REQUIREMENTS FOR BUILDING PLAN APPROVAL
RESIDENTIAL BUILDING
Bungalow Building in Ado Ekiti.
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦25/M3
iv. Ratification Fee= ₦10/M2
v. Land use clearance = ₦1,000
vi. Perimeter Fencing = (Perimeter) x ₦50
vii. Location plan must be sealed by a Registered Town Planner.
Bungalow Building in Other Local Government Headquarters
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦22.5/M3
iv. Ratification Fee= ₦5/M2
v. Land use clearance = ₦1,000
vi. Perimeter Fencing = (Perimeter) x ₦50
vii. Location plan must be sealed by a Registered Town Planner.
Bungalow Building in Other Towns
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦20/M3
iv. Ratification Fee= ₦5/M2
v. Land use clearance = ₦1,000
vi. Perimeter Fencing = (Perimeter) x ₦50
vii. Location plan must be sealed by a Registered Town Planner.
Storey Building in Ado Ekiti.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦25/M3
vi. Ratification Fee= ₦10/M2
vii. Land use clearance = ₦1,000
viii. Perimeter Fencing = (Perimeter) x ₦50
ix. Location plan must be sealed by a Registered Town Planner.
Storey Building in Other Local Government Headquarters.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦22.5/M3
vi. Ratification Fee= ₦5/M2
vii. Land use clearance = ₦1,000
viii. Perimeter Fencing = (Perimeter) x ₦50
ix. Location plan must be sealed by a Registered Town Planner.
Storey Building in Other Towns.
I. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦20/M3
vi. Ratification Fee= ₦5/M2
vii. Land use clearance = ₦1,000
viii. Perimeter Fencing = (Perimeter) x ₦50
ix. Location plan must be sealed by a Registered Town Planner.
COMMERCIAL BUILDING
Bungalow/ Storey Building in Ado Ekiti.
I. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Environmental Impact Assessment.
iv. Letter of supervision by the Structural Engineer.
v. Approved survey plan by surveyor General.
vi. Assessment Fee = ₦40/M3
vii. Ratification Fee= ₦15/M2
viii. Land use clearance = ₦5,000
ix. Perimeter Fencing = (Perimeter) x ₦100
x. Location plan must be sealed by a Registered Town Planner.
Bungalow/ Storey Building in Other Towns.
I. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Environmental Impact Assessment.
iv. Letter of supervision by the Structural Engineer.
v. Approved survey plan by surveyor General.
vi. Assessment Fee = ₦40/M3
vii. Ratification Fee= ₦10/M2
viii. Land use clearance = ₦5,000
ix. Perimeter Fencing = (Perimeter) x ₦100
x. Location plan must be sealed by a Registered Town Planner.
BANK BUILDING
I. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Environmental Impact Assessment.
iv. Letter of supervision by the Structural Engineer.
v. Approved survey plan by surveyor General.
vi. Assessment Fee = ₦400/M3
vii. Ratification Fee= ₦15/M2
viii. Land use clearance = ₦5,000
ix. Perimeter Fencing = (Perimeter) x ₦100
x. Location plan must be sealed by a Registered Town Planner.
PETROL FILLING STATION
Filling Station in Ado Ekiti.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Four (4) sets of Mechanical drawings sealed by a Registered Engineer.
iv. Four (4) sets of Electrical drawings sealed by a Registered Engineer
v. Environmental Impact Assessment.
vi. Fire Service Clearance.
vii. Police Traffic Clearance.
viii. Letter of suitability/feasibility Approval from DPR.
ix. Land use clearance Approval.
x. Current 3 years tax clearance and 3 years Development levy.
xi. Letter of supervision by the Structural Engineer.
xii. Approved survey plan by surveyor General.
xiii. Assessment Fee = ₦200,000/pump
xiv. Ratification Fee= ₦15/M2
xv. Land use clearance = ₦5,000
xvi. Perimeter Fencing = (Perimeter) x ₦100
xvii. Location plan must be sealed by a Registered Town Planner.
Filling Station in Other Local Government Area.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Four (4) sets of Mechanical drawings sealed by a Registered Engineer.
iv. Four (4) sets of Electrical drawings sealed by a Registered Engineer
v. Environmental Impact Assessment.
vi. Fire Service Clearance.
vii. Police Traffic Clearance.
viii. Land use clearance Approval.
ix. Letter of suitability/feasibility Approval from DPR.
x. Current 3 years tax clearance and 3 years Development levy.
xi. Letter of supervision by the Structural Engineer.
xii. Approved survey plan by surveyor General.
xiii. Assessment Fee = ₦150,000/pump
xiv. Ratification Fee= ₦15/M2
xv. Land use clearance = ₦5,000
xvi. Perimeter Fencing = (Perimeter) x ₦100
xvii. Location plan must be sealed by a Registered Town Planner.
Filling Station in Other Towns.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Four (4) sets of Mechanical drawings sealed by a Registered Engineer.
iii. Four (4) sets of Electrical drawings sealed by a Registered Engineer
iv. Environmental Impact Assessment.
v. Fire Service Clearance.
vi. Police Traffic Clearance.
vii. Land use clearance Approval.
viii. Letter of suitability/feasibility Clearance from DPR.
ix. Current 3 years tax clearance and 3 years Development Levy.
x. Letter of supervision by the Structural Engineer.
xi. Approved survey plan by surveyor General.
xii. Assessment Fee = ₦100,000/pump
xiii. Ratification Fee= ₦15/M2
xiv. Land use clearance = ₦5,000
xv. Perimeter Fencing = (Perimeter) x ₦100
xvi. Location plan must be sealed by a Registered Town Planner.
GAS STATION.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Four (4) sets of Mechanical drawings sealed by a Registered Engineer.
iv. Four (4) sets of Electrical drawings sealed by a Registered Engineer
v. Environmental Impact Assessment.
vi. Fire Service Clearance.
vii. Police Traffic Clearance.
viii. Land use clearance Approval.
ix. Letter of suitability/feasibility from DPR.
x. Current 3 years tax clearance and 3 years Development Levy.
xi. Letter of supervision by the Structural Engineer.
xii. Approved survey plan by surveyor General.
xiii. Assessment Fee = ₦500,000
xiv. Ratification Fee= ₦15/M2
xv. Land use clearance = ₦5,000
xvi. Perimeter Fencing = (Perimeter) x ₦100
xvii. Location plan must be sealed by a Registered Town Planner.
HOSTEL.
Bungalow Building in Ado Ekiti.
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦35/M3
iv. Ratification Fee= ₦15/M2
v. Land use clearance = ₦5,000
vi. Perimeter Fencing = (Perimeter) x ₦100
vii. Location plan must be sealed by a Registered Town Planner.
viii. Environmental Impact Assessment.
Storey Building in Ado Ekiti.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦35/M3
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
