- 2. Report
Detailed Estimate framed by Er. Jagjit Singh
Executive Engineer Const. Division PWD B&R
Patiala for S/R to L/R (Samana to Samana
Patiala Road via Noorpur Waraichan,
Khadadpur, Muradpur Mial Khurd, Tarkhan
Majra & Dhandhal) Under NABARD Scheme
– XIX.
- 3. Types of Road
NATIONAL HIGHWAY
STATE HIGHWAY
MAJOR DISTRIC ROAD
OTHER DISTRIC ROAD
LINK ROAD
- 4. Work on Link Road Diagonal Cut :
* It is provided at the distance of 3m.
Angle of the diagonal cut is to be 45ᵒ
- 5. Edging :
* It is provided both sides of
the road for stability of
stones.
* It is provided with brick’s and
its height is 4”
- 6. Laying Stones :
* Laying G-II Stones in the half
of the road i.e. 3m.
* thickness of loss stone is 4”
- 10. Wet Rolling :
* It is also known as WBM
(water bond mechadum)
- 12. Cleaning soil with compressor :
* For bonding tack coat
with metal stone
- 13. Tack Coating :
* Laying tack coat with distrubuter
* It is laying 1kg/m²
- 14. Laying 10mm aggregate over tack coat :
* Rolling after tack coat over aggregate
* For settling the metal stone
- 18. Name :- Bhupesh Sharma Roll No. :- 1180324