SlideShare a Scribd company logo
P R E S E N T E D B Y
SEEING THE BIG PICTURE:
Best practices for contracting and
construction risk management for 2021
Members of the American Bar Association Forum on Construction Law:
Jeremy S. Baker, Esquire/Robin Goldberg Banks, Esquire/Patrick J. O’Connor, Esquire
Moderator: Claramargaret H. Groover, Esquire
CMA Focus21
CMAA Focus21
Statement of Purpose
» Define and understand the role of CM advisor under agreements
such as AIA Document C132-2019.
» Define and understand the CMAR’s role under agreements such
as AIA Document A133-209 or A134-2019
» Identify and protect against construction risks likely to occur
» Identify
» Identify and understand insurance applicable to project risks
2
CMA Focus21
CMAA Focus21
CMAA Member Benefits with ABA Forum
3
CMAA and ABA Forum Member Benefits
CMAA members discount on Forum publications
15% with special code
https://www.americanbar.org/groups/departmentsoffices/publishing/ci-book-catalog/
CM Advisor in Construction
Administration
CMA Focus21
CMAA Focus21
AIA’s 2019 CMa Documents
» Owner-Contractor Agreement
- A132-2019: Owner-Contractor Agreement
- A132-2019 Exhibit A: Insurance & Bonds Exhibit
- A132-2019 Exhibit B: Cost of Work Determination
- A232-2019: General Conditions
- E235-2019: Sustainable Projects Exhibit
» Owner-Architect Agreement: B132-2019
» Owner-CMa Agreement: C132-2019
» CMa-Specific Forms
- G731-2019 (Change Order, CMa Edition)
- G732-2019 (Application and Certificate for Payment, CMa Edition)
- G733-2019 (CCD, CMa Edition)
- G734-2019 (Certificate of Substantial Completion, CMa Edition)
5
CMA Focus21
CMAA Focus21
CMa Similarities to Architect
Standard of Care
The Construction Manager shall perform its services consistent with
the skill and care ordinarily provided by construction managers
practicing in the same or similar locality under the same or similar
circumstances. The Construction Manager shall perform its services
as expeditiously as is consistent with such skill and care and the
orderly progress of the Project. C132-2019, §2.2
6
CMA Focus21
CMAA Focus21
CMa Similarities to Architect
» Review shop drawings and other submittals
The Construction Manager shall promptly review all Shop Drawings, Product Data, Samples and other
submittals from the Contractors for compliance with the submittal requirements of the Contracts, coordinate
submittals with information contained in related documents, and transmit to the Architect those that the
Construction Manager recommends for approval… C132-2019, § 3.3.20
» Review and certify payment applications
…the Construction Manager shall review and certify the amounts due the respective Contractors… C132-2019,
§3.3.12.2
7
CMA Focus21
CMAA Focus21
CMa Similarities to Architect
» CMa’s certification language is the same as that for a certifying
architect
The Construction Manager’s certification for payment shall constitute a representation to the Owner, based on
the Construction Manager’s evaluations of the Work and on the data comprising the Contractors’ Applications
for Payment, that, to the best of the Construction Manager’s knowledge, information and belief, the Work has
progressed to the point indicated, the quality of the Work is in accordance with the Contract Documents, and
the Contractors are entitled to payment in the amount certified… C132-2019, §3.3.12.3
» CMa shall provide professional liability insurance for CMa’s errors
and omissions
The Construction Manager shall maintain the following insurance until termination of this Agreement...
Professional Liability covering negligent acts, errors and omissions in the performance of professional
services with policy limits of not less than ($ ) per claim and ($ ) in the aggregate. C132-2019, §§ 2.8, 2.8.5
8
CMA Focus21
CMAA Focus21
CMa Similarities to Contractor/CMAR
» Maintain daily log of weather, labor force, work performed, issues
that arise
The Construction Manager shall keep a daily log containing a record of weather, each Contractor’s Work on
the site, number of workers, identification of equipment, Work accomplished, problems encountered, and
other similar relevant data as the Owner may require. C132-2019, § 3.3.21
» Handle delivery, storage, security of materials and equipment at
the site
The Construction Manager shall arrange for the delivery, storage, protection and security of Owner-purchased
materials, systems and equipment that are a part of the Project until such items are incorporated into the
Work. C132-2019, § 3.3.23
9
CMA Focus21
CMAA Focus21
CMa Similarities to Contractor/CMAR
» Schedule and coordinate overall construction sequence and
allocate on-site storage (lay down) space
…utilizing information from the Contractors, the Construction Manager shall review, analyze, schedule and
coordinate the overall sequence of construction and assignment of space in areas where the Contractors are
performing Work. C132-2019, § 3.3.7
» Provide general liability and other coverages
The Construction Manager shall maintain the following insurance until termination of this Agreement...
Commercial General Liability with policy limits of not less than ($ ) for each occurrence and ($ ) in the
aggregate for bodily injury and property damage… the Construction Manager shall cause the… policies for
Commercial General Liability… to include the Owner as an additional insured… C132-2019, §§ 2.8, 2.8.1, 2.8.6
10
CMA Focus21
CMAA Focus21
CMa-Specific General Conditions: A232
» CMa Performs Functions Traditionally Reserved for Architect
- Receiving prompt reports of any errors, inconsistencies or omissions in the Contract Documents
discovered by the Contactor. A232-2019, §3.2.2
- Assessing whether substitutions proposed by the Contractor are acceptable. A232-2019, § 3.4.2
- Investigating concealed or unknown conditions. A232-2019, § 3.7.4
- Receiving certifications from the Contractor’s design professional, if any. A232-2019, § 3.12.10.2.
- Reviewing and certifying Applications for Payment or withholding Certificates for Payment. A232-
2019, §§ 4.2.7, 9.4, 9.5
- Rejecting Work that does not conform to the Contract Documents. A232-2019, § 4.2.8
- Reviewing the Contractor’s submittals. A232-2019, §§ 4.2.10, 4.2.11
- Conducting inspections to determine the date or dates of Substantial Completion and the date of final
completion. A232-2019, §§ 4.2.16, 9.8.3, 9.8.4, 9.10.1
- Signing Change Orders and Construction Change Directives. A232-2019, §§ 7.2, 7.3
11
CMA Focus21
CMAA Focus21
CMa-Specific General Conditions: A232
» CMa More Involved than Architect in Construction Phase
- Owner shall forward all communications to the Contractor through the CMa. A232-2019, §2.3.8
- … Contractor shall cooperate with the CMa in scheduling and performing the Contractor’s Work…
A232-2019, § 3.10.1
- Contractor shall participate with other Contractors, the CMa, and the Owner in reviewing and
coordinating all schedules for incorporation into the Project schedule,,, A232-2019, § 3.10.3
- The Contractor shall coordinate the Contractor’s operations with, and secure the approval of, the
CMa before using any portion of the site. A232-2019, § 3.13.2
- The CMa will schedule and coordinate the activities of the Contractor and other Contractors in
accordance with the latest approved Project schedule. A232-2019, § 4.2.4
- Utilizing the submittal schedule provided by the Contractor, the CMa shall prepare, and revise as
necessary, a Project submittal schedule…A232-2019, § 4.2.9
- CMa will receive and review requests for information from the Contractor, and forward each request
for information to the Architect, with the CMa’s recommendation… A232-2019, § 4.2.21.
12
CMA Focus21
CMAA Focus21
CMa-Specific General Conditions: A232
» Allocation of CMa and Contractor Responsibility
- CMa plays a role in project safety:
» “…The Contractor shall submit the Contractor’s safety program to the Construction Manager for
review and coordination with the safety programs of other Contractors…” A232-2019, § 10.1
- But the CMa’s role in safety is secondary:
» …The Contractor shall be solely responsible for, and have control over, construction means,
methods, techniques, sequences, and procedures... A232-2019, §3.3.1
» The Construction Manager… will not have control over, charge of, or responsibility for, the
construction means, methods, techniques, sequences or procedures, or for the safety precautions
and programs in connection with the Work, since these are solely the Contractor’s rights and
responsibilities under the Contract Documents… A232-2019, §4.2.5
13
CM at Risk (CMAR)
CMA Focus21
CMAA Focus21
CMAR Conundrum
15
Owner – Time
Problem
CMAR – Needs to
price project
based on
incomplete design
CMA Focus21
CMAA Focus21
Liability for Exceeding GMP/Excess Costs
To the extent that the Contract Documents are anticipated to require
further development, the Guaranteed Maximum Price includes the
costs attributable to such further development consistent with the
