JAIME R. LÓPEZ-HERNÁNDEZ
6202 Costa Brava Ceiba PR, 00735
Cel. 787-249-7563
E-mail: lopezjaimer@gmail.com
OBJECTIVE
To get a challenging position where I can apply my problem-solving skills and management ability as a Mechanical
Engineer.
PROFESSIONAL PROFILE
• Review the project plans and specifications and comment on the building design, scheduling, possible
Cost savings measures and potential construction problems.
• Preparation of project budget.
• Prepare the general conditions budget.
• Assist in assembling the job site office and equipment requirements.
• Have confidence in own ability to intelligently communicate with design team/client as well as effectively
Lead the trades.
• Expedite all shop drawings and approvals
• Preparation of the project schedule
• Monitor and maintain the project construction schedule on a weekly basis.
• Raise and discuss relevant issues at the job site meetings. Prepare & issue minutes of all site meetings
• Inform the Consultant/Client of any errors, discrepancies or omissions contained within the Consultant’s
design drawings.
• Expedite all CO (change order) costs. Maintain current CO logs.
• Monitor site safety and ensure that the requirements of the Occupational Health and Safety Act are
enforced.
• Ensure completion of and track all independent testing and inspections as required.
• Issue monthly progress draws and invoicing to consultant and client including final hold backs.
• Maintain and enforce good construction standards and quality control.
• Maintain control and responsibility for the security and operation directly owned equipment on the job site
in conjunction with site staff.
• Control and monitor labor, material and equipment expenses.
• Prepare monthly cost forecasting summaries.
• Ensure that “as built” drawings are prepared on an ongoing basis by all trades during the construction
period and issue final closeouts to consultant/owner accordingly.
• Ensure all required owner inspections are performed.
EXPERIENCE
Dic 2014 – Present Celso L. González & Asociados Loíza, PR
Project Manager
• Engineering Consultant and Contracted Inspection.
• Coordinated and performed field inspection of Civil works, Mechanical and Electrical Installation.
• Performed construction plans & shop drawing in auto cad.
• Performed project meetings.
• Performed construction permits.
• Project Coordination according with the project schedule
Oct 2012 – Dic 2014 Caguas Mechanical Contractors Caguas, PR
Project Manager
Johnson & Johnson Plant, “Janssen” projects. Gurabo, PR
A. Chiller and Pumps Installation in Condensed & Chilled Water System
• Chiller and Cooling Tower installation works at JI building.
• Coordinate works with the plant engineer and EHS Manager.
• Coordinate with sub-contractor the system balancing, insulation and alignment pumps for plant
commissioning.
• Generate requisitions for sub - contractor and Suppliers.
• Performing Daily Safety Meetings.
• Performing Risk Analysis report on project.
B. Replacement of 71 Chilled Water Control Valves at JI & JII Buildings.
• Work was conducted at the time of plant shutdown.
• Estimate work and preparation of proposals.
• Negotiation with Suppliers & Client.
• Generate requisitions for Sub - Contracts and Suppliers.
• Coordinator jobs prefabricated connection Chilled Water system.
• Coordinate with sub-contractor the insulation, controls installation and balancing test.
• Coordinate works with the plant engineer and EHS Manager.
• Performing Daily Safety Meetings.
• Performing Risk Analysis report on project.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
C. Fabrication and Installation of an Access Ladder at Manufacturing Building Area JI -9 -10.
• Estimate work and preparation of proposals
• Coordinator purchasing materials for carrying out work.
• Coordination "Rigging Plan."
• Coordinate works with the plant engineer and EHS Manager.
• Performing Daily Safety Meetings.
• Performing Risk Analysis report on project.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
D. Demolition Controls Panel System at Mechanic Room JI.
• Estimate work and preparation of proposals
• Coordinator of demolition work.
• Supervision of works.
• Performing Daily Safety Meetings.