Bungalow Building in Other Local Government.
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦35/M3
iv. Ratification Fee= ₦10/M2
v. Land use clearance = ₦5,000
vi. Perimeter Fencing = (Perimeter) x ₦100
vii. Location plan must be sealed by a Registered Town Planner.
viii. Environmental Impact Assessment.
Storey Building in Other Towns.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦35/M3
vi. Ratification Fee= ₦10/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
SAWMILL.
Saw Mill in Ado Ekiti.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦250,000/Mill
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
Saw Mill in Other Towns.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦150,000/Mill
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
HOTEL/EATERY/RESTAURANTS
Bungalow Building in Ado Ekiti.
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦50/M3
iv. Ratification Fee= ₦15/M2
v. Land use clearance = ₦5,000
vi. Perimeter Fencing = (Perimeter) x ₦100
vii. Location plan must be sealed by a Registered Town Planner.
viii. Environmental Impact Assessment.
Storey Building in Ado Ekiti.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦50/M3
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
Bungalow Building in Other Local Government.
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦50/M3
iv. Ratification Fee= ₦10/M2
v. Land use clearance = ₦5,000
vi. Perimeter Fencing = (Perimeter) x ₦100
vii. Location plan must be sealed by a Registered Town Planner.
viii. Environmental Impact Assessment.
Storey Building in Other Towns.
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦50/M3
vi. Ratification Fee= ₦10/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
LIGHT INDUSTRY
Block Making Industry
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦25,000
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
Concrete Industry
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦40,000
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
Stone crushing Industry (Mechanical)
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦500,000
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
Stone crushing Industry with Asphalt
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦800,000
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
AGRICULTURAL DEVELOPMENT
Mechanized Farming
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦5,000/Ha
iv. Ratification Fee= ₦15/M2
v. Land use clearance = ₦5,000
vi. Perimeter Fencing = (Perimeter) x ₦100
vii. Location plan must be sealed by a Registered Town Planner.
viii. Environmental Impact Assessment.
POULTRY FARMING
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦10,000 for (100-200) Birds
iv. Assessment Fee = ₦20,000 for (201-500) Birds
v. Ratification Fee= ₦15/M2
vi. Land use clearance = ₦5,000
vii. Perimeter Fencing = (Perimeter) x ₦100
viii. Location plan must be sealed by a Registered Town Planner.
ix. Environmental Impact Assessment.
FISHERY FARMING
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee (commercial)= ₦20,000
iv. Assessment Fee (Domestic)= ₦5,000
v. Ratification Fee= ₦15/M2
vi. Land use clearance = ₦5,000
vii. Perimeter Fencing = (Perimeter) x ₦100
viii. Location plan must be sealed by a Registered Town Planner.
ix. Environmental Impact Assessment.
PIGGERY FARMING
i. Four (4) sets of working drawings with architectural seal.
ii. Approved survey plan by surveyor General.
iii. Assessment Fee (commercial)= ₦25,000
iv. Assessment Fee (Domestic)= ₦10,000
v. Ratification Fee= ₦15/M2
vi. Land use clearance = ₦5,000
vii. Perimeter Fencing = (Perimeter) x ₦100
viii. Location plan must be sealed by a Registered Town Planner.
ix. Environmental Impact Assessment.
RELIGION CAMP GROUND
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦25/M3
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
PLACE OF WORSHIP
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦20/M3
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
EDUCATION INSTITUTION
Nursery/Primary school/Secondary school/post-Secondary school
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = ₦30/M3
vi. Ratification Fee= ₦15/M2
vii. Land use clearance = ₦5,000
viii. Perimeter Fencing = (Perimeter) x ₦100
ix. Location plan must be sealed by a Registered Town Planner.
x. Environmental Impact Assessment.
CHANGE OF SITE OF AN APPROVED PLAN
Residential
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = 25% of current charge
vi. Location plan must be sealed by a Registered Town Planner.
Commercial/Petrol Station/ Sawmill
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = 25% of current charge
vi. Location plan must be sealed by a Registered Town Planner.
vii. Environmental Impact Assessment.
RENEWAL OF BUILDING PLAN
Residential/Commercial/Industrial
i. Four (4) sets of working drawings with architectural seal.
ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
iii. Letter of supervision by the Structural Engineer.
iv. Approved survey plan by surveyor General.
v. Assessment Fee = 20% of current charge
vi. Location plan must be sealed by a Registered Town Planner.
vii. Environmental Impact Assessment. (Commercial/Industrial)
LAYOUT PLAN
i. Six (6) sets of layout plan with locational plan prepared by a Registered
Town Planner.
ii. Approved survey plan by surveyor General.
iii. Land Use Clearance =₦5,000
iv. Assessment Fee 0.5 Ha- 2.5Ha = ₦10,000
2.5Ha - 5.0Ha = ₦20,000
5.1Ha - 10Ha = ₦40,000
Above 10Ha = ₦100,000
v. Location plan must be sealed by a Registered Town Planner.
vi. Environmental Impact Assessment.
ROAD CONSTRUCTION YARD PROJECT SITE
i. Four (4) sets of working drawings with architectural seal
ii. Approved survey plan by surveyor General.
iii. Assessment Fee = ₦50,000
iv. Location plan must be sealed by a Registered Town Planner.
v. Environmental Impact Assessment.
PENALTY IN RESPECT OF UNAPPROVED EXISTING BUILDING PLAN
i. Assessment Fee = The present Assessment + 50% of the assessment
Stanchion 5
S/N Category Purpose
Amount
N
ANALYSIS
Form
fee
LUC
Registration
Construction
Permit fee
EIA
Registration
Site
inspection/
Supervision
1. Commercial 850,000 50,000 100,000 400,000 150,000 150,000
2. Corporate Bodies 200,000 20,000 25,000 100,000 30,000 25,000
3. Individual/Private 75,000 5,000 10,000 35,000 15,000 10,000
4.
Payment of Optic
Fibre
2,500 Per linear metre.
5. Caution fee 1,500 Per linear metre.
Note: Penalty for contravenor is double of the assessment fee above and other
condition determined by the ministry.

