SlideShare a Scribd company logo
1 of 4
Download to read offline
DATACENTER

E-MEDICAL

TRANSPORT

EMERGENCY

Master
Switch
STS Three-phase
3:3 100-600 A

Service
1st start

Highlights

•	 High reliability
•	 Hot Replacement
function
•	 3- or 4-pole version
•	 Advanced
communications

Installing a Master Switch static transfer
switch provides additional resilience and
protection from the disruption that can
be caused by the failure of a single power
source.
The result is the absolute protection of
industrial utilities and critical information
technology against power supply and load
faults.

Operating principle
Master Switch guarantees a source of
redundant power, allowing the load to
be switched between to alternative and
independent power sources.
Switching can be automatic (when a
supply source falls outside of acceptable

tolerances) or manually done by an operator
from the front panel or remotely.

Protection against power supply
faults
If one of the two power sources falls outside
tolerance levels, Master Switch will transfer
the consumers to the second power source
(switching is instantaneous if the two sources
are in phase).

Protection against environmental
disturbances
Overloads and load faults
In the event of an overload, the user can
decide the level of intervention of the
internal protection devices in order to block

Tel: 0800 210 0088 - Email: sales@ecopowersupplies.com - Website: www.ecopowersupplies.com - part of the Thamesgate Group
Redundant design
Power is supplied to the internal logic by
two physically separate supply circuits
that are fully independent and that can
be replaced in “hot replacement” mode
without causing power supply interruptions
to the load. In the event that the power
supplied by both sources fails, full system
operation is guaranteed by the “Power
Supply back up” function, which provides
auxiliary power supply to the circuits from
an external, independent power source.
Master Switch is equipped with a dual
redundant ventilation system known as:
“fan redundance plus”. Thanks to this
feature, and in the unlikely event that two
fans fail at the same time, those remaining
would still be able to dissipate the heat
generated at nominal load and with an
ambient temperature of up to 40° C.
Also the fans can be replaced in “hot
replacement” mode, ensuring continuity
during the replacement operation.

Superior protection
In the event of an output short circuit,
Master Switch blocks the transfer between
the two power sources, eliminating the
risk of propagating the short circuit and its
effects to the other loads.
A back feed control circuit ensures the

LEDs

S2

The layout of the moving components and
parts is designed to ensure easy frontal
access:
•	 power cable connections that are easily
accessed with entry from below
•	 boards housed in a dedicated area for
rapid diagnosis / replacement
•	 all parts subject to monitoring,
maintenance and/or replacement.

S4-2

Advanced communications
Master Switch provides information,
measurements, statuses, and alarms via the
LCD display.
The STS is compatible with PowerShield3
supervision and shutdown software for
Windows operating systems 8, 7, 2008,
Vista, 2003, XP, Linux, Mac OS X and Sun
Solaris.

OPTIONS
Software
PowerShield3

PRODUCT ACCESSORIES
RS232 serial duplicator
“no neutral on input” kit
IP rating IP31

ACCESSORIES
NETMAN 101 PLUS
multicom 301
multicom 351

DIMENSIONS
MTS 100
MTS 150

MTS 200 - MTS 250
MTS 300 - MTS 400

685

0
53

685

0
58

Static transfer switch SS2 closed

L7

Alarm indicator

L8

S4-1

3P + N
Output

Static transfer switch SS1 closed

L6

SS1

S3

S2 Present

L5

SS2

Output
Switch 1

S1 Present

L4

S1
Maintenance
Switch 1

S2 Priority Source

L3

Input
MCCB 2

Maintenance
Switch 2

S1 Priority Source

L2

Accessibility

  FUNCTION

L1

Input
MCCB 1

MTS 600

1900

Microprocessor control logic ensures:
• 	 Fast and safe switching between power
sources
• 	 Monitoring of all parameters via LCD
display
• 	 Constant monitoring of SCR operation
• 	 Advanced remote diagnostics (RS232 and
TCP/IP).

3P + N
Source 2
Input

1770

Total microprocessor control

3P + N
Source 1
Input

automatic intervention of the protection
devices when a return of power to one of the
two Master Switch inputs is detected.