Contract Documents and reasonably inferable therefrom. Such
further development does not include changes in scope, systems,
kinds and quality of materials, finishes, or equipment, all of which, if
required, shall be incorporated by Change Order. A133-2019
§ 3.2.2; A134-2019, § 3.2.4
16
CMA Focus21
CMAA Focus21
New CMAR Preconstruction Phase Responsibilities
A133-2019 and A134-2019, § 3.1.14 Other Preconstruction Services.
Insert a description of any other Preconstruction Phase services to be provided by the
Construction Manager, or reference an exhibit attached to this document.
(Describe any other Preconstruction Phase services, such as providing cash flow projections,
development of a project information management system, early selection or procurement of
subcontractors, etc.)
A133-2019 and A134-2019, § 3.1.3.2 … The Construction Manager shall consult with the
Architect regarding professional services to be provided by the Construction Manager during the
Construction Phase.
17
CMA Focus21
CMAA Focus21
New CMAR Preconstruction Phase Responsibilities
A133-2019 and A134-2019, § 3.1.3.3 The Construction Manager shall assist the Owner and
Architect in establishing building information modeling and digital data protocols for the Project,
using AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, to
establish the protocols for the development, use, transmission, and exchange of digital data.
A133-2019 and A134-2019, § 3.1.8 The Construction Manager shall provide recommendations
and information to the Owner and Architect regarding equipment, materials, services, and
temporary Project facilities.
A133-2019 and A134-2019, § 3.1.9 The Construction Manager shall provide a staffing plan for
Preconstruction Phase services for the Owner’s review and approval.
A133-2019 and A134-2019, § 3.1.10 If the Owner identified a Sustainable Objective in Article 1,
the Construction Manager shall fulfill its Preconstruction Phase responsibilities as required in
AIA Document E234™–2019, Sustainable Projects Exhibit, Construction Manager as
Constructor Edition, attached to this Agreement.
18
CMA Focus21
CMAA Focus21
New CMAR Preconstruction Standards of Care and
Insurance Requirements
A133-2019 and A134-2019, § 3.1.1 Extent of Responsibility
The Construction Manager shall exercise reasonable care in performing its Preconstruction
Services. …
A133-2019 and A134-2019, § 14.3.1 Preconstruction Phase Insurance
» CGL
» Automobile
» Worker’s Compensation
» Professional Liability
» Other
19
CMA Focus21
CMAA Focus21
Benefits of CMAR
20
• Advise and provide input into
design, cost, constructability,
scheduling, etc.
Preconstruction
• Fabrication of long lead items
• Site preparation
• Exploratory investigation
• Limited construction
Construction
CMA Focus21
CMAA Focus21
New Option to Start CMAR Construction Phase
The Construction Phase shall commence upon the Owner’s execution of the
Guaranteed Maximum Price Amendment or, prior to acceptance of the
Guaranteed Maximum Price proposal, by written agreement of the parties. The
written agreement shall set forth a description of the Work to be performed by
the Construction Manager, and any insurance and bond requirements for Work
performed prior to execution of the Guaranteed Maximum Price Amendment.
A133-2019, § 3.3.1.2; A134-2019, § 3.3.1.2. (approval of Control Estimate in
lieu of acceptance of GMP proposal and execution of GMP Amendment)
21
CMA Focus21
CMAA Focus21
**NEW CMAR FORM FOR 2021 **
G735-2021 - Authorization to Proceed with Early Release Work
» Executed after Owner-CM Agreement, but prior to agreement on GMP or
approval of Control Estimate
» Contains fill points for parties to address specifics of Early Work being
released
» Adopts terms and conditions from Owner-CM Agreement
22
CMA Focus21
CMAA Focus21
General CMAR Construction Phase Updates
» Key 2017 revisions:
• New termination fee provision
• New fill points for liquidated damages and incentives
• More streamlined project communications
• New retainage section
» Generally conform with A102-2017 and A201-2017 revisions:
• For detailed look at 2017 revisions, please visit www.aiacontracts.org/learn
23
CMA Focus21
CMAA Focus21
The Spearin Doctrine – Implied Warranty
24
“if the contractor is bound to build according to plans and
specifications prepared by the owner, the contractor will not be
responsible for the consequences of defects in
the plans and specifications” United States v. Spearin, 248 U.S.
132, 136 (1918).
CMA Focus21
CMAA Focus21
CMAR and the Spearin Doctrine
25
Coghlin Elec. Contractors, Inc. v. Gilbane Bldg. Co., 36 N.E.3d 505
(Mass. 2015)
» CMAR may benefit from implied warranty only:
- Where it acted in good faith reliance on design; and
- Acted reasonably in light of CMAR’s own design responsibilities
» Court looks at:
- Level of participation in design phase of project; and
- Extent to which contract delegates design responsibility
CMA Focus21
CMAA Focus21
Extent to which A201 delegates design responsibility
26
A201-2017, § 3.12.10.1 If professional design services or certifications by a design professional related
to systems, materials, or equipment are specifically required of the Contractor by the Contract
Documents, the Owner and the Architect will specify all performance and design criteria that such
services must satisfy. The Contractor shall be entitled to rely upon the adequacy and accuracy of the
performance and design criteria provided in the Contract Documents. The Contractor shall cause such
services or certifications to be provided by an appropriately licensed design professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, Shop
Drawings, and other submittals prepared by such professional. Shop Drawings, and other submittals
related to the Work, designed or certified by such professional, if prepared by others, shall bear such
professional’s written approval when submitted to the Architect. The Owner and the Architect shall be
entitled to rely upon the adequacy and accuracy of the services, certifications, and approvals performed
or provided by such design professionals, provided the Owner and Architect have specified to the
Contractor the performance and design criteria that such services must satisfy. Pursuant to this
Section 3.12.10, the Architect will review and approve or take other appropriate action on submittals
only for the limited purpose of checking for conformance with information given and the design concept
expressed in the Contract Documents.
CMA Focus21
CMAA Focus21
** New Cost of the Work Payment Applications for 2021**
» G702 GMP-2021 – Application for Payment where the basis of
payment is Cost of the Work with a Guaranteed Maximum Price
» G702 CW-2021 – Application for Payment where the basis of
payment is Cost of the Work
» G703CW-2021 – Cost of the Work Continuation Sheet
27
CMA Focus21
CMAA Focus21
G703-CW Continuation Sheet
28
Claims and Insurance
CMA Focus21
CMAA Focus21
Owner Claims and Risk Management
» Defective design
» Defective construction
» Changes and cost overruns
» Delays
- Force majeure
- COVID-19
30
CMA Focus21
CMAA Focus21
Insurance and Bonds – 2017 Exhibit
31
»Liability limits
»Causes of loss sublimits
»Property insurance sublimits
»Other coverages
»Specifics of optional coverages
»Coverage durations if other than specified
CMA Focus21
CMAA Focus21
Required Provisions to be Completed
» Commercial general liability limits (§ B.3.2.2)
» Automobile liability limits (§ B.3.2.3)
» Employer’s liability limits (§ B.3.2.6)
AND IF
Contractor’s work involves…
►Professional services (professional liability limits) (§ B.3.2.8)
►Transport or use of pollutants (pollution liability limits) (§ B.3.2.9)
►Maritime/aviation risks (limits for such insurance) (§§ B.3.2.11 & 3.2.12)
32
CMA Focus21
CMAA Focus21
CGL – What Must Not Be Excluded or Restricted
» CGL policy shall not exclude or restrict coverage by way of:
- Insured vs. insured exclusion
- Elimination of subcontractor exception (completed operations hazard)
- Broad employee exclusions (e.g. independent contractors)
- Elimination of insured contract exception to the contractual liability
exclusion (employee injuries)
- Prior work endorsements
- Prior injury endorsements
» (§ B.3.2.2)
33
CMA Focus21
CMAA Focus21
Builder’s Risk – Causes of Loss
» “All-risks” ≠ coverage for all risks
» Exhibit prohibits certain exclusions
- Fire, explosion, theft, vandalism, malicious mischief, collapse, earthquake,
flood, or windstorm
» Exhibit permits adjustment of coverage limits
- Prompts specifying sublimits
» Must provide coverage for ensuing loss
- Resulting from bad design or construction
(§ B.2.3.1.1)
34
CMA Focus21
CMAA Focus21
Insurance for Existing Structures (§ B.2.3.3)
» When work involves remodeling an existing structure or
constructing addition to existing structure…
» Owner must purchase all-risks property insurance protecting the
existing structure against same causes of loss to which builder’s