More Related Content

What's hot

Preservation of heritage structures
Preservation of heritage structuresPreservation of heritage structures
Preservation of heritage structuresDr K M SONI
 
Fire proof boards and tiles
Fire proof boards and tilesFire proof boards and tiles
Fire proof boards and tilesShamitha Reddy
 
Urban Design at different levels of Planning
Urban Design at different levels of PlanningUrban Design at different levels of Planning
Urban Design at different levels of PlanningYajush Sonar
 
Theory of architecture
Theory of architectureTheory of architecture
Theory of architectureKrishna Jhawar
 
Site Planning- Principles and Considerations
Site Planning- Principles and Considerations Site Planning- Principles and Considerations
Site Planning- Principles and Considerations ameed inam
 
Site Planning in the Context of Architectural Projects
Site Planning in the Context of Architectural Projects Site Planning in the Context of Architectural Projects
Site Planning in the Context of Architectural Projects JIT KUMAR GUPTA
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practiceAditya Sanyal
 
Theories and Concepts of town planning
Theories and Concepts of town planningTheories and Concepts of town planning
Theories and Concepts of town planningSrishti Mehta
 
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...Galala University
 
Architectural Conservation_Ac b lec 01
Architectural Conservation_Ac b lec 01Architectural Conservation_Ac b lec 01
Architectural Conservation_Ac b lec 01Joarder Hafiz Ullah
 
Planning concepts
Planning conceptsPlanning concepts
Planning conceptsctlachu
 
What's different between urban planning, urban design, architecture, AADI
What's different between urban planning, urban design, architecture, AADIWhat's different between urban planning, urban design, architecture, AADI
What's different between urban planning, urban design, architecture, AADIaalliance
 

What's hot (20)

Preservation of heritage structures
Preservation of heritage structuresPreservation of heritage structures
Preservation of heritage structures
 
Fire proof boards and tiles
Fire proof boards and tilesFire proof boards and tiles
Fire proof boards and tiles
 
Urban Design at different levels of Planning
Urban Design at different levels of PlanningUrban Design at different levels of Planning
Urban Design at different levels of Planning
 
Theory of architecture
Theory of architectureTheory of architecture
Theory of architecture
 
2.2 zoning
2.2 zoning2.2 zoning
2.2 zoning
 
Site Planning- Principles and Considerations
Site Planning- Principles and Considerations Site Planning- Principles and Considerations
Site Planning- Principles and Considerations
 
Site Planning in the Context of Architectural Projects
Site Planning in the Context of Architectural Projects Site Planning in the Context of Architectural Projects
Site Planning in the Context of Architectural Projects
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 
Theories and Concepts of town planning
Theories and Concepts of town planningTheories and Concepts of town planning
Theories and Concepts of town planning
 
SPA Professional Practice II
SPA Professional Practice IISPA Professional Practice II
SPA Professional Practice II
 
Planning Surveys
Planning SurveysPlanning Surveys
Planning Surveys
 
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
 
Architectural Conservation_Ac b lec 01
Architectural Conservation_Ac b lec 01Architectural Conservation_Ac b lec 01
Architectural Conservation_Ac b lec 01
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Planning concepts
Planning conceptsPlanning concepts
Planning concepts
 
Urban Design
Urban Design Urban Design
Urban Design
 
URDPFI - 2016
URDPFI - 2016URDPFI - 2016
URDPFI - 2016
 
Urban Roads
Urban RoadsUrban Roads
Urban Roads
 
Site planing
Site planingSite planing
Site planing
 
What's different between urban planning, urban design, architecture, AADI
What's different between urban planning, urban design, architecture, AADIWhat's different between urban planning, urban design, architecture, AADI
What's different between urban planning, urban design, architecture, AADI
 

Similar to REQUIREMENTS FOR BUILDING PLAN APPROVAL

CAC BUOC DAU TU DU AN.pdf
CAC BUOC DAU TU DU AN.pdfCAC BUOC DAU TU DU AN.pdf
CAC BUOC DAU TU DU AN.pdfHuynhVu29
 