1500

the power supply. In the extreme case of
a downstream short circuit, Master Switch
disconnects the load in order to avoid
jeopardising the operation of the other
loads (i.e. in the event of poor selectivity of
the protection devices).

Output selector ON/OFF

5 function keys and LCD operation
Tel: 0800 210 0088 - Email: sales@ecopowersupplies.com - Website: www.ecopowersupplies.com - part of the Thamesgate Group

950

0
73
MASTER SWITCH in REDUNDANT mode
The secondary power source [AS], although
highly reliable, only powers the load in the
event of a failure with the priority power
source [PS], ensuring maximum redundancy
and power quality to the loads.

[PS]

[AS]

USER 1

[AS] = Secondary
[PS] = Priority

MASTER SWITCH in CROSS FEEDING Mode
The two sources power critical loads using
Master Switches configured to selected one
of the two power sources as the priority
source [PS]. In case of a failure in one of two
sources, the other will be able to supply
power to all the loads connected to the
system).

[PS]

[AS]

USER 1
[AS]

[PS]

[AS] = Secondary
[PS] = Priority

USER 2

MASTER SWITCH in BACK-UP mode
Independent
separate lines

Master Switches power utilities via the
priority energy source [PS]; the secondary
energy source [AS] is made up of
independent, separate power sources and to
make up for any faults in the priority power
source [PS].

[PS]

[AS]

USER 1
[PS]

[AS]

[AS] = Secondary
[PS] = Priority

USER 2

DYNAMIC DUAL BUS CONFIGURATION
Bypass 1

System B
Mains

Mains

UPS2A

Mains

UPS1B

Battery

UPS1A

Bypass 2

UPS2B

Battery

Mains

Battery

System A

Battery

The Riello UPS solution guarantees
maximum reliability and ensures continuity
of power supply under all operating
conditions thanks to the UGS option that
keeps the two systems, A and B, perfectly
synchronised.
The flexibility of the UGS system ensures
synchronism between the sources even
when one of the two systems is not a
Riello UPS model, but made by another
manufacturer, or when the input sources are
not from uninterruptible power supplies.

UGS
Sinchroniser

Static Transfer
SWITCH

Load 3
Load 1

Static Transfer
SWITCH

Load 2

Load 4

Tel: 0800 210 0088 - Email: sales@ecopowersupplies.com - Website: www.ecopowersupplies.com - part of the Thamesgate Group
MODELS
NOMINAL CURRENT

MTS 100

MTS 150

MTS 200

MTS 250

MTS 300

MTS 400

MTS 600

100 A

150 A

200 A

250 A

300 A

400 A

600 A

55 dBA

57 dBA

INPUT
Nominal voltage - sources
S1/S2

380 - 400 - 415 Vac three-phase + N

Input voltage tolerance

180-264 Vac (selectable)

Switched input phases

3+N (4-pole) - 3 (3-pole)

Nominal frequency

50/60 Hz

Input frequency tolerance
range

+/-10% (selectable)

Distribution compatibility

IT, TT, TNS, TNC

OPERATING SPECIFICATIONS
Transfer type

“Break Before Make” (no overlapping sources)

Available transfer methods

Automatic / Manual / Remote

Transfer time following source
failure

< 4 msec (S1/S2 synchronised)
10 msec (S1/S2 non synchronised)

ENVIRONMENTAL
SPECIFICATIONS
Efficiency at full load
Noise at 1 m from front (from
0 to full load)

> 99%
55 dBA

55 dBA

55 dBA

Storage temperature

55 dBA

55 dBA

-10 °C up to +50 °C

Operating temperature

O °C - 40 °C

Relative humidity

95% non-condensing

Max. installation height

1000 m at nominal power (-1% power for every 100 m above 1000 m) - Max 4000 m

Reference standard

EN 62310-1 (safety) EN 62310-2 (electro-magnetic compatibility)

INFO FOR INSTALLATION
Weight (kg)
Dimensions (WxDxH) (mm)
Colour
IP rating
Moving the STS

155

160

685 x 530 x 1500

205

210

235

685 x 580 x 1770
RAL 7016
IP 20
transpallet

Tel: 0800 210 0088 - Email: sales@ecopowersupplies.com - Website: www.ecopowersupplies.com - part of the Thamesgate Group

