This document discusses notable projects that used Reflex formwork systems to construct curved concrete walls. Some of the projects mentioned include the Mildura Waste Water Treatment Plant, Burringbar Waste Water Treatment Facility, West Pottsville Reservoir, Yepoon Reservoir Tanks, Sandgate WWTP, Mt. Julian Reservoir Tank, Point Lonsdale Tank, Heathfield Waste Water Clarifier Tank, and Mt Usher Reservoir. Reflex formwork allows for easy construction of curved walls using pre-assembled panels that can be adjusted for dimensions. Customers chose Reflex due to benefits like labor savings, improved productivity, and ease of erection and dismantling.
Replacement of 625 LF of 8" diameter sanitary sewer force main located in the Waynewood Community in Alexandria, Virginia. The new force main alignment relocated the force main from areas between residential houses and in back yards to the right of way. The project also included a waterline relocation to accommodate the new force main, two new manholes, 30 feet of sanitary gravity sewer line, new pump station driveway, and site restoration. This project was substantially complete on May 12, 2021.
Pipex FASTBUILD™ Packaged Pumping Stations can be supplied complete with Pipex FASTBUILD™ Valve Chambers and Pipex CHEMSAFE™ Pipe Systems heavy gauge HDPE rising mains. Alternatively the chambers can be supplied standalone for connection to any concrete, plastic, clay, FRP, cast iron or metallic drainage pipe system as required.
Replacement of 625 LF of 8" diameter sanitary sewer force main located in the Waynewood Community in Alexandria, Virginia. The new force main alignment relocated the force main from areas between residential houses and in back yards to the right of way. The project also included a waterline relocation to accommodate the new force main, two new manholes, 30 feet of sanitary gravity sewer line, new pump station driveway, and site restoration. This project was substantially complete on May 12, 2021.
Pipex FASTBUILD™ Packaged Pumping Stations can be supplied complete with Pipex FASTBUILD™ Valve Chambers and Pipex CHEMSAFE™ Pipe Systems heavy gauge HDPE rising mains. Alternatively the chambers can be supplied standalone for connection to any concrete, plastic, clay, FRP, cast iron or metallic drainage pipe system as required.
The Victorian Desalination Plant, based near Wonthaggi, is able to provide a source of drinking water independent of rainfall for Melbourne and some regional communities. It is capable of supplying up to 450,000 m3 of drinking water per day. The Victorian Desalination Plant, based near Wonthaggi, is able to provide a source of drinking water independent of rainfall for Melbourne and some regional communities. It is capable of supplying up to 450,000 m3 of drinking water per day.The Victorian Desalination Plant, based near Wonthaggi, is able to provide a source of drinking water independent of rainfall for Melbourne and some regional communities. It is capable of supplying up to 450,000 m3 of drinking water per day. http://www.degremont.com.au/
An ambulance station was required on the northern outskirts of Beverley to replace the ageing and outdated station in a traffic congested area of Beverley.
Enviro Excavations Capability StatementSusan Jones
Enviro Excavations is a respected hydro excavation specialist located in Melbourne, with 30 years' experience in civil construction, landscaping, tree work, and tree surgery. Providing custom on-site solutions to meet the needs of any project. The team specialise in underground utility location and have access to advanced safety and area protection equipment.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
2. Notable Reflex projects
• Mildura Waste Water Treatment Plant
• Burringbar Waste Water Treatment Facility
• West Pottsville Reservoir
• Yepoon Reservoir Tanks
• Sandgate WWTP
• Mt. Julian Reservoir Tank
• Point Lonsdale Tank
• Heathfield Waste Water Clarifier Tank
• Mt Usher Reservoir
3. Mildura WWTP
Client: G & A Constructions
Location: Mildura, Victoria
A water treatment plant was constructed
in Mildura with the capacity of 80,000Ml
to remove high levels of blue green
algae toxins from water taken from the
Murray River.
RMD Australia supported the project by
supplying Reflex formwork to construct
the circular PAC Contact Tank and Wash
Water Tank. The main reason Reflex was
used on this project was because Reflex
makes the construction of curved
concrete walls easy due to it being a
pre-assembled panel that is easily
adjusted to suit the dimensions of just
about any curved wall.
