Roads in Victoria
                 Arterial Roads




                                  National Hwy funded by Commonwealth,
                                  managed by States
  National Hwy                    Arterial Rd funded and managed by States
Roads in Victoria
                                        Length           Networ          Travel
                  Road Type
                                         (km)            k (%)            (%)

               National
                                             1,010              0.9           8.9
               highway
 VicRoads




               Rural arterial              18,060             10.2           21.8
               Urban arterial                3,180              3.2          51.7
               Arterial Roads1            22,250             14.3           82.4

               Rural local                106,100             67.3            5.2
Govt.
Local




               Urban local                 26,400             16.8           12.4

               All road types           154,750             100.0          100.0
1           Road assets valued at AUD$23 billion, incl. 3,000+ bridges
Overall Approach
Road Safety is fully integrated into road
  infrastructure management and operations
 Specific road safety programs
  – Safer Road Infrastructure Program
 Project development & implementation
 Maintenance planning & operations
 Working on roads

“Safety is an integrated part of all
      of our road programs”
Safer Road Infrastructure
Program
Program Focus
 Run-off-road crashes on high-speed roads
 Dangerous intersections in outer metropolitan
  Melbourne
 Greyspot intersections
 Mass action treatments
   – tactile centrelines / edgelines
 Route treatment approach
 Innovation component (up to $3m per annum)
Project Development &
Implementation
Project Planning &
 Scope Approval


                     Pre-construction




      Project
    Completion
                      Construction
Road Safety Audit Policy
Road Safety Audit Stages
Project Planning & Scope
Approval
1. Identify need for project
    congestion, land use development, safety,
     special needs
2. Identify treatment options & objectives
    evaluate treatments & options to identify
     most effective project (economic & other
     criteria)
3. Approval to scope & cost
4. Listing with other candidate projects for future
   programs
Preconstruction
1. Standards for safe roads and facilities
2. Design-phase road safety audits
3. Community & stakeholder consultation
4. Construction planning
    minimise inconvenience to residents & traffic
    maximise safety for workers, traffic & residents
Construction

1. Detailed work plans
   minimise impact, maximise safety
2. Ongoing communications
   motorists & residents
3. Ongoing safety management, inspections &
   record keeping
4. Stage road safety audits
5. Site reinstatement & final acceptance
Project Completion

1. Hand over for maintenance
2. Post-construction review against project
   objectives
3. Ongoing monitoring against project objectives
   traffic volumes, delays
   road safety outcomes
   environmental outcomes
Maintenance Planning &
Operations


                              Maintenance Program


                              Routine       Periodic
                            Maintenance   Maintenance


             Road Safety

 Objective
                Asset
             Preservation
Routine Maintenance
Hazard Alerts           Regular
 from Public          Inspections



           Safety                    Condition
        Inspections                 Inspections


        Response                    Response
         Criteria                    Criteria

                      Maintenance
                         Work
Specified Requirements
Safety Inspections
 Day & Night Inspections
  – frequency depends on importance of road
     • urban freeways -> minor rural arterials
 Criteria for what is a “safety hazard”, eg.
   – any object in a traffic lane
   – pothole >300mm diameter, 100mm depth
 Specified response times
   – depends on hazard & importance of road
      • Object on urban freeway -> missing sign
        on minor rural arterial
Specified Requirements
Condition Inspections
 Monthly inspection for all roads
 Cover all road elements
   – standard list of pavement,
     drainage, roadside, structure
     items
 Criteria for what is a “Defect”
   – potholes, blocked drain, long
     grass
 Specified response times
   – depends on defect & importance
     of road
 Scheduled as routine maintenance
  activities
Periodic Maintenance
Pavement Guidelines
Roadside Guidelines
Working on Roads
Worksite Traffic Management
  Framework
 Responsibilities
 Records Management
 Traffic Management Plans
 Audit and Surveillance
 Training
 Approvals
Worksite Hazard Management
Worksite Hazard Management Process
 Step 1 – Worksite Hazard Rating
 Step 2 – Required Level of Planning
 Step 3 – Hazards at the Worksite
 Step 4 – Hazard Control Measures – Hierarchy of Safety Controls
 Step 5 – Hazard Control Measures to be Implemented
 Step 6 – Prepare and Implement Traffic Management Plan
 Step 7 – Review the Traffic Management Plan in Practice
 Step 8 – Carry Out the Work
Guidelines
Work-Related Guidelines for:
 Short term works
   – Low impact
   – Mobile works
   – Emergency works
 Long term works
   – Traffic management during works
   – Traffic management at night
   – Provision for other road users
   – Use of safety barriers
 Speed Zones
Guidelines