240

375
950 x 730 x
1900

More Related Content

What's hot

Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid designsusanta das
 
Automatic Phase Changer
Automatic Phase ChangerAutomatic Phase Changer
Automatic Phase ChangerBhanu Bhawesh
 
Digital phase selector
Digital phase selectorDigital phase selector
Digital phase selectorSashank G
 
IRJET- Phase Changer Mechanism in Abnormal Conditions for Single Phase Applic...
IRJET- Phase Changer Mechanism in Abnormal Conditions for Single Phase Applic...IRJET- Phase Changer Mechanism in Abnormal Conditions for Single Phase Applic...
IRJET- Phase Changer Mechanism in Abnormal Conditions for Single Phase Applic...IRJET Journal
 
power grid synchronization failure detection
power grid synchronization failure detectionpower grid synchronization failure detection
power grid synchronization failure detectionJay Hind
 
Power grid synchronization failure detection and recovery
Power grid synchronization failure detection and recoveryPower grid synchronization failure detection and recovery
Power grid synchronization failure detection and recoveryeSAT Journals
 
Joseph Staniowski - Design Project
Joseph Staniowski - Design ProjectJoseph Staniowski - Design Project
Joseph Staniowski - Design ProjectJoseph Staniowski
 
Design and Construction of Automatic Three Phase Power System Selector
Design and Construction of Automatic Three Phase Power System SelectorDesign and Construction of Automatic Three Phase Power System Selector
Design and Construction of Automatic Three Phase Power System Selectoriosrjce
 
Power Grid Control System
Power Grid Control SystemPower Grid Control System
Power Grid Control SystemJigyasa Singh
 
UPS Electrical Design and Installation
UPS Electrical Design and InstallationUPS Electrical Design and Installation
UPS Electrical Design and InstallationJason Koffler
 
automatic phase changer in three phase supply
automatic phase changer in three phase supplyautomatic phase changer in three phase supply
automatic phase changer in three phase supplyamaljo joju e
 
IRJET - An Automatic Phase Selector from Any Available Three Phase Supply...
IRJET -  	  An Automatic Phase Selector from Any Available Three Phase Supply...IRJET -  	  An Automatic Phase Selector from Any Available Three Phase Supply...
IRJET - An Automatic Phase Selector from Any Available Three Phase Supply...IRJET Journal
 
distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangementManjunath Ds
 
Power grid synopsis
Power grid synopsisPower grid synopsis
Power grid synopsisParveen Jaat
 
Automatic load sharing of transformer using microcontroller
Automatic load sharing of transformer using microcontrollerAutomatic load sharing of transformer using microcontroller
Automatic load sharing of transformer using microcontrollerPrakhar Anand
 
IRJET- Microcontroller based Automatic Power Change Over Mechanism
IRJET- Microcontroller based Automatic Power Change Over MechanismIRJET- Microcontroller based Automatic Power Change Over Mechanism
IRJET- Microcontroller based Automatic Power Change Over MechanismIRJET Journal
 
Transformer protection using microcontroller and gsm technology
Transformer protection using microcontroller and gsm technologyTransformer protection using microcontroller and gsm technology
Transformer protection using microcontroller and gsm technologyKartik Patel
 
Detecting Power Grid Synchronization Failure on Sensing Frequency or Voltage ...
Detecting Power Grid Synchronization Failure on Sensing Frequency or Voltage ...Detecting Power Grid Synchronization Failure on Sensing Frequency or Voltage ...
Detecting Power Grid Synchronization Failure on Sensing Frequency or Voltage ...Edgefxkits & Solutions
 
SELF SWITCHING POWER SUPLLY
SELF SWITCHING POWER SUPLLYSELF SWITCHING POWER SUPLLY
SELF SWITCHING POWER SUPLLYshiv kapil
 
Controlled Power Company Overview 2010
Controlled Power Company Overview 2010Controlled Power Company Overview 2010
Controlled Power Company Overview 2010scottburge
 

What's hot (20)

Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid design
 
Automatic Phase Changer
Automatic Phase ChangerAutomatic Phase Changer
Automatic Phase Changer
 
Digital phase selector
Digital phase selectorDigital phase selector
Digital phase selector
 