4. Burringbar waste water treatment facility
Client: Delnote Constructions
Location: Mooball, Northern NSW
RMD designed and supplied the
Reflex circular wall formwork
system for the construction of two
circular Reactor Tanks with an
internal diameter of 7.5m and wall
height of 2.2m.
When these tanks were completed
extra panels were used to construct
an Overflow Storage Tank with an
internal diameter of 9.6m and wall
height of 4.5m. To achieve this height
two 2.4m high Reflex panels were
used on top of each other. A Reflex
walkway was used to keep workers
safe and provide access.
5. Client: Tweed Shire Council
Location: North East, New South Wales
The Reflex curved wall formwork system was
ideal for the Tweed Council’s requirements
because of its excellent durability, high
productivity and significant labour gains. The
majority of the reservoirs they required were
32m in diameter and 7.2m high. The walls were
poured in four full height segments.
RMD Australia supplied special 3.6m high reflex
panels with splice plates to eliminate the need
for any stiffening soldiers across horizontal
joints. Super Slim Soldiers, push/pull props and
accessories were supplied for plumbing
purposes with special walkways on external
and internal forms. A pour rate of 1.5m per hour
was achieved.
West Pottsville reservoir
6. Yepoon reservoir tanks
Client: Hornick Constructions
Location: Yepoon, Queensland
This is one of two reservoir tanks that
Hornick Constructions built in Yepoon,
this one is 12m in height and 45
metres in Diameter.
Hornick Constructions are recognised
as one of the leaders in the design
and construction of liquid retaining
structures, reservoirs and tanks in
Queensland.
Hornick used the Reflex circular
formwork system to construct the
base of the tanks and they were very
happy with its capabilities.
7. Sandgate WWTP
Client: John Holland Pty Ltd
Location: Boondal, Queensland
The Sandgate WWTP is located at
Boondal in Brisbane and was
constructed by the Brisbane Water
Enviro-Alliance (B.W.E.A). RMD Australia’s
client was John Holland Pty Ltd.
RMD supplied 540m² of Reflex Panels to
form the clarifier tank wall and the baffle
wall forms; the pour length was 8.0m (4
panels long) and 6m high 2 x (2.4 + 1.2
Panels). The photograph shows the
Reflex formwork with Super Slim
Soldiers running up the back of them,
these are required to strengthen the join
in the panels when the panels are being
gang lifted.
8. Mt. Julian reservoir tank
Client: Clough Downer RML JV
Location: Mackay, Queensland
The Mt. Julian Reservoir Tank located
near Mackay in Queensland was
constructed using the Reflex circular wall
system. The tank has an internal
diameter of 11.8m, wall height of 3.8m and
wall thickness of 250mm. The Reflex
panel system was erected to the full
height of the reservoir using a 2.4m high
panel and a 1.2m panel bolted and
clamped together.
The main benefits realised from using
Reflex on this project was the need for
less labour and the ease and speed at
which the Reflex was erected and
dismantled.
9. Point Lonsdale tank
Client: Ace Water
Location: Point Lonsdale, Victoria
Single sided Reflex circular formwork
was used by Ace Water to construct a
tank at Point Lonsdale, a coastal
township on the Bellarine Peninsula,
near Queenscliff in Victoria.
Due to the Reflex panels being single
sided, Slimshor vertical shoring was
required to keep the panels in place.
10. Heathfield waste water clarifier tank
Client: Delnote Constructions
Location: Heathfield, South Australia
Delnote Constructions required support
in the construction of a waste-water
clarifier tank. This involved the
construction of one tank inside
another. The smaller tank has the
radius of 6.9m and the larger tank has
a radius of 14.7m. Both tanks have the
same wall height of 4.8m, which was
catered for by using 2 x 2.4m Reflex
panels.
Delnote Constructions elected to use
RMD on this project because Reflex
provides significantly improved on-site
productivity and improved labor costs.
11. Mount Usher reservoir
Client: Whitsunday Island council
Location: Whitsunday Island
The Mt Usher Reservoir is a 1.52ml
water reservoir with a diameter of
21.5m and a height of 4.9m.
The initial wall pour used the Reflex
curved wall system only, and for the
second pour, the Reflex panels were
supported on a Super Slim Soldier
walkway structure that used the tie
locations from the first pour. This
provided an access walkway around
the external and internal panels.
The Council were pleased with the
Reflex system because the panels are
easy to radius and erect, had fewer
components to use and required less
labour than other systems.