SlideShare a Scribd company logo
Biomedical Textile Development & Research Center
Steph Dudak & Mina Bellare | Fall 2015 | Design VIII | Professor Matthew Gindlesparger
Table of Contents
Minneapolis, MN Demographics	 01
St. Anthony Falls	 02
Site Selection	 03
Medical Textiles	 04
Program Mock Up	 05
Mid Crit Presentation	 06
Plans	 07
Sefaira Analyses	 09
Facade Development	 11
Wall Sections	 17
Atrium Development	 19
Mechanical Systems	 25
Plumbing	 27
Occupancy Loads	 28
Final Presentation Mock Up & Other 		
	 Development						 29
1/4" Final Model	 33
1/32" Final Model	 35
Final Presentation	 36
Final Boards	 37
Demographics
01
St. Anthony Falls
02
Site Selection
03
Medical Textiles
04
Program Mock Up
05
	 The following two
boards were developed within
three days of each other.
	 While we continue to
bring in basic demographic
and site information in to
these presentations, the
focus for the board to
the right is mainly on plan
organization and massing.
Mid Crit Board
06
	 The board for our mid crit features more definitive plan organization, site location, and bioclimatic strategies at the
time. At this stage, however, we did not have much of an attitude about the exterior of the building and what it really should
be. We had an idea of peeling away the existing facade but it was not executed in a way that we felt displayed our intentions
about a biomedical textile center.
Plans
07
	 Following our previous presentations, we worked to finalize our plans as we began to develop the facade systems. After
this set of drawings, our plans would only see minor changes. We created a criteria for each room in order for it to be placed
most efficiently in the building. This information also helped with the systems that we implemented and the treatment of the
facade.
Lighting and system needs per programmatic function
Plans
08
Safaira Analyses
09
	 To begin progressing with the facade, we started with Sefaira daylight analyses of both the existing building and of our
general intentions of the building. Doing this allowed us to see what kind of light conditions the existing and new building were
experiencing in their most basic forms.
	 What we found with these was that the existing building was mostly underlit in terms of daylight. Our proposed idea
at the time was mostly overlit, with the right side showing data of being underlit. This was not an issue, however, because we
already determined that the right side of the building, which houses labs and research, would need mostly artificial lighting
and very little daylight. The rest of the building, however, would have to be dealt with.
Safaira Analyses
10
	 The information gathered from the daylighting analyses was then used to inform our facade. After this, we figured out
how much light each programmatic space needed and continued from there.
	 Overall Sefaira analyses of
existing building, our proposed building,
and the three separate sections of our
new building. It was relevant to separate
the three "sections" because each one
requires different conditions in terms of
light and air.
Facade Development
11
Facade: Initial sketches regarding facade treatments
Woven facade that opens and closes according to each space and time of day
Metal facade with perforations of different sizes according to programmatic spaces
Fabric panels that lift in order to bring in light according to space and time of day
Facade Development
12
	 During the development of our facade, we also made a decision to change the structural system of our building. While we knew we wanted to
alter the existing structure, the previous alterations we had made were less informed and less structurally efficient. As a result, a decision was made
to go with a steel diagrid structure around the exterior as it provides stability, uniform load distribution, and relates to the "structure" of medical
textiles while facilitating the idea of wrapping.
	 From this point, we developed a facade that featured varied levels of transparencies. We chose to develop a metal facade in an attempt to
stay away from using a literal textile, but creating the various transparencies and qualities that a pulled textile would produce. The facade includes
perforated metal panels, solid metal panels, clear glass, and fritted glass. Aside from acting as visual interest, these particular treatments are
meant to mitigate weather and solar effects on the building based on the specific facade as well as the programmatic spaces behind the panels.
Facade Development
13
	 This rendition starts to combine the idea of the aluminum panels (left) with an opening for glazing (right) with
a glass pattern and a perforated metal skin wrapping. Trying to combine all of these at once perhaps was not the best
way to go, however. The openings and the screens all together did not make a lot of sense.
Facade Development
14
	 We began to develop a facade that "wrapped" around the building, revealing the structure where there are no panels. The idea behind this
variation of the facade was that where there needs to be opaque walls, we would have an aluminum composite panel system. The transparency would be
controlled with perforated panels attached to the outside of the structure to control sunlight and shade. The south facade features a double skin and
the glass along the atrium would contain a fritted glass pattern similar to the perforated metal screen pattern. The fritted glass allows for some
control over heat gain and shading but still allows views over the river.
Facade Development
15
	 After having an idea of what the facade should be,
another iteration was created and the exterior structure
was laid out. From here, it made sense to continue a similar
structural language to hold up the west side of the
building, which before this point we were unsure of what
to do. A considerable load had to be accounted for, so
the existing columns were to be replaced by three large V
shaped concrete supports.
	 The facade would follow a similar pattern from
here, changing depending on what each space needs. The
structure at this stage also would see some changes;
the intersections line up with the floor plates but still
appeared very rigid as a result of their square shape.
Considering we also kept the interior structure of the
existing building, we found it necessary to reflect that with
the exterior structure. With our final iteration, the grid
would stretch so the intersections would line up with the
columns and the floor plates.
Facade Development
16
Final Elevations
Wall Sections
17
	 First attempts at wall sections for the double skin attached to the south facade and for walls containing aluminum composite panels.