IRJET- Phase Changer Mechanism in Abnormal Conditions for Single Phase Applic...
IRJET- Phase Changer Mechanism in Abnormal Conditions for Single Phase Applic...IRJET- Phase Changer Mechanism in Abnormal Conditions for Single Phase Applic...
IRJET- Phase Changer Mechanism in Abnormal Conditions for Single Phase Applic...
 
power grid synchronization failure detection
power grid synchronization failure detectionpower grid synchronization failure detection
power grid synchronization failure detection
 
Power grid synchronization failure detection and recovery
Power grid synchronization failure detection and recoveryPower grid synchronization failure detection and recovery
Power grid synchronization failure detection and recovery
 
Joseph Staniowski - Design Project
Joseph Staniowski - Design ProjectJoseph Staniowski - Design Project
Joseph Staniowski - Design Project
 
Design and Construction of Automatic Three Phase Power System Selector
Design and Construction of Automatic Three Phase Power System SelectorDesign and Construction of Automatic Three Phase Power System Selector
Design and Construction of Automatic Three Phase Power System Selector
 
Power Grid Control System
Power Grid Control SystemPower Grid Control System
Power Grid Control System
 
UPS Electrical Design and Installation
UPS Electrical Design and InstallationUPS Electrical Design and Installation
UPS Electrical Design and Installation
 
automatic phase changer in three phase supply
automatic phase changer in three phase supplyautomatic phase changer in three phase supply
automatic phase changer in three phase supply
 
IRJET - An Automatic Phase Selector from Any Available Three Phase Supply...
IRJET -  	  An Automatic Phase Selector from Any Available Three Phase Supply...IRJET -  	  An Automatic Phase Selector from Any Available Three Phase Supply...
IRJET - An Automatic Phase Selector from Any Available Three Phase Supply...
 
distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangement
 
Power grid synopsis
Power grid synopsisPower grid synopsis
Power grid synopsis
 
Automatic load sharing of transformer using microcontroller
Automatic load sharing of transformer using microcontrollerAutomatic load sharing of transformer using microcontroller
Automatic load sharing of transformer using microcontroller
 
IRJET- Microcontroller based Automatic Power Change Over Mechanism
IRJET- Microcontroller based Automatic Power Change Over MechanismIRJET- Microcontroller based Automatic Power Change Over Mechanism
IRJET- Microcontroller based Automatic Power Change Over Mechanism
 
Transformer protection using microcontroller and gsm technology
Transformer protection using microcontroller and gsm technologyTransformer protection using microcontroller and gsm technology
Transformer protection using microcontroller and gsm technology
 
Detecting Power Grid Synchronization Failure on Sensing Frequency or Voltage ...
Detecting Power Grid Synchronization Failure on Sensing Frequency or Voltage ...Detecting Power Grid Synchronization Failure on Sensing Frequency or Voltage ...
Detecting Power Grid Synchronization Failure on Sensing Frequency or Voltage ...
 
SELF SWITCHING POWER SUPLLY
SELF SWITCHING POWER SUPLLYSELF SWITCHING POWER SUPLLY
SELF SWITCHING POWER SUPLLY
 
Controlled Power Company Overview 2010
Controlled Power Company Overview 2010Controlled Power Company Overview 2010
Controlled Power Company Overview 2010
 

Similar to Riello master-switch-sts-3p

M501 d datasheet_rev1.0_20050930
M501 d datasheet_rev1.0_20050930M501 d datasheet_rev1.0_20050930
M501 d datasheet_rev1.0_20050930Raafat younis
 
LayerZero 4-Pole eSTS Static Transfer Switch with SafePanel Distribution
LayerZero 4-Pole eSTS Static Transfer Switch with SafePanel DistributionLayerZero 4-Pole eSTS Static Transfer Switch with SafePanel Distribution
LayerZero 4-Pole eSTS Static Transfer Switch with SafePanel DistributionLayerZero Power Systems, Inc.
 
