypresentations for the project of solar energy
presentations for the project of solar energy
 
The Economics of Parallel System Design in Commercial-Scale Solar Plants
The Economics of Parallel System Design in Commercial-Scale Solar PlantsThe Economics of Parallel System Design in Commercial-Scale Solar Plants
The Economics of Parallel System Design in Commercial-Scale Solar Plants
 
Solar ppt
Solar pptSolar ppt
Solar ppt
 
17 mse011 solar inverter
17 mse011 solar inverter17 mse011 solar inverter
17 mse011 solar inverter
 
ISRO Funded IEEE Paper
ISRO Funded IEEE PaperISRO Funded IEEE Paper
ISRO Funded IEEE Paper
 
IRJET- Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET-  	  Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...IRJET-  	  Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
IRJET- Photovoltaic 10MW Power Plant Simulation & Design using Mathwork &...
 
1232d
1232d1232d
1232d
 
Solar junction boxes jmv lps ltd
Solar junction boxes   jmv lps ltdSolar junction boxes   jmv lps ltd
Solar junction boxes jmv lps ltd
 
Solar junction boxes jmv lps ltd
Solar junction boxes   jmv lps ltdSolar junction boxes   jmv lps ltd
Solar junction boxes jmv lps ltd
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DC
 
High voltage module
High voltage moduleHigh voltage module
High voltage module
 
Solar Panel Installations
Solar Panel InstallationsSolar Panel Installations
Solar Panel Installations
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1
 
Project body(powersupply+timer+filter7thsem)
Project body(powersupply+timer+filter7thsem)Project body(powersupply+timer+filter7thsem)
Project body(powersupply+timer+filter7thsem)
 
Afd Parts Operation
Afd Parts OperationAfd Parts Operation
Afd Parts Operation
 
Afd Parts Operation
Afd Parts OperationAfd Parts Operation
Afd Parts Operation
 
Single phase power systems
Single phase power systemsSingle phase power systems
Single phase power systems
 
Single phase power systems
Single phase power systemsSingle phase power systems
Single phase power systems
 
Single phase power systems
Single phase power systemsSingle phase power systems
Single phase power systems
 
Inverter selection
Inverter selectionInverter selection
Inverter selection
 

Small_Cabin_PV_Design

  • 1. Final Design: Small PV System for Cabin in Boone, NC James Koehler Scanlin
  • 2. 1) Intro For this project, a small battery-based, grid-tied PV system was designed for a small cabin in the Ap- palachian Mountains of Boone, NC. It will include a 24V battery-based system with a MPPT controller, 60 cell modules and a connection to the grid. 2) Loads These loads will all be AC-powered with the exception of heating, which is assumed to be powered by an alternative energy source (grid or other). 3) Modules For this system, Canadian Solar polycrystalline 260W, 24V, 60-cell solar modules were used. The cost of a module is $0.90 per Watt, or $233.
  • 3. 4) Array Sizing Using the Excel spread sheet, it was found that 2 series strings with 2 modules per string (4 total) would be required to power the loads when using a MPPT controller with a maximum input voltage of 150 volts. 