Wall Sections
18
	 Final Wall Sections
Atrium Development
19
	 In developing the atrium space, we knew it was going to be a space that was going to be the major connector between
all other spaces, almost as a bridge, and was going to be a space that had multiple functions. Because of this, the quality
of the space was very important and it was necessary that it be used to allow ventilation between both sides of the building.
The atrium also acts as a lightwell through the building, allowing in natural light where it wasn't before, and acts as an
intermediate space between both sides to promote collaboration between different disciplines (student v professional). The
atrium also juxtaposes the sterile nature of a lab space, providing a green space with fresh air that removes the user from
work momentarily.
Atrium Development
20
Version 1: Initial sketches and digital representations
	 This iteration of the atrium space explored pathways that
crossed between each other and sloped upward; circulation would take
place along them. As we went through this version, we realized it
becomes difficult structurally and functionally. The continuous slope
was not ideal on the basis that the atrium is a space that acts as a
link to promote collaboration or that becomes a space that one could
use to relax. The horizontal connections only existing at the edges
between sloping paths also would cause a struggle to use the space.
Atrium Development
21
Version 2: Initial section sketches of atrium space
	 After discussing what would and would not
work within the atrium, we decided to further
develop a different rendition of the space that
featured a continuous green wall to promote
clean air (which also conceals the restroom and
mechanical core) while still keeping various levels
of plantings. the following plan sketches and
digital representation would greatly influence our
final atrium design.
Atrium Development
22
Version 2: Initial plan sketches of atrium space
Atrium Development
23
	 The intention of this iteration
of the atrium is to allow the plantings
to pop through the spaces from below.
The circulation then cuts into the floor
plates, creating areas where you're
still able to look below to the other
levels. There is also an equal travel
distance to get from side to side, and
the atrium space is symmetrical. The L
shaped stairs that connect the top two
levels let a user directly off to their
desired side of the building (student v
professional space). The stairs that
connect the double height space to
the level above it let the user out at
the front of the floor, but are also
connected to the L steps.
	 The front of the floor plates
are left unaltered because this is the
primary viewing space over the river
and is also an important piece of the
horizontal circulation. The pathways
are wide enough to accomodate basic
circulation as well as plantings and
seating.
Version 2: Digital Representation
Atrium Development
24
	 Initial sketches of the interior of the
atrium spaces at each level. It is intended
that the atrium would be open on the inside
to promote ventilation between both sides.
Mechanical Systems
25
	 Spending a lot of time on atrium and facade development, we also had to develop the mechanical systems as well as
occupancy loads to determine egress. While determining plan organization, we found it most efficient for the mechanical core
to be located in the very back of the atrium space. Below is our first attempt at laying out the mechanical systems.
Mechanical Systems
26
	 From the beginning of the project, we had to keep the building in mind in "sections"--the student section, atrium section,
and professional section--because each section required a different system because of the functions of the spaces. The labs,
for example, all required new air and exhaust--air could not be recirculated through these spaces. We determined the use
of CAV and VAV reheat systems for the atrium and lab spaces, respectively. Below is our final inclusion of the mechanical
Plumbing
27Initial pipe layout
Final Plumbing Layout
Occupancy Loads
28
	 Occupancy loads for the spaces were calculated to determine the means of egress for our building--one stair to the
right of the mechanical room and one at the northwest corner of the "student side" of the building.
Final Presentation Mock Up
29
	 The following presentation boards were the last mock up before the final presentation. Further facade development and
treatment of the atrium space was also included in the workings of these boards.
Final Presentation Mock Up
30
Final Presentation Mock Up
31
Final Presentation Mock Up
32
1/4" Section Model
33
1/4" Section Model
34
1/32" Model & Site
35
Final Presentation
36
	 Minneapolis has a strong medical, educational, and science industry that is
continuing to grow and develop. Similarly, biomedical textiles is a developing industry
which provides an essential service to a variety of medical practices, allowing the
implementation of artificial parts in the human body. The proposal for a biomedical
textile facility aims to strengthen the advancement of Minneapolis' medical practices,
providing a space to manufacture, develop, implement, and research biomedical textiles
as well as teach about their applications--it will also serve as a node along the
Mississippi for professionals and the community alike.
---
	 Our building site takes advantage of expansive views over the Mississippi river, proximity to relevant
industry, southern exposure, and water power. However, the existing building was not efficient for our
particular program. With a failing exterior structure and a desire to keep some of the character of the old
building, we opted to replace the exterior structure with a steel diagrid; this allows the rigidity and structure
we need to hold up the building, provide even load distribution, and reinvent the level of transparency which
was not provided before. The form of the structure is derived from the structure of an actual textile, which
also provides different levels of rigidity and load distribution as it is stretched and pulled.
	 The atrium space acts as a continuation of the exterior landscape and aims to continue Minneapolis'
trend of bringing green space into buildings. Cutting through the middle of the building allows the atrium to
separate the "student" and "professional" sections, which require different mechanical and passive strategies
while simultaneously connecting them back together through a space that intends to increase collaboration
between the two. The atrium also holds all the main circulation and service cores.
Final Boards
37
Final Boards
38
Final Boards
39
Final Boards
40