3 Phase Output UPS System - Riello Power India
3 Phase Output  UPS System - Riello Power India3 Phase Output  UPS System - Riello Power India
3 Phase Output UPS System - Riello Power IndiaJacklin Berry
 
Industry tech overview by golden coffee business & investment consulting
Industry tech overview by golden coffee business & investment consultingIndustry tech overview by golden coffee business & investment consulting
Industry tech overview by golden coffee business & investment consultingSamuel Dawit
 
LayerZero Series 70: eSTS Static Transfer Switch 1600 A - 4000 A
LayerZero Series 70: eSTS Static Transfer Switch 1600 A - 4000 A LayerZero Series 70: eSTS Static Transfer Switch 1600 A - 4000 A
LayerZero Series 70: eSTS Static Transfer Switch 1600 A - 4000 A LayerZero Power Systems, Inc.
 
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOMModeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOMijsrd.com
 
Microcontroller Based Devices By Novatek Electro (India) Pvt. Ltd, Delhi
Microcontroller Based Devices By Novatek Electro (India) Pvt. Ltd, DelhiMicrocontroller Based Devices By Novatek Electro (India) Pvt. Ltd, Delhi
Microcontroller Based Devices By Novatek Electro (India) Pvt. Ltd, DelhiIndiaMART InterMESH Limited
 
Eaton 93PM 30-50kW UPS.pptx
Eaton 93PM 30-50kW UPS.pptxEaton 93PM 30-50kW UPS.pptx
Eaton 93PM 30-50kW UPS.pptxmancangkul1
 

Similar to Riello master-switch-sts-3p (20)

Riello multi-switch-ats
Riello multi-switch-atsRiello multi-switch-ats
Riello multi-switch-ats
 
Riello multi-switch-ats-16a
Riello multi-switch-ats-16aRiello multi-switch-ats-16a
Riello multi-switch-ats-16a
 
Ats brochure
Ats brochureAts brochure
Ats brochure
 
132 kv seminar ppt
132 kv seminar ppt132 kv seminar ppt
132 kv seminar ppt
 
132 kv
132 kv132 kv
132 kv
 
M501 d datasheet_rev1.0_20050930
M501 d datasheet_rev1.0_20050930M501 d datasheet_rev1.0_20050930
M501 d datasheet_rev1.0_20050930
 
Riello master-switch-sts-1p
Riello master-switch-sts-1pRiello master-switch-sts-1p
Riello master-switch-sts-1p
 
LayerZero 4-Pole eSTS Static Transfer Switch with SafePanel Distribution
LayerZero 4-Pole eSTS Static Transfer Switch with SafePanel DistributionLayerZero 4-Pole eSTS Static Transfer Switch with SafePanel Distribution
LayerZero 4-Pole eSTS Static Transfer Switch with SafePanel Distribution
 
Riello multi-guard-industrial-ups
Riello multi-guard-industrial-upsRiello multi-guard-industrial-ups
Riello multi-guard-industrial-ups
 
Riello master-hp-ups-datasheet
Riello master-hp-ups-datasheetRiello master-hp-ups-datasheet
Riello master-hp-ups-datasheet
 
3 Phase Output UPS System - Riello Power India
3 Phase Output  UPS System - Riello Power India3 Phase Output  UPS System - Riello Power India
3 Phase Output UPS System - Riello Power India
 
Industry tech overview by golden coffee business & investment consulting
Industry tech overview by golden coffee business & investment consultingIndustry tech overview by golden coffee business & investment consulting
Industry tech overview by golden coffee business & investment consulting
 
LayerZero Series 70: eSTS Static Transfer Switch 1600 A - 4000 A
LayerZero Series 70: eSTS Static Transfer Switch 1600 A - 4000 A LayerZero Series 70: eSTS Static Transfer Switch 1600 A - 4000 A
LayerZero Series 70: eSTS Static Transfer Switch 1600 A - 4000 A
 
Riello Multi Sentry Uninterruptible Power Supplies Suppliers,London UK
  Riello Multi Sentry Uninterruptible Power Supplies Suppliers,London UK  Riello Multi Sentry Uninterruptible Power Supplies Suppliers,London UK
Riello Multi Sentry Uninterruptible Power Supplies Suppliers,London UK
 
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOMModeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
 
Eaton 5130-ups-datasheet
Eaton 5130-ups-datasheetEaton 5130-ups-datasheet
Eaton 5130-ups-datasheet
 