ICI/ITD P1
ICI/ITD P1ICI/ITD P1
ICI/ITD P1Mao Hua
 
ICI_P1_PLANNER
ICI_P1_PLANNERICI_P1_PLANNER
ICI_P1_PLANNERMao Hua
 
ITD/ICI Project 1
ITD/ICI Project 1ITD/ICI Project 1
ITD/ICI Project 1TeoViVien
 
ITD_P1_PLANNER DRAWING
ITD_P1_PLANNER DRAWINGITD_P1_PLANNER DRAWING
ITD_P1_PLANNER DRAWINGMao Hua
 
ICI Project 1- Urban Planner
ICI Project 1- Urban PlannerICI Project 1- Urban Planner
ICI Project 1- Urban PlannerEricaGloriaChin
 

Similar to REQUIREMENTS FOR BUILDING PLAN APPROVAL (6)

CAC BUOC DAU TU DU AN.pdf
CAC BUOC DAU TU DU AN.pdfCAC BUOC DAU TU DU AN.pdf
CAC BUOC DAU TU DU AN.pdf
 
ICI/ITD P1
ICI/ITD P1ICI/ITD P1
ICI/ITD P1
 
ICI_P1_PLANNER
ICI_P1_PLANNERICI_P1_PLANNER
ICI_P1_PLANNER
 
ITD/ICI Project 1
ITD/ICI Project 1ITD/ICI Project 1
ITD/ICI Project 1
 
ITD_P1_PLANNER DRAWING
ITD_P1_PLANNER DRAWINGITD_P1_PLANNER DRAWING
ITD_P1_PLANNER DRAWING
 
ICI Project 1- Urban Planner
ICI Project 1- Urban PlannerICI Project 1- Urban Planner
ICI Project 1- Urban Planner
 

More from Government of Ekiti State, Nigeria

An Account of Stewardship by the Biodun Abayomi Oyebanji Administration of Ek...
An Account of Stewardship by the Biodun Abayomi Oyebanji Administration of Ek...An Account of Stewardship by the Biodun Abayomi Oyebanji Administration of Ek...
An Account of Stewardship by the Biodun Abayomi Oyebanji Administration of Ek...Government of Ekiti State, Nigeria
 
2021 REPORT OF THE EKITI STATE DEBT SUSTAINABILITY ANALYSIS AND DEBT MANAGEME...
2021 REPORT OF THE EKITI STATE DEBT SUSTAINABILITY ANALYSIS AND DEBT MANAGEME...2021 REPORT OF THE EKITI STATE DEBT SUSTAINABILITY ANALYSIS AND DEBT MANAGEME...
2021 REPORT OF THE EKITI STATE DEBT SUSTAINABILITY ANALYSIS AND DEBT MANAGEME...Government of Ekiti State, Nigeria
 
Ekiti State Drugs and Health Supplies Management Agency Law 2021
Ekiti State Drugs and Health Supplies Management Agency Law 2021Ekiti State Drugs and Health Supplies Management Agency Law 2021
Ekiti State Drugs and Health Supplies Management Agency Law 2021Government of Ekiti State, Nigeria
 
State Address on the Occasion of 25th Anniversary of Ekiti State.
State Address on the Occasion of 25th Anniversary of Ekiti State.State Address on the Occasion of 25th Anniversary of Ekiti State.
State Address on the Occasion of 25th Anniversary of Ekiti State.Government of Ekiti State, Nigeria
 
REQUEST FOR EXPRESSIONS OF INTEREST (CONSULTING SERVICES – FIRMS)
REQUEST FOR EXPRESSIONS OF INTEREST (CONSULTING SERVICES – FIRMS)REQUEST FOR EXPRESSIONS OF INTEREST (CONSULTING SERVICES – FIRMS)
REQUEST FOR EXPRESSIONS OF INTEREST (CONSULTING SERVICES – FIRMS)Government of Ekiti State, Nigeria
 
PRESS STATEMENT FROM THE DESK OF THE CHAIRMAN, LOCAL COUNCIL DEVELOPMENT AREA...
PRESS STATEMENT FROM THE DESK OF THE CHAIRMAN, LOCAL COUNCIL DEVELOPMENT AREA...PRESS STATEMENT FROM THE DESK OF THE CHAIRMAN, LOCAL COUNCIL DEVELOPMENT AREA...
PRESS STATEMENT FROM THE DESK OF THE CHAIRMAN, LOCAL COUNCIL DEVELOPMENT AREA...Government of Ekiti State, Nigeria
 
PROFILE OF HIS ROYAL MAJESTY OBA GABRIEL AYODELE ADEJUWON, FCTI., ADETILA ILU...
PROFILE OF HIS ROYAL MAJESTY OBA GABRIEL AYODELE ADEJUWON, FCTI., ADETILA ILU...PROFILE OF HIS ROYAL MAJESTY OBA GABRIEL AYODELE ADEJUWON, FCTI., ADETILA ILU...
PROFILE OF HIS ROYAL MAJESTY OBA GABRIEL AYODELE ADEJUWON, FCTI., ADETILA ILU...Government of Ekiti State, Nigeria
 
Ekiti State Joint Local Government Account and Allocation of Revenue (3rd Ame...
Ekiti State Joint Local Government Account and Allocation of Revenue (3rd Ame...Ekiti State Joint Local Government Account and Allocation of Revenue (3rd Ame...
Ekiti State Joint Local Government Account and Allocation of Revenue (3rd Ame...Government of Ekiti State, Nigeria
 
Projects (Completed and Ongoing) MINISTRY OF PHYSICAL, URBAN AND REGIONAL PLA...
Projects (Completed and Ongoing) MINISTRY OF PHYSICAL, URBAN AND REGIONAL PLA...Projects (Completed and Ongoing) MINISTRY OF PHYSICAL, URBAN AND REGIONAL PLA...
Projects (Completed and Ongoing) MINISTRY OF PHYSICAL, URBAN AND REGIONAL PLA...Government of Ekiti State, Nigeria
 