More Related Content

What's hot

GN02 ADM presentation
GN02 ADM presentation GN02 ADM presentation
GN02 ADM presentation
michiefishie
 
Kenyeang green building
Kenyeang green buildingKenyeang green building
Kenyeang green building
mohd abu bakar
 
J.christopher ray sample_portfolio 2013
J.christopher ray sample_portfolio 2013J.christopher ray sample_portfolio 2013
J.christopher ray sample_portfolio 2013
jchrisray
 
CL Final Project: Report
CL Final Project: ReportCL Final Project: Report
CL Final Project: Report
NatalieKi
 
Ma'en Bata - Portfolio
Ma'en Bata - PortfolioMa'en Bata - Portfolio
Ma'en Bata - PortfolioMa'en Bata
 
WONG_ASHLEY-PORTFOLIO
WONG_ASHLEY-PORTFOLIOWONG_ASHLEY-PORTFOLIO
WONG_ASHLEY-PORTFOLIOAshley Wong
 
REISER + UMEMOTO
REISER + UMEMOTOREISER + UMEMOTO
REISER + UMEMOTO
Kethees Waran
 
Ma'en Bata - Bachelor Thesis Booklet
Ma'en Bata - Bachelor Thesis BookletMa'en Bata - Bachelor Thesis Booklet
Ma'en Bata - Bachelor Thesis BookletMa'en Bata
 
J.christopher ray portfolio 2014
J.christopher ray portfolio 2014 J.christopher ray portfolio 2014
J.christopher ray portfolio 2014
jchrisray
 