Microcontroller Based Devices By Novatek Electro (India) Pvt. Ltd, Delhi
Microcontroller Based Devices By Novatek Electro (India) Pvt. Ltd, DelhiMicrocontroller Based Devices By Novatek Electro (India) Pvt. Ltd, Delhi
Microcontroller Based Devices By Novatek Electro (India) Pvt. Ltd, Delhi
 
Eaton 93PM 30-50kW UPS.pptx
Eaton 93PM 30-50kW UPS.pptxEaton 93PM 30-50kW UPS.pptx
Eaton 93PM 30-50kW UPS.pptx
 
Riello master-mps-ups-datasheet
Riello master-mps-ups-datasheetRiello master-mps-ups-datasheet
Riello master-mps-ups-datasheet
 
industrial traninig.pptx
industrial traninig.pptxindustrial traninig.pptx
industrial traninig.pptx
 

More from Electrical and renewable energy engineering

More from Electrical and renewable energy engineering (20)

Riello vdc-xeb-flywheel-enery-storage-systems
Riello vdc-xeb-flywheel-enery-storage-systemsRiello vdc-xeb-flywheel-enery-storage-systems
Riello vdc-xeb-flywheel-enery-storage-systems
 
Riello vdc-xeb-flywheel-enery-storage-systems
Riello vdc-xeb-flywheel-enery-storage-systemsRiello vdc-xeb-flywheel-enery-storage-systems
Riello vdc-xeb-flywheel-enery-storage-systems
 
Riello aros-central-transformer-based-solar-inverters
Riello aros-central-transformer-based-solar-invertersRiello aros-central-transformer-based-solar-inverters
Riello aros-central-transformer-based-solar-inverters
 
Riello ups-powerbox-containerised-ups
Riello ups-powerbox-containerised-upsRiello ups-powerbox-containerised-ups
Riello ups-powerbox-containerised-ups
 
Eaton 9sx-datasheet
Eaton 9sx-datasheetEaton 9sx-datasheet
Eaton 9sx-datasheet
 
Riello aros-transformerless-solar-inverters
Riello aros-transformerless-solar-invertersRiello aros-transformerless-solar-inverters
Riello aros-transformerless-solar-inverters
 
Riello aros-transformerless-solar-inverters
Riello aros-transformerless-solar-invertersRiello aros-transformerless-solar-inverters
Riello aros-transformerless-solar-inverters
 
Riello flywheel-energy-storge-systems
Riello flywheel-energy-storge-systemsRiello flywheel-energy-storge-systems
Riello flywheel-energy-storge-systems
 
Eaton epdu-power-distribution-units
Eaton epdu-power-distribution-unitsEaton epdu-power-distribution-units
Eaton epdu-power-distribution-units
 
Riello master-frequency-converters
Riello master-frequency-convertersRiello master-frequency-converters
Riello master-frequency-converters
 
Riello master-ups-vdc
Riello master-ups-vdcRiello master-ups-vdc
Riello master-ups-vdc
 
Eaton 5s-ups-datasheet
Eaton 5s-ups-datasheetEaton 5s-ups-datasheet
Eaton 5s-ups-datasheet
 
Sdmo telecoms-generator-solutions
Sdmo telecoms-generator-solutionsSdmo telecoms-generator-solutions
Sdmo telecoms-generator-solutions
 
Riello master-industrial-ups-datasheet
Riello master-industrial-ups-datasheetRiello master-industrial-ups-datasheet
Riello master-industrial-ups-datasheet
 
Riello master-wrap-around-static-bypass
Riello master-wrap-around-static-bypassRiello master-wrap-around-static-bypass
Riello master-wrap-around-static-bypass
 
Eaton ellipse-eco-ups-datasheet
Eaton ellipse-eco-ups-datasheetEaton ellipse-eco-ups-datasheet
Eaton ellipse-eco-ups-datasheet
 
Eaton 3s-ups-datasheet
Eaton 3s-ups-datasheetEaton 3s-ups-datasheet
Eaton 3s-ups-datasheet
 
Ecopowersupplies: Riello multi-guard-ups-datasheet
Ecopowersupplies: Riello multi-guard-ups-datasheetEcopowersupplies: Riello multi-guard-ups-datasheet
Ecopowersupplies: Riello multi-guard-ups-datasheet
 
