City Council
      Workshop
November 8, 2012
Rock Prairie Road Corridor

 East side pavement rehabilitation


 Overpass


 West side expansion
Rock Prairie Road East
   Heavy truck traffic contributed to pavement
    degradation
      ○ Hydrocarbon trucks accessing wells
      ○ Sanitation trucks accessing the landfill


   Acquiring right-of-way for future expansion to
    four-lane boulevard section
      ○ SH 6 to William D. Fitch
      ○ ROW width is between 118-feet and 115-feet
      ○ Acquiring 20-foot wide PUE
Pavement Condition
Thoroughfare Plan – East Side
Rock Prairie Road East
 Current traffic does not warrant a four-lane
  boulevard section
 Rehabilitation project will reconstruct Rock
  Prairie from Bird Pond to William D. Fitch
      ○ Two travel lanes
      ○ Asphalt pavement
      ○ Open drainage
      ○ No sidewalks
      ○ No raised medians
   Staff will bring a design contract to Council for
    consideration in early 2013
Rock Prairie Road Overpass
   BCSMPO received $4.6 million in State
    Proposition 12 funds from TxDOT
   BCSMPO voted to allocate the funds to the
    expansion of the Rock Prairie Road Overpass
      ○ Addition of one travel lane (east bound)
      ○ 10-foot wide multi-use path on both sides of the
        overpass
      ○ U-turn structures on the north and south side
      ○ Area lighting
Rock Prairie Road Overpass
   City is responsible for funding the engineering
    design and environmental studies
   TxDOT will manage the construction of the
    project
   Final plans will be submitted to TxDOT in
    January 2013
   Construction will begin in the spring of 2013
Conceptual Layout
Rock Prairie Road West
   State Highway 6 to Wellborn Road
      ○ Four-lane Minor Arterial
      ○ General Suburban

   Adjacent land uses:
      ○ Single Family Residential
      ○ Parks
      ○ Medical Facilities
      ○ Schools
      ○ Churches
      ○ Commercial
Traffic Conditions
 Rock Prairie and Rio Grande are operating at LOS A
 Rock Prairie and Longmire are operating at LOS C
 Rock Prairie and Longmire and expected to operate
  at LOS D in 2013
 Challenges at the Longmire Intersection:
    ○ Traffic signal spacing
    ○ Land use generates high traffic volumes
    ○ Numerous left turns/driveways
    ○ Vertical deflections for drainage
Longmire Intersection
Rock Prairie Road West
 ROW acquisition for the widening of Rock
  Prairie Road West was included in the 2008
  Bond Authorization
 Collected traffic data in 2011
 Traffic model considered the following:
    ○ Barron Road Overpass

    ○ Barron Road East/Lakeway South

    ○ New development at SH 6 and William D. Fitch

    ○ Anticipated traffic from Scott and White Hospital
Conceptual Layout
Rock Prairie Road West
   Land acquisition is in progress
   Funding for design is included in the FY2013
    capital budget
   Construction of the Rock Prairie Road West
    project is expected to immediately follow
    the overpass construction
Conclusion
 Three important projects in progress
 Construction on the overpass to begin in the
  spring of 2013, and expected to take 12-
  months to complete.
 Staff will request Council approval for
  design contracts for the improvements to
  the east and west side of Rock Prairie Road
  in early 2013
East Side Acquisition
Rock Prairie Road Corridor Transportation Projects

Rock Prairie Road Corridor Transportation Projects

  • 1.
    City Council Workshop November 8, 2012
  • 2.
    Rock Prairie RoadCorridor  East side pavement rehabilitation  Overpass  West side expansion
  • 3.
    Rock Prairie RoadEast  Heavy truck traffic contributed to pavement degradation ○ Hydrocarbon trucks accessing wells ○ Sanitation trucks accessing the landfill  Acquiring right-of-way for future expansion to four-lane boulevard section ○ SH 6 to William D. Fitch ○ ROW width is between 118-feet and 115-feet ○ Acquiring 20-foot wide PUE
  • 4.
  • 5.
  • 6.
    Rock Prairie RoadEast  Current traffic does not warrant a four-lane boulevard section  Rehabilitation project will reconstruct Rock Prairie from Bird Pond to William D. Fitch ○ Two travel lanes ○ Asphalt pavement ○ Open drainage ○ No sidewalks ○ No raised medians  Staff will bring a design contract to Council for consideration in early 2013
  • 7.
    Rock Prairie RoadOverpass  BCSMPO received $4.6 million in State Proposition 12 funds from TxDOT  BCSMPO voted to allocate the funds to the expansion of the Rock Prairie Road Overpass ○ Addition of one travel lane (east bound) ○ 10-foot wide multi-use path on both sides of the overpass ○ U-turn structures on the north and south side ○ Area lighting
  • 8.
    Rock Prairie RoadOverpass  City is responsible for funding the engineering design and environmental studies  TxDOT will manage the construction of the project  Final plans will be submitted to TxDOT in January 2013  Construction will begin in the spring of 2013
  • 9.
  • 10.
    Rock Prairie RoadWest  State Highway 6 to Wellborn Road ○ Four-lane Minor Arterial ○ General Suburban  Adjacent land uses: ○ Single Family Residential ○ Parks ○ Medical Facilities ○ Schools ○ Churches ○ Commercial
  • 12.
    Traffic Conditions  RockPrairie and Rio Grande are operating at LOS A  Rock Prairie and Longmire are operating at LOS C  Rock Prairie and Longmire and expected to operate at LOS D in 2013  Challenges at the Longmire Intersection: ○ Traffic signal spacing ○ Land use generates high traffic volumes ○ Numerous left turns/driveways ○ Vertical deflections for drainage
  • 13.
  • 14.
    Rock Prairie RoadWest  ROW acquisition for the widening of Rock Prairie Road West was included in the 2008 Bond Authorization  Collected traffic data in 2011  Traffic model considered the following: ○ Barron Road Overpass ○ Barron Road East/Lakeway South ○ New development at SH 6 and William D. Fitch ○ Anticipated traffic from Scott and White Hospital
  • 15.
  • 16.
    Rock Prairie RoadWest  Land acquisition is in progress  Funding for design is included in the FY2013 capital budget  Construction of the Rock Prairie Road West project is expected to immediately follow the overpass construction
  • 17.
    Conclusion  Three importantprojects in progress  Construction on the overpass to begin in the spring of 2013, and expected to take 12- months to complete.  Staff will request Council approval for design contracts for the improvements to the east and west side of Rock Prairie Road in early 2013
  • 18.