risk policy would respond
» Must maintain until expiration of period for correction of Work
35
CMA Focus21
CMAA Focus21
Optional Property Coverage Extension
» Loss of use, business interruption, delay in completion (§ B.2.4.1)
» Ordinance or law insurance (§ B.2.4.2)
» Expediting cost insurance (§ B.2.4.3)
» Extra expense insurance (§ B.2.4.4)
» Civil authority insurance (§ B.2.4.5)
» Ingress/egress insurance (§ B.2.4.6)
» Soft costs insurance (§ B.2.4.7
36
CMA Focus21
CMAA Focus21
GL Coverage for Specific Scopes of Work
» Residential or habitational exclusions
» Roofing exclusions
» EIFS exclusions
» Earth movement exclusions
» XCU exclusions
(§ B.3.2.2.2)
37
CMA Focus21
CMAA Focus21
Additional Insured Coverage
Why draw a line in the sand at the 2004
ISO forms?
38
CMA Focus21
CMAA Focus21
Excess or Umbrella Insurance
» Contractor can secure liability limits through any combination of
primary and excess or umbrella insurance
» Excess insurance, however, may not dictate exhaustion of the
underlying limits only through actual exhaustion (must permit
functional exhaustion)
39
Questions
CMAA Focus21
Jeremy S. Baker, a Chicago-based construction attorney, founded Baker
Law Group LLC after nearly fifteen years at Schiff Hardin LLP, where he
was a partner and a member of its national Construction Law practice. As
an Adjunct Professor of Law at The John Marshall Law School, he taught
an elective Construction Law course though its Center for Real Estate
Law (2016, 2017, 2018). Jeremy’s practice involves project structuring
across many project delivery methods, plus contract review and
negotiation. He has prosecuted and defended lawsuits in over 30 state
and federal court venues, but he prefers to help clients complete
challenging projects by emphasizing dispute avoidance and early, cost-
efficient resolution of claims. Jeremy is a graduate of the Tulane
University Law School (2002) and the University of California, Santa
Barbara (1999).
___________________________________________________________
Baker Law Group Direct: 312-621-7184
Chicago, Illinois www.buildchicagolaw.com
Jeremy S. Baker
41
CMAA Focus21
Ms. Banks focuses her practice in all areas of construction law, from contract drafting and negotiation
to pre-litigation dispute resolution and complex construction disputes involving mechanics liens,
payment bond claims, and construction defect claims. She represents clients across the construction
spectrum, including design professionals, owners, construction managers, contractors,
subcontractors, and suppliers. In addition to her construction practice, Ms. Banks serves as an
associate outside legal counsel to the AIA Contract Documents Committee.
Ms. Banks frequently presents on topics including updates to, and analysis of, AIA Contract
Documents and risk management for design professionals, construction managers/contractors, and
owners. Ms. Banks has also been published in the Construction Law Handbook, 4th Ed. (Stanley A.
Martin and Leah A. Rochwarg, eds. 2020) and the Maryland State Bar Association Deskbook, 2nd Ed.
(Joseph C. Kovars and Michael Schollaert, eds. 2017) as well as in other books and professional
publications.
Ms. Banks has been recognized by U.S. News – Best Lawyers in America for Construction Law in
Maryland (2020-present) and Maryland Super Lawyers in Construction Litigation (2021) and is a
member of the American Bar Association Forum on the Construction Industry, Maryland State Bar
Association, and District of Columbia Bar Association, and an Allied Member of the National American
Institute of Architects.
_________________________________________________________________________________
Goldberg & Banks, P.C. Direct: 443-940-1342
Baltimore, Maryland Email: rgbanks@gbpclawfirm.com
42
Robin G. Banks
CMAA Focus21
Mr. O’Connor is a partner with the international law firm of Faegre Drinker Biddle & Reath LLP in its
Minneapolis, Minnesota office. He received his B.A. degree from Hamline University in 1975 and his JD
degree from The American University in 1981. He was law clerk to Miles W. Lord, Chief Judge of the
Federal District Court for the District of Minnesota. Mr. O’Connor’s practice focuses on construction,
suretyship and insurance. He has served as litigation or coverage counsel for contractors, owners, design
professionals, and product suppliers in disputes venued in over 25 states and Canada. He also acts as a
mediator, arbitrator and expert witness in construction and insurance disputes. Mr. O’Connor is co-author
of Bruner & O’Connor on Construction Law (West Group 2002), a twelve-volume construction law treatise.
He was an adviser to the American Law Institute’s Restatement of the Law Third, Suretyship and
Guaranty. He works closely with a number of industry organizations on Building Information Modeling and
Integrated Project Delivery initiatives. Mr. O’Connor is former Co-Chair of the BIMForum’s Legal
Subforum. Since 2007, Mr. O’Connor has counseled the AIA’s Documents Committee in connection with
numerous contract forms. Mr. O’Connor has held LEED AP (New Construction) certification through the
U.S. Green Building Council. He is a Fellow, former member of the Executive Committee, and Past-
President of the American College of Construction Lawyers. Mr. O’Connor is also a former member of the
Governing Committee for the ABA Forum on the Construction Industry. Mr. O’Connor is listed in “The
Best Lawyers in America,” “International Who’s Who of Construction Lawyers,” and “Minnesota Super
Lawyers.”
____________________________________________________________________________________
Faegre Drinker Biddle & Reath LLP Direct: 612-766-7413
Minneapolis, Minnesota Email: patrick.oconnor@faegredrinker.com.)
Patrick J. O’Connor, Jr.
43
CMAA Focus21
Claire Groover is Florida Bar Board Certified in construction law and has practiced law in
Central Florida since her admission to The Florida Bar in 1988. Claire served on the Governing
Committee of the American Bar Association’s Forum on Construction Law and she chaired its
Division 12- Owners & Project Finance. She currently serves on the Forum’s Publications and
Marketing Committees. She also is a member of The Florida Bar Construction Law Committee
and chairs its Subcommittee on Construction Transactions.
Claire focuses her practice on owner and developer representation. She is a Florida Certified
Circuit Civil and Appellate Mediator, is a Panel Arbitrator with the American Arbitration
Association, and she is qualified to serve in Florida court-appointed and voluntary arbitration
proceedings. She is a member of Thomson-Reuters’ Practical Law Magazine Real Estate
Advisory Board and frequently writes and speaks on claims avoidance and construction risk
management. She was in-house counsel to Universal Orlando in its $2.5B theme park
development in the late 1990’s and she was Senior Counsel to Signature Flight Support
Corporation in the years following 9/11’s impact on the aviation industry. She has been
selected as a Florida Super Lawyer each year since 2009 and she is a Fellow of the
Construction Lawyers Society of America. Claire is of counsel to Becker’s construction
practice group which has been rated “Band 1” by Chambers USA every year since inception of
its global law firm rankings.
__________________________________________________________________
Becker & Poliakoff Direct: 407-875-0955
Orlando, Florida Email: cgroover@beckerlawyers.com
Claramargaret H. Groover
44
CMA Focus21
CMAA Focus21
45
Continuing Education Credit
» A credit value is assigned to CMAA courses and seminars in units of Professional Development Hours (PDH),
Learning Units (LU), and CCM Recertification Points. CMAA guarantees that course material meets the minimum
requirements for a PDH, which is 60
» Not all sessions and activities offered may be acceptable for continuing education credit in your state. Please check
your state licensing board’s requirements before submitting your credits.
All courses approved by CMAA count toward CCM recertification points. Points are awarded for
attending CM related education sessions; one point per hour of instruction plus two points per
conference attended. For more information on recertification points, please visit
https://recerttrack.com/home.php?portal=24
CMAA is registered with the American Institute of Architects (AIA) as an approved CES provider
of LUs. One educational contact hour equals one (1) LU. To receive LUs through CMAA, you
must provide your AIA member number on all registration materials and attendance forms.
www.aia.com
CMAA has met the standards and requirements of the Registered Continuing Education
Program. Credit earned on completion of this program will be reported to RCEP. A certificate of
completion will be issued to each participant. As such, it does not include content that may be
deemed or construed to be an approval or endorsement by RCEP. www.rcep.net