2020-2022 MEDIUM TERM EXPENDITURE FRAMEWORK (MTEF) MEDIUM TERM SECTORAL STRA...
2020-2022 MEDIUM TERM EXPENDITURE FRAMEWORK (MTEF)  MEDIUM TERM SECTORAL STRA...2020-2022 MEDIUM TERM EXPENDITURE FRAMEWORK (MTEF)  MEDIUM TERM SECTORAL STRA...
2020-2022 MEDIUM TERM EXPENDITURE FRAMEWORK (MTEF) MEDIUM TERM SECTORAL STRA...Government of Ekiti State, Nigeria
 
A Communique issued at the end of the 30th teleconference meeting of the Nige...
A Communique issued at the end of the 30th teleconference meeting of the Nige...A Communique issued at the end of the 30th teleconference meeting of the Nige...
A Communique issued at the end of the 30th teleconference meeting of the Nige...Government of Ekiti State, Nigeria
 

More from Government of Ekiti State, Nigeria (20)

An Account of Stewardship by the Biodun Abayomi Oyebanji Administration of Ek...
An Account of Stewardship by the Biodun Abayomi Oyebanji Administration of Ek...An Account of Stewardship by the Biodun Abayomi Oyebanji Administration of Ek...
An Account of Stewardship by the Biodun Abayomi Oyebanji Administration of Ek...
 
2021 REPORT OF THE EKITI STATE DEBT SUSTAINABILITY ANALYSIS AND DEBT MANAGEME...
2021 REPORT OF THE EKITI STATE DEBT SUSTAINABILITY ANALYSIS AND DEBT MANAGEME...2021 REPORT OF THE EKITI STATE DEBT SUSTAINABILITY ANALYSIS AND DEBT MANAGEME...
2021 REPORT OF THE EKITI STATE DEBT SUSTAINABILITY ANALYSIS AND DEBT MANAGEME...
 
COVID-19 VACCINATION SITES (EKITI STATE)
COVID-19  VACCINATION SITES (EKITI STATE)COVID-19  VACCINATION SITES (EKITI STATE)
COVID-19 VACCINATION SITES (EKITI STATE)
 
Re-Imagining Health Service Delivery 2020-2021 Annual Report
Re-Imagining Health Service Delivery  2020-2021 Annual ReportRe-Imagining Health Service Delivery  2020-2021 Annual Report
Re-Imagining Health Service Delivery 2020-2021 Annual Report
 
Ekiti State Mental Health Law 2021
Ekiti State Mental Health Law 2021Ekiti State Mental Health Law 2021
Ekiti State Mental Health Law 2021
 
Ekiti State Drugs and Health Supplies Management Agency Law 2021
Ekiti State Drugs and Health Supplies Management Agency Law 2021Ekiti State Drugs and Health Supplies Management Agency Law 2021
Ekiti State Drugs and Health Supplies Management Agency Law 2021
 
State Address on the Occasion of 25th Anniversary of Ekiti State.
State Address on the Occasion of 25th Anniversary of Ekiti State.State Address on the Occasion of 25th Anniversary of Ekiti State.
State Address on the Occasion of 25th Anniversary of Ekiti State.
 
REQUEST FOR EXPRESSIONS OF INTEREST (CONSULTING SERVICES – FIRMS)
REQUEST FOR EXPRESSIONS OF INTEREST (CONSULTING SERVICES – FIRMS)REQUEST FOR EXPRESSIONS OF INTEREST (CONSULTING SERVICES – FIRMS)
REQUEST FOR EXPRESSIONS OF INTEREST (CONSULTING SERVICES – FIRMS)
 
ENTITLED: TOWARDS A MORE PERFECT UNION
ENTITLED: TOWARDS A MORE PERFECT UNIONENTITLED: TOWARDS A MORE PERFECT UNION
ENTITLED: TOWARDS A MORE PERFECT UNION
 
2021 WORLD HUMANITARIAN DAY
2021 WORLD HUMANITARIAN DAY2021 WORLD HUMANITARIAN DAY
2021 WORLD HUMANITARIAN DAY
 
PRESS STATEMENT FROM THE DESK OF THE CHAIRMAN, LOCAL COUNCIL DEVELOPMENT AREA...
PRESS STATEMENT FROM THE DESK OF THE CHAIRMAN, LOCAL COUNCIL DEVELOPMENT AREA...PRESS STATEMENT FROM THE DESK OF THE CHAIRMAN, LOCAL COUNCIL DEVELOPMENT AREA...
PRESS STATEMENT FROM THE DESK OF THE CHAIRMAN, LOCAL COUNCIL DEVELOPMENT AREA...
 
PROFILE OF HIS ROYAL MAJESTY OBA GABRIEL AYODELE ADEJUWON, FCTI., ADETILA ILU...
PROFILE OF HIS ROYAL MAJESTY OBA GABRIEL AYODELE ADEJUWON, FCTI., ADETILA ILU...PROFILE OF HIS ROYAL MAJESTY OBA GABRIEL AYODELE ADEJUWON, FCTI., ADETILA ILU...
PROFILE OF HIS ROYAL MAJESTY OBA GABRIEL AYODELE ADEJUWON, FCTI., ADETILA ILU...
 
Ekiti State Joint Local Government Account and Allocation of Revenue (3rd Ame...
Ekiti State Joint Local Government Account and Allocation of Revenue (3rd Ame...Ekiti State Joint Local Government Account and Allocation of Revenue (3rd Ame...
Ekiti State Joint Local Government Account and Allocation of Revenue (3rd Ame...
 
