SlideShare a Scribd company logo
WYCO Construction Services LLC
4240 East Elwood Street
Phoenix, Arizona 85040
Multiple Carrier Site
Seattle, Washington
120’ Self Supporting Tower
20-Block Concrete Ballast foundation
Rapid Deployment System (RDS)
(WYCO Proprietary - Temp Tower Solution Design)
Highlights
• Existing failing structure requires a tower modification for additional capacity needs & 20’ tower-
extension.
• (4) wireless carriers required temporary displacement of equipment along one of Seattle’s busiest
highways.
• Carriers were able to achieve full network deployment of new RFDS with this robust tower design
assisting in better and faster coverage for residents while the existing structure was modified
• Jurisdiction would only approve one temp structure making this a very challenging deployment
• Project location is a critical cellular coverage area, all carriers needed to remain on air during
what was estimated as a 60-day project duration.
• Wyco Field Services & Client design collaboration
• No ground disturbance and no restoration post decomm
• Rapid deployment (total of three days from start to finish in the construction phase
Tower & Foundation Data
• Wyco Field Services, project specific foundation &
structural analysis completed and approved with CD’s
through jurisdiction
• Monopole, stealth & self-support structure options can be
utilized
• Loading supports configurations of multiple carriers to
200’+
• Concrete ballast block foundation; multi-use ballast blocks
designed for continued use & transport
• Minimal real estate footprint for compact lease areas in
many cases
• Material & equipment inventory managed by Wyco Field
Services as a value-added service
Portable Tower Site Lease Area
• Turn-Key solution, from inception of project through completion – Full Site
Acquisition, A&E & Construction services were completed to get this site
approved to be built
• Wyco Field Services coordinated pre, during, & post construction meetings
with necessary stake-holders; municipality, client, carriers
Foundation Base Material
• Native or Non-native base material can be utilized for pad leveling
• Provides level surface for ease of ballast installation
Ballast Block Installation
• Pad was built in sloped area by bringing in base rock and completed to
meet compaction requirements in one day
• Provides level surface for ease of ballast installation
Ballast Block Installation
• Keyed ballast for ease of installation & securement
• Site area must be level, sand/gravel base is used as top layer to achieve
desired foundation grade and compaction requirements
Ballast Block Installation
• Use of hydraulic ram to tighten & secure ballast blocks
• 1.25” diameter tension rods are used to fasten ballast blocks by way of
hydraulic ram-jack
Ballast Block Installation
• Final pad surface secured; strong enough to maintain most equipment shelter
enclosures, generators, and other carrier cabinet equipment
• Foundation ready for staged tower
Tower Installation
• Tower or pole Installation
• Next Steps; configuration of carrier equipment to be placed on new structure
Tower Installation Complete
• Total build time on this project from start to finish, was three days.
• After removal once the structural MOD is complete on existing tower, this site
will be removed and relocated to a new project (Multiple Use)
• Upon removal of this temp structure, the site will go back to original condition
after cleanup, requiring no restoration saving money at the decomm phase

More Related Content

What's hot

New Presentation Layout 09-09-16 Linkedin
New Presentation Layout 09-09-16 LinkedinNew Presentation Layout 09-09-16 Linkedin
New Presentation Layout 09-09-16 Linkedin
Danny Spaans
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
Aaron Cooper
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
Aaron Cooper
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
Crosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Crosstown TO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
Crosstown TO
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Neart na Gaoithe Offshore Wind
Neart na Gaoithe Offshore Wind Neart na Gaoithe Offshore Wind
Neart na Gaoithe Offshore Wind
Niamh McGrath
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Montrose BLP
Montrose BLPMontrose BLP
Montrose BLP
James Tumilty
 
Armtec Precast Insulated Wall Panels Webinar
Armtec Precast Insulated Wall Panels WebinarArmtec Precast Insulated Wall Panels Webinar
Armtec Precast Insulated Wall Panels Webinar
Communications Branding
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Loksa Shipyard presentation
Loksa Shipyard presentationLoksa Shipyard presentation
Loksa Shipyard presentation
LoksaShipyard
 
teleagaf74
teleagaf74teleagaf74
teleagaf74
Faleniu Teleaga
 
Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017
Crosstown TO
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
David H Moloney
 

What's hot (20)

New Presentation Layout 09-09-16 Linkedin
New Presentation Layout 09-09-16 LinkedinNew Presentation Layout 09-09-16 Linkedin
New Presentation Layout 09-09-16 Linkedin
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Neart na Gaoithe Offshore Wind
Neart na Gaoithe Offshore Wind Neart na Gaoithe Offshore Wind
Neart na Gaoithe Offshore Wind
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
 
