This document summarizes the risks of filming a scene involving a car driving on the pavement near crew members. [1] The risk of the car hitting and injuring cast or crew is rated C+, as a fatal injury is possible but not frequent. [2] Preventive measures include filming in an area with a paved pavement, ensuring crew do not stand at the edge, and having stationary backup cars. [3] If an accident occurs, emergency services will be called immediately and first aid will be administered by a crew member carrying a first aid box.