Ekiti State Audit Service Commission Law, 2021
Ekiti State Audit Service Commission Law, 2021Ekiti State Audit Service Commission Law, 2021
Ekiti State Audit Service Commission Law, 2021
 
Projects (Completed and Ongoing) MINISTRY OF PHYSICAL, URBAN AND REGIONAL PLA...
Projects (Completed and Ongoing) MINISTRY OF PHYSICAL, URBAN AND REGIONAL PLA...Projects (Completed and Ongoing) MINISTRY OF PHYSICAL, URBAN AND REGIONAL PLA...
Projects (Completed and Ongoing) MINISTRY OF PHYSICAL, URBAN AND REGIONAL PLA...
 
2020-2022 MEDIUM TERM EXPENDITURE FRAMEWORK (MTEF) MEDIUM TERM SECTORAL STRA...
2020-2022 MEDIUM TERM EXPENDITURE FRAMEWORK (MTEF)  MEDIUM TERM SECTORAL STRA...2020-2022 MEDIUM TERM EXPENDITURE FRAMEWORK (MTEF)  MEDIUM TERM SECTORAL STRA...
2020-2022 MEDIUM TERM EXPENDITURE FRAMEWORK (MTEF) MEDIUM TERM SECTORAL STRA...
 
RECORDS OF LAND DISPUTE (PETITION) AND RESOLUTION, 2017-2019
RECORDS OF LAND DISPUTE (PETITION) AND RESOLUTION, 2017-2019RECORDS OF LAND DISPUTE (PETITION) AND RESOLUTION, 2017-2019
RECORDS OF LAND DISPUTE (PETITION) AND RESOLUTION, 2017-2019
 
Keep Girls In School
Keep Girls In SchoolKeep Girls In School
Keep Girls In School
 
A Communique issued at the end of the 30th teleconference meeting of the Nige...
A Communique issued at the end of the 30th teleconference meeting of the Nige...A Communique issued at the end of the 30th teleconference meeting of the Nige...
A Communique issued at the end of the 30th teleconference meeting of the Nige...
 
FLAGGING OFF 0F EKITI RICE PYRAMID PROJECT
FLAGGING OFF 0F EKITI RICE PYRAMID PROJECTFLAGGING OFF 0F EKITI RICE PYRAMID PROJECT
FLAGGING OFF 0F EKITI RICE PYRAMID PROJECT
 

Recently uploaded

YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfyalehistoricalreview
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...ResolutionFoundation
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Christina Parmionova
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhellokittymaearciaga
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Christina Parmionova
 
Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Christina Parmionova
 
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...saminamagar
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...narwatsonia7
 
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Servicesnajka9823
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.pptsilvialandin2
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbaisonalikaur4
 
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...Christina Parmionova
 
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...saminamagar
 
Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...yalehistoricalreview
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...ankitnayak356677
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26JSchaus & Associates
 
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Call Girls In Le Meridien hotel New Delhi 9873777170
Call Girls In Le Meridien hotel New Delhi 9873777170Call Girls In Le Meridien hotel New Delhi 9873777170
Call Girls In Le Meridien hotel New Delhi 9873777170avaniranaescorts
 

Recently uploaded (20)

YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptx
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...
 
Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.
 
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
 
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
 
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Punjabi Bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
“Exploring the world: One page turn at a time.” World Book and Copyright Day ...
 
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
call girls in West Patel Nagar DELHI 🔝 >༒9540349809 🔝 genuine Escort Service ...
 
Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...Jewish Efforts to Influence American Immigration Policy in the Years Before t...
Jewish Efforts to Influence American Immigration Policy in the Years Before t...
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26
 
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in sector 22 Gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in sector 22 Gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Call Girls In Le Meridien hotel New Delhi 9873777170
Call Girls In Le Meridien hotel New Delhi 9873777170Call Girls In Le Meridien hotel New Delhi 9873777170
Call Girls In Le Meridien hotel New Delhi 9873777170
 