Foreground/Mid-ground/Background - 2017
Foreground/Mid-ground/Background - 2017Foreground/Mid-ground/Background - 2017
Foreground/Mid-ground/Background - 2017
cvadheim
 
Jai-Agrawal-DesignPortfolio-2015
Jai-Agrawal-DesignPortfolio-2015Jai-Agrawal-DesignPortfolio-2015
Jai-Agrawal-DesignPortfolio-2015Jai Agrawal
 
MNikolousi Portfolio-ilovepdf-compressed
MNikolousi Portfolio-ilovepdf-compressedMNikolousi Portfolio-ilovepdf-compressed
MNikolousi Portfolio-ilovepdf-compressedMaria Nikolousi
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga final
adamtys
 
The Singapore Engineer - NTU Sports Hall Cover Story
The Singapore Engineer - NTU Sports Hall Cover StoryThe Singapore Engineer - NTU Sports Hall Cover Story
The Singapore Engineer - NTU Sports Hall Cover Story
T.Y. Lin International
 
Environmental & sustainable issue of high rise building
Environmental & sustainable issue of high rise buildingEnvironmental & sustainable issue of high rise building
Environmental & sustainable issue of high rise building
khulna university
 
CL final report for proposed Garden
CL final report for proposed GardenCL final report for proposed Garden
CL final report for proposed GardenSchani B
 

What's hot (17)

GN02 ADM presentation
GN02 ADM presentation GN02 ADM presentation
GN02 ADM presentation
 
Kenyeang green building
Kenyeang green buildingKenyeang green building
Kenyeang green building
 
J.christopher ray sample_portfolio 2013
J.christopher ray sample_portfolio 2013J.christopher ray sample_portfolio 2013
J.christopher ray sample_portfolio 2013
 
CL Final Project: Report
CL Final Project: ReportCL Final Project: Report
CL Final Project: Report
 
Ma'en Bata - Portfolio
Ma'en Bata - PortfolioMa'en Bata - Portfolio
Ma'en Bata - Portfolio
 
WONG_ASHLEY-PORTFOLIO
WONG_ASHLEY-PORTFOLIOWONG_ASHLEY-PORTFOLIO
WONG_ASHLEY-PORTFOLIO
 
REISER + UMEMOTO
REISER + UMEMOTOREISER + UMEMOTO
REISER + UMEMOTO
 
Resume
ResumeResume
Resume
 
Ma'en Bata - Bachelor Thesis Booklet
Ma'en Bata - Bachelor Thesis BookletMa'en Bata - Bachelor Thesis Booklet
Ma'en Bata - Bachelor Thesis Booklet
 
J.christopher ray portfolio 2014
J.christopher ray portfolio 2014 J.christopher ray portfolio 2014
J.christopher ray portfolio 2014
 
Foreground/Mid-ground/Background - 2017
Foreground/Mid-ground/Background - 2017Foreground/Mid-ground/Background - 2017
Foreground/Mid-ground/Background - 2017
 
Jai-Agrawal-DesignPortfolio-2015
Jai-Agrawal-DesignPortfolio-2015Jai-Agrawal-DesignPortfolio-2015
Jai-Agrawal-DesignPortfolio-2015
 
MNikolousi Portfolio-ilovepdf-compressed
MNikolousi Portfolio-ilovepdf-compressedMNikolousi Portfolio-ilovepdf-compressed
MNikolousi Portfolio-ilovepdf-compressed
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga final
 
The Singapore Engineer - NTU Sports Hall Cover Story
The Singapore Engineer - NTU Sports Hall Cover StoryThe Singapore Engineer - NTU Sports Hall Cover Story
The Singapore Engineer - NTU Sports Hall Cover Story
 
Environmental & sustainable issue of high rise building
Environmental & sustainable issue of high rise buildingEnvironmental & sustainable issue of high rise building
Environmental & sustainable issue of high rise building
 
CL final report for proposed Garden
CL final report for proposed GardenCL final report for proposed Garden
CL final report for proposed Garden
 