• Performing Risk Analysis report on project.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
E. Replacement Diesel Tank Control Valves System for Generators in JI & JII.
• Estimate work and preparation of proposals
• Generate requisitions for suppliers.
• Installation Coordinator works control valves.
• Spooler connecting pre-fabricated in the system.
• Supervision of works.
• Performing Daily Safety Meetings.
• Performing Risk Analysis report on project.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
F. Replacement of two (2) Manufacturing Water Booster Pump systems at JI
• Estimate work and preparation of proposals
• Coordinator purchasing materials for carrying out work.
• Installation Coordinator works "Booster Pump".
• Supervision of works.
• Performing Daily Safety Meetings.
• Performing Risk Analysis report on project.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
G. Estimate Department
• Visit customers to quote jobs.
• Project evaluation.
• Make estimates and proposals.
• Making purchase orders.
• Negotiating with suppliers and customers.
__________________________________________________________________________________________
Mennonite Hospital Projects Caguas Mechanical Contractors Caguas, PR
A. Electrical System Improvements and A / C.
• Installation of "Chiller" Pumps & Systems at mechanical room.
• Fabrication of Electrical Sub-station.
• Supervised jobs in Condensate and Cold Water lines.
• Coordinate electrical works, Test, Balancing and pump Alignment.
• Generate requisitions for sub - contracts and suppliers.
• Supervision of works.
• Performing Daily Safety Meetings.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
B. Clean Room Construction for Drug Store.
• Installing the clean room.
• Coordinate with the sub-contractors the test and balance works.
• Ductworks installation.
• Supervision of works.
• Performing Daily Safety Meetings.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
C. Improvements Labor & Delivery Room.
• Estimate and proposal preparation work.
• Coordinator purchasing materials for carrying out work.
• Installation and AHU works coordinator.
• Coordination of work controls, insulation and installation of lines "Chilled Water"
• Supervision of works.
• Performing Daily Safety Meetings.
• Performing Risk Analysis report on project.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
______________________________________________________________________________
Puerto Rico Convention Center Projects Caguas Mechanical Contractor San Juan, PR
A. Pump System Improvement at mechanical room.
• Estimate and proposal preparation work.
• Coordinator purchasing materials for carrying out work.
• Coordinator pumps installation.
• Performing Daily Safety Meetings.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
B. Anchoring System Improvements to Ceiling Storm Water System.
• Estimate and proposal preparation work.
• Generate requisitions for sub - contracts and suppliers.
• Coordination "Rigging Plan."
• Install roof anchoring system Convention Center.
• Performing Daily Safety Meetings.
• Weekly and monthly assessments of project costs.
• Preparation of documents for invoicing.
Hotel Conrad San Juan Condado Plaza Project San Juan, PR
A. Improvements to the Building Cooling Towers "Ocean Wing & Lagoon Wing"
• Estimate and proposal preparation work.
• Negotiating with suppliers and customers.
• Coordinator purchasing materials for carrying out work.
• Coordination "Rigging Plan."
• Coordinator of manufacturing steel structures for cooling towers.
• Replacement water pipe for cooling towers.
• Installing foundation structure for existing towers.
• Performing Daily Safety Meetings.
• Weekly and monthly assessments of project costs.
• Preparation of certifications.
Dic 2005 – Oct 2012 Celso L. González & Asociados Loíza, PR
Project Manager
• Engineering Consultant and Contracted Inspection.
• Coordinated and performed field inspection of Civil works, Mechanical and Electrical Installation.
• Performed construction plans & shop drawing in auto cad.
• Performed project meetings.
• Performed construction permits.
• Project Coordination according with the project schedule.
Nov 2003 – Dic 2005 Autoridad de Carretera y Transportación Fajardo, PR
Project Engineer
Construction of Bridge PR-194 project Fajardo, PR
• Coordinator of field inspection.
• Project Coordination according with the project schedule.
• Inspection of Civil works, Mechanical and Electrical Installation.
• Perform Certifications according project schedule.