REQUIREMENTS FOR BUILDING PLAN APPROVAL

  • 1. REQUIREMENTS FOR BUILDING PLAN APPROVAL RESIDENTIAL BUILDING Bungalow Building in Ado Ekiti. i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦25/M3 iv. Ratification Fee= ₦10/M2 v. Land use clearance = ₦1,000 vi. Perimeter Fencing = (Perimeter) x ₦50 vii. Location plan must be sealed by a Registered Town Planner. Bungalow Building in Other Local Government Headquarters i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦22.5/M3 iv. Ratification Fee= ₦5/M2 v. Land use clearance = ₦1,000 vi. Perimeter Fencing = (Perimeter) x ₦50 vii. Location plan must be sealed by a Registered Town Planner. Bungalow Building in Other Towns i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦20/M3 iv. Ratification Fee= ₦5/M2 v. Land use clearance = ₦1,000 vi. Perimeter Fencing = (Perimeter) x ₦50 vii. Location plan must be sealed by a Registered Town Planner.
  • 2. Storey Building in Ado Ekiti. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦25/M3 vi. Ratification Fee= ₦10/M2 vii. Land use clearance = ₦1,000 viii. Perimeter Fencing = (Perimeter) x ₦50 ix. Location plan must be sealed by a Registered Town Planner. Storey Building in Other Local Government Headquarters. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦22.5/M3 vi. Ratification Fee= ₦5/M2 vii. Land use clearance = ₦1,000 viii. Perimeter Fencing = (Perimeter) x ₦50 ix. Location plan must be sealed by a Registered Town Planner. Storey Building in Other Towns. I. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦20/M3 vi. Ratification Fee= ₦5/M2 vii. Land use clearance = ₦1,000 viii. Perimeter Fencing = (Perimeter) x ₦50 ix. Location plan must be sealed by a Registered Town Planner.
  • 3. COMMERCIAL BUILDING Bungalow/ Storey Building in Ado Ekiti. I. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Environmental Impact Assessment. iv. Letter of supervision by the Structural Engineer. v. Approved survey plan by surveyor General. vi. Assessment Fee = ₦40/M3 vii. Ratification Fee= ₦15/M2 viii. Land use clearance = ₦5,000 ix. Perimeter Fencing = (Perimeter) x ₦100 x. Location plan must be sealed by a Registered Town Planner. Bungalow/ Storey Building in Other Towns. I. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Environmental Impact Assessment. iv. Letter of supervision by the Structural Engineer. v. Approved survey plan by surveyor General. vi. Assessment Fee = ₦40/M3 vii. Ratification Fee= ₦10/M2 viii. Land use clearance = ₦5,000 ix. Perimeter Fencing = (Perimeter) x ₦100 x. Location plan must be sealed by a Registered Town Planner. BANK BUILDING I. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Environmental Impact Assessment. iv. Letter of supervision by the Structural Engineer. v. Approved survey plan by surveyor General.
  • 4. vi. Assessment Fee = ₦400/M3 vii. Ratification Fee= ₦15/M2 viii. Land use clearance = ₦5,000 ix. Perimeter Fencing = (Perimeter) x ₦100 x. Location plan must be sealed by a Registered Town Planner. PETROL FILLING STATION Filling Station in Ado Ekiti. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Four (4) sets of Mechanical drawings sealed by a Registered Engineer. iv. Four (4) sets of Electrical drawings sealed by a Registered Engineer v. Environmental Impact Assessment. vi. Fire Service Clearance. vii. Police Traffic Clearance. viii. Letter of suitability/feasibility Approval from DPR. ix. Land use clearance Approval. x. Current 3 years tax clearance and 3 years Development levy. xi. Letter of supervision by the Structural Engineer. xii. Approved survey plan by surveyor General. xiii. Assessment Fee = ₦200,000/pump xiv. Ratification Fee= ₦15/M2 xv. Land use clearance = ₦5,000 xvi. Perimeter Fencing = (Perimeter) x ₦100 xvii. Location plan must be sealed by a Registered Town Planner. Filling Station in Other Local Government Area. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Four (4) sets of Mechanical drawings sealed by a Registered Engineer. iv. Four (4) sets of Electrical drawings sealed by a Registered Engineer v. Environmental Impact Assessment.
  • 5. vi. Fire Service Clearance. vii. Police Traffic Clearance. viii. Land use clearance Approval. ix. Letter of suitability/feasibility Approval from DPR. x. Current 3 years tax clearance and 3 years Development levy. xi. Letter of supervision by the Structural Engineer. xii. Approved survey plan by surveyor General. xiii. Assessment Fee = ₦150,000/pump xiv. Ratification Fee= ₦15/M2 xv. Land use clearance = ₦5,000 xvi. Perimeter Fencing = (Perimeter) x ₦100 xvii. Location plan must be sealed by a Registered Town Planner. Filling Station in Other Towns. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Four (4) sets of Mechanical drawings sealed by a Registered Engineer. iii. Four (4) sets of Electrical drawings sealed by a Registered Engineer iv. Environmental Impact Assessment. v. Fire Service Clearance. vi. Police Traffic Clearance. vii. Land use clearance Approval. viii. Letter of suitability/feasibility Clearance from DPR. ix. Current 3 years tax clearance and 3 years Development Levy. x. Letter of supervision by the Structural Engineer. xi. Approved survey plan by surveyor General. xii. Assessment Fee = ₦100,000/pump xiii. Ratification Fee= ₦15/M2 xiv. Land use clearance = ₦5,000 xv. Perimeter Fencing = (Perimeter) x ₦100 xvi. Location plan must be sealed by a Registered Town Planner.
  • 6. GAS STATION. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Four (4) sets of Mechanical drawings sealed by a Registered Engineer. iv. Four (4) sets of Electrical drawings sealed by a Registered Engineer v. Environmental Impact Assessment. vi. Fire Service Clearance. vii. Police Traffic Clearance. viii. Land use clearance Approval. ix. Letter of suitability/feasibility from DPR. x. Current 3 years tax clearance and 3 years Development Levy. xi. Letter of supervision by the Structural Engineer. xii. Approved survey plan by surveyor General. xiii. Assessment Fee = ₦500,000 xiv. Ratification Fee= ₦15/M2 xv. Land use clearance = ₦5,000 xvi. Perimeter Fencing = (Perimeter) x ₦100 xvii. Location plan must be sealed by a Registered Town Planner. HOSTEL. Bungalow Building in Ado Ekiti. i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦35/M3 iv. Ratification Fee= ₦15/M2 v. Land use clearance = ₦5,000 vi. Perimeter Fencing = (Perimeter) x ₦100 vii. Location plan must be sealed by a Registered Town Planner. viii. Environmental Impact Assessment.