More Related Content

What's hot

PP1 Project 2 Project Report
PP1 Project 2 Project ReportPP1 Project 2 Project Report
PP1 Project 2 Project Report
Teo Kean Hui
 
The NEW Role of the AIA's Digital Practice Documents
The NEW Role of the AIA's Digital Practice DocumentsThe NEW Role of the AIA's Digital Practice Documents
The NEW Role of the AIA's Digital Practice Documents
Jeremy Baker
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Rae Davies
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Rae Davies
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
Delhi Technological University
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
Browne Jacobson LLP
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
Galala University
 
Chapter 3- Construction Law
Chapter 3- Construction Law Chapter 3- Construction Law
Chapter 3- Construction Law
Delhi Technological University
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
Delhi Technological University
 
Construction Documents Required by the Connecticut Building Code
Construction Documents Required by the Connecticut Building CodeConstruction Documents Required by the Connecticut Building Code
Construction Documents Required by the Connecticut Building Code
Milton Grew
 
The AIA's NEW Sustainable Projects Exhibit, E204-2017
The AIA's NEW Sustainable Projects Exhibit, E204-2017The AIA's NEW Sustainable Projects Exhibit, E204-2017
The AIA's NEW Sustainable Projects Exhibit, E204-2017
Jeremy Baker
 
Chapter 2- Construction Law
Chapter 2- Construction Law Chapter 2- Construction Law
Chapter 2- Construction Law
Delhi Technological University
 
Architect-Led Design-Build: a PRACTICAL business plan
Architect-Led Design-Build:  a PRACTICAL business planArchitect-Led Design-Build:  a PRACTICAL business plan
Architect-Led Design-Build: a PRACTICAL business plan
Jeremy Baker
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
Project Controls Expo
 
Fidic
FidicFidic
E-governance Project Contract Development: Challenges and How to Overcome Them
E-governance Project Contract Development: Challenges and How to Overcome ThemE-governance Project Contract Development: Challenges and How to Overcome Them
E-governance Project Contract Development: Challenges and How to Overcome Them
Prakash Kumar
 
claims management framework
 claims management framework claims management framework
claims management framework
Mohammad Salama,PMP,PgMP,PMI-SP,PMI-RMP, PMOC
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
Delhi Technological University
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
Delhi Technological University
 
ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1
Anne Arundel Community College
 

What's hot (20)

PP1 Project 2 Project Report
PP1 Project 2 Project ReportPP1 Project 2 Project Report
PP1 Project 2 Project Report
 
The NEW Role of the AIA's Digital Practice Documents
The NEW Role of the AIA's Digital Practice DocumentsThe NEW Role of the AIA's Digital Practice Documents
The NEW Role of the AIA's Digital Practice Documents
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 
Chapter 3- Construction Law
Chapter 3- Construction Law Chapter 3- Construction Law
Chapter 3- Construction Law
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
Construction Documents Required by the Connecticut Building Code
Construction Documents Required by the Connecticut Building CodeConstruction Documents Required by the Connecticut Building Code
Construction Documents Required by the Connecticut Building Code
 
The AIA's NEW Sustainable Projects Exhibit, E204-2017
The AIA's NEW Sustainable Projects Exhibit, E204-2017The AIA's NEW Sustainable Projects Exhibit, E204-2017
The AIA's NEW Sustainable Projects Exhibit, E204-2017
 
Chapter 2- Construction Law
Chapter 2- Construction Law Chapter 2- Construction Law
Chapter 2- Construction Law
 
Architect-Led Design-Build: a PRACTICAL business plan
Architect-Led Design-Build:  a PRACTICAL business planArchitect-Led Design-Build:  a PRACTICAL business plan
Architect-Led Design-Build: a PRACTICAL business plan
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Fidic
FidicFidic
Fidic
 
E-governance Project Contract Development: Challenges and How to Overcome Them
E-governance Project Contract Development: Challenges and How to Overcome ThemE-governance Project Contract Development: Challenges and How to Overcome Them
E-governance Project Contract Development: Challenges and How to Overcome Them
 
claims management framework
 claims management framework claims management framework
claims management framework
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1
 

Similar to Seeing the Big Picture: Best Practices for Contracting and Construction Risk Management in 2021

How to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and DevelopersHow to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and Developers
Kegler Brown Hill + Ritter
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Kegler Brown Hill + Ritter
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
Cerasela Angelescu
 
Presentation on as 7 and 9
Presentation on as 7 and 9Presentation on as 7 and 9
Presentation on as 7 and 9
nitish aggarwal
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
Yee Len Wan
 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contracts
AC&C Consulting Co., Ltd.
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
ssuser32da691
 
Construction contract
Construction contractConstruction contract
Construction contract
Delhi Technological University
 
Construction contract
Construction contractConstruction contract
Construction contract
Delhi Technological University
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
Maatla Moadi
 
Matrix207
Matrix207Matrix207
Matrix207
jbonvier
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
MANNU KUMAR
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
Association for Project Management
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
Praveen Premkumar
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
LAKSHITHA RAJAPAKSHA
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
Egyptian Engineers Association
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
Pui Chun Shian
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
Arissa Loh
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
John Ashton
 

Similar to Seeing the Big Picture: Best Practices for Contracting and Construction Risk Management in 2021 (20)

How to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and DevelopersHow to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and Developers
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 
Presentation on as 7 and 9
Presentation on as 7 and 9Presentation on as 7 and 9
Presentation on as 7 and 9
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contracts
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
Matrix207
Matrix207Matrix207
Matrix207
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 

Recently uploaded

Things to Consider When Selling Your House - Summer 2024 Edition
Things to Consider When Selling Your House - Summer 2024 EditionThings to Consider When Selling Your House - Summer 2024 Edition
Things to Consider When Selling Your House - Summer 2024 Edition
Tom Blefko
 
BEST FARMLAND FOR SALE | FARM PLOTS NEAR BANGALORE | KANAKAPURA | CHICKKABALP...
BEST FARMLAND FOR SALE | FARM PLOTS NEAR BANGALORE | KANAKAPURA | CHICKKABALP...BEST FARMLAND FOR SALE | FARM PLOTS NEAR BANGALORE | KANAKAPURA | CHICKKABALP...
BEST FARMLAND FOR SALE | FARM PLOTS NEAR BANGALORE | KANAKAPURA | CHICKKABALP...
knox groups real estate
 
Dholera Smart City Latest Development Status 2024.pdf
Dholera Smart City Latest Development Status 2024.pdfDholera Smart City Latest Development Status 2024.pdf
Dholera Smart City Latest Development Status 2024.pdf
Shivgan Infratech
 
SVN Live 6.10.24 Weekly Property Broadcast
SVN Live 6.10.24 Weekly Property BroadcastSVN Live 6.10.24 Weekly Property Broadcast
SVN Live 6.10.24 Weekly Property Broadcast
SVN International Corp.
 
