The document describes the risk identification and risk register for a planned vacation to Disneyland. It lists various risks that were identified across managerial, financial, environmental, individual and external categories. Some key risks included passport/visa delay, flight cancellation, natural disasters, medical emergencies and running out of money. It then provides a failure mode and effect analysis and risk probability impact matrix to analyze the risks. Finally, it includes a risk register tracking the identified risks, potential events, time, frequency and remarks to review the setup for the vacation.
41. PROBABILITY AND IMPACT MATRIX
5
Low Medium High
High 2,10,13,16,1
7,30
11,14,24,26 12,19
Mediu
m
7,28,,32,33 18,23,25 29,31
Low 1,6,22 3,8,27 4,5,9
Probability
Impact
46. Setup review
What is Setup Review?
7
Sr. No Event Time Frequency Remark
1 Passport delivery 1 month 3 Received
2 Visa confirmation 1 month 4 Confirmed
3 Flight tickets 20 days 2 Confirmed
4 Disneyland tickets 22 days 1 Confirmed
5 Resort availability 22 days 2 Confirmed
6 Forex availability 5 days 1 Available
7 Airport distress Same day 1 Confirmed
8 Flight delay same day 1 On time
9 Flight cancel same day 1 Confirmed
10 Airplane distress during journey 1 Safe
11 Natural calamities 5 days 3 No sign
12 Infrastructure damage at disneyland 2 days 1 Okay
13 Medical Emergency 5 days 2 No
14 Ran out of money anytime Not specific Backup plan
15 Weather update 4 days 4 Clear
16 Outbreak of contagious diseases 2 days 1 Not harmful
17 War situation 1day 1 No