May 2000 – Nov 2003 Belmec Construction San Juan, PR
Project Engineer
Hospital de la Concepción New Facilites PR-2 Project San
Germán, PR
• Performed take-off of mechanical construction plans & shop drawing in auto cad.
• Make modification in air building distribution.
• Revised and manage quotations, purchase orders and submittals.
• Negotiated and accomplished price reduction from suppliers.
• Project field coordination according with the project schedule.
• Coordinate Mechanical (HVAC, Ductwork, chilled water, cold and hot water, fire protection, medical
gases, Plumbing), Electrical installations and rough-in with Arquitectural & Structural Drawings.
• Preparation of submittal.
• Estimate department.
June 1999- May 2000 Bared Construction San Juan, PR
Project Engineer
Reconstruction of facilities in Animal Resource at Medical Science Campus.
• Project Supervisor and Coordinator.
• Inspection of mechanical and electrical works.
• Coordinate installation HVAC, Ductwork, chilled water, cold and hot water, fire protection, plumbing
woks.
• Project field coordination according with the project schedule.
• Performed project meetings.
EDUCATION
1993-2000
• Completed a B.S. in Mechanical Engineering at the Polytechnic University of Puerto Rico.
• Extended Knowledge of management skills like planning, scheduling and contract.
• Certificate Introduction to Good Manufacturing Practices in the regulated industry (GMPs)
SKILLS
• Verbal and written skills in English and Spanish.
• Computer Programs: MS Office, Auto Cad, Construction Manager among others.
• Work under pressure and with minimum supervision, can also train and supervice people.
ORGANIZATIONS
• American Society of mechanical Engineering (ASME),
• Society Automotive Engineering (SAE).
• U.P.P.R Formula SAE and Thermal Design Team.
• Association of General Contractors of Puerto Rico.
REFERENCE:
Available upon requested.

Resume Jaime Lopez 2016

  • 1.
    JAIME R. LÓPEZ-HERNÁNDEZ 6202Costa Brava Ceiba PR, 00735 Cel. 787-249-7563 E-mail: lopezjaimer@gmail.com OBJECTIVE To get a challenging position where I can apply my problem-solving skills and management ability as a Mechanical Engineer. PROFESSIONAL PROFILE • Review the project plans and specifications and comment on the building design, scheduling, possible Cost savings measures and potential construction problems. • Preparation of project budget. • Prepare the general conditions budget. • Assist in assembling the job site office and equipment requirements. • Have confidence in own ability to intelligently communicate with design team/client as well as effectively Lead the trades. • Expedite all shop drawings and approvals • Preparation of the project schedule • Monitor and maintain the project construction schedule on a weekly basis. • Raise and discuss relevant issues at the job site meetings. Prepare & issue minutes of all site meetings • Inform the Consultant/Client of any errors, discrepancies or omissions contained within the Consultant’s design drawings. • Expedite all CO (change order) costs. Maintain current CO logs. • Monitor site safety and ensure that the requirements of the Occupational Health and Safety Act are enforced. • Ensure completion of and track all independent testing and inspections as required. • Issue monthly progress draws and invoicing to consultant and client including final hold backs. • Maintain and enforce good construction standards and quality control. • Maintain control and responsibility for the security and operation directly owned equipment on the job site in conjunction with site staff. • Control and monitor labor, material and equipment expenses. • Prepare monthly cost forecasting summaries. • Ensure that “as built” drawings are prepared on an ongoing basis by all trades during the construction period and issue final closeouts to consultant/owner accordingly. • Ensure all required owner inspections are performed. EXPERIENCE Dic 2014 – Present Celso L. González & Asociados Loíza, PR Project Manager • Engineering Consultant and Contracted Inspection. • Coordinated and performed field inspection of Civil works, Mechanical and Electrical Installation. • Performed construction plans & shop drawing in auto cad. • Performed project meetings. • Performed construction permits. • Project Coordination according with the project schedule
  • 2.