Work-Related Guidelines for:
 Hazard control measures
  – High Visibility Clothing
  – Use of Traffic Control Signs & Controllers
  – Use of Portable Traffic Signals
  – Use of Electronic Variable Message Signs
  – Traffic Management with Electronic Signs
Guidelines
Supplemented by Handbooks
Discussion

More Related Content

Similar to Road infrastructure safety in victoria greg chambers

Road safety tools for authorities
Road safety tools for authorities  Road safety tools for authorities
Road safety tools for authorities
Tristan Wiggill
 
Road Safety Auditing of Koratty Intersection
Road Safety Auditing of Koratty IntersectionRoad Safety Auditing of Koratty Intersection
Road Safety Auditing of Koratty Intersection
IRJET Journal
 
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
IRJET Journal
 
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
IRJET Journal
 
Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020
Fairfax County
 
Chapter 3 geometric design
Chapter 3 geometric  designChapter 3 geometric  design
Chapter 3 geometric design
BashaFayissa1
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
Roshani Shahi
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
Er. Bam Bhandari
 
Highway and railway geometric design-Revised.pptx
Highway and railway geometric design-Revised.pptxHighway and railway geometric design-Revised.pptx
Highway and railway geometric design-Revised.pptx
kiranmaqsood5
 
Introduction to Transportation Engineering_1.ppt
Introduction to Transportation Engineering_1.pptIntroduction to Transportation Engineering_1.ppt
Introduction to Transportation Engineering_1.ppt
AlyzaCaszyUmayat
 
URBAN DESIGN COMPENDIUM 1
URBAN DESIGN COMPENDIUM 1URBAN DESIGN COMPENDIUM 1
Thandapani Portfolio
Thandapani PortfolioThandapani Portfolio
Thandapani Portfolio
RONIEE Sparks
 
IRJET- Design of Parking Area and Traffic Signal for Moodbidri Town based...
IRJET-  	  Design of Parking Area and Traffic Signal for Moodbidri Town based...IRJET-  	  Design of Parking Area and Traffic Signal for Moodbidri Town based...
IRJET- Design of Parking Area and Traffic Signal for Moodbidri Town based...
IRJET Journal
 
A Critical Review on Planning & Designing Complete Intersections
A Critical Review on Planning & Designing Complete IntersectionsA Critical Review on Planning & Designing Complete Intersections
A Critical Review on Planning & Designing Complete Intersections
IRJET Journal
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
IRJET Journal
 
14.30 tarek shuaib, pace
14.30 tarek shuaib, pace14.30 tarek shuaib, pace
14.30 tarek shuaib, pace
Ibrahim Al-Hudhaif
 
Boosting Active Transportation at the Regional Level: Setting and Meeting Per...
Boosting Active Transportation at the Regional Level: Setting and Meeting Per...Boosting Active Transportation at the Regional Level: Setting and Meeting Per...
Boosting Active Transportation at the Regional Level: Setting and Meeting Per...
Project for Public Spaces & National Center for Biking and Walking
 
Case Study on Highway Geometry for Two Lane Highway
Case Study on Highway Geometry for Two Lane HighwayCase Study on Highway Geometry for Two Lane Highway
Case Study on Highway Geometry for Two Lane Highway
IRJET Journal
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Crosstown TO
 
IRJET- Comprehensive Geometric and Pavement Design of Kabaya Road, Rwanda
IRJET- Comprehensive Geometric and Pavement Design of Kabaya Road, RwandaIRJET- Comprehensive Geometric and Pavement Design of Kabaya Road, Rwanda
IRJET- Comprehensive Geometric and Pavement Design of Kabaya Road, Rwanda
IRJET Journal
 

Similar to Road infrastructure safety in victoria greg chambers (20)

Road safety tools for authorities
Road safety tools for authorities  Road safety tools for authorities
Road safety tools for authorities
 
Road Safety Auditing of Koratty Intersection
Road Safety Auditing of Koratty IntersectionRoad Safety Auditing of Koratty Intersection
Road Safety Auditing of Koratty Intersection
 
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
 
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
MEASURE EFFECTIVENESS OF ROUNDABOUTS IN URBAN AREAS AND THEIR COMPARISON WITH...
 
Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020
 
Chapter 3 geometric design
Chapter 3 geometric  designChapter 3 geometric  design
Chapter 3 geometric design
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
 
Highway and railway geometric design-Revised.pptx
Highway and railway geometric design-Revised.pptxHighway and railway geometric design-Revised.pptx
Highway and railway geometric design-Revised.pptx
 
Introduction to Transportation Engineering_1.ppt
Introduction to Transportation Engineering_1.pptIntroduction to Transportation Engineering_1.ppt
Introduction to Transportation Engineering_1.ppt
 
URBAN DESIGN COMPENDIUM 1
URBAN DESIGN COMPENDIUM 1URBAN DESIGN COMPENDIUM 1
URBAN DESIGN COMPENDIUM 1
 
Thandapani Portfolio
Thandapani PortfolioThandapani Portfolio
Thandapani Portfolio
 
IRJET- Design of Parking Area and Traffic Signal for Moodbidri Town based...
IRJET-  	  Design of Parking Area and Traffic Signal for Moodbidri Town based...IRJET-  	  Design of Parking Area and Traffic Signal for Moodbidri Town based...
IRJET- Design of Parking Area and Traffic Signal for Moodbidri Town based...
 
A Critical Review on Planning & Designing Complete Intersections
A Critical Review on Planning & Designing Complete IntersectionsA Critical Review on Planning & Designing Complete Intersections
A Critical Review on Planning & Designing Complete Intersections
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
 
14.30 tarek shuaib, pace
14.30 tarek shuaib, pace14.30 tarek shuaib, pace
14.30 tarek shuaib, pace
 
Boosting Active Transportation at the Regional Level: Setting and Meeting Per...
Boosting Active Transportation at the Regional Level: Setting and Meeting Per...Boosting Active Transportation at the Regional Level: Setting and Meeting Per...
Boosting Active Transportation at the Regional Level: Setting and Meeting Per...
 
Case Study on Highway Geometry for Two Lane Highway
Case Study on Highway Geometry for Two Lane HighwayCase Study on Highway Geometry for Two Lane Highway
Case Study on Highway Geometry for Two Lane Highway
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
IRJET- Comprehensive Geometric and Pavement Design of Kabaya Road, Rwanda
IRJET- Comprehensive Geometric and Pavement Design of Kabaya Road, RwandaIRJET- Comprehensive Geometric and Pavement Design of Kabaya Road, Rwanda
IRJET- Comprehensive Geometric and Pavement Design of Kabaya Road, Rwanda
 

More from Indonesia Infrastructure Initiative

Presentasi Sanitasi INDII
Presentasi Sanitasi INDIIPresentasi Sanitasi INDII
Presentasi Sanitasi INDII
Indonesia Infrastructure Initiative
 
Balikpapan Public Diplomacy 25 May 2015
Balikpapan  Public Diplomacy 25 May 2015Balikpapan  Public Diplomacy 25 May 2015
Balikpapan Public Diplomacy 25 May 2015
Indonesia Infrastructure Initiative
 
World experience-in-railway-restructuring
World experience-in-railway-restructuringWorld experience-in-railway-restructuring
World experience-in-railway-restructuring
Indonesia Infrastructure Initiative
 
Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesian railways revitalisation   bambang susantono, vice minister for tra...Indonesian railways revitalisation   bambang susantono, vice minister for tra...
Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesia Infrastructure Initiative
 
WS2 Infrastructure Issues
WS2 Infrastructure IssuesWS2 Infrastructure Issues
WS2 Infrastructure Issues
Indonesia Infrastructure Initiative
 
Development of multimodal transport in north java corridor
Development of multimodal transport in north java corridorDevelopment of multimodal transport in north java corridor
Development of multimodal transport in north java corridor
Indonesia Infrastructure Initiative
 
Railway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in javaRailway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in java
Indonesia Infrastructure Initiative
 
The role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in javaThe role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in java
Indonesia Infrastructure Initiative
 
Government strategy in developing multimodal transportation
Government strategy in developing multimodal transportationGovernment strategy in developing multimodal transportation
Government strategy in developing multimodal transportation
Indonesia Infrastructure Initiative
 