Stark Builders: Where Quality Meets Craftsmanship!
Stark Builders: Where Quality Meets Craftsmanship!Stark Builders: Where Quality Meets Craftsmanship!
Stark Builders: Where Quality Meets Craftsmanship!
shuilykhatunnil
 
原版制作(Greenwich毕业证书)格林威治大学毕业证PDF成绩单一模一样
原版制作(Greenwich毕业证书)格林威治大学毕业证PDF成绩单一模一样原版制作(Greenwich毕业证书)格林威治大学毕业证PDF成绩单一模一样
原版制作(Greenwich毕业证书)格林威治大学毕业证PDF成绩单一模一样
a7xjm8n4
 
Deed 3754 S Honeysuckle Mesa AZ 85212 owner Shawn Freeman - Pamela Brown Nota...
Deed 3754 S Honeysuckle Mesa AZ 85212 owner Shawn Freeman - Pamela Brown Nota...Deed 3754 S Honeysuckle Mesa AZ 85212 owner Shawn Freeman - Pamela Brown Nota...
Deed 3754 S Honeysuckle Mesa AZ 85212 owner Shawn Freeman - Pamela Brown Nota...
olgashriki
 
制作(ucr毕业证书)加州大学河滨分校毕业证学历学位证书原版一模一样
制作(ucr毕业证书)加州大学河滨分校毕业证学历学位证书原版一模一样制作(ucr毕业证书)加州大学河滨分校毕业证学历学位证书原版一模一样
制作(ucr毕业证书)加州大学河滨分校毕业证学历学位证书原版一模一样
z5h13yqc
 
Addis Bleaching Mixed use Apartment- Documentation 6.pdf
Addis Bleaching Mixed use Apartment- Documentation 6.pdfAddis Bleaching Mixed use Apartment- Documentation 6.pdf
Addis Bleaching Mixed use Apartment- Documentation 6.pdf
hawifitumaed
 
G+10 apartment 1- Sustainable apartment building.pdf
G+10 apartment 1- Sustainable apartment building.pdfG+10 apartment 1- Sustainable apartment building.pdf
G+10 apartment 1- Sustainable apartment building.pdf
hawifitumaed
 
AVRUPA KONUTLARI ESENTEPE - ENGLISH - Listing Turkey
AVRUPA KONUTLARI ESENTEPE - ENGLISH - Listing TurkeyAVRUPA KONUTLARI ESENTEPE - ENGLISH - Listing Turkey
AVRUPA KONUTLARI ESENTEPE - ENGLISH - Listing Turkey
Listing Turkey
 

Recently uploaded (11)

Things to Consider When Selling Your House - Summer 2024 Edition
Things to Consider When Selling Your House - Summer 2024 EditionThings to Consider When Selling Your House - Summer 2024 Edition
Things to Consider When Selling Your House - Summer 2024 Edition
 
BEST FARMLAND FOR SALE | FARM PLOTS NEAR BANGALORE | KANAKAPURA | CHICKKABALP...
BEST FARMLAND FOR SALE | FARM PLOTS NEAR BANGALORE | KANAKAPURA | CHICKKABALP...BEST FARMLAND FOR SALE | FARM PLOTS NEAR BANGALORE | KANAKAPURA | CHICKKABALP...
BEST FARMLAND FOR SALE | FARM PLOTS NEAR BANGALORE | KANAKAPURA | CHICKKABALP...
 
Dholera Smart City Latest Development Status 2024.pdf
Dholera Smart City Latest Development Status 2024.pdfDholera Smart City Latest Development Status 2024.pdf
Dholera Smart City Latest Development Status 2024.pdf
 
SVN Live 6.10.24 Weekly Property Broadcast
SVN Live 6.10.24 Weekly Property BroadcastSVN Live 6.10.24 Weekly Property Broadcast
SVN Live 6.10.24 Weekly Property Broadcast
 
Stark Builders: Where Quality Meets Craftsmanship!
Stark Builders: Where Quality Meets Craftsmanship!Stark Builders: Where Quality Meets Craftsmanship!
Stark Builders: Where Quality Meets Craftsmanship!
 
原版制作(Greenwich毕业证书)格林威治大学毕业证PDF成绩单一模一样
原版制作(Greenwich毕业证书)格林威治大学毕业证PDF成绩单一模一样原版制作(Greenwich毕业证书)格林威治大学毕业证PDF成绩单一模一样
原版制作(Greenwich毕业证书)格林威治大学毕业证PDF成绩单一模一样
 
Deed 3754 S Honeysuckle Mesa AZ 85212 owner Shawn Freeman - Pamela Brown Nota...
Deed 3754 S Honeysuckle Mesa AZ 85212 owner Shawn Freeman - Pamela Brown Nota...Deed 3754 S Honeysuckle Mesa AZ 85212 owner Shawn Freeman - Pamela Brown Nota...
Deed 3754 S Honeysuckle Mesa AZ 85212 owner Shawn Freeman - Pamela Brown Nota...
 
制作(ucr毕业证书)加州大学河滨分校毕业证学历学位证书原版一模一样
制作(ucr毕业证书)加州大学河滨分校毕业证学历学位证书原版一模一样制作(ucr毕业证书)加州大学河滨分校毕业证学历学位证书原版一模一样
制作(ucr毕业证书)加州大学河滨分校毕业证学历学位证书原版一模一样
 
Addis Bleaching Mixed use Apartment- Documentation 6.pdf
Addis Bleaching Mixed use Apartment- Documentation 6.pdfAddis Bleaching Mixed use Apartment- Documentation 6.pdf
Addis Bleaching Mixed use Apartment- Documentation 6.pdf
 
G+10 apartment 1- Sustainable apartment building.pdf
G+10 apartment 1- Sustainable apartment building.pdfG+10 apartment 1- Sustainable apartment building.pdf
G+10 apartment 1- Sustainable apartment building.pdf
 
AVRUPA KONUTLARI ESENTEPE - ENGLISH - Listing Turkey
AVRUPA KONUTLARI ESENTEPE - ENGLISH - Listing TurkeyAVRUPA KONUTLARI ESENTEPE - ENGLISH - Listing Turkey
AVRUPA KONUTLARI ESENTEPE - ENGLISH - Listing Turkey
 

Seeing the Big Picture: Best Practices for Contracting and Construction Risk Management in 2021