    Oct 2012 –Dic 2014 Caguas Mechanical Contractors Caguas, PR Project Manager Johnson & Johnson Plant, “Janssen” projects. Gurabo, PR A. Chiller and Pumps Installation in Condensed & Chilled Water System • Chiller and Cooling Tower installation works at JI building. • Coordinate works with the plant engineer and EHS Manager. • Coordinate with sub-contractor the system balancing, insulation and alignment pumps for plant commissioning. • Generate requisitions for sub - contractor and Suppliers. • Performing Daily Safety Meetings. • Performing Risk Analysis report on project. B. Replacement of 71 Chilled Water Control Valves at JI & JII Buildings. • Work was conducted at the time of plant shutdown. • Estimate work and preparation of proposals. • Negotiation with Suppliers & Client. • Generate requisitions for Sub - Contracts and Suppliers. • Coordinator jobs prefabricated connection Chilled Water system. • Coordinate with sub-contractor the insulation, controls installation and balancing test. • Coordinate works with the plant engineer and EHS Manager. • Performing Daily Safety Meetings. • Performing Risk Analysis report on project. • Weekly and monthly assessments of project costs. • Preparation of documents for invoicing. C. Fabrication and Installation of an Access Ladder at Manufacturing Building Area JI -9 -10. • Estimate work and preparation of proposals • Coordinator purchasing materials for carrying out work. • Coordination "Rigging Plan." • Coordinate works with the plant engineer and EHS Manager. • Performing Daily Safety Meetings. • Performing Risk Analysis report on project. • Weekly and monthly assessments of project costs. • Preparation of documents for invoicing. D. Demolition Controls Panel System at Mechanic Room JI. • Estimate work and preparation of proposals • Coordinator of demolition work. • Supervision of works. • Performing Daily Safety Meetings. • Performing Risk Analysis report on project. • Weekly and monthly assessments of project costs. • Preparation of documents for invoicing. E. Replacement Diesel Tank Control Valves System for Generators in JI & JII. • Estimate work and preparation of proposals • Generate requisitions for suppliers. • Installation Coordinator works control valves. • Spooler connecting pre-fabricated in the system. • Supervision of works. • Performing Daily Safety Meetings. • Performing Risk Analysis report on project. • Weekly and monthly assessments of project costs.
  • 3.
    • Preparation ofdocuments for invoicing. F. Replacement of two (2) Manufacturing Water Booster Pump systems at JI • Estimate work and preparation of proposals • Coordinator purchasing materials for carrying out work. • Installation Coordinator works "Booster Pump". • Supervision of works. • Performing Daily Safety Meetings. • Performing Risk Analysis report on project. • Weekly and monthly assessments of project costs. • Preparation of documents for invoicing. G. Estimate Department • Visit customers to quote jobs. • Project evaluation. • Make estimates and proposals. • Making purchase orders. • Negotiating with suppliers and customers. __________________________________________________________________________________________ Mennonite Hospital Projects Caguas Mechanical Contractors Caguas, PR A. Electrical System Improvements and A / C. • Installation of "Chiller" Pumps & Systems at mechanical room. • Fabrication of Electrical Sub-station. • Supervised jobs in Condensate and Cold Water lines. • Coordinate electrical works, Test, Balancing and pump Alignment. • Generate requisitions for sub - contracts and suppliers. • Supervision of works. • Performing Daily Safety Meetings. • Weekly and monthly assessments of project costs. • Preparation of documents for invoicing. B. Clean Room Construction for Drug Store. • Installing the clean room. • Coordinate with the sub-contractors the test and balance works. • Ductworks installation. • Supervision of works. • Performing Daily Safety Meetings. • Weekly and monthly assessments of project costs. • Preparation of documents for invoicing. C. Improvements Labor & Delivery Room. • Estimate and proposal preparation work. • Coordinator purchasing materials for carrying out work. • Installation and AHU works coordinator. • Coordination of work controls, insulation and installation of lines "Chilled Water" • Supervision of works. • Performing Daily Safety Meetings. • Performing Risk Analysis report on project. • Weekly and monthly assessments of project costs. • Preparation of documents for invoicing.