Montrose BLP
Montrose BLPMontrose BLP
Montrose BLP
 
Armtec Precast Insulated Wall Panels Webinar
Armtec Precast Insulated Wall Panels WebinarArmtec Precast Insulated Wall Panels Webinar
Armtec Precast Insulated Wall Panels Webinar
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
 
Loksa Shipyard presentation
Loksa Shipyard presentationLoksa Shipyard presentation
Loksa Shipyard presentation
 
teleagaf74
teleagaf74teleagaf74
teleagaf74
 
Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
 

Similar to RDS WYCO - Install overview 2018

Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
ManviVarshney2
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
varun km
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
jose bonifacio de souza leite cuadros
 
2015 CRW - Project Spotlight: New NY Bridge Project
2015 CRW -  Project Spotlight: New NY Bridge Project2015 CRW -  Project Spotlight: New NY Bridge Project
2015 CRW - Project Spotlight: New NY Bridge Project
Specialized Carriers & Rigging Association
 
2018 CRW: Engineered Lift Plans From A to Z
2018 CRW: Engineered Lift Plans From A to Z2018 CRW: Engineered Lift Plans From A to Z
2018 CRW: Engineered Lift Plans From A to Z
Specialized Carriers & Rigging Association
 
Commdex Capabilities Presentation
Commdex  Capabilities PresentationCommdex  Capabilities Presentation
Commdex Capabilities Presentation
Mark Shepherd
 
Services Master
Services MasterServices Master
Services Master
1amfrankmasson1
 
CEMATRIX Corporation - Product Overview
CEMATRIX Corporation - Product OverviewCEMATRIX Corporation - Product Overview
CEMATRIX Corporation - Product Overview
The Howard Group Inc.
 
Buildings
BuildingsBuildings
Buildings
MECandPMV
 
CIRCULAM VITA MUHAMMAD ISMAIL
CIRCULAM VITA MUHAMMAD ISMAILCIRCULAM VITA MUHAMMAD ISMAIL
CIRCULAM VITA MUHAMMAD ISMAIL
M-ISMAIL khan
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09
zaff69
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Fairfax County
 
PFS.pptx
PFS.pptxPFS.pptx
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
Nick Bentley
 
CCTVHeadquarters.pdf
CCTVHeadquarters.pdfCCTVHeadquarters.pdf
CCTVHeadquarters.pdf
DANISHPUTRAMDFARIS
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
Krystian Gnysinski
 
Trulift presentation
Trulift presentationTrulift presentation
Trulift presentation
RMD Kwikform Ltd
 

Similar to RDS WYCO - Install overview 2018 (20)

Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
2015 CRW - Project Spotlight: New NY Bridge Project
2015 CRW -  Project Spotlight: New NY Bridge Project2015 CRW -  Project Spotlight: New NY Bridge Project
2015 CRW - Project Spotlight: New NY Bridge Project
 
2018 CRW: Engineered Lift Plans From A to Z
2018 CRW: Engineered Lift Plans From A to Z2018 CRW: Engineered Lift Plans From A to Z
2018 CRW: Engineered Lift Plans From A to Z
 
Commdex Capabilities Presentation
Commdex  Capabilities PresentationCommdex  Capabilities Presentation
Commdex Capabilities Presentation
 
Services Master
Services MasterServices Master
Services Master
 
CEMATRIX Corporation - Product Overview
CEMATRIX Corporation - Product OverviewCEMATRIX Corporation - Product Overview
CEMATRIX Corporation - Product Overview
 
Buildings
BuildingsBuildings
Buildings
 
 
CIRCULAM VITA MUHAMMAD ISMAIL
CIRCULAM VITA MUHAMMAD ISMAILCIRCULAM VITA MUHAMMAD ISMAIL
CIRCULAM VITA MUHAMMAD ISMAIL
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
PFS.pptx
PFS.pptxPFS.pptx
PFS.pptx
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
 
CCTVHeadquarters.pdf
CCTVHeadquarters.pdfCCTVHeadquarters.pdf
CCTVHeadquarters.pdf
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
Trulift presentation
Trulift presentationTrulift presentation
Trulift presentation
 

More from Jon Boutilier

TelCyte - 2019 brochure
TelCyte - 2019 brochureTelCyte - 2019 brochure
TelCyte - 2019 brochure
Jon Boutilier
 
Tel cyte 2019 service lines
Tel cyte 2019 service linesTel cyte 2019 service lines
Tel cyte 2019 service lines
Jon Boutilier
 