Ecopowersupplies: Riello-Multi-Sentry-UPS
Ecopowersupplies: Riello-Multi-Sentry-UPSEcopowersupplies: Riello-Multi-Sentry-UPS
Ecopowersupplies: Riello-Multi-Sentry-UPS
 
Ecopowersupplies: Riello Sentinel Dual High Power UPS
Ecopowersupplies: Riello Sentinel Dual High Power UPSEcopowersupplies: Riello Sentinel Dual High Power UPS
Ecopowersupplies: Riello Sentinel Dual High Power UPS
 

Recently uploaded

Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 

Recently uploaded (20)

Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 

Riello master-switch-sts-3p

  • 1. DATACENTER E-MEDICAL TRANSPORT EMERGENCY Master Switch STS Three-phase 3:3 100-600 A Service 1st start Highlights • High reliability • Hot Replacement function • 3- or 4-pole version • Advanced communications Installing a Master Switch static transfer switch provides additional resilience and protection from the disruption that can be caused by the failure of a single power source. The result is the absolute protection of industrial utilities and critical information technology against power supply and load faults. Operating principle Master Switch guarantees a source of redundant power, allowing the load to be switched between to alternative and independent power sources. Switching can be automatic (when a supply source falls outside of acceptable tolerances) or manually done by an operator from the front panel or remotely. Protection against power supply faults If one of the two power sources falls outside tolerance levels, Master Switch will transfer the consumers to the second power source (switching is instantaneous if the two sources are in phase). Protection against environmental disturbances Overloads and load faults In the event of an overload, the user can decide the level of intervention of the internal protection devices in order to block Tel: 0800 210 0088 - Email: sales@ecopowersupplies.com - Website: www.ecopowersupplies.com - part of the Thamesgate Group
  • 2. Redundant design Power is supplied to the internal logic by two physically separate supply circuits that are fully independent and that can be replaced in “hot replacement” mode without causing power supply interruptions to the load. In the event that the power supplied by both sources fails, full system operation is guaranteed by the “Power Supply back up” function, which provides auxiliary power supply to the circuits from an external, independent power source. Master Switch is equipped with a dual redundant ventilation system known as: “fan redundance plus”. Thanks to this feature, and in the unlikely event that two fans fail at the same time, those remaining would still be able to dissipate the heat generated at nominal load and with an ambient temperature of up to 40° C. Also the fans can be replaced in “hot replacement” mode, ensuring continuity during the replacement operation. Superior protection In the event of an output short circuit, Master Switch blocks the transfer between the two power sources, eliminating the risk of propagating the short circuit and its effects to the other loads. A back feed control circuit ensures the LEDs S2 The layout of the moving components and parts is designed to ensure easy frontal access: • power cable connections that are easily accessed with entry from below • boards housed in a dedicated area for rapid diagnosis / replacement • all parts subject to monitoring, maintenance and/or replacement. S4-2 Advanced communications Master Switch provides information, measurements, statuses, and alarms via the LCD display. The STS is compatible with PowerShield3 supervision and shutdown software for Windows operating systems 8, 7, 2008, Vista, 2003, XP, Linux, Mac OS X and Sun Solaris. OPTIONS Software PowerShield3 PRODUCT ACCESSORIES RS232 serial duplicator “no neutral on input” kit IP rating IP31 ACCESSORIES NETMAN 101 PLUS multicom 301 multicom 351 DIMENSIONS MTS 100 MTS 150 MTS 200 - MTS 250 MTS 300 - MTS 400 685 0 53 685 0 58 Static transfer switch SS2 closed L7 Alarm indicator L8 S4-1 3P + N Output Static transfer switch SS1 closed L6 SS1 S3 S2 Present L5 SS2 Output Switch 1 S1 Present L4 S1 Maintenance Switch 1 S2 Priority Source L3 Input MCCB 2 Maintenance Switch 2 S1 Priority Source L2 Accessibility FUNCTION L1 Input MCCB 1 MTS 600 1900 Microprocessor control logic ensures: • Fast and safe switching between power sources • Monitoring of all parameters via LCD display • Constant monitoring of SCR operation • Advanced remote diagnostics (RS232 and TCP/IP). 