  • 4.
    ______________________________________________________________________________ Puerto Rico ConventionCenter Projects Caguas Mechanical Contractor San Juan, PR A. Pump System Improvement at mechanical room. • Estimate and proposal preparation work. • Coordinator purchasing materials for carrying out work. • Coordinator pumps installation. • Performing Daily Safety Meetings. • Weekly and monthly assessments of project costs. • Preparation of documents for invoicing. B. Anchoring System Improvements to Ceiling Storm Water System. • Estimate and proposal preparation work. • Generate requisitions for sub - contracts and suppliers. • Coordination "Rigging Plan." • Install roof anchoring system Convention Center. • Performing Daily Safety Meetings. • Weekly and monthly assessments of project costs. • Preparation of documents for invoicing. Hotel Conrad San Juan Condado Plaza Project San Juan, PR A. Improvements to the Building Cooling Towers "Ocean Wing & Lagoon Wing" • Estimate and proposal preparation work. • Negotiating with suppliers and customers. • Coordinator purchasing materials for carrying out work. • Coordination "Rigging Plan." • Coordinator of manufacturing steel structures for cooling towers. • Replacement water pipe for cooling towers. • Installing foundation structure for existing towers. • Performing Daily Safety Meetings. • Weekly and monthly assessments of project costs. • Preparation of certifications. Dic 2005 – Oct 2012 Celso L. González & Asociados Loíza, PR Project Manager • Engineering Consultant and Contracted Inspection. • Coordinated and performed field inspection of Civil works, Mechanical and Electrical Installation. • Performed construction plans & shop drawing in auto cad. • Performed project meetings. • Performed construction permits. • Project Coordination according with the project schedule. Nov 2003 – Dic 2005 Autoridad de Carretera y Transportación Fajardo, PR Project Engineer Construction of Bridge PR-194 project Fajardo, PR • Coordinator of field inspection. • Project Coordination according with the project schedule. • Inspection of Civil works, Mechanical and Electrical Installation. • Perform Certifications according project schedule.
  • 5.
    May 2000 –Nov 2003 Belmec Construction San Juan, PR Project Engineer Hospital de la Concepción New Facilites PR-2 Project San Germán, PR • Performed take-off of mechanical construction plans & shop drawing in auto cad. • Make modification in air building distribution. • Revised and manage quotations, purchase orders and submittals. • Negotiated and accomplished price reduction from suppliers. • Project field coordination according with the project schedule. • Coordinate Mechanical (HVAC, Ductwork, chilled water, cold and hot water, fire protection, medical gases, Plumbing), Electrical installations and rough-in with Arquitectural & Structural Drawings. • Preparation of submittal. • Estimate department. June 1999- May 2000 Bared Construction San Juan, PR Project Engineer Reconstruction of facilities in Animal Resource at Medical Science Campus. • Project Supervisor and Coordinator. • Inspection of mechanical and electrical works. • Coordinate installation HVAC, Ductwork, chilled water, cold and hot water, fire protection, plumbing woks. • Project field coordination according with the project schedule. • Performed project meetings. EDUCATION 1993-2000 • Completed a B.S. in Mechanical Engineering at the Polytechnic University of Puerto Rico. • Extended Knowledge of management skills like planning, scheduling and contract. • Certificate Introduction to Good Manufacturing Practices in the regulated industry (GMPs) SKILLS • Verbal and written skills in English and Spanish. • Computer Programs: MS Office, Auto Cad, Construction Manager among others. • Work under pressure and with minimum supervision, can also train and supervice people. ORGANIZATIONS • American Society of mechanical Engineering (ASME), • Society Automotive Engineering (SAE). • U.P.P.R Formula SAE and Thermal Design Team. • Association of General Contractors of Puerto Rico. REFERENCE: Available upon requested.