The role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportationThe role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportation
Indonesia Infrastructure Initiative
 
Development of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiyDevelopment of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiy
Indonesia Infrastructure Initiative
 
Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)
Indonesia Infrastructure Initiative
 
Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)
Indonesia Infrastructure Initiative
 
Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)
Indonesia Infrastructure Initiative
 
Ws3 presentation
Ws3 presentationWs3 presentation
Ws3 me
Ws3 meWs3 me
Ws3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safetyWs3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safety
Indonesia Infrastructure Initiative
 
Ws3 gender and disability presentation
Ws3 gender and disability presentationWs3 gender and disability presentation
Ws3 gender and disability presentation
Indonesia Infrastructure Initiative
 
Ws2 introduction
Ws2 introductionWs2 introduction
Workshop #2 safe system approach
Workshop #2 safe system approachWorkshop #2 safe system approach
Workshop #2 safe system approach
Indonesia Infrastructure Initiative
 

More from Indonesia Infrastructure Initiative (20)

Presentasi Sanitasi INDII
Presentasi Sanitasi INDIIPresentasi Sanitasi INDII
Presentasi Sanitasi INDII
 
Balikpapan Public Diplomacy 25 May 2015
Balikpapan  Public Diplomacy 25 May 2015Balikpapan  Public Diplomacy 25 May 2015
Balikpapan Public Diplomacy 25 May 2015
 
World experience-in-railway-restructuring
World experience-in-railway-restructuringWorld experience-in-railway-restructuring
World experience-in-railway-restructuring
 
Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesian railways revitalisation   bambang susantono, vice minister for tra...Indonesian railways revitalisation   bambang susantono, vice minister for tra...
Indonesian railways revitalisation bambang susantono, vice minister for tra...
 
WS2 Infrastructure Issues
WS2 Infrastructure IssuesWS2 Infrastructure Issues
WS2 Infrastructure Issues
 
Development of multimodal transport in north java corridor
Development of multimodal transport in north java corridorDevelopment of multimodal transport in north java corridor
Development of multimodal transport in north java corridor
 
Railway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in javaRailway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in java
 
The role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in javaThe role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in java
 
Government strategy in developing multimodal transportation
Government strategy in developing multimodal transportationGovernment strategy in developing multimodal transportation
Government strategy in developing multimodal transportation
 
The role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportationThe role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportation
 
Development of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiyDevelopment of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiy
 
Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)
 
Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)
 
Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)
 
Ws3 presentation
Ws3 presentationWs3 presentation
Ws3 presentation
 
Ws3 me
Ws3 meWs3 me
Ws3 me
 
Ws3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safetyWs3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safety
 
Ws3 gender and disability presentation
Ws3 gender and disability presentationWs3 gender and disability presentation
Ws3 gender and disability presentation
 
Ws2 introduction
Ws2 introductionWs2 introduction
Ws2 introduction
 
Workshop #2 safe system approach
Workshop #2 safe system approachWorkshop #2 safe system approach
Workshop #2 safe system approach
 

Recently uploaded

1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
ISONIKELtd
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
katiejasper96
 
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Prescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPTPrescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPT
Freelance
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
HajeJanKamps
 
The Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac SignThe Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac Sign
my Pandit
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
concepsionchomo153
 
AI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your BusinessAI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your Business
Arijit Dutta
 
Enhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: IntroductionEnhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: Introduction
Cor Verdouw
 
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
CIOWomenMagazine
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
GraceKohler1
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
ZevinAttisha
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
Cambridge Product Management Network
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Niswey
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
taqyea
 
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani case
 
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip
 
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
Ksquare Energy Pvt. Ltd.
 