Tel cyte 2019 brochure
Tel cyte 2019 brochureTel cyte 2019 brochure
Tel cyte 2019 brochure
Jon Boutilier
 
Wyco field services overview
Wyco field services overviewWyco field services overview
Wyco field services overview
Jon Boutilier
 
Wyco wireless services 2018
Wyco wireless services 2018Wyco wireless services 2018
Wyco wireless services 2018
Jon Boutilier
 
Wyco wireline services 2018
Wyco wireline services 2018Wyco wireline services 2018
Wyco wireline services 2018
Jon Boutilier
 

More from Jon Boutilier (6)

TelCyte - 2019 brochure
TelCyte - 2019 brochureTelCyte - 2019 brochure
TelCyte - 2019 brochure
 
Tel cyte 2019 service lines
Tel cyte 2019 service linesTel cyte 2019 service lines
Tel cyte 2019 service lines
 
Tel cyte 2019 brochure
Tel cyte 2019 brochureTel cyte 2019 brochure
Tel cyte 2019 brochure
 
Wyco field services overview
Wyco field services overviewWyco field services overview
Wyco field services overview
 
Wyco wireless services 2018
Wyco wireless services 2018Wyco wireless services 2018
Wyco wireless services 2018
 
Wyco wireline services 2018
Wyco wireline services 2018Wyco wireline services 2018
Wyco wireline services 2018
 

Recently uploaded

New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 

Recently uploaded (20)

New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 

RDS WYCO - Install overview 2018

  • 1. WYCO Construction Services LLC 4240 East Elwood Street Phoenix, Arizona 85040 Multiple Carrier Site Seattle, Washington 120’ Self Supporting Tower 20-Block Concrete Ballast foundation Rapid Deployment System (RDS) (WYCO Proprietary - Temp Tower Solution Design)
  • 2. Highlights • Existing failing structure requires a tower modification for additional capacity needs & 20’ tower- extension. • (4) wireless carriers required temporary displacement of equipment along one of Seattle’s busiest highways. • Carriers were able to achieve full network deployment of new RFDS with this robust tower design assisting in better and faster coverage for residents while the existing structure was modified • Jurisdiction would only approve one temp structure making this a very challenging deployment • Project location is a critical cellular coverage area, all carriers needed to remain on air during what was estimated as a 60-day project duration. • Wyco Field Services & Client design collaboration • No ground disturbance and no restoration post decomm • Rapid deployment (total of three days from start to finish in the construction phase
  • 3. Tower & Foundation Data • Wyco Field Services, project specific foundation & structural analysis completed and approved with CD’s through jurisdiction • Monopole, stealth & self-support structure options can be utilized • Loading supports configurations of multiple carriers to 200’+ • Concrete ballast block foundation; multi-use ballast blocks designed for continued use & transport • Minimal real estate footprint for compact lease areas in many cases • Material & equipment inventory managed by Wyco Field Services as a value-added service
  • 4. Portable Tower Site Lease Area • Turn-Key solution, from inception of project through completion – Full Site Acquisition, A&E & Construction services were completed to get this site approved to be built • Wyco Field Services coordinated pre, during, & post construction meetings with necessary stake-holders; municipality, client, carriers
  • 5. Foundation Base Material • Native or Non-native base material can be utilized for pad leveling • Provides level surface for ease of ballast installation
  • 6. Ballast Block Installation • Pad was built in sloped area by bringing in base rock and completed to meet compaction requirements in one day • Provides level surface for ease of ballast installation
  • 7. Ballast Block Installation • Keyed ballast for ease of installation & securement • Site area must be level, sand/gravel base is used as top layer to achieve desired foundation grade and compaction requirements
  • 8. Ballast Block Installation • Use of hydraulic ram to tighten & secure ballast blocks • 1.25” diameter tension rods are used to fasten ballast blocks by way of hydraulic ram-jack
  • 9. Ballast Block Installation • Final pad surface secured; strong enough to maintain most equipment shelter enclosures, generators, and other carrier cabinet equipment • Foundation ready for staged tower
  • 10. Tower Installation • Tower or pole Installation • Next Steps; configuration of carrier equipment to be placed on new structure
  • 11. Tower Installation Complete • Total build time on this project from start to finish, was three days. • After removal once the structural MOD is complete on existing tower, this site will be removed and relocated to a new project (Multiple Use) • Upon removal of this temp structure, the site will go back to original condition after cleanup, requiring no restoration saving money at the decomm phase