  • 4. 5) Array Schematic 6) Array Wire Sizing Calculations Maximum amperage in each series string will be Isc x 1.56 = 8.99 x 1.56 = 14.02 A. Therefore a 90 C, wet-rated, and sunlight resistant USE-2 or PV wire must be selected that has a temperature derated ampacity greater than 14.02 A. # 14 USE-2 copper wire in free air has a rated ampacity of 35 amps at 86 degrees and should be enough to carry the 14.02 amps. However, since the conductors will be located in the hot junction boxes the conductors will need to be temperature derated to a temperature of 141 – 158 F. This requires a 58% derating or 35 x .58 = 20.3 A. Even with this derating, # 14 USE-2 conductors in free air would be enough to carry the maximum amperage and as a result # 14 USE-2 will be used. 7) Rack A DPW Power Rail P4 racking system will be used to mount these modules to the roof of the cabin. The modules each have a width of 3.225 feet; since we have 4 total modules, the racking system will have to have a minimum length of 13 feet (156”). So, there would need to be two 13-foot racks mounted to the roof, which would cost roughly $96 ($48 each). Important Module Specs *8.99 Isc *37 Voc *0.58 temperature derating for record cold temp of 141-158 F #14 USE-2 Cop- per wire: 90C, wet rated, sunlight resistant
  • 5. 8) Combiner Box and Overcurrent Protection Devices Since there are 2 module series string, there will be 2 overcurrent protections in the combiner box of this system. The fuses or circuit breakers must be greater than the short circuit current of the module multi- plied by 1.56, and the fuse or circuit breaker size must be less than the series fuse rating of the module. The Isc of the module is 8.99 amps and the series fuse rating is 15 amps. Also, we can use circuit breakers only if the open circuit voltage Voc multiplied by the number of module in the series string and by 1.25 (for record cold temperatures), is less than 150 Volts. As the result is smaller than 150 V, we can use circuit breakers in the combiner box. Therefore we need 2 – 15 amp circuit breakers with a DC rating of 150 volts, which would cost roughly $22.70. These 2 circuit breakers will be put in the MidNite Solar MNPV3 combiner box, which costs $99. The MidNite lightning arrestor shown in schematic on the next page costs $250. Below are the characteristics of this combiner box: 9) Array Schematic and Combiner Box Name Amps DC Voltage Rating Cost MidNite Solar MNEPV 15 150 $11.35 Max 150 VDC breakers Max out- put cir- cuits Max out- put wire size MNPV combiner dimensions Cost 3 1 #1/0 11x5x4 $99
  • 6. 10) Wire Sizing between Combiner Box and BOS Components The conductors coming out of the combiner box and traveling to the house will have to carry the Isc X 1.56 x 2 strings or 8.99 A x 1.56 x 2 = 28.04 Amps. Since these conductors are in a potentially hot envi- ronment inside the combiner box, they will have to be temperature derated and will need to have a tem- perature derated capacity of 28.04 amps. # 8 – 90 C conductors in conduit have an ampacity of 55 amps at 86 F, but since they will be installed inside a potentially hot combiner box we will derate the ampacity by multiplying by .58. 55 x .58 = 31.9, which is greater than the 28.04 A required. They will be installed in conduit which will run between the combiner box and the house. We assume that there is 100’ distance between the combiner box and the BOS components. To avoid a voltage drop greater than 2%, we are going to size the wire by calculating the Voltage Drop Index. We should use the Imp coming out of the combiner box and do not have to multiply by 1.56. Since this is not a code violation or safety issue we just want to model typical performance. Using the VDI Chart, the copper wire size #4 will carry the Imp with no more than a 2 % voltage drop and therefore # 4 will be used. 11) DC Junction Box and Charge Controller The DC junction Box will be an E-panel from MidNite Solar and will include a Positive bus bar to transition from the larger #4 to small gauge wires that will be easier to work with and a 30 amp breaker on the incoming side of the charge controller. This breaker needs to be larger than the Isc x 1.56 amps coming out of the combiner box, but less than the ampacity of the wire used, which will be #12 which can carry the 30 amps that are coming into the DC junction box. We will have to have 2 of these: 1 before the charge controller and one after going to the batteries.
  • 7. The charge controller used will be MidNite Solar’s The KID, which costs $315. The specifications are listed below: The two breakers used will also cost a combined total of $22.70. Specifications are listed below: Name Amps DC Voltage Rating Cost MidNite Solar MNEPV 30 150 $11.35
  • 8. These breakers will be installed in a MidNite Solar Mini-DC Disconnect Power Center MNDC250, which costs $184.92. The specifications are listed below: 12) Array, Combiner and DC Junction Schematic Combiner Box DC Junction Box
  • 9. 13) Inverter Sizing The total of AC power in the cabin is 2,912 W. Therefore, the continuous watts of the inverter must be greater than or equal to 2,912 W. So, the Sunny Boy SMA SB5000TL-US-22 3,200 W inverter was cho- sen, which costs around $2,000. Specifications are listed below: 14) Breaker Sizing for Inverter Wiring The minimum breaker size for inverter wiring is the maximum DC wattage divided by the cut-out voltage with the maximum DC wattage, which is equal to the maximum continuous AC output wattage divided by the inverter efficiency. Moreover, it has to be less than the ampacity of the wire use (#4/0) 90 C conductor which is 260 amps. There is only the DC rated circuit breaker MNEDC 250, which costs $86.18. Specs listed below: Amps Poles Voltage Rating (DC) Cost 250 1 125 $86.18
  • 10. 15) Battery Sizing For this design, 4 “L-16” 350 Ah batteries would have to be used. This would create a com- bined cost of $152.50. Specifications are listed below:
  • 11. 16) Final Schematic Total costs listed below:
  • 12. 17) Cost Estimate and Conclusion Total cost of system: $4,160.90 (not including taxes and wire costs) Cost of power: $4,160.90/1,040W = $4 per Watt Batteries $152.50 Rack $96 260 A Breaker $86.18 Sunny Boy 3,200 W Inverter $2,000 DC Junction Box $184.82 4 20-30A Breakers $45.4 Charge Controller $315 Lighting Arrestor $250 4 260W Modules $932 Combiner Box $99