  • 7. Storey Building in Ado Ekiti. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦35/M3 vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. Bungalow Building in Other Local Government. i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦35/M3 iv. Ratification Fee= ₦10/M2 v. Land use clearance = ₦5,000 vi. Perimeter Fencing = (Perimeter) x ₦100 vii. Location plan must be sealed by a Registered Town Planner. viii. Environmental Impact Assessment. Storey Building in Other Towns. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦35/M3 vi. Ratification Fee= ₦10/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment.
  • 8. SAWMILL. Saw Mill in Ado Ekiti. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦250,000/Mill vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. Saw Mill in Other Towns. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦150,000/Mill vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. HOTEL/EATERY/RESTAURANTS Bungalow Building in Ado Ekiti. i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦50/M3 iv. Ratification Fee= ₦15/M2 v. Land use clearance = ₦5,000 vi. Perimeter Fencing = (Perimeter) x ₦100
  • 9. vii. Location plan must be sealed by a Registered Town Planner. viii. Environmental Impact Assessment. Storey Building in Ado Ekiti. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦50/M3 vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. Bungalow Building in Other Local Government. i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦50/M3 iv. Ratification Fee= ₦10/M2 v. Land use clearance = ₦5,000 vi. Perimeter Fencing = (Perimeter) x ₦100 vii. Location plan must be sealed by a Registered Town Planner. viii. Environmental Impact Assessment. Storey Building in Other Towns. i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦50/M3 vi. Ratification Fee= ₦10/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100
  • 10. ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. LIGHT INDUSTRY Block Making Industry i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦25,000 vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. Concrete Industry i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦40,000 vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. Stone crushing Industry (Mechanical) i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer.
  • 11. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦500,000 vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. Stone crushing Industry with Asphalt i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦800,000 vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. AGRICULTURAL DEVELOPMENT Mechanized Farming i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦5,000/Ha iv. Ratification Fee= ₦15/M2 v. Land use clearance = ₦5,000 vi. Perimeter Fencing = (Perimeter) x ₦100 vii. Location plan must be sealed by a Registered Town Planner. viii. Environmental Impact Assessment.
  • 12. POULTRY FARMING i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦10,000 for (100-200) Birds iv. Assessment Fee = ₦20,000 for (201-500) Birds v. Ratification Fee= ₦15/M2 vi. Land use clearance = ₦5,000 vii. Perimeter Fencing = (Perimeter) x ₦100 viii. Location plan must be sealed by a Registered Town Planner. ix. Environmental Impact Assessment. FISHERY FARMING i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee (commercial)= ₦20,000 iv. Assessment Fee (Domestic)= ₦5,000 v. Ratification Fee= ₦15/M2 vi. Land use clearance = ₦5,000 vii. Perimeter Fencing = (Perimeter) x ₦100 viii. Location plan must be sealed by a Registered Town Planner. ix. Environmental Impact Assessment. PIGGERY FARMING i. Four (4) sets of working drawings with architectural seal. ii. Approved survey plan by surveyor General. iii. Assessment Fee (commercial)= ₦25,000 iv. Assessment Fee (Domestic)= ₦10,000 v. Ratification Fee= ₦15/M2 vi. Land use clearance = ₦5,000 vii. Perimeter Fencing = (Perimeter) x ₦100 viii. Location plan must be sealed by a Registered Town Planner. ix. Environmental Impact Assessment.
  • 13. RELIGION CAMP GROUND i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦25/M3 vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. PLACE OF WORSHIP i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦20/M3 vi. Ratification Fee= ₦15/M2 vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. EDUCATION INSTITUTION Nursery/Primary school/Secondary school/post-Secondary school i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = ₦30/M3 vi. Ratification Fee= ₦15/M2
  • 14. vii. Land use clearance = ₦5,000 viii. Perimeter Fencing = (Perimeter) x ₦100 ix. Location plan must be sealed by a Registered Town Planner. x. Environmental Impact Assessment. CHANGE OF SITE OF AN APPROVED PLAN Residential i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = 25% of current charge vi. Location plan must be sealed by a Registered Town Planner. Commercial/Petrol Station/ Sawmill i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = 25% of current charge vi. Location plan must be sealed by a Registered Town Planner. vii. Environmental Impact Assessment. RENEWAL OF BUILDING PLAN Residential/Commercial/Industrial i. Four (4) sets of working drawings with architectural seal. ii. Four (4) sets of structural drawings sealed by a Registered Engineer. iii. Letter of supervision by the Structural Engineer. iv. Approved survey plan by surveyor General. v. Assessment Fee = 20% of current charge vi. Location plan must be sealed by a Registered Town Planner. vii. Environmental Impact Assessment. (Commercial/Industrial)
  • 15. LAYOUT PLAN i. Six (6) sets of layout plan with locational plan prepared by a Registered Town Planner. ii. Approved survey plan by surveyor General. iii. Land Use Clearance =₦5,000 iv. Assessment Fee 0.5 Ha- 2.5Ha = ₦10,000 2.5Ha - 5.0Ha = ₦20,000 5.1Ha - 10Ha = ₦40,000 Above 10Ha = ₦100,000 v. Location plan must be sealed by a Registered Town Planner. vi. Environmental Impact Assessment. ROAD CONSTRUCTION YARD PROJECT SITE i. Four (4) sets of working drawings with architectural seal ii. Approved survey plan by surveyor General. iii. Assessment Fee = ₦50,000 iv. Location plan must be sealed by a Registered Town Planner. v. Environmental Impact Assessment. PENALTY IN RESPECT OF UNAPPROVED EXISTING BUILDING PLAN i. Assessment Fee = The present Assessment + 50% of the assessment Stanchion 5 S/N Category Purpose Amount N ANALYSIS Form fee LUC Registration Construction Permit fee EIA Registration Site inspection/ Supervision 1. Commercial 850,000 50,000 100,000 400,000 150,000 150,000
  • 16. 2. Corporate Bodies 200,000 20,000 25,000 100,000 30,000 25,000 3. Individual/Private 75,000 5,000 10,000 35,000 15,000 10,000 4. Payment of Optic Fibre 2,500 Per linear metre. 5. Caution fee 1,500 Per linear metre. Note: Penalty for contravenor is double of the assessment fee above and other condition determined by the ministry.