Similar to S15 d8 Minneapolis Process Book

london-city-hall-.pptx
london-city-hall-.pptxlondon-city-hall-.pptx
london-city-hall-.pptx
gero33
 
Kirby_Tucker_Portfolio_20June2015.compressed
Kirby_Tucker_Portfolio_20June2015.compressedKirby_Tucker_Portfolio_20June2015.compressed
Kirby_Tucker_Portfolio_20June2015.compressedKirby Tucker
 
Portfolio educational alicia_a_nardo
Portfolio educational alicia_a_nardoPortfolio educational alicia_a_nardo
Portfolio educational alicia_a_nardo
Alicia Nardo
 
Sesmester 2 Portfolio
Sesmester 2 PortfolioSesmester 2 Portfolio
Sesmester 2 PortfolioStephan Homer
 
Environmental modelling report
Environmental modelling reportEnvironmental modelling report
Environmental modelling report
Jude Ndikanwu [ACIAT]
 
Blob architecture research paper
Blob architecture research paperBlob architecture research paper
Blob architecture research paper
Khushboo Saxena
 
High rise
High riseHigh rise
High rise
Ar. Sahid Akhtar
 
01-2015-Intergration
01-2015-Intergration01-2015-Intergration
01-2015-IntergrationBrad Elsbury
 
Dubai Skyline Welcomes the New Museum of the Future.docx
Dubai Skyline Welcomes the New Museum of the Future.docxDubai Skyline Welcomes the New Museum of the Future.docx
Dubai Skyline Welcomes the New Museum of the Future.docx
Dr. Ehsan Bayat
 
Btech
BtechBtech
Btech
kerneng
 
Passive Solar Design (Architecture)
Passive Solar Design (Architecture)Passive Solar Design (Architecture)
Passive Solar Design (Architecture)
williamvanzyl94
 
Inside Shanghai Tower - Exclusive interview with Chief Architect, Marshall St...
Inside Shanghai Tower - Exclusive interview with Chief Architect, Marshall St...Inside Shanghai Tower - Exclusive interview with Chief Architect, Marshall St...
Inside Shanghai Tower - Exclusive interview with Chief Architect, Marshall St...Darwin Jayson Mariano
 
Passive Solar Design (Architecture)
Passive Solar Design (Architecture)Passive Solar Design (Architecture)
Passive Solar Design (Architecture)
William van Zyl
 
Teri university campus, new delhi
Teri university campus, new delhiTeri university campus, new delhi
Teri university campus, new delhi
TAMANNA TEWARI
 
bullit center zero energy building study.pdf
bullit center zero energy building study.pdfbullit center zero energy building study.pdf
bullit center zero energy building study.pdf
ShaDy Mohamed
 

Similar to S15 d8 Minneapolis Process Book (20)

london-city-hall-.pptx
london-city-hall-.pptxlondon-city-hall-.pptx
london-city-hall-.pptx
 
Kirby_Tucker_Portfolio_20June2015.compressed
Kirby_Tucker_Portfolio_20June2015.compressedKirby_Tucker_Portfolio_20June2015.compressed
Kirby_Tucker_Portfolio_20June2015.compressed
 
Portfolio educational alicia_a_nardo
Portfolio educational alicia_a_nardoPortfolio educational alicia_a_nardo
Portfolio educational alicia_a_nardo
 
Sesmester 2 Portfolio
Sesmester 2 PortfolioSesmester 2 Portfolio
Sesmester 2 Portfolio
 
Environmental modelling report
Environmental modelling reportEnvironmental modelling report
Environmental modelling report
 
Final_Capstone_2016
Final_Capstone_2016Final_Capstone_2016
Final_Capstone_2016
 
Blob architecture research paper
Blob architecture research paperBlob architecture research paper
Blob architecture research paper
 
High rise
High riseHigh rise
High rise
 
01-2015-Intergration
01-2015-Intergration01-2015-Intergration
01-2015-Intergration
 