  • 1. P R E S E N T E D B Y SEEING THE BIG PICTURE: Best practices for contracting and construction risk management for 2021 Members of the American Bar Association Forum on Construction Law: Jeremy S. Baker, Esquire/Robin Goldberg Banks, Esquire/Patrick J. O’Connor, Esquire Moderator: Claramargaret H. Groover, Esquire
  • 2. CMA Focus21 CMAA Focus21 Statement of Purpose » Define and understand the role of CM advisor under agreements such as AIA Document C132-2019. » Define and understand the CMAR’s role under agreements such as AIA Document A133-209 or A134-2019 » Identify and protect against construction risks likely to occur » Identify » Identify and understand insurance applicable to project risks 2
  • 3. CMA Focus21 CMAA Focus21 CMAA Member Benefits with ABA Forum 3 CMAA and ABA Forum Member Benefits CMAA members discount on Forum publications 15% with special code https://www.americanbar.org/groups/departmentsoffices/publishing/ci-book-catalog/
  • 4. CM Advisor in Construction Administration
  • 5. CMA Focus21 CMAA Focus21 AIA’s 2019 CMa Documents » Owner-Contractor Agreement - A132-2019: Owner-Contractor Agreement - A132-2019 Exhibit A: Insurance & Bonds Exhibit - A132-2019 Exhibit B: Cost of Work Determination - A232-2019: General Conditions - E235-2019: Sustainable Projects Exhibit » Owner-Architect Agreement: B132-2019 » Owner-CMa Agreement: C132-2019 » CMa-Specific Forms - G731-2019 (Change Order, CMa Edition) - G732-2019 (Application and Certificate for Payment, CMa Edition) - G733-2019 (CCD, CMa Edition) - G734-2019 (Certificate of Substantial Completion, CMa Edition) 5
  • 6. CMA Focus21 CMAA Focus21 CMa Similarities to Architect Standard of Care The Construction Manager shall perform its services consistent with the skill and care ordinarily provided by construction managers practicing in the same or similar locality under the same or similar circumstances. The Construction Manager shall perform its services as expeditiously as is consistent with such skill and care and the orderly progress of the Project. C132-2019, §2.2 6
  • 7. CMA Focus21 CMAA Focus21 CMa Similarities to Architect » Review shop drawings and other submittals The Construction Manager shall promptly review all Shop Drawings, Product Data, Samples and other submittals from the Contractors for compliance with the submittal requirements of the Contracts, coordinate submittals with information contained in related documents, and transmit to the Architect those that the Construction Manager recommends for approval… C132-2019, § 3.3.20 » Review and certify payment applications …the Construction Manager shall review and certify the amounts due the respective Contractors… C132-2019, §3.3.12.2 7
  • 8. CMA Focus21 CMAA Focus21 CMa Similarities to Architect » CMa’s certification language is the same as that for a certifying architect The Construction Manager’s certification for payment shall constitute a representation to the Owner, based on the Construction Manager’s evaluations of the Work and on the data comprising the Contractors’ Applications for Payment, that, to the best of the Construction Manager’s knowledge, information and belief, the Work has progressed to the point indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractors are entitled to payment in the amount certified… C132-2019, §3.3.12.3 » CMa shall provide professional liability insurance for CMa’s errors and omissions The Construction Manager shall maintain the following insurance until termination of this Agreement... Professional Liability covering negligent acts, errors and omissions in the performance of professional services with policy limits of not less than ($ ) per claim and ($ ) in the aggregate. C132-2019, §§ 2.8, 2.8.5 8
  • 9. CMA Focus21 CMAA Focus21 CMa Similarities to Contractor/CMAR » Maintain daily log of weather, labor force, work performed, issues that arise The Construction Manager shall keep a daily log containing a record of weather, each Contractor’s Work on the site, number of workers, identification of equipment, Work accomplished, problems encountered, and other similar relevant data as the Owner may require. C132-2019, § 3.3.21 » Handle delivery, storage, security of materials and equipment at the site The Construction Manager shall arrange for the delivery, storage, protection and security of Owner-purchased materials, systems and equipment that are a part of the Project until such items are incorporated into the Work. C132-2019, § 3.3.23 9
  • 10. CMA Focus21 CMAA Focus21 CMa Similarities to Contractor/CMAR » Schedule and coordinate overall construction sequence and allocate on-site storage (lay down) space …utilizing information from the Contractors, the Construction Manager shall review, analyze, schedule and coordinate the overall sequence of construction and assignment of space in areas where the Contractors are performing Work. C132-2019, § 3.3.7 » Provide general liability and other coverages The Construction Manager shall maintain the following insurance until termination of this Agreement... Commercial General Liability with policy limits of not less than ($ ) for each occurrence and ($ ) in the aggregate for bodily injury and property damage… the Construction Manager shall cause the… policies for Commercial General Liability… to include the Owner as an additional insured… C132-2019, §§ 2.8, 2.8.1, 2.8.6 10
  • 11. CMA Focus21 CMAA Focus21 CMa-Specific General Conditions: A232 » CMa Performs Functions Traditionally Reserved for Architect - Receiving prompt reports of any errors, inconsistencies or omissions in the Contract Documents discovered by the Contactor. A232-2019, §3.2.2 - Assessing whether substitutions proposed by the Contractor are acceptable. A232-2019, § 3.4.2 - Investigating concealed or unknown conditions. A232-2019, § 3.7.4 - Receiving certifications from the Contractor’s design professional, if any. A232-2019, § 3.12.10.2. - Reviewing and certifying Applications for Payment or withholding Certificates for Payment. A232- 2019, §§ 4.2.7, 9.4, 9.5 - Rejecting Work that does not conform to the Contract Documents. A232-2019, § 4.2.8 - Reviewing the Contractor’s submittals. A232-2019, §§ 4.2.10, 4.2.11 - Conducting inspections to determine the date or dates of Substantial Completion and the date of final completion. A232-2019, §§ 4.2.16, 9.8.3, 9.8.4, 9.10.1 - Signing Change Orders and Construction Change Directives. A232-2019, §§ 7.2, 7.3 11
  • 12. CMA Focus21 CMAA Focus21 CMa-Specific General Conditions: A232 » CMa More Involved than Architect in Construction Phase - Owner shall forward all communications to the Contractor through the CMa. A232-2019, §2.3.8 - … Contractor shall cooperate with the CMa in scheduling and performing the Contractor’s Work… A232-2019, § 3.10.1 - Contractor shall participate with other Contractors, the CMa, and the Owner in reviewing and coordinating all schedules for incorporation into the Project schedule,,, A232-2019, § 3.10.3 - The Contractor shall coordinate the Contractor’s operations with, and secure the approval of, the CMa before using any portion of the site. A232-2019, § 3.13.2 - The CMa will schedule and coordinate the activities of the Contractor and other Contractors in accordance with the latest approved Project schedule. A232-2019, § 4.2.4 - Utilizing the submittal schedule provided by the Contractor, the CMa shall prepare, and revise as necessary, a Project submittal schedule…A232-2019, § 4.2.9 - CMa will receive and review requests for information from the Contractor, and forward each request for information to the Architect, with the CMa’s recommendation… A232-2019, § 4.2.21. 12
  • 13. CMA Focus21 CMAA Focus21 CMa-Specific General Conditions: A232 » Allocation of CMa and Contractor Responsibility - CMa plays a role in project safety: » “…The Contractor shall submit the Contractor’s safety program to the Construction Manager for review and coordination with the safety programs of other Contractors…” A232-2019, § 10.1 - But the CMa’s role in safety is secondary: » …The Contractor shall be solely responsible for, and have control over, construction means, methods, techniques, sequences, and procedures... A232-2019, §3.3.1 » The Construction Manager… will not have control over, charge of, or responsibility for, the construction means, methods, techniques, sequences or procedures, or for the safety precautions and programs in connection with the Work, since these are solely the Contractor’s rights and responsibilities under the Contract Documents… A232-2019, §4.2.5 13
  • 14. CM at Risk (CMAR)
  • 15. CMA Focus21 CMAA Focus21 CMAR Conundrum 15 Owner – Time Problem CMAR – Needs to price project based on incomplete design