3P + N Source 2 Input 1770 Total microprocessor control 3P + N Source 1 Input automatic intervention of the protection devices when a return of power to one of the two Master Switch inputs is detected. 1500 the power supply. In the extreme case of a downstream short circuit, Master Switch disconnects the load in order to avoid jeopardising the operation of the other loads (i.e. in the event of poor selectivity of the protection devices). Output selector ON/OFF 5 function keys and LCD operation Tel: 0800 210 0088 - Email: sales@ecopowersupplies.com - Website: www.ecopowersupplies.com - part of the Thamesgate Group 950 0 73
  • 3. MASTER SWITCH in REDUNDANT mode The secondary power source [AS], although highly reliable, only powers the load in the event of a failure with the priority power source [PS], ensuring maximum redundancy and power quality to the loads. [PS] [AS] USER 1 [AS] = Secondary [PS] = Priority MASTER SWITCH in CROSS FEEDING Mode The two sources power critical loads using Master Switches configured to selected one of the two power sources as the priority source [PS]. In case of a failure in one of two sources, the other will be able to supply power to all the loads connected to the system). [PS] [AS] USER 1 [AS] [PS] [AS] = Secondary [PS] = Priority USER 2 MASTER SWITCH in BACK-UP mode Independent separate lines Master Switches power utilities via the priority energy source [PS]; the secondary energy source [AS] is made up of independent, separate power sources and to make up for any faults in the priority power source [PS]. [PS] [AS] USER 1 [PS] [AS] [AS] = Secondary [PS] = Priority USER 2 DYNAMIC DUAL BUS CONFIGURATION Bypass 1 System B Mains Mains UPS2A Mains UPS1B Battery UPS1A Bypass 2 UPS2B Battery Mains Battery System A Battery The Riello UPS solution guarantees maximum reliability and ensures continuity of power supply under all operating conditions thanks to the UGS option that keeps the two systems, A and B, perfectly synchronised. The flexibility of the UGS system ensures synchronism between the sources even when one of the two systems is not a Riello UPS model, but made by another manufacturer, or when the input sources are not from uninterruptible power supplies. UGS Sinchroniser Static Transfer SWITCH Load 3 Load 1 Static Transfer SWITCH Load 2 Load 4 Tel: 0800 210 0088 - Email: sales@ecopowersupplies.com - Website: www.ecopowersupplies.com - part of the Thamesgate Group
  • 4. MODELS NOMINAL CURRENT MTS 100 MTS 150 MTS 200 MTS 250 MTS 300 MTS 400 MTS 600 100 A 150 A 200 A 250 A 300 A 400 A 600 A 55 dBA 57 dBA INPUT Nominal voltage - sources S1/S2 380 - 400 - 415 Vac three-phase + N Input voltage tolerance 180-264 Vac (selectable) Switched input phases 3+N (4-pole) - 3 (3-pole) Nominal frequency 50/60 Hz Input frequency tolerance range +/-10% (selectable) Distribution compatibility IT, TT, TNS, TNC OPERATING SPECIFICATIONS Transfer type “Break Before Make” (no overlapping sources) Available transfer methods Automatic / Manual / Remote Transfer time following source failure < 4 msec (S1/S2 synchronised) 10 msec (S1/S2 non synchronised) ENVIRONMENTAL SPECIFICATIONS Efficiency at full load Noise at 1 m from front (from 0 to full load) > 99% 55 dBA 55 dBA 55 dBA Storage temperature 55 dBA 55 dBA -10 °C up to +50 °C Operating temperature O °C - 40 °C Relative humidity 95% non-condensing Max. installation height 1000 m at nominal power (-1% power for every 100 m above 1000 m) - Max 4000 m Reference standard EN 62310-1 (safety) EN 62310-2 (electro-magnetic compatibility) INFO FOR INSTALLATION Weight (kg) Dimensions (WxDxH) (mm) Colour IP rating Moving the STS 155 160 685 x 530 x 1500 205 210 235 685 x 580 x 1770 RAL 7016 IP 20 transpallet Tel: 0800 210 0088 - Email: sales@ecopowersupplies.com - Website: www.ecopowersupplies.com - part of the Thamesgate Group 240 375 950 x 730 x 1900