Dubai Skyline Welcomes the New Museum of the Future.docx
Dubai Skyline Welcomes the New Museum of the Future.docxDubai Skyline Welcomes the New Museum of the Future.docx
Dubai Skyline Welcomes the New Museum of the Future.docx
 
2015 Addendum
2015 Addendum2015 Addendum
2015 Addendum
 
Portfolio
PortfolioPortfolio
Portfolio
 
Btech
BtechBtech
Btech
 
Presentation1
Presentation1Presentation1
Presentation1
 
Passive Solar Design (Architecture)
Passive Solar Design (Architecture)Passive Solar Design (Architecture)
Passive Solar Design (Architecture)
 
Inside Shanghai Tower - Exclusive interview with Chief Architect, Marshall St...
Inside Shanghai Tower - Exclusive interview with Chief Architect, Marshall St...Inside Shanghai Tower - Exclusive interview with Chief Architect, Marshall St...
Inside Shanghai Tower - Exclusive interview with Chief Architect, Marshall St...
 
Designing a Super Tall Skyscraper
Designing a Super Tall Skyscraper Designing a Super Tall Skyscraper
Designing a Super Tall Skyscraper
 
Passive Solar Design (Architecture)
Passive Solar Design (Architecture)Passive Solar Design (Architecture)
Passive Solar Design (Architecture)
 
Teri university campus, new delhi
Teri university campus, new delhiTeri university campus, new delhi
Teri university campus, new delhi
 
bullit center zero energy building study.pdf
bullit center zero energy building study.pdfbullit center zero energy building study.pdf
bullit center zero energy building study.pdf
 

Recently uploaded

Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
garcese
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
ResDraft
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
7sd8fier
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
9a93xvy
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
fabianavillanib
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
ameli25062005
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
h7j5io0
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
7sd8fier
 
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
gpffo76j
 
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
708pb191
 
vernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdfvernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdf
PrabhjeetSingh219035
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
PlanitIsrael
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
madhavlakhanpal29
 
projectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdfprojectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdf
farazahmadas6
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
n0tivyq
 
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
asuzyq
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
smpc3nvg
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
h7j5io0
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 

Recently uploaded (20)

Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
 
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
 
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
 
vernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdfvernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdf
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
 
projectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdfprojectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdf
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
 