  • 16. CMA Focus21 CMAA Focus21 Liability for Exceeding GMP/Excess Costs To the extent that the Contract Documents are anticipated to require further development, the Guaranteed Maximum Price includes the costs attributable to such further development consistent with the Contract Documents and reasonably inferable therefrom. Such further development does not include changes in scope, systems, kinds and quality of materials, finishes, or equipment, all of which, if required, shall be incorporated by Change Order. A133-2019 § 3.2.2; A134-2019, § 3.2.4 16
  • 17. CMA Focus21 CMAA Focus21 New CMAR Preconstruction Phase Responsibilities A133-2019 and A134-2019, § 3.1.14 Other Preconstruction Services. Insert a description of any other Preconstruction Phase services to be provided by the Construction Manager, or reference an exhibit attached to this document. (Describe any other Preconstruction Phase services, such as providing cash flow projections, development of a project information management system, early selection or procurement of subcontractors, etc.) A133-2019 and A134-2019, § 3.1.3.2 … The Construction Manager shall consult with the Architect regarding professional services to be provided by the Construction Manager during the Construction Phase. 17
  • 18. CMA Focus21 CMAA Focus21 New CMAR Preconstruction Phase Responsibilities A133-2019 and A134-2019, § 3.1.3.3 The Construction Manager shall assist the Owner and Architect in establishing building information modeling and digital data protocols for the Project, using AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, to establish the protocols for the development, use, transmission, and exchange of digital data. A133-2019 and A134-2019, § 3.1.8 The Construction Manager shall provide recommendations and information to the Owner and Architect regarding equipment, materials, services, and temporary Project facilities. A133-2019 and A134-2019, § 3.1.9 The Construction Manager shall provide a staffing plan for Preconstruction Phase services for the Owner’s review and approval. A133-2019 and A134-2019, § 3.1.10 If the Owner identified a Sustainable Objective in Article 1, the Construction Manager shall fulfill its Preconstruction Phase responsibilities as required in AIA Document E234™–2019, Sustainable Projects Exhibit, Construction Manager as Constructor Edition, attached to this Agreement. 18
  • 19. CMA Focus21 CMAA Focus21 New CMAR Preconstruction Standards of Care and Insurance Requirements A133-2019 and A134-2019, § 3.1.1 Extent of Responsibility The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. … A133-2019 and A134-2019, § 14.3.1 Preconstruction Phase Insurance » CGL » Automobile » Worker’s Compensation » Professional Liability » Other 19
  • 20. CMA Focus21 CMAA Focus21 Benefits of CMAR 20 • Advise and provide input into design, cost, constructability, scheduling, etc. Preconstruction • Fabrication of long lead items • Site preparation • Exploratory investigation • Limited construction Construction
  • 21. CMA Focus21 CMAA Focus21 New Option to Start CMAR Construction Phase The Construction Phase shall commence upon the Owner’s execution of the Guaranteed Maximum Price Amendment or, prior to acceptance of the Guaranteed Maximum Price proposal, by written agreement of the parties. The written agreement shall set forth a description of the Work to be performed by the Construction Manager, and any insurance and bond requirements for Work performed prior to execution of the Guaranteed Maximum Price Amendment. A133-2019, § 3.3.1.2; A134-2019, § 3.3.1.2. (approval of Control Estimate in lieu of acceptance of GMP proposal and execution of GMP Amendment) 21
  • 22. CMA Focus21 CMAA Focus21 **NEW CMAR FORM FOR 2021 ** G735-2021 - Authorization to Proceed with Early Release Work » Executed after Owner-CM Agreement, but prior to agreement on GMP or approval of Control Estimate » Contains fill points for parties to address specifics of Early Work being released » Adopts terms and conditions from Owner-CM Agreement 22
  • 23. CMA Focus21 CMAA Focus21 General CMAR Construction Phase Updates » Key 2017 revisions: • New termination fee provision • New fill points for liquidated damages and incentives • More streamlined project communications • New retainage section » Generally conform with A102-2017 and A201-2017 revisions: • For detailed look at 2017 revisions, please visit www.aiacontracts.org/learn 23
  • 24. CMA Focus21 CMAA Focus21 The Spearin Doctrine – Implied Warranty 24 “if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications” United States v. Spearin, 248 U.S. 132, 136 (1918).
  • 25. CMA Focus21 CMAA Focus21 CMAR and the Spearin Doctrine 25 Coghlin Elec. Contractors, Inc. v. Gilbane Bldg. Co., 36 N.E.3d 505 (Mass. 2015) » CMAR may benefit from implied warranty only: - Where it acted in good faith reliance on design; and - Acted reasonably in light of CMAR’s own design responsibilities » Court looks at: - Level of participation in design phase of project; and - Extent to which contract delegates design responsibility
  • 26. CMA Focus21 CMAA Focus21 Extent to which A201 delegates design responsibility 26 A201-2017, § 3.12.10.1 If professional design services or certifications by a design professional related to systems, materials, or equipment are specifically required of the Contractor by the Contract Documents, the Owner and the Architect will specify all performance and design criteria that such services must satisfy. The Contractor shall be entitled to rely upon the adequacy and accuracy of the performance and design criteria provided in the Contract Documents. The Contractor shall cause such services or certifications to be provided by an appropriately licensed design professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, Shop Drawings, and other submittals prepared by such professional. Shop Drawings, and other submittals related to the Work, designed or certified by such professional, if prepared by others, shall bear such professional’s written approval when submitted to the Architect. The Owner and the Architect shall be entitled to rely upon the adequacy and accuracy of the services, certifications, and approvals performed or provided by such design professionals, provided the Owner and Architect have specified to the Contractor the performance and design criteria that such services must satisfy. Pursuant to this Section 3.12.10, the Architect will review and approve or take other appropriate action on submittals only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
  • 27. CMA Focus21 CMAA Focus21 ** New Cost of the Work Payment Applications for 2021** » G702 GMP-2021 – Application for Payment where the basis of payment is Cost of the Work with a Guaranteed Maximum Price » G702 CW-2021 – Application for Payment where the basis of payment is Cost of the Work » G703CW-2021 – Cost of the Work Continuation Sheet 27
  • 28. CMA Focus21 CMAA Focus21 G703-CW Continuation Sheet 28
  • 30. CMA Focus21 CMAA Focus21 Owner Claims and Risk Management » Defective design » Defective construction » Changes and cost overruns » Delays - Force majeure - COVID-19 30
  • 31. CMA Focus21 CMAA Focus21 Insurance and Bonds – 2017 Exhibit 31 »Liability limits »Causes of loss sublimits »Property insurance sublimits »Other coverages »Specifics of optional coverages »Coverage durations if other than specified
  • 32. CMA Focus21 CMAA Focus21 Required Provisions to be Completed » Commercial general liability limits (§ B.3.2.2) » Automobile liability limits (§ B.3.2.3) » Employer’s liability limits (§ B.3.2.6) AND IF Contractor’s work involves… ►Professional services (professional liability limits) (§ B.3.2.8) ►Transport or use of pollutants (pollution liability limits) (§ B.3.2.9) ►Maritime/aviation risks (limits for such insurance) (§§ B.3.2.11 & 3.2.12) 32
  • 33. CMA Focus21 CMAA Focus21 CGL – What Must Not Be Excluded or Restricted » CGL policy shall not exclude or restrict coverage by way of: - Insured vs. insured exclusion - Elimination of subcontractor exception (completed operations hazard) - Broad employee exclusions (e.g. independent contractors) - Elimination of insured contract exception to the contractual liability exclusion (employee injuries) - Prior work endorsements - Prior injury endorsements » (§ B.3.2.2) 33
  • 34. CMA Focus21 CMAA Focus21 Builder’s Risk – Causes of Loss » “All-risks” ≠ coverage for all risks » Exhibit prohibits certain exclusions - Fire, explosion, theft, vandalism, malicious mischief, collapse, earthquake, flood, or windstorm » Exhibit permits adjustment of coverage limits - Prompts specifying sublimits » Must provide coverage for ensuing loss - Resulting from bad design or construction (§ B.2.3.1.1) 34
  • 35. CMA Focus21 CMAA Focus21 Insurance for Existing Structures (§ B.2.3.3) » When work involves remodeling an existing structure or constructing addition to existing structure… » Owner must purchase all-risks property insurance protecting the existing structure against same causes of loss to which builder’s risk policy would respond » Must maintain until expiration of period for correction of Work 35