Recently uploaded (20)

1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
 
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
 
Prescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPTPrescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPT
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
 
The Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac SignThe Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac Sign
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
IMG_20240615_091110.pdf dpboss guessing
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
 
AI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your BusinessAI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your Business
 
Enhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: IntroductionEnhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: Introduction
 
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
 
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
 
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
 
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
 

Road infrastructure safety in victoria greg chambers

  • 1. Road Infrastructure Safety in Victoria Greg Chambers Acting Director, Commercial & Business Services
  • 2. Roads in Victoria Arterial Roads National Hwy funded by Commonwealth, managed by States National Hwy Arterial Rd funded and managed by States
  • 3. Roads in Victoria Length Networ Travel Road Type (km) k (%) (%) National 1,010 0.9 8.9 highway VicRoads Rural arterial 18,060 10.2 21.8 Urban arterial 3,180 3.2 51.7 Arterial Roads1 22,250 14.3 82.4 Rural local 106,100 67.3 5.2 Govt. Local Urban local 26,400 16.8 12.4 All road types 154,750 100.0 100.0 1 Road assets valued at AUD$23 billion, incl. 3,000+ bridges
  • 4. Overall Approach Road Safety is fully integrated into road infrastructure management and operations  Specific road safety programs – Safer Road Infrastructure Program  Project development & implementation  Maintenance planning & operations  Working on roads “Safety is an integrated part of all of our road programs”
  • 5. Safer Road Infrastructure Program Program Focus  Run-off-road crashes on high-speed roads  Dangerous intersections in outer metropolitan Melbourne  Greyspot intersections  Mass action treatments – tactile centrelines / edgelines  Route treatment approach  Innovation component (up to $3m per annum)
  • 6. Project Development & Implementation Project Planning & Scope Approval Pre-construction Project Completion Construction
  • 9. Project Planning & Scope Approval 1. Identify need for project  congestion, land use development, safety, special needs 2. Identify treatment options & objectives  evaluate treatments & options to identify most effective project (economic & other criteria) 3. Approval to scope & cost 4. Listing with other candidate projects for future programs
  • 10. Preconstruction 1. Standards for safe roads and facilities 2. Design-phase road safety audits 3. Community & stakeholder consultation 4. Construction planning  minimise inconvenience to residents & traffic  maximise safety for workers, traffic & residents
  • 11. Construction 1. Detailed work plans  minimise impact, maximise safety 2. Ongoing communications  motorists & residents 3. Ongoing safety management, inspections & record keeping 4. Stage road safety audits 5. Site reinstatement & final acceptance
  • 12. Project Completion 1. Hand over for maintenance 2. Post-construction review against project objectives 3. Ongoing monitoring against project objectives  traffic volumes, delays  road safety outcomes  environmental outcomes
  • 13. Maintenance Planning & Operations Maintenance Program Routine Periodic Maintenance Maintenance Road Safety Objective Asset Preservation
  • 14. Routine Maintenance Hazard Alerts Regular from Public Inspections Safety Condition Inspections Inspections Response Response Criteria Criteria Maintenance Work
  • 15. Specified Requirements Safety Inspections  Day & Night Inspections – frequency depends on importance of road • urban freeways -> minor rural arterials  Criteria for what is a “safety hazard”, eg. – any object in a traffic lane – pothole >300mm diameter, 100mm depth  Specified response times – depends on hazard & importance of road • Object on urban freeway -> missing sign on minor rural arterial
  • 16. Specified Requirements Condition Inspections  Monthly inspection for all roads  Cover all road elements – standard list of pavement, drainage, roadside, structure items  Criteria for what is a “Defect” – potholes, blocked drain, long grass  Specified response times – depends on defect & importance of road  Scheduled as routine maintenance activities
  • 20. Working on Roads Worksite Traffic Management Framework  Responsibilities  Records Management  Traffic Management Plans  Audit and Surveillance  Training  Approvals
  • 21. Worksite Hazard Management Worksite Hazard Management Process  Step 1 – Worksite Hazard Rating  Step 2 – Required Level of Planning  Step 3 – Hazards at the Worksite  Step 4 – Hazard Control Measures – Hierarchy of Safety Controls  Step 5 – Hazard Control Measures to be Implemented  Step 6 – Prepare and Implement Traffic Management Plan  Step 7 – Review the Traffic Management Plan in Practice  Step 8 – Carry Out the Work
  • 22. Guidelines Work-Related Guidelines for:  Short term works – Low impact – Mobile works – Emergency works  Long term works – Traffic management during works – Traffic management at night – Provision for other road users – Use of safety barriers  Speed Zones
  • 23. Guidelines Work-Related Guidelines for:  Hazard control measures – High Visibility Clothing – Use of Traffic Control Signs & Controllers – Use of Portable Traffic Signals – Use of Electronic Variable Message Signs – Traffic Management with Electronic Signs