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 

S15 d8 Minneapolis Process Book

  • 1. Biomedical Textile Development & Research Center Steph Dudak & Mina Bellare | Fall 2015 | Design VIII | Professor Matthew Gindlesparger
  • 2.
  • 3. Table of Contents Minneapolis, MN Demographics 01 St. Anthony Falls 02 Site Selection 03 Medical Textiles 04 Program Mock Up 05 Mid Crit Presentation 06 Plans 07 Sefaira Analyses 09 Facade Development 11 Wall Sections 17 Atrium Development 19 Mechanical Systems 25 Plumbing 27 Occupancy Loads 28 Final Presentation Mock Up & Other Development 29 1/4" Final Model 33 1/32" Final Model 35 Final Presentation 36 Final Boards 37
  • 8. Program Mock Up 05 The following two boards were developed within three days of each other. While we continue to bring in basic demographic and site information in to these presentations, the focus for the board to the right is mainly on plan organization and massing.
  • 9. Mid Crit Board 06 The board for our mid crit features more definitive plan organization, site location, and bioclimatic strategies at the time. At this stage, however, we did not have much of an attitude about the exterior of the building and what it really should be. We had an idea of peeling away the existing facade but it was not executed in a way that we felt displayed our intentions about a biomedical textile center.
  • 10. Plans 07 Following our previous presentations, we worked to finalize our plans as we began to develop the facade systems. After this set of drawings, our plans would only see minor changes. We created a criteria for each room in order for it to be placed most efficiently in the building. This information also helped with the systems that we implemented and the treatment of the facade. Lighting and system needs per programmatic function
  • 12. Safaira Analyses 09 To begin progressing with the facade, we started with Sefaira daylight analyses of both the existing building and of our general intentions of the building. Doing this allowed us to see what kind of light conditions the existing and new building were experiencing in their most basic forms. What we found with these was that the existing building was mostly underlit in terms of daylight. Our proposed idea at the time was mostly overlit, with the right side showing data of being underlit. This was not an issue, however, because we already determined that the right side of the building, which houses labs and research, would need mostly artificial lighting and very little daylight. The rest of the building, however, would have to be dealt with.
  • 13. Safaira Analyses 10 The information gathered from the daylighting analyses was then used to inform our facade. After this, we figured out how much light each programmatic space needed and continued from there. Overall Sefaira analyses of existing building, our proposed building, and the three separate sections of our new building. It was relevant to separate the three "sections" because each one requires different conditions in terms of light and air.
  • 14. Facade Development 11 Facade: Initial sketches regarding facade treatments Woven facade that opens and closes according to each space and time of day Metal facade with perforations of different sizes according to programmatic spaces Fabric panels that lift in order to bring in light according to space and time of day
  • 15. Facade Development 12 During the development of our facade, we also made a decision to change the structural system of our building. While we knew we wanted to alter the existing structure, the previous alterations we had made were less informed and less structurally efficient. As a result, a decision was made to go with a steel diagrid structure around the exterior as it provides stability, uniform load distribution, and relates to the "structure" of medical textiles while facilitating the idea of wrapping. From this point, we developed a facade that featured varied levels of transparencies. We chose to develop a metal facade in an attempt to stay away from using a literal textile, but creating the various transparencies and qualities that a pulled textile would produce. The facade includes perforated metal panels, solid metal panels, clear glass, and fritted glass. Aside from acting as visual interest, these particular treatments are meant to mitigate weather and solar effects on the building based on the specific facade as well as the programmatic spaces behind the panels.
  • 16. Facade Development 13 This rendition starts to combine the idea of the aluminum panels (left) with an opening for glazing (right) with a glass pattern and a perforated metal skin wrapping. Trying to combine all of these at once perhaps was not the best way to go, however. The openings and the screens all together did not make a lot of sense.
  • 17. Facade Development 14 We began to develop a facade that "wrapped" around the building, revealing the structure where there are no panels. The idea behind this variation of the facade was that where there needs to be opaque walls, we would have an aluminum composite panel system. The transparency would be controlled with perforated panels attached to the outside of the structure to control sunlight and shade. The south facade features a double skin and the glass along the atrium would contain a fritted glass pattern similar to the perforated metal screen pattern. The fritted glass allows for some control over heat gain and shading but still allows views over the river.
  • 18. Facade Development 15 After having an idea of what the facade should be, another iteration was created and the exterior structure was laid out. From here, it made sense to continue a similar structural language to hold up the west side of the building, which before this point we were unsure of what to do. A considerable load had to be accounted for, so the existing columns were to be replaced by three large V shaped concrete supports. The facade would follow a similar pattern from here, changing depending on what each space needs. The structure at this stage also would see some changes; the intersections line up with the floor plates but still appeared very rigid as a result of their square shape. Considering we also kept the interior structure of the existing building, we found it necessary to reflect that with the exterior structure. With our final iteration, the grid would stretch so the intersections would line up with the columns and the floor plates.
  • 20. Wall Sections 17 First attempts at wall sections for the double skin attached to the south facade and for walls containing aluminum composite panels.