  • 36. CMA Focus21 CMAA Focus21 Optional Property Coverage Extension » Loss of use, business interruption, delay in completion (§ B.2.4.1) » Ordinance or law insurance (§ B.2.4.2) » Expediting cost insurance (§ B.2.4.3) » Extra expense insurance (§ B.2.4.4) » Civil authority insurance (§ B.2.4.5) » Ingress/egress insurance (§ B.2.4.6) » Soft costs insurance (§ B.2.4.7 36
  • 37. CMA Focus21 CMAA Focus21 GL Coverage for Specific Scopes of Work » Residential or habitational exclusions » Roofing exclusions » EIFS exclusions » Earth movement exclusions » XCU exclusions (§ B.3.2.2.2) 37
  • 38. CMA Focus21 CMAA Focus21 Additional Insured Coverage Why draw a line in the sand at the 2004 ISO forms? 38
  • 39. CMA Focus21 CMAA Focus21 Excess or Umbrella Insurance » Contractor can secure liability limits through any combination of primary and excess or umbrella insurance » Excess insurance, however, may not dictate exhaustion of the underlying limits only through actual exhaustion (must permit functional exhaustion) 39
  • 41. CMAA Focus21 Jeremy S. Baker, a Chicago-based construction attorney, founded Baker Law Group LLC after nearly fifteen years at Schiff Hardin LLP, where he was a partner and a member of its national Construction Law practice. As an Adjunct Professor of Law at The John Marshall Law School, he taught an elective Construction Law course though its Center for Real Estate Law (2016, 2017, 2018). Jeremy’s practice involves project structuring across many project delivery methods, plus contract review and negotiation. He has prosecuted and defended lawsuits in over 30 state and federal court venues, but he prefers to help clients complete challenging projects by emphasizing dispute avoidance and early, cost- efficient resolution of claims. Jeremy is a graduate of the Tulane University Law School (2002) and the University of California, Santa Barbara (1999). ___________________________________________________________ Baker Law Group Direct: 312-621-7184 Chicago, Illinois www.buildchicagolaw.com Jeremy S. Baker 41
  • 42. CMAA Focus21 Ms. Banks focuses her practice in all areas of construction law, from contract drafting and negotiation to pre-litigation dispute resolution and complex construction disputes involving mechanics liens, payment bond claims, and construction defect claims. She represents clients across the construction spectrum, including design professionals, owners, construction managers, contractors, subcontractors, and suppliers. In addition to her construction practice, Ms. Banks serves as an associate outside legal counsel to the AIA Contract Documents Committee. Ms. Banks frequently presents on topics including updates to, and analysis of, AIA Contract Documents and risk management for design professionals, construction managers/contractors, and owners. Ms. Banks has also been published in the Construction Law Handbook, 4th Ed. (Stanley A. Martin and Leah A. Rochwarg, eds. 2020) and the Maryland State Bar Association Deskbook, 2nd Ed. (Joseph C. Kovars and Michael Schollaert, eds. 2017) as well as in other books and professional publications. Ms. Banks has been recognized by U.S. News – Best Lawyers in America for Construction Law in Maryland (2020-present) and Maryland Super Lawyers in Construction Litigation (2021) and is a member of the American Bar Association Forum on the Construction Industry, Maryland State Bar Association, and District of Columbia Bar Association, and an Allied Member of the National American Institute of Architects. _________________________________________________________________________________ Goldberg & Banks, P.C. Direct: 443-940-1342 Baltimore, Maryland Email: rgbanks@gbpclawfirm.com 42 Robin G. Banks
  • 43. CMAA Focus21 Mr. O’Connor is a partner with the international law firm of Faegre Drinker Biddle & Reath LLP in its Minneapolis, Minnesota office. He received his B.A. degree from Hamline University in 1975 and his JD degree from The American University in 1981. He was law clerk to Miles W. Lord, Chief Judge of the Federal District Court for the District of Minnesota. Mr. O’Connor’s practice focuses on construction, suretyship and insurance. He has served as litigation or coverage counsel for contractors, owners, design professionals, and product suppliers in disputes venued in over 25 states and Canada. He also acts as a mediator, arbitrator and expert witness in construction and insurance disputes. Mr. O’Connor is co-author of Bruner & O’Connor on Construction Law (West Group 2002), a twelve-volume construction law treatise. He was an adviser to the American Law Institute’s Restatement of the Law Third, Suretyship and Guaranty. He works closely with a number of industry organizations on Building Information Modeling and Integrated Project Delivery initiatives. Mr. O’Connor is former Co-Chair of the BIMForum’s Legal Subforum. Since 2007, Mr. O’Connor has counseled the AIA’s Documents Committee in connection with numerous contract forms. Mr. O’Connor has held LEED AP (New Construction) certification through the U.S. Green Building Council. He is a Fellow, former member of the Executive Committee, and Past- President of the American College of Construction Lawyers. Mr. O’Connor is also a former member of the Governing Committee for the ABA Forum on the Construction Industry. Mr. O’Connor is listed in “The Best Lawyers in America,” “International Who’s Who of Construction Lawyers,” and “Minnesota Super Lawyers.” ____________________________________________________________________________________ Faegre Drinker Biddle & Reath LLP Direct: 612-766-7413 Minneapolis, Minnesota Email: patrick.oconnor@faegredrinker.com.) Patrick J. O’Connor, Jr. 43
  • 44. CMAA Focus21 Claire Groover is Florida Bar Board Certified in construction law and has practiced law in Central Florida since her admission to The Florida Bar in 1988. Claire served on the Governing Committee of the American Bar Association’s Forum on Construction Law and she chaired its Division 12- Owners & Project Finance. She currently serves on the Forum’s Publications and Marketing Committees. She also is a member of The Florida Bar Construction Law Committee and chairs its Subcommittee on Construction Transactions. Claire focuses her practice on owner and developer representation. She is a Florida Certified Circuit Civil and Appellate Mediator, is a Panel Arbitrator with the American Arbitration Association, and she is qualified to serve in Florida court-appointed and voluntary arbitration proceedings. She is a member of Thomson-Reuters’ Practical Law Magazine Real Estate Advisory Board and frequently writes and speaks on claims avoidance and construction risk management. She was in-house counsel to Universal Orlando in its $2.5B theme park development in the late 1990’s and she was Senior Counsel to Signature Flight Support Corporation in the years following 9/11’s impact on the aviation industry. She has been selected as a Florida Super Lawyer each year since 2009 and she is a Fellow of the Construction Lawyers Society of America. Claire is of counsel to Becker’s construction practice group which has been rated “Band 1” by Chambers USA every year since inception of its global law firm rankings. __________________________________________________________________ Becker & Poliakoff Direct: 407-875-0955 Orlando, Florida Email: cgroover@beckerlawyers.com Claramargaret H. Groover 44
  • 45. CMA Focus21 CMAA Focus21 45 Continuing Education Credit » A credit value is assigned to CMAA courses and seminars in units of Professional Development Hours (PDH), Learning Units (LU), and CCM Recertification Points. CMAA guarantees that course material meets the minimum requirements for a PDH, which is 60 » Not all sessions and activities offered may be acceptable for continuing education credit in your state. Please check your state licensing board’s requirements before submitting your credits. All courses approved by CMAA count toward CCM recertification points. Points are awarded for attending CM related education sessions; one point per hour of instruction plus two points per conference attended. For more information on recertification points, please visit https://recerttrack.com/home.php?portal=24 CMAA is registered with the American Institute of Architects (AIA) as an approved CES provider of LUs. One educational contact hour equals one (1) LU. To receive LUs through CMAA, you must provide your AIA member number on all registration materials and attendance forms. www.aia.com CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be reported to RCEP. A certificate of completion will be issued to each participant. As such, it does not include content that may be deemed or construed to be an approval or endorsement by RCEP. www.rcep.net