  • 21. Wall Sections 18 Final Wall Sections
  • 22. Atrium Development 19 In developing the atrium space, we knew it was going to be a space that was going to be the major connector between all other spaces, almost as a bridge, and was going to be a space that had multiple functions. Because of this, the quality of the space was very important and it was necessary that it be used to allow ventilation between both sides of the building. The atrium also acts as a lightwell through the building, allowing in natural light where it wasn't before, and acts as an intermediate space between both sides to promote collaboration between different disciplines (student v professional). The atrium also juxtaposes the sterile nature of a lab space, providing a green space with fresh air that removes the user from work momentarily.
  • 23. Atrium Development 20 Version 1: Initial sketches and digital representations This iteration of the atrium space explored pathways that crossed between each other and sloped upward; circulation would take place along them. As we went through this version, we realized it becomes difficult structurally and functionally. The continuous slope was not ideal on the basis that the atrium is a space that acts as a link to promote collaboration or that becomes a space that one could use to relax. The horizontal connections only existing at the edges between sloping paths also would cause a struggle to use the space.
  • 24. Atrium Development 21 Version 2: Initial section sketches of atrium space After discussing what would and would not work within the atrium, we decided to further develop a different rendition of the space that featured a continuous green wall to promote clean air (which also conceals the restroom and mechanical core) while still keeping various levels of plantings. the following plan sketches and digital representation would greatly influence our final atrium design.
  • 25. Atrium Development 22 Version 2: Initial plan sketches of atrium space
  • 26. Atrium Development 23 The intention of this iteration of the atrium is to allow the plantings to pop through the spaces from below. The circulation then cuts into the floor plates, creating areas where you're still able to look below to the other levels. There is also an equal travel distance to get from side to side, and the atrium space is symmetrical. The L shaped stairs that connect the top two levels let a user directly off to their desired side of the building (student v professional space). The stairs that connect the double height space to the level above it let the user out at the front of the floor, but are also connected to the L steps. The front of the floor plates are left unaltered because this is the primary viewing space over the river and is also an important piece of the horizontal circulation. The pathways are wide enough to accomodate basic circulation as well as plantings and seating. Version 2: Digital Representation
  • 27. Atrium Development 24 Initial sketches of the interior of the atrium spaces at each level. It is intended that the atrium would be open on the inside to promote ventilation between both sides.
  • 28. Mechanical Systems 25 Spending a lot of time on atrium and facade development, we also had to develop the mechanical systems as well as occupancy loads to determine egress. While determining plan organization, we found it most efficient for the mechanical core to be located in the very back of the atrium space. Below is our first attempt at laying out the mechanical systems.
  • 29. Mechanical Systems 26 From the beginning of the project, we had to keep the building in mind in "sections"--the student section, atrium section, and professional section--because each section required a different system because of the functions of the spaces. The labs, for example, all required new air and exhaust--air could not be recirculated through these spaces. We determined the use of CAV and VAV reheat systems for the atrium and lab spaces, respectively. Below is our final inclusion of the mechanical
  • 31. Occupancy Loads 28 Occupancy loads for the spaces were calculated to determine the means of egress for our building--one stair to the right of the mechanical room and one at the northwest corner of the "student side" of the building.
  • 32. Final Presentation Mock Up 29 The following presentation boards were the last mock up before the final presentation. Further facade development and treatment of the atrium space was also included in the workings of these boards.
  • 38. 1/32" Model & Site 35
  • 39. Final Presentation 36 Minneapolis has a strong medical, educational, and science industry that is continuing to grow and develop. Similarly, biomedical textiles is a developing industry which provides an essential service to a variety of medical practices, allowing the implementation of artificial parts in the human body. The proposal for a biomedical textile facility aims to strengthen the advancement of Minneapolis' medical practices, providing a space to manufacture, develop, implement, and research biomedical textiles as well as teach about their applications--it will also serve as a node along the Mississippi for professionals and the community alike. --- Our building site takes advantage of expansive views over the Mississippi river, proximity to relevant industry, southern exposure, and water power. However, the existing building was not efficient for our particular program. With a failing exterior structure and a desire to keep some of the character of the old building, we opted to replace the exterior structure with a steel diagrid; this allows the rigidity and structure we need to hold up the building, provide even load distribution, and reinvent the level of transparency which was not provided before. The form of the structure is derived from the structure of an actual textile, which also provides different levels of rigidity and load distribution as it is stretched and pulled. The atrium space acts as a continuation of the exterior landscape and aims to continue Minneapolis' trend of bringing green space into buildings. Cutting through the middle of the building allows the atrium to separate the "student" and "professional" sections, which require different mechanical and passive strategies while simultaneously connecting them back together through a space that intends to increase collaboration between the two. The atrium also holds